WT 17518487 AF Form 66.xlsx

Air Force Form XLSX spreadsheet 36 KB Posted

Attached to
Repair Structural Fire Trainer B17903, 17904
Solicitation number
FA480126R0005
Issued by

About this file

This is an AF Form 66 Schedule of Material Submittals for the repair of Buildings 17903 and 17904 at Holloman Air Force Base, New Mexico, under contract WT #17518529. The form establishes submittal requirements and deadlines for various materials, components, and documentation required throughout the project execution and closeout phases.

The submittal schedule specifies delivery timelines relative to Notice to Proceed (NTP) and design completion milestones. General submittals include the Project Specific Form 66 (NTP + 3 days), construction schedule (NTP + 5 days), and design drawings with a 95% design submission at NTP + 60 days followed by 100% design approval within 5 days of 95% acceptance. Architectural and component submittals due at Design + 30 days include doors, window shutters, liner panels, plumbing fittings, paint specifications, ladders, and hatch covers. Technical submittals include an anchor pull test certification (Test + 10 days), pyrometer, thermocouple, and engineer qualifications documentation. Closeout requirements consist of the final DD Form 1354 and warranty documentation, both due within 7 days of final project completion. All submittals require three copies in hard format with electronic copies provided; the government retains all submitted materials. The form serves as the project engineer and contract administrator's tool for tracking approval status across required submissions.

View the file

Other versions and copies of AF Form 66

File Revision Posted Attached to
Attachment 09-AF form 66 03.27.2025.pdf Mar 27, 2025 B611 HVAC Repair
Attachment 2 AF Form 66.pdf Revision not stated REPAIR AC PAVING
AF form 66 Blank.pdf Revision not stated Demo Mini mute sites
Attach 9_AF Form 66 Submittal Register.pdf Revision not stated PKAA Dorm Water Damage Repair (Construction)
AF Form 66-EEPZ260842 Renovate Convert Comm to SAPR B730.xlsx Revision not stated B730 Renovate Convert Comm to SAPR
AF Form 66_EEPZ254664-B972 UOQ.xlsx Revision not stated B972 Renovate UOQ Community Commons
AF Form 66 B268.xlsx Revision not stated B268 Replace STUS Backup Generator
AF Form 66 B730.xlsx Revision not stated B730 - Renovate RM106 for Emergency Operations Center
AF Form 66.xlsx Revision not stated B836 Replace Electrical in Airfield Lighting Vault
AF Form 66 OSI Flooring.xlsx Revision not stated OSI B926 Flooring
EEPZ254660 Repair Control Tower HVAC B1806 - AF Form 66.xlsx Revision not stated B1806 Repair Control Tower HVAC
AF Form 66 Template.xlsx Revision not stated Replace AAS BAK-15 Controls, B2001, B2003
AF Form 66 EEPZ216808 Replace Security Forces Elevator B926.xlsx Revision not stated B926 Replace Security Forces Elevator
AF Form 66.xlsx Revision not stated RENOVATE/CONVERT 50th 49th SQ OPS, B230
AF Form 66.xlsx Revision not stated T-6 Flightline Shacks
AF Form 66 Template.xlsx Revision not stated Replace Fire Alarms, Multi Facility
EEPZ248229 -- AF Form 66.xlsx Revision not stated Repair Kiddie Pool
Atch 2 AF Form 66.pdf Revision not stated Removal of Underground Storage Tank at Launch Facility E-10 (Laramie County, WY)
Attachment 4 - AF Form 66 Submittal Register.pdf Revision not stated Bldg 65 - Renovation of Telephone Office Area, FE Warren AFB, WY AMENDMENT 03
Attachment 7 - AF Form 66.xlsx Revision not stated Replace Chapel Windows B912
Show all 20

Who attaches AF Form 66

State Files
Iowa 1
Massachusetts 1

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittal 1

SCHEDULE OF MATERIAL SUBMITTALSPROJECT NUMBERPROJECT NAMESOLICITATION /CONTRACT NUMBER
WT #17518529Repair Bldgs 17903 & 17904
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
LINE NUMBERNote: 3 copies required per submittal. Government will retain all submittals.Provide an electronic copy for each submittal.CERTIF. OF COMPLIANCESHOP DRAWINGSCOLOR SELECTIONMANUFATURUR'S RECOMMENDATIONCATALOG DATAO&M RECOMMENDATIONSCALCULATIONSWARRANTYDRAWINGSREPORTTEST RESULTSREQUIRED SUBMISSION DATEDATE TO CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSAPPROVEDDISAPPROVEDCONTRACTOR SUBMITTALFINAL APPROVAL
GENERAL
Project Specific Form 66XNTP + 3
Construction ScheduleXNTP + 5
DESIGN
PDF Drawings.X95% Design: NTP + 60 days. 100% Design: Acceptance of 95% + 5 days.
ARCHITECTURAL
DoorsXDesign + 30
Window ShuttersXDesign + 30
Liner PanelsXDesign + 30
Plumbing FittingsXDesign + 30
PaintXDesign + 30
LadderXDesign + 30
Hatch CoverXDesign + 30
Anchor Pull Test CertificationXTest + 10
PyrometerXDesign + 30
Engineer QualificationsXDesign + 30
ThermocoupleXDesign + 30
CLOSEOUT
Final DD - 1354XFinal + 7
Provide WarrantyXFinal + 7

&"Arial,Bold"&6AF FORM 66, OCT 99 &"Arial,Regular"Previous Edition Will Be Used

File details come from the government source that posted it. Updated .