Attachment 7 - AF Form 66.xlsx

XLSX spreadsheet 27 KB Posted

Attached to
Replace Chapel Windows B912
Solicitation number
FA480326Q0040
Issued by

About this file

AF Form 66 (Schedule of Material Submittals) is a tracking template used by the Air Force to manage contractor submissions throughout a construction project. This form is populated for Solicitation FA480326Q0040 for the Replace Chapel Windows B912 project at Shaw Air Force Base, South Carolina, and documents all required material submittals, approvals, and associated timelines.

The form identifies five key submittal items required from the contractor: a Construction Schedule (due within 5 days of Notice to Proceed), Operation & Maintenance Manuals, Window Shop Drawings, Glass Cut Sheet, and As-Built Drawings. For each submittal, the form provides columns to track submission dates, dates received by the contracting office, return suspense dates, submittal numbers, contractor resubmittal dates, and final approval status with remarks indicating whether items were approved or disapproved. This template serves as the administrative tool for the Contracting Officer and Project Engineer to monitor compliance with material submittal requirements and ensure all submittals are completed in accordance with the contract schedule during the 60-calendar-day period of performance for this small business set-aside construction project.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NCOC-A

PROJECT NUMBER :PROJECT TITLE:SOLICITATION/CONTRACT NO.:
SCHEDULE OF MATERIAL SUBMITTALS
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIFICATION OF COMPLIANCESHOP DRAWINGSSAMPLESCOLOR SELECTIONMANUFACTURER'S RECOMMENDATIONSMANUFACTURER'S WARRANTYCATALOG DATAOPERATING INSTRUCTIONSOTHERREQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS
APPROVEDDIS- APPROVED
1Construction SchedulexWithin 5 days of NTP
2O&M Manualsx
3Window Shop Drawingsx
4Glass Cut Sheetx
5As-Built Drawingsx
6
7
8
9
10
11
12
13
14
15
16
17
18
19

Solicitation No. F38604-99-1480 Attachment 6

AF FORM 66

(Computer Generated) PAGE &P of &N