AF Form 66 B730.xlsx
XLSX spreadsheet 86 KB Posted
- Solicitation number
- FA302226R0022
About this file
This is an AF Form 66 Schedule of Material Submittals for the renovation of Room 106 at an Emergency Operations Center (Project No. EEPZ255862), dated May 17, 2026. The form establishes submission and approval requirements for construction materials and documentation across multiple trade disciplines.
The General section requires submission of work/construction/phasing plans, as-built drawings, progress schedules, guarantees and warranties, superintendent qualifications, and certificates of compliance. The Environmental section mandates Safety Data Sheets (SDS), hazardous waste reports, AF Form 3000 Hazardous Material Reports, recycled material/construction debris reports, Storm Water Pollution Prevention Plans with Best Management Practices, weekly inspection reports, state asbestos licenses for workers and supervisors, firm asbestos licenses, 10-day demolition/asbestos notifications, work plans, and ACM disposal manifests. The Architectural section requires shop drawings and samples for carpet tile, cove base, ceiling tile, and ceiling grid. The Mechanical section specifies submittals for air handlers, compressors, ductless split systems, refrigerant lines, ducts, insulation, and JCI controllers with shop drawings and samples required for certain items. The Electrical section requires submittals for conduit, conductors, generators, panelboards, automatic transfer switches, receptacles, and circuit breakers, with shop drawings and samples designated for generators, panelboards, and transfer switches. The Civil and Special Systems sections indicate no submittal requirements. The Other/Miscellaneous section requires an airfield waiver (including site plan, equipment type, maximum height, and work hours) and height of equipment documentation. Additionally, a Hazardous Materials Usage Tracking Form must be completed with all anticipated quantities prior to construction start and updated upon project completion, submitted with manufacturer SDS and AF Form 3000 documentation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B730 Renovate Rm 106 RFIs (002).docx | DOCX document | |
| Site Visit Sign in Sheet.pdf | ||
| Solicitation Amendment FA302226R00220002 SF 30.pdf | ||
| Solicitation Amendment FA302226R00220001 SF 30 CO Signed.pdf | ||
| Appendix A Cost Breakdown.xlsx | XLSX spreadsheet | |
| 5 August Statement of Work B730.pdf | ||
| CUI Contractor Training Slides.pptx | PPTX presentation | |
| EAL Form.pdf | ||
| 26 April Statement of Work B730.pdf | ||
| 18 May Wage Determination.pdf | ||
| Solicitation - FA302226R0022.pdf | ||
| CUI Contractor Training Acknowledgment.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
General
| Project No: | Project Title: | Date: | |||||||||||||||||
| EEPZ255862 | Renovate RM106 For EOC | 17-May-26 | |||||||||||||||||
| LINE NO. | ITEM DESCRIPTION | SPEC REF | NUMBER OF COPIES REQUIRED | DATE KTR REQUIRES APPROVAL | DATE RECEIVED KTR | DATE TO CIVIL ENG | DATE RECEIVED FROM CE | DATE CONTRACTOR NOTIFIED APR DISAPR | CONTRACT RESUBMIT DUE | CONTRACT RESUBMITTAL RECEIVED | FINAL APPROVAL RCVD KTR NOTIFIED | ||||||||
| Certificate of Compliance | Shop Drawings | Samples | Color Selction | Manufacturer's Recommendations | Manufacturer's Warranty | Catalog Data | Operating Instructions | Other | |||||||||||
| GENERAL | |||||||||||||||||||
| 1 | Work/Construction/phasing Plan | BASIC | X | ||||||||||||||||
| 3 | As-Built Drawings | BASIC | X | ||||||||||||||||
| 4 | Progress Schedule | BASIC | X | ||||||||||||||||
| 5 | Guarantees and Warranties | BASIC | X | ||||||||||||||||
| 6 | Superintendent's Qualifications and Experience | BASIC | X |
AF Form 66 (Substitute) GENERAL Page&Pof&N
SCHEDULE OF MATERIAL SUBMITTALS
Environmental
| Project No: | Project Title: | Date: | |||||||||||||||||
| EEPZ255862 | Renovate RM106 For EOC | 17-May-26 | |||||||||||||||||
| LINE NO. | ITEM DESCRIPTION | SPEC REF | NUMBER OF COPIES REQUIRED | DATE KTR REQUIRES APPROVAL | DATE RECEIVED KTR | DATE TO CIVIL ENG | DATE RECEIVED FROM CE | DATE CONTRACTOR NOTIFIED APR DISAPR | CONTRACT RESUBMIT DUE | CONTRACT RESUBMITTAL RECEIVED | FINAL APPROVAL RCVD KTR NOTIFIED | ||||||||
| Certificate of Compliance | Shop Drawings | Samples | Color Selction | Manufacturer's Recommendations | Manufacturer's Warranty | Catalog Data | Operating Instructions | Other | |||||||||||
| GENERAL | |||||||||||||||||||
| 7 | Appropriate SDS | BASIC | |||||||||||||||||
| 8 | Hazardous waste report | BASIC | |||||||||||||||||
| 9 | Hazardous Material Report (AF Form 3000) | BASIC | |||||||||||||||||
| 10 | Recycled Material Report/Construction Debris report | BASIC | |||||||||||||||||
| 11 | Storm Water Pollution Prevention Plan with Best Management Practices Identified | BASIC | |||||||||||||||||
| 12 | Weekly Inspection Reports for Projects | BASIC | |||||||||||||||||
| 13 | State Licenses for workers and supervisors (Asbestos) | BASIC | |||||||||||||||||
| 14 | State license for the firm (Asbestos) | BASIC | |||||||||||||||||
| 15 | 10 Day Notification (Demolition and Asbestos) | BASIC | |||||||||||||||||
| 16 | Work Plan | BASIC | |||||||||||||||||
| 17 | Copy of ACM DisposalManifest | BASIC |
AF Form 66 (Substitute) Environmental Page&Pof &N
SCHEDULE OF MATERIAL SUBMITTALS
Architectural
| Project No: | Project Title: | Date: | |||||||||||||||||
| EEPZ255862 | Renovate RM106 For EOC | 17-May-26 | |||||||||||||||||
| LINE NO. | ITEM DESCRIPTION | SPEC REF | NUMBER OF COPIES REQUIRED | DATE KTR REQUIRES APPROVAL | DATE RECEIVED KTR | DATE TO CIVIL ENG | DATE RECEIVED FROM CE | DATE CONTRACTOR NOTIFIED APR DISAPR | CONTRACT RESUBMIT DUE | CONTRACT RESUBMITTAL RECEIVED | FINAL APPROVAL RCVD KTR NOTIFIED | ||||||||
| Certificate of Compliance | Shop Drawings | Samples | Color Selction | Manufacturer's Recommendations | Manufacturer's Warranty | Catalog Data | Operating Instructions | Other | |||||||||||
| GENERAL | |||||||||||||||||||
| 14 | Carpet Tile | X | X | ||||||||||||||||
| Cove Base | X | X | |||||||||||||||||
| Ceiling Tile | X | X | |||||||||||||||||
| Ceiling Grid | X | X |
AF Form 66 (Substitute) Architectural Page&Pof&N
Civil
| Project No: | Project Title: | Date: | |||||||||||||||||
| EEPZ255862 | Renovate RM106 For EOC | 17-May-26 | |||||||||||||||||
| LINE NO. | ITEM DESCRIPTION | SPEC REF | NUMBER OF COPIES REQUIRED | DATE KTR REQUIRES APPROVAL | DATE RECEIVED KTR | DATE TO CIVIL ENG | DATE RECEIVED FROM CE | DATE CONTRACTOR NOTIFIED APR DISAPR | CONTRACT RESUBMIT DUE | CONTRACT RESUBMITTAL RECEIVED | FINAL APPROVAL RCVD KTR NOTIFIED | ||||||||
| Certificate of Compliance | Shop Drawings | Samples | Color Selction | Manufacturer's Recommendations | Manufacturer's Warranty | Catalog Data | Operating Instructions | Other | |||||||||||
| GENERAL | |||||||||||||||||||
| NONE |
AF Form 66 (Substitute) CIVIL Page&Pof &N
Mechanical
| Project No: | Project Title: | Date: | |||||||||||||||||
| EEPZ255862 | Renovate RM106 For EOC | 17-May-26 | |||||||||||||||||
| LINE NO. | ITEM DESCRIPTION | SPEC REF | NUMBER OF COPIES REQUIRED | DATE KTR REQUIRES APPROVAL | DATE RECEIVED KTR | DATE TO CIVIL ENG | DATE RECEIVED FROM CE | DATE CONTRACTOR NOTIFIED APR DISAPR | CONTRACT RESUBMIT DUE | CONTRACT RESUBMITTAL RECEIVED | FINAL APPROVAL RCVD KTR NOTIFIED | ||||||||
| Certificate of Compliance | Shop Drawings | Samples | Color Selction | Manufacturer's Recommendations | Manufacturer's Warranty | Catalog Data | Operating Instructions | Other | |||||||||||
| GENERAL | |||||||||||||||||||
| Air handler | X | X | |||||||||||||||||
| Compressor | X | ||||||||||||||||||
| Ductless Split System | X | X | |||||||||||||||||
| refrigerant lines | X | ||||||||||||||||||
| Ducts | X | ||||||||||||||||||
| Insulation | X | ||||||||||||||||||
| JCI Controller | X | X |
AF Form 66 (Substitute) Mechanical Page&Pof&N
Electrical
| Project No: | Project Title: | Date: | |||||||||||||||||
| EEPZ255862 | Renovate RM106 For EOC | 17-May-26 | |||||||||||||||||
| LINE NO. | ITEM DESCRIPTION | SPEC REF | NUMBER OF COPIES REQUIRED | DATE KTR REQUIRES APPROVAL | DATE RECEIVED KTR | DATE TO CIVIL ENG | DATE RECEIVED FROM CE | DATE CONTRACTOR NOTIFIED APR DISAPR | CONTRACT RESUBMIT DUE | CONTRACT RESUBMITTAL RECEIVED | FINAL APPROVAL RCVD KTR NOTIFIED | ||||||||
| Certificate of Compliance | Shop Drawings | Samples | Color Selction | Manufacturer's Recommendations | Manufacturer's Warranty | Catalog Data | Operating Instructions | Other | |||||||||||
| GENERAL | |||||||||||||||||||
| Conduit | X | ||||||||||||||||||
| Conductor | X | ||||||||||||||||||
| Generator | X | X | |||||||||||||||||
| Panelboards | X | X | |||||||||||||||||
| Automatic Transfer Switch | X | X | |||||||||||||||||
| Recepticle | X | ||||||||||||||||||
| Circuit Breakers | X |
AF Form 66 (Substitute) Electrical Page&Pof &N
Special Systems
| Project No: | Project Title: | Date: | |||||||||||||||||
| EEPZ255862 | Renovate RM106 For EOC | 17-May-26 | |||||||||||||||||
| LINE NO. | ITEM DESCRIPTION | SPEC REF | NUMBER OF COPIES REQUIRED | DATE KTR REQUIRES APPROVAL | DATE RECEIVED KTR | DATE TO CIVIL ENG | DATE RECEIVED FROM CE | DATE CONTRACTOR NOTIFIED APR DISAPR | CONTRACT RESUBMIT DUE | CONTRACT RESUBMITTAL RECEIVED | FINAL APPROVAL RCVD KTR NOTIFIED | ||||||||
| Certificate of Compliance | Shop Drawings | Samples | Color Selction | Manufacturer's Recommendations | Manufacturer's Warranty | Catalog Data | Operating Instructions | Other | |||||||||||
| GENERAL | |||||||||||||||||||
| 26 | NONE |
AF Form 66 (Substitute) Special Systems Page&Pof &N
Other&Misc
| Project No: | Project Title: | Date: | |||||||||||||||||
| EEPZ255862 | Renovate RM106 For EOC | 17-May-26 | |||||||||||||||||
| LINE NO. | ITEM DESCRIPTION | SPEC REF | NUMBER OF COPIES REQUIRED | DATE KTR REQUIRES APPROVAL | DATE RECEIVED KTR | DATE TO CIVIL ENG | DATE RECEIVED FROM CE | DATE CONTRACTOR NOTIFIED APR DISAPR | CONTRACT RESUBMIT DUE | CONTRACT RESUBMITTAL RECEIVED | FINAL APPROVAL RCVD KTR NOTIFIED | ||||||||
| Certificate of Compliance | Shop Drawings | Samples | Color Selction | Manufacturer's Recommendations | Manufacturer's Warranty | Catalog Data | Operating Instructions | Other | |||||||||||
| GENERAL | |||||||||||||||||||
| 26 | Airfield Waiver | ||||||||||||||||||
| Prepared by CE but contractor must supply: | |||||||||||||||||||
| 1. Site Plan/Area of Work | |||||||||||||||||||
| 2. Type of Equipment to be used | |||||||||||||||||||
| 3. Maximum height of equipment | |||||||||||||||||||
| 4. Work Hours (24/7, nights, non-flying, etc). | |||||||||||||||||||
| 5. Work Schedule |
27 Height of equipment on the airfield
AF Form 66 (Substitute) Other and Misc Page&Pof &N
HAZMAT Tracking Sheet
| Contractor Hazardous Materials Usage Tracking Form | |||||
| Return this form to Contracting/Project Manager with Manufacturers original SDS | |||||
| EEPZ255862 | Renovate RM106 For EOC | Contract # | |||
| Start Date: | End Date: | Cotractor: | |||
| Product Name as seen on SDS | |||||
| Process (How is material used) | Part # | Manufacturer | Type of | ||
| Container | Size of Container | Total |
Quantity
| Used | EESOH MSN | |
| 1 | ||
| Process: | ||
| 2 | ||
| Process: | ||
| 3 | ||
| Process: | ||
| 4 | ||
| Process: | ||
| 5 | ||
| Process: | ||
| 6 | ||
| Process: | ||
| 7 | ||
| Process: | ||
| 8 | ||
| Process: | ||
| 9 | ||
| Process: | ||
| 10 | ||
| Process: | ||
| 11 | ||
| Process: | ||
| 12 | ||
| Process: | ||
| 13 | ||
| Process: | ||
| 14 | ||
| Process: | ||
| 15 | ||
| Process: | ||
| 16 | ||
| Process: | ||
| 17 | ||
| Process: | ||
| 18 | ||
| Process: | ||
| 19 | ||
| Process: | ||
| 20 | ||
| Process: | ||
| 21 | ||
| Process: | ||
| 22 | ||
| Process: | ||
| 23 | ||
| Process: | ||
| 24 | ||
| Process: | ||
| 25 | ||
| Process: | ||
| 26 | ||
| Process: | ||
| 27 | ||
| Process: | ||
| 28 | ||
| Process: |
Example and Instructions
| WORKSHEET INSTRUCTIONS | ||
| BLOCK | DESCRIPTION | INFORMATION REQUIRED |
| A | Project Number | Project number or Opportunity number assigned to the project by Civil Engineering. |
| B | Project Title | The title of the project. |
| C | Contract Number | The contract number or delivery order assigned by contracting. |
| D | Product Name | The name of the product as listed on the SDS. |
| E | Process | A Brief description of the work performed with each material. |
| F | Part # | The part number as listed on the SDS. |
| G | Manufacturer | The name of the Manufacturer of the product (not the distributor) |
| H | Type of Container | The type of container that the product comes in. Example: can, barrel, bottle, container, cylinder, drum, etc… |
| I | Size of Container | Size as listed on container. Example: oz, lbs, Liter, Quart, Gallon, etc… |
| J | Total Quantity Used | This will be the amount that you anticipate using for the first submission. At the conclusion of the project you will need to provide a final list with updated quantities. |
| K | EESOH MSN | This is the Material Stock Number assigned for EESOH-MIS tracking. (The Air Force Hazardous Materials Manager will provide this number) |
NOTE: Complete the HAZMAT Tracking Sheet located on the first TAB of this Excel spreadsheet with all hazardous materials to be used during the duration of the construction project. Once completed, save the sheet as a .pdf file and submit to the contracting officer with an AF Form 3000 Submittal form. This data will need to be submitted prior to construction start. When construction is complete, you will submit a final revised report with updated quanties.
image1.emf
File details come from the government source that posted it. Updated .