Attachment 5 Seed Proj FXSB 21-1058 SOW SPECS DRAWINGS.pdf
PDF 6 MB Posted
- Attached to
- JBER MACC Federal contract opportunity
- Solicitation number
- FA500021R0023
About this file
This scope of work document outlines the renovation of two restrooms and conversion of a storage closet into an additional restroom at Building 13373 on Joint Base Elmendorf-Richardson in Alaska. The work includes demolishing existing fixtures and finishes, installing new plumbing, fixtures, partitions, ceilings, lighting, and doors. Requirements include pressure jet cleaning and camera inspection of sewer lines, coordinating with the base for access and utility clearances, using fiberglass reinforced plastic and commercial grade materials, and complying with environmental and safety standards. The related solicitation is for an indefinite delivery/indefinite quantity multiple award construction contract through the Department of the Air Force Pacific Air Forces to complete repair, alteration, and construction projects on Joint Base Elmendorf-Richardson.
View the file
Other files for this federal contract opportunity
Show all 44
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 1: SCOPE OF WORK
01020
03/12/2021
1. GENERAL:
1.1. Intent is to renovate the restrooms in building 13373, and convert the existing closet in the southwest corner of the building closet into a restroom.
1.2. If the codes contradict each other regarding a specific requirement, the contractor is to use the most stringent requirement.
1.3. The contractor shall limit the work to the areas indicated by the government. The contractor shall make every effort not to disturb or obstruct portions of the facilities still occupied by the government. The contractor shall make efforts to minimize interference to Government operations. The contractor shall dispose of all construction debris off base at an approved disposal facility.
1.4. Power Outages: if required, any power outage notifications must be sent to government a minimum of 2 weeks prior with a 24 hour confirmation notification prior to outage.
1.5. Water outages: Any water outages must be preceded with a minimum of 2 weeks notification with a 24 hour confirmation notification prior to the water outage.
1.6. Site Storage: On site storage outside of the project area is limited. The contractor shall minimize storage of materials and equipment on site.
1.7. A Civil Engineer Work Clearance request (673 ABW Form 3) is required to be completed before starting with any work. Contractor shall check with the appropriate authorities for Gas, Electric, Comm, Sewer, Storm and Water lines prior to beginning work.
1.8. A Storm Water Pollution Prevention Plan (SWPPP) is not required for this project;
however, best management practice will be followed.
1.9. DAMAGE TO EXISTING SITE CONDITIONS: The contractor shall be responsible to repair any and all damage incurred to existing Real Property/Grounds at no cost to the government. Contractor shall not park or drive on, sidewalk or grassy/snowy areas.
Damage incurred shall be repaired at no cost to the government.
1.10. Contractors are strongly encouraged to visit the site and get familiar with all the work related to the project prior to submitting a bid, to verify existing site condition and other information as noted in the scope of work and drawings, as well as to become familiar with the scope of work. Failure to visit the site does not relieve the Contractor from the responsibility of performing all work required to provide a complete and useable project in accordance with the Contract documents.
FA500021R0023-JBER MACC
Attachment 5-Seed Proj FXSB 21-1058
SOW SPECS DRAWINGS
1.11. Sketches provided are not for construction. Contractor must create their own construction shop drawings and submit to the government for approval prior to starting work on site.
1.12. It is the inherent responsibility of the Contractor to practice good fire prevention measures while working on Elmendorf Air Force Base, including the use of a fire watch.
1.13. Protection of Existing Utilities: The Contractor shall safeguard and protect from damage all utilities encountered or uncovered during work. Any damaged utilities caused by contractor’s negligence shall be repaired immediately at no additional cost to the government.
1.14. COVID Base Access Information: When work under this contract requires entry to controlled or restricted areas, the contractor shall comply with AFI 31-101, Integrated Defense, and DODMAN5200.02_AFMAN 16-1405, Air Force Personnel Security Program. Contractors requiring access to any area on Joint Base Elmendorf- Richardson (JBER) shall comply with installation, state, and local COVID-19 policies and mandates and respect any guidelines or restrictions imposed by local businesses. These policies and mandates frequently change. COVID-19 policies and mandates are found at https://www.jber.jb.mil/Coronavirus/ for JBER COVID-19 Policy Memo, https://covid19.alaska.gov/ for State of Alaska COVID-19 Coronavirus Information, and https://covid-responsemoa- muniorg.hub.arcgis.com/pages/emergency-orders for the Municipality of Anchorage Emergency Orders. Failure to comply with the guidelines or restrictions may result in suspended access to JBER or debarment. Contractors shall comply with the above-referenced documents] citing the appropriate paragraphs as applicable.
1.15. Facility is located on a secured airfield and will require escorts from the facility user, as well as advanced scheduling.
2. DEMOLISH: *** Before starting excavation, schedule a meeting with project inspector to perform a site walk to confirm demolition scope of work and mark items to be removed.
2.1. Existing Restrooms: Demolish and dispose of existing fixtures, plumbing, partitions, cove base, ceiling, lighting, and smoke detectors. Demolish plumbing and electrical only so far as required to reinstall new fixtures, lighting, and heat detectors.
2.2. Ceiling: Demolish and dispose of existing ceiling, insulation, and debris on ceiling. Walls are to be maintained.
3. NEW WORK:
3.1. Plumbing: Install hot and cold water supply using Type L copper with soldered or copper-press-joining-system joints to all fixtures. Install isolation ball valves in each restroom in accessible locations for maintenance.
FA500021R0023-JBER MACC
3.2. Walls: Repair damaged locations. Install fiber-reinforced plastic full height from floor to ceiling on all interior walls of the restrooms. Install cove base in same location as FRP.
Coordinate finish and color selection with user and 673rd CES prior to installation.
3.3. Floor: Clean existing concrete slab and seal with a commercial sealant.
3.4. HVAC: Install new vent covers, vent ductwork, radiant baseboard covers, and diffusers for all existing vents, baseboards, and diffusers. Install new exhaust fans in both rooms.
Fully duct both exhaust fans to exterior of the building. Penetration to exterior of the building shall be sealed with wire mesh or flapper to prevent bird entry. Coordinate material and equipment selection as well as color selection with user and 673rd CES prior to installation. Exhaust fans to be separately activated via new occupancy sensors installed by the contractor.
3.4.1. In existing restroom, install minimum 180 CFM exhaust fan
3.4.2. In closet being converted to a restroom, install minimum 100 CFM exhaust fan
3.5. Ceiling: Install new finished insulated ceiling. Ceiling joists to be 2x8 on 12 inch centers, assuming Douglas Fir-Larch #2. Install ½ inch gypsum wallboard to underside of joists.
Mud and tape to level 4 finish. On top of joists install 19/32 inch plywood. Paint “MAX LOAD 20 PSF” on top of ceiling.
3.6. Paint: For all areas not covered by FRP, including both sides of ceiling and outer walls of bathrooms and FAP closet, install primer and two coats of commercial grade latex paint. Coordinate paint finish and color selection with user and 673rd CES prior to installation.
3.7. Doors: Install new solid core commercial grade doors with steel frames and stainless steel hardware at all locations indicated in the drawings. Doors shall be installed with closers. Stops shall be installed to prevent wall damage for each door if needed.
3.7.1. Install Best MX8B interchangeable core keying system, as well as cylinder that will receive these cores, with 7 pin IC small format as shown on the plans.
Contractor shall provide any removed door locks and/or cores to 773 CES/CEOHS Lock Shop prior to demolition/renovation.
3.8. Lighting: Install LED lighting in ceilings. Coordinate light fixture selection with user and 673rd CES prior to installation. Lighting to be separately activated via new occupancy sensors installed by the contractor.
3.9. Occupancy sensors: Install occupancy sensors in all rooms. Sensors shall be spaced so all areas are covered.
3.10. Pressure Jet and clean the existing sewer line. Piping will be free of any visible foreign material. Approximately 250 linear feet will need to be cleaned and jetted.
Conduct sewer camera inspection and documentation of all sanitary sewer piping out to the first manhole. Provide thorough video and documentation of all piping joints, connections, any and all low spots and imperfections.
FA500021R0023-JBER MACC
3.11. Fixtures:
3.11.1. Toilets: Install commercial grade toilet fixtures as noted on the drawings. Toilet selection shall be coordinated with user and 673rd CES prior to installation. Connect to water supply and DWV piping. Toilets shall be equipped with touchless sensor activation.
3.11.2. Urinals: Install commercial grade urinal fixtures as noted on the drawings. Urinal selection shall be coordinated with user and 673rd CES prior to installation. Connect to water supply and DWV piping. Toilets shall be equipped with touchless sensor activation.
3.11.3. Sinks: Install commercial grade sink/lavatory fixtures as noted on the drawings.
Sink/lavatory selection shall be coordinated with user and 673rd CES before installation. Connect to water supply and DWV piping. Flexible connections shall be braided stainless only. Sinks shall be equipped with touchless sensor activation.
3.11.4. Partitions: Install solid phenolic partitions and doors as indicated on the drawings. Coordinate color and finish with user and 673rd CES before installation.
FA500021R0023-JBER MACC
MAP KEY
LOCATION DESCRIPTION
RICHARDSON VISITORS GATE
ARCTIC VALLEY GATE GLENN HWY SOUTHBOUND EXIT
ELMENDORF VISITORS GATE
654 6TH STREET: FIRE STATION 4
8517 20TH STREET: SECURITY FORCES
CLEAN FILL LANDFILL SITE
CONCRETE LANDFILL SITE
POST ROAD GATE
BUILDING 13373
PROJECT LOCATION
JOINT BASE ELMENDORF-RICHARDSON
673RD CIVIL ENGINEER SQUADRON
KEY PLAN
A B C D E F G H I
SHEET
REFERENCE
NUMBER
AF PROJECT NUMBER:
AEC FILE NAME:
DRAWING SCALE:
PLOT SCALE:
SYMBOL DATE DESCRIPTION
REVISIONS
JOINT BASE ELMENDORF-RICHARDSON, AK
DESIGNED BY:
DRAWN BY:
CHECKED BY:
PROJ. ENG.
DESIGN
DRAWINGS
1:1
AF CONTRACT NUMBER:
INV. NUMBER:
DATE APPR
DATE:
DATE:
DATE:
DATE:
DRAWING NO:
U.S. AIR FORCE
01 MAR 2021
03/01/2021
03/01/2021
N
RPR MODIFY TRAFFIC PATTERNS - TRAFFIC
CALMING GOV'T HILL & POST ROAD
FXSB 19-5239 & FXSB 19-5240
ANSI
D
PRELIMINARY
C-1
PROJECT LOCATION
SCHEDULE OF DRAWINGS
SHEET NUMBER SHEET TITLE
C-1 COVER SHEET
AD 100 DEMOLITION SHEET
A-100 REMODEL SHEET
1. CONTRACTOR SHALL FIELD VERIFY ALL DIMENSIONS.
2. AT NO TIME WILL THE CONTRACTORS WORK, STORAGE OF MATERIALS, PARKING OF VEHICLES OR OTHER ACTIVITIES BE ALLOWED TO INTERFERE WITH THE WORK ACTIVITIES OF GOVERNMENT PERSONNEL OR TO DAMAGE GOVERNMENT OR PRIVATE PROPERTY.
3. THE CONTRACTOR SHALL AT ALL TIMES KEEP THE WORK AREA FREE FROM ACCUMULATION OF WASTE MATERIALS. DEBRIS SHALL BE REMOVED ON A DAILY
BASIS.
4. ALL WELDING AND / OR THE USE OF FLAME PRODUCING DEVICES SHALL BE CLEARED THROUGH THE FIRE DEPARTMENT.
5. ALL CONSTRUCTION PERMITS, FEES AND COORDINATION OF ANCILLARY ITEMS SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR.
6. THE WORK OF THIS CONTRACT SHALL COMPLY WITH APPLICABLE FEDERAL, STATE AND LOCAL CODES OR STANDARDS, INCLUDING BUT NOT LIMITED TO:
ENVIRONMENTAL PROTECTION AGENCY, NATIONAL ELECTRICAL CODE, NATIONAL ELECTRICAL SAFETY CODE, NATIONAL FIRE PROTECTION ASSOCIATION, OSHA
STANDARDS, FIRE CODES, INTERNATIONAL BUILDING CODE.
PROJECT NOTES:
COVER SHEET
FA500021R0023-JBER MACC
A B C D E F G H
F I L
E
N
O
I
SHEET
REFERENCE
NUMBER
ANSI
D
AF PROJECT NUMBER:
AEC FILE NAME:
DRAWING SCALE:
D E
S C
R I P
T I O
N
R E
V I S
I O
N S
RICHARDSON, ALASKA
AF CONTRACT NUMBER:
FACILITY NO:
D A
T E
A P
P R
O V
E R
JOINT BASE ELMENDORF
PROJ. MGR:
DRAFTER:
CHECKER:
PROJ. ENGR:
DATE:
DATE:
DATE:
DATE:
DESIGNER LOGO
AIR FORCE
S Y
M B
O L
D A
T E
AD100
DEMOLITION
PLAN
REPAIR
RESTROOMS
AMS
13373
FXSB191080AD100
FXSB 21-1058
NTS
DEMOLITION FLOOR PLAN
KEY PLAN
PROJECT
LOCATION
DEMOLITION NOTES:
REMOVE EXISTING SINKS
REMOVE EXISTING TOILETS
REMOVE EXISTING URINALS.
REMOVE DOOR, FRAME AND HARDWARE.
REMOVE TOILET PARTITIONS.
REMOVE CEILING.
DEMO ELECTRICAL & PLUMBING ONLY AS NEEDED.
REMOVE COVE BASE
LEGEND:
DEMO PARTITION
DEMO DOOR.
DEMO TOILET.
DEMO URINAL
DEMO SINK
2 2
3 3
4 4
FA500021R0023-JBER MACC
Attachment 5-Seed Proj FXSB 21-1058
SOW SPECS DRAWINGS
AutoCAD SHX Text N
AutoCAD SHX Text N
AutoCAD SHX Text
BUILDING: 13373
AutoCAD SHX Text
FLOOR: 1
AutoCAD SHX Text
STORAGE FACILITY
AutoCAD SHX Text
BATHROOM
AutoCAD SHX Text
CLOSET
A B C D E F G H
F I L
E
N
O
I
SHEET
REFERENCE
NUMBER
ANSI
D
AF PROJECT NUMBER:
AEC FILE NAME:
DRAWING SCALE:
D E
S C
R I P
T I O
N
R E
V I S
I O
N S
RICHARDSON, ALASKA
AF CONTRACT NUMBER:
FACILITY NO:
D A
T E
A P
P R
O V
E R
JOINT BASE ELMENDORF
PROJ. MGR:
DRAFTER:
CHECKER:
PROJ. ENGR:
DATE:
DATE:
DATE:
DATE:
DESIGNER LOGO
AIR FORCE
S Y
M B
O L
D A
T E
A100
DEMOLITION
PLAN
REPAIR
RESTROOMS
AMS
13373
FXSB191080AD100
FXSB 21-1058
NTS
NEW REMODEL FLOOR PLAN
KEY PLAN
PROJECT
LOCATION
Ø5'
SINGLE
USE
UNISEX
MENS
CONSTRUCTION NOTES:
INSTALL SOLID CORE DOOR, STEEL FRAME, STAINLESS
HARDWARE, AND CLOSURE
INSTALL 1 ADA COMPLIANT TOILET
INSTALL 1 ADA COMPLIANT SINK
INSTALL 1 MEN'S SINK
INSTALL 2 EACH MEN'S TOILET AND STALL
INSTALL 2 URINALS
INSTALL COVE BASE
INSTALL FRP WALL COVERING FULL HEIGHT FROM FLOOR
TO CEILING
INSTALL NEW FINISHED CEILING WITH LED LIGHTING. PAINT
"MAX LOAD 20 PSF" ON TOP OF CEILING
ALL FIXTURES SHALL HAVE AUTOMATIC HARDWARE
CLEAN AND SEAL CONCRETE FLOOR
INSTALL SIGNS ON DOOR STATING RESTROOM USE TYPE
(MENS, SINGLE USE UNISEX, OR 673 CES APPROVED
EQUIVALENT)
INSTALL PRIVACY LOCK
INSTALL STOREROOM LOCK WITH BEST LOCKS MX8 CORE
INSTALL SIGN ON DOOR STATING "FAP INSIDE"
INSTALL SIGN ON WALL STATING "MAX LOAD 20 PSF"
FA500021R0023-JBER MACC
Attachment 5-Seed Proj FXSB 21-1058
SOW SPECS DRAWINGS
AutoCAD SHX Text N
AutoCAD SHX Text N
AutoCAD SHX Text
BUILDING: 13373
AutoCAD SHX Text
FLOOR: 1
AutoCAD SHX Text
STORAGE FACILITY
AutoCAD SHX Text
BATHROOM
AutoCAD SHX Text
CLOSET
P a c i f i c G e o B a s e T a b l o i d [ A N S I B - L a n d s c a p e ] P a c i f i c G e o B a s e T a b l o i d [ A N S I B - L a n d s c a p e ] µ
0.025 0 0.025 0.05 0.075 0.10.0125 mi
0.045 0 0.045 0.09 0.135 0.180.0225 km
UNCLASSIFIED // CONTROLLED UNCLASSIFIED INFORMATION
EXHIBIT DRAWING
FA500021R0023-JBER MACC
EXHIBIT DRAWING
FA500021R0023-JBER MACC
| 01020 SOW 20210414 |
| SECTION 1: SCOPE OF WORK |
| 9. FXSB 21-1058 Drawings |
| Sheets and Views |
| Cover Sheet |
| 2. Demo sheet 20210312.pdf |