EEPZ248229 -- AF Form 66.xlsx

XLSX spreadsheet 82 KB Posted

Attached to
Repair Kiddie Pool
Solicitation number
FA302226R0002
Issued by

About this file

This file is an AF Form 66 (Substitute) Schedule of Material Submittals for the Repair Kiddie Pool project (EEPZ248229, Building B948), dated 29 May 2025. The form establishes the submission and approval workflow for contractor deliverables across multiple construction disciplines, with columns tracking submission dates, approval timelines, and resubmittal requirements.

The General section requires five baseline submittals: Work/Construction/Phasing Plan, Shop Drawings, Progress Schedule, Guarantees and Warranties, and Superintendent's Qualifications and Experience. The Environmental section mandates seven submittals including Safety Data Sheets (SDS), Hazardous Waste Report, AF Form 3000 (Hazardous Material Report), Recycled Material Report/Construction Debris Report, Weekly Inspection Reports, 10-Day Notification for Demolition and Asbestos, and Work Plan. Architectural requirements include Fence Gate/Latch specifications. Civil requirements specify Concrete Mix and Grout submittals with multiple copies required. Mechanical submissions cover Skimmer System, Channel Drain/Clean Out, and Side Jet and Central Spray Nozzles. The Special Systems section requires Pool Liner submittals (with multiple copies), Caulking, and Fasteners. No electrical or other miscellaneous submittals are specified. The form also includes a Hazardous Materials Tracking Sheet requiring contractors to document all hazardous materials used during construction, including product name, process description, part number, manufacturer, container type, container size, and total quantity used, with submissions required prior to construction start and final reporting at project completion.

View the file

Other files

File Type Posted
Solicitation - FA302226R0002.pdf PDF
Contractors CUI Training Slides.pptx PPTX presentation
MFR CUI Contractor Training Acknowledgment July 2024.pdf PDF
Wage Determination.pdf PDF
Design Bulid SOW.pdf PDF
EAL Form.pdf PDF
Appendix A - Cost Breakdown.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

General

Project No:Project Title:Date:
EEPZ248229Repair Kiddie Pool, B94829-May-25
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
1Work/Construction/Phasing PlanBASICX
2Shop DrawingsBASICX
3Progress ScheduleBASICX
4Guarantees and WarrantiesBASICX
5Superintendent's Qualifications and ExperienceBASICX

AF Form 66 (Substitute) GENERAL Page&Pof&N

SCHEDULE OF MATERIAL SUBMITTALS

Environmental

Project No:Project Title:Date:
EEPZ248229Repair Kiddie Pool, B94829-May-25
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
6Appropriate SDSBASICX
7Hazardous waste reportBASICX
8Hazardous Material Report (AF Form 3000)BASICX
9Recycled Material Report/Construction Debris reportBASICX
10Weekly Inspection Reports for ProjectsBASICX
1110 Day Notification (Demolition and Asbestos)BASICX
12Work PlanBASICX

AF Form 66 (Substitute) Environmental Page&Pof &N

SCHEDULE OF MATERIAL SUBMITTALS

Architectural

Project No:Project Title:Date:
EEPZ248229Repair Kiddie Pool, B94829-May-25
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
13Fence Gate/ LatchX

AF Form 66 (Substitute) Architectural Page&Pof&N

Civil

Project No:Project Title:Date:
EEPZ248229Repair Kiddie Pool, B94829-May-25
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
14Concrete Mix and GroutXX

AF Form 66 (Substitute) CIVIL Page&Pof &N

Mechanical

Project No:Project Title:Date:
EEPZ248229Repair Kiddie Pool, B94829-May-25
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
15Skimmer SystemX
16Channel Drain/ Clean OutX
17Side Jet and Central Spray NozzlesX

AF Form 66 (Substitute) Mechanical Page&Pof&N

Electrical

Project No:Project Title:Date:
EEPZ248229Repair Kiddie Pool, B94829-May-25
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
NA

AF Form 66 (Substitute) Electrical Page&Pof &N

Special Systems

Project No:Project Title:Date:
EEPZ248229Repair Kiddie Pool, B94829-May-25
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
18Pool linerXXXX
19CaulkingXX
20FastenersXX

AF Form 66 (Substitute) Special Systems Page&Pof &N

Other&Misc

Project No:Project Title:Date:
EEPZ248229Repair Kiddie Pool, B94829-May-25
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
NA

AF Form 66 (Substitute) Other and Misc Page&Pof &N

HAZMAT Tracking Sheet

Contractor Hazardous Materials Usage Tracking Form
Return this form to Contracting/Project Manager with Manufacturers original SDS
EEPZ248229Repair Kiddie Pool, B948Contract #
Start Date:End Date:Cotractor:
Product Name as seen on SDS
Process (How is material used)Part #ManufacturerType of
ContainerSize of ContainerTotal

Quantity

UsedEESOH MSN
1
Process:
2
Process:
3
Process:
4
Process:
5
Process:
6
Process:
7
Process:
8
Process:
9
Process:
10
Process:
11
Process:
12
Process:
13
Process:
14
Process:
15
Process:
16
Process:
17
Process:
18
Process:
19
Process:
20
Process:
21
Process:
22
Process:
23
Process:
24
Process:
25
Process:
26
Process:
27
Process:
28
Process:

Example and Instructions

WORKSHEET INSTRUCTIONS
BLOCKDESCRIPTIONINFORMATION REQUIRED
AProject NumberProject number or Opportunity number assigned to the project by Civil Engineering.
BProject TitleThe title of the project.
CContract NumberThe contract number or delivery order assigned by contracting.
DProduct NameThe name of the product as listed on the SDS.
EProcessA Brief description of the work performed with each material.
FPart #The part number as listed on the SDS.
GManufacturerThe name of the Manufacturer of the product (not the distributor)
HType of ContainerThe type of container that the product comes in. Example: can, barrel, bottle, container, cylinder, drum, etc…
ISize of ContainerSize as listed on container. Example: oz, lbs, Liter, Quart, Gallon, etc…
JTotal Quantity UsedThis will be the amount that you anticipate using for the first submission. At the conclusion of the project you will need to provide a final list with updated quantities.
KEESOH MSNThis is the Material Stock Number assigned for EESOH-MIS tracking. (The Air Force Hazardous Materials Manager will provide this number)

NOTE: Complete the HAZMAT Tracking Sheet located on the first TAB of this Excel spreadsheet with all hazardous materials to be used during the duration of the construction project. Once completed, save the sheet as a .pdf file and submit to the contracting officer with an AF Form 3000 Submittal form. This data will need to be submitted prior to construction start. When construction is complete, you will submit a final revised report with updated quanties.