Attachment 26 AF Form 66 Seed Proj FXSB 20-5254.pdf
PDF 657 KB Posted
- Attached to
- JBER MACC Federal contract opportunity
- Solicitation number
- FA500021R0023
About this file
This document is an AF Form 66 schedule of material submittals for a repair and alteration project at Joint Base Elmendorf-Richardson under the JBER MACC multiple award construction contract. Key submittals and deadlines include a construction schedule, health and safety plan, and QA/QC plan due 15 days after notice to proceed. Design drawings are due in three phases from 45 to 90 days after notice to proceed culminating in 100% design drawings. Other required submittals include demolition plans, elastomeric roofing, fiberglass grating, and painting plans due 45 days after notice to proceed. Electrical, fire alarm, and fire device submittals are due between 45 to 120 days after notice to proceed depending on the item. HAZMAT usage forms must be submitted 10 to 7 days in advance of materials arriving on site. Closeout documents such as O&M manuals, as-built drawings, and DD1354 forms are due between installation and 7 days after final completion.
View the file
Other files for this federal contract opportunity
Show all 44
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AF FORM 66, OCT 99 Previous Edition Will Be Used
LI
N
E N
U M
B ER Note: 3 copies required per submittal. Government will retain all submittals.Provide an electronic copy for each submittal.
C
ER
TI
F.
O F
C O
M
PL
IA
N
C E
SH
O
P D
R
AW
IN
G
S
C O
LO
R
S
EL
EC
TI
O N
M
AN
U
FA
TU
R
U R
'S R
EC
O
M M
EN
D
AT
C
AT
AL
O
G D
AT
A
O &M
R
EC
O M
M
EN
D
AT
IO
N
S
C
AL
C U
LA
TI
O N
S
W
AR
R
AN
TY
D R
AW
IN
G S
R
EP
O R
T
SA
FE
TY
D
AT
A
SH
EE
TS
O
TH
ER
TE
ST
R
ES
U
LT
S
R
EQ
U
IR
ED
S
U
BM
IS
SI
O N
D
AT
E
D
AT
E
TO
C O
N
TR
AC
TI
N G
D
AT
E
TO
C
IV
IL
E
N G
IN
EE
R
IN
G
R
ET
U R
N S
U
SP
EN
SE
D
AT
E
SU
BM
IT
TA
L N
U M
BE
R
S
AP
PR
O
VE
D
D
IS
AP
PR
O
VE
D
C O
N
TR
AC
TO
R S
U
BM
IT
TA
L
FI
N
AL
A
PP
R
O
VA
L
NOTES
GENERAL
1 Project Specific Form 66 X NTP + 15 2 Construction Schedule X NTP + 15 3 Contractor's Health, Safety, and Environment Plan X NTP + 15 4 Contractor's QA/QC Plan X NTP + 15 5 Material Safety Data Sheet (MSDS) X NTP + 15
6 Lead Based Paint Abatement Plan X See Notes LBP Abatement Plan must be submitted and approved by Government prior to start of abatement.
DESIGN
All submissions to be provided in hard copy and electronically (The electronic submission will include the *.CTB file and any other supporting file required to print the drawing correctly) and 100% Design Drawings to include:
X NTP + 90
(100%) All required disciplines
8 Plans, Elevations, Sections, Schedules, and Details -- 65% Design X NTP + 45 All required disciplines
9 Plans, Elevations, Sections, Schedules, and Details -- 95% Design X NTP + 75 All required disciplines
10 Plans, Elevations, Sections, Schedules, and Details -- 100% Design X NTP + 90 All required disciplines
11 Plans, Elevations, Sections, Details -- Shop Drawings X NTP + 120
DEMOLITION
12 Demolition Plan X X X NTP + 45
ARCHITECTURAL
13 Elastomeric Roofing X X X NTP + 45 14 Fiberglass Grating X X NTP + 45 15 Primer & Paint X X X NTP + 45
ELECTRICAL
16 Receptacles X NTP + 45 17 Cables (Electrical, Fire Alarm) X NTP + 45 18 Conduits (Electrical, Fire Alarm) X NTP + 45 19 Fire Alarm Devices (*All) X NTP + 45
20 Fire Device Test Results X See Notes
3 DAYS AFTER TEST *IF NEEDED DUE TO
DISTURBANCE OF EXISTING FIRE SYSTEM
HAZMAT
21 JBER HAZMAT Usage Tracking Form X See Notes NLT 10 working days prior to material being brought onto installation
SOLICITATION /CONTRACT NUMBERPROJECT NAME
REPAIR ALT CONTROL TOWER
FIRE-ELEC-GEN B11525
SCHEDULE OF MATERIAL SUBMITTALS
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
PROJECT NUMBER
FXSB 20-5254
FA500021R0023-JBER MACC
Attachment 26 - AF Form 66 Seed Proj FXSB 20-5254
AF FORM 66, OCT 99 Previous Edition Will Be Used
LI
N
E N
U M
B ER Note: 3 copies required per submittal. Government will retain all submittals.Provide an electronic copy for each submittal.
C
ER
TI
F.
O F
C O
M
PL
IA
N
C E
SH
O
P D
R
AW
IN
G
S
C O
LO
R
S
EL
EC
TI
O N
M
AN
U
FA
TU
R
U R
'S R
EC
O
M M
EN
D
AT
C
AT
AL
O
G D
AT
A
O &M
R
EC
O M
M
EN
D
AT
IO
N
S
C
AL
C U
LA
TI
O N
S
W
AR
R
AN
TY
D R
AW
IN
G S
R
EP
O R
T
SA
FE
TY
D
AT
A
SH
EE
TS
O
TH
ER
TE
ST
R
ES
U
LT
S
R
EQ
U
IR
ED
S
U
BM
IS
SI
O N
D
AT
E
D
AT
E
TO
C O
N
TR
AC
TI
N G
D
AT
E
TO
C
IV
IL
E
N G
IN
EE
R
IN
G
R
ET
U R
N S
U
SP
EN
SE
D
AT
E
SU
BM
IT
TA
L N
U M
BE
R
S
AP
PR
O
VE
D
D
IS
AP
PR
O
VE
D
C O
N
TR
AC
TO
R S
U
BM
IT
TA
L
FI
N
AL
A
PP
R
O
VA
L
NOTES
SOLICITATION /CONTRACT NUMBERPROJECT NAME
REPAIR ALT CONTROL TOWER
FIRE-ELEC-GEN B11525
SCHEDULE OF MATERIAL SUBMITTALS
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
PROJECT NUMBER
FXSB 20-5254
22 JBER HAZMAT Usage Tracking Form X See Notes NLT 7 working days after final acceptance 23 Environmental PreCON Checklist X NTP + 15
CLOSEOUT
24 O&M maintenance data and maintenance manuals & Manufacturer's Warranty for All Equipment Installed X X X Install + 5
25 As Builts (electronic in AutoCAD and hard copies on Mylar) X Final + 7
26 Completion of DD1354 X Final + 7
FA500021R0023-JBER MACC
Attachment 26 - AF Form 66 Seed Proj FXSB 20-5254
Submittal 1