Attachment 27 AF Form 66 Seed Proj FXSB 21-1058.pdf
PDF 613 KB Posted
- Attached to
- JBER MACC Federal contract opportunity
- Solicitation number
- FA500021R0023
About this file
This document contains a schedule of materials submittals for a federal construction project. The schedule outlines 18 line items of required submittals for repair work on restrooms in Building 13373 at Joint Base Elmendorf-Richardson in Alaska. Submittals include project plans, material safety data sheets, as-built drawings, operation and maintenance manuals, test results, and shop drawings for items like HVAC systems, ceilings, doors, and finishes. Due dates for submittals range from 10 days after notice to proceed to 7 days after final acceptance. The schedule includes columns for submission dates, dates materials are received by the contracting office, dates for returns to the civil engineering office, follow-up dates, and spaces to record contractor notifications and approval status. This submittal schedule provides a framework to track and review contractor documentation for a construction project awarded under the Joint Base Elmendorf-Richardson Multiple Award Construction Contract.
View the file
Other files for this federal contract opportunity
Show all 44
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AF FORM 66, SEP 86 PAGE 1 of 2
SCHEDULE OF MATERIALS SUBMITTALS PROJECT NUMBER PROJECT TITLE SOLICITATION/CONTRACT NO.
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF COPIES REQUIRED
L I N E
N U M B E R
ITEM OR DESCRIPTION OF ITEM,
CONTRACT PREFERENCE, TYPE OF
SUBMITTAL
C
E R
TI
FI
C A
TI
O
N O
F C
O M
P
LI
A N
C E
D R
A W
IN
G
S
P
LA
N
M S
D S
M A
N F'
R R
E C
O M
M E
N D
A
TI
O N
S
R E
Q U
E S
T
LE
TT
E
R
C A
TA
LO
G D
A
TA
R E
P O
R
TS
O
TH
E R
D A
TA
TE
S
T R
E S
U
LT
S
REQUIRED
SUBMISSION
DATE
DATE
RECEIVED IN
CONTRACTIN
G
DATE TO CIVIL
ENGINEERING
RETURN
SUSPENSE DATE
FOLLOW-UP
DATE CONTRACTOR
NOTIFIED
CONTRACTOR RE-
SUBMITTAL
FINAL APPROVAL REMARKS
1 Project Specific Form 66 1 10 days prior to start of any work
2 Notice of Start of Work 1 10 days prior to start of any work
3 As Builts 1 Final +7 Days
4 Environment Pre-Con Checklist 1 NTP +10 Days
5 HAZMAT Usage Tracking Form 1 See Remarks NLT 10 working days piror to material being brought onto installation
6 HAZMAT Usage Tracking Form 1 See Remarks NLT 7 working days after final acceptance
O&M maint. data and maint manuals & Manufacturer's Warranty for All Equipment Installed
1 1 Install + 5 Days
Factory and Field Test Certificates, Logs and Test Results 1 Before
Acceptance
9 Completion of DD 1354 1 Final +7 Days
10 Section 01000, Para. 4.3 Material Safety Data Sheet
1 See Remarks
MSDSs must be submitted and approved by the Government prior to procurement of all potential hazardous materials
Section 01000, Para. 4.3 Schedule 1 NTP +10 Days
12 Section 01020, para. 1.7 Form 3
After completion of Form
Section 01020, Para. 3.2 FRP 1 NTP +10 Days
Section 01020, Para. 3.2 Cove Base 1 NTP +10 Days
Repair Restrooms Building 13373
FXSB 21-1058
FA500021R0023-JBER MACC
Attachment 27 - Seed Proj FXSB 21-1058
AF From 66
FA5000-06-R-0011
AF FORM 66, SEP 86 PAGE 2 of 2
SCHEDULE OF MATERIALS SUBMITTALS PROJECT NUMBER PROJECT TITLE SOLICITATION/CONTRACT NO.
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF COPIES REQUIRED
L I N E
N U M B E R
ITEM OR DESCRIPTION OF ITEM,
CONTRACT PREFERENCE, TYPE OF
SUBMITTAL
C
E R
TI
FI
C A
TI
O
N O
F C
O M
P
LI
A N
C E
D R
A W
IN
G
S
P
LA
N
M S
D S
M A
N F'
R R
E C
O M
M E
N D
A
TI
O N
S
R E
Q U
E S
T
LE
TT
E
R
C A
TA
LO
G D
A
TA
R E
P O
R
TS
O
TH
E R
D A
TA
TE
S
T R
E S
U
LT
S
REQUIRED
SUBMISSION
DATE
DATE
RECEIVED IN
CONTRACTIN
G
DATE TO CIVIL
ENGINEERING
RETURN
SUSPENSE DATE
FOLLOW-UP
DATE CONTRACTOR
NOTIFIED
CONTRACTOR RE-
SUBMITTAL
FINAL APPROVAL REMARKS
Repair Restrooms Building 13373
FXSB 21-1058
Section 01020, Para. 3.4 HVAC 1 1 NTP +10 Days
Section 01020, Para. 3.5 Ceiling 1 NTP +10 Days
Section 01020, Para. 3.6 Paint 1 1 NTP +10 Days
Section 01020, Para. 3.7 Doors 1 NTP +10 Days
FA500021R0023-JBER MACC
Attachment 27 - Seed Proj FXSB 21-1058
AF From 66
AF66e.XLS
File details come from the government source that posted it. Updated .