About this file

This document is an AF Form 66 schedule of material submittals for a repair and alteration project at Joint Base Elmendorf-Richardson under the JBER MACC multiple award construction contract. Key submittals and deadlines include a construction schedule, health and safety plan, and QA/QC plan due 15 days after notice to proceed. Design drawings are due in three phases from 45 to 90 days after notice to proceed culminating in 100% design drawings. Other required submittals include demolition plans, elastomeric roofing, fiberglass grating, and painting plans due 45 days after notice to proceed. Electrical, fire alarm, and fire device submittals are due between 45 to 120 days after notice to proceed depending on the item. HAZMAT usage forms must be submitted 10 to 7 days in advance of materials arriving on site. Closeout documents such as O&M manuals, as-built drawings, and DD1354 forms are due between installation and 7 days after final completion.

View the file

Other files for this federal contract opportunity

Other files attached to JBER MACC, newest first.
File Type Posted
Attachment 29 QA CAO 7 Jul 21.xlsx XLSX spreadsheet
Solicitation Amendment FA500021R00230005 SF 30.pdf PDF
Solicitation Amendment FA500021R00230004 SF 30.pdf PDF
Attachment 28 SUPPLEMENTAL HAZMAT SPECS Seed Proj 20-5254.pdf PDF
Attachment 4 Seed Project FXSB 20-5254 Price Schedule.pdf PDF
Attachment 6 Seed Project FXSB 21-1058 Price Schedule.pdf PDF
Attachment 27 AF Form 66 Seed Proj FXSB 21-1058.pdf PDF
Attachment 29 QA CAO 24 Jun 21.xlsx XLSX spreadsheet
Attachment 2 MACC SOW(CAO 25 June 21).pdf PDF
Attachment 5 Seed Proj FXSB 21-1058 SOW SPECS DRAWINGS.pdf PDF
Attachment 24 FOPR-Seed Project FXSB 21-1058.pdf PDF
Attachment 25 Seed Proj FXSB 20-5254 EXHIBITS 09-JUN-2021.pdf PDF
Attachment 17 Teaming consent 20201208.pdf PDF
Attachment 23 FOPR-Seed Project FXSB 20-5254.pdf PDF
Solicitation Amendment FA500021R00230001 SF 30.pdf PDF
Solicitation Amendment FA500021R00230003 SF 30.pdf PDF
Solicitation Amendment - FA500021R00230002.pdf PDF
Solicitation Amendment FA500021R00230002 (Summary of Changes).pdf PDF
Amendment 2 Attachment 1 - Site Visit Sign in Sheets FXSB 20-5254 and 21-1058.pdf PDF
Attachment 5 Seed Proj FXSB 21-1058 SOW SPECS DRAWINGS v2.pdf PDF
Solicitation Amendment No. 1_FA500021R00230001.pdf PDF
Attachment 1 Wage Determination.pdf PDF
Attachment 2 MACC SOW(CAO 3 May 21).pdf PDF
Attachment 8 Past Performance Tabs A-B 20210401.xlsx XLSX spreadsheet
Attachment 13 JBER Richardson IFS_PreFinal.pdf PDF
Attachment 15 JBER Hazardous Waste Management Plan - 7 May 2020.pdf PDF
Attachment 19 NAFI General Provisions and Clauses.pdf PDF
Attachment 18 DD1354 _ FILLABLE Template _ AUG2013.pdf PDF
Solicitation - FA500021R0023.pdf PDF
Attachment 3 Seed Proj FXSB 20-5254 SOW SPECS DRAWINGS.pdf PDF
Attachment 5 Seed Proj FXSB 21-1058 SOW SPECS DRAWINGS.pdf PDF
Attachment 6 Seed Project FXSB 21-1058 Price Schedule.pdf PDF
Attachment 7 PPQ 20210113.pdf PDF
Attachment 9 673ABW3 Dig Permit (2020 Version).pdf PDF
Attachment 11 Weather Data.pdf PDF
Attachment 12 JBER Telecommunications Installation Standards18DEC2018.pdf PDF
Attachment 16 Contractors Fire Safety Guide.pdf PDF
Attachment 20 ENV_PRECON Checklist_2020.pdf PDF
Attachment 21 REVISED JBER CAD GIS RECORD DRAWING DESIGN AND AS BUILT STANDARD Dec 2019.pdf PDF
Attachment 22 PPCL 20210519.pdf PDF
Attachment 4 Seed Project FXSB 20-5254 Price Schedule.pdf PDF
Attachment 14 JBER Richardson IFS_Pre-Final.pdf PDF
Attachment 17 Teaming consent 20201208.pdf PDF
Attachment 10 Financial Data Form 20201208.pdf PDF
Show all 44

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AF FORM 66, OCT 99 Previous Edition Will Be Used

LI

N

E N

U M

B ER Note: 3 copies required per submittal. Government will retain all submittals.Provide an electronic copy for each submittal.

C

ER

TI

F.

O F

C O

M

PL

IA

N

C E

SH

O

P D

R

AW

IN

G

S

C O

LO

R

S

EL

EC

TI

O N

M

AN

U

FA

TU

R

U R

'S R

EC

O

M M

EN

D

AT

C

AT

AL

O

G D

AT

A

O &M

R

EC

O M

M

EN

D

AT

IO

N

S

C

AL

C U

LA

TI

O N

S

W

AR

R

AN

TY

D R

AW

IN

G S

R

EP

O R

T

SA

FE

TY

D

AT

A

SH

EE

TS

O

TH

ER

TE

ST

R

ES

U

LT

S

R

EQ

U

IR

ED

S

U

BM

IS

SI

O N

D

AT

E

D

AT

E

TO

C O

N

TR

AC

TI

N G

D

AT

E

TO

C

IV

IL

E

N G

IN

EE

R

IN

G

R

ET

U R

N S

U

SP

EN

SE

D

AT

E

SU

BM

IT

TA

L N

U M

BE

R

S

AP

PR

O

VE

D

D

IS

AP

PR

O

VE

D

C O

N

TR

AC

TO

R S

U

BM

IT

TA

L

FI

N

AL

A

PP

R

O

VA

L

NOTES

GENERAL

1 Project Specific Form 66 X NTP + 15 2 Construction Schedule X NTP + 15 3 Contractor's Health, Safety, and Environment Plan X NTP + 15 4 Contractor's QA/QC Plan X NTP + 15 5 Material Safety Data Sheet (MSDS) X NTP + 15

6 Lead Based Paint Abatement Plan X See Notes LBP Abatement Plan must be submitted and approved by Government prior to start of abatement.

DESIGN

All submissions to be provided in hard copy and electronically (The electronic submission will include the *.CTB file and any other supporting file required to print the drawing correctly) and 100% Design Drawings to include:

X NTP + 90

(100%) All required disciplines

8 Plans, Elevations, Sections, Schedules, and Details -- 65% Design X NTP + 45 All required disciplines

9 Plans, Elevations, Sections, Schedules, and Details -- 95% Design X NTP + 75 All required disciplines

10 Plans, Elevations, Sections, Schedules, and Details -- 100% Design X NTP + 90 All required disciplines

11 Plans, Elevations, Sections, Details -- Shop Drawings X NTP + 120

DEMOLITION

12 Demolition Plan X X X NTP + 45

ARCHITECTURAL

13 Elastomeric Roofing X X X NTP + 45 14 Fiberglass Grating X X NTP + 45 15 Primer & Paint X X X NTP + 45

ELECTRICAL

16 Receptacles X NTP + 45 17 Cables (Electrical, Fire Alarm) X NTP + 45 18 Conduits (Electrical, Fire Alarm) X NTP + 45 19 Fire Alarm Devices (*All) X NTP + 45

20 Fire Device Test Results X See Notes

3 DAYS AFTER TEST *IF NEEDED DUE TO

DISTURBANCE OF EXISTING FIRE SYSTEM

HAZMAT

21 JBER HAZMAT Usage Tracking Form X See Notes NLT 10 working days prior to material being brought onto installation

SOLICITATION /CONTRACT NUMBERPROJECT NAME

REPAIR ALT CONTROL TOWER

FIRE-ELEC-GEN B11525

SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

PROJECT NUMBER

FXSB 20-5254

FA500021R0023-JBER MACC

Attachment 26 - AF Form 66 Seed Proj FXSB 20-5254

AF FORM 66, OCT 99 Previous Edition Will Be Used

LI

N

E N

U M

B ER Note: 3 copies required per submittal. Government will retain all submittals.Provide an electronic copy for each submittal.

C

ER

TI

F.

O F

C O

M

PL

IA

N

C E

SH

O

P D

R

AW

IN

G

S

C O

LO

R

S

EL

EC

TI

O N

M

AN

U

FA

TU

R

U R

'S R

EC

O

M M

EN

D

AT

C

AT

AL

O

G D

AT

A

O &M

R

EC

O M

M

EN

D

AT

IO

N

S

C

AL

C U

LA

TI

O N

S

W

AR

R

AN

TY

D R

AW

IN

G S

R

EP

O R

T

SA

FE

TY

D

AT

A

SH

EE

TS

O

TH

ER

TE

ST

R

ES

U

LT

S

R

EQ

U

IR

ED

S

U

BM

IS

SI

O N

D

AT

E

D

AT

E

TO

C O

N

TR

AC

TI

N G

D

AT

E

TO

C

IV

IL

E

N G

IN

EE

R

IN

G

R

ET

U R

N S

U

SP

EN

SE

D

AT

E

SU

BM

IT

TA

L N

U M

BE

R

S

AP

PR

O

VE

D

D

IS

AP

PR

O

VE

D

C O

N

TR

AC

TO

R S

U

BM

IT

TA

L

FI

N

AL

A

PP

R

O

VA

L

NOTES

SOLICITATION /CONTRACT NUMBERPROJECT NAME

REPAIR ALT CONTROL TOWER

FIRE-ELEC-GEN B11525

SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

PROJECT NUMBER

FXSB 20-5254

22 JBER HAZMAT Usage Tracking Form X See Notes NLT 7 working days after final acceptance 23 Environmental PreCON Checklist X NTP + 15

CLOSEOUT

24 O&M maintenance data and maintenance manuals & Manufacturer's Warranty for All Equipment Installed X X X Install + 5

25 As Builts (electronic in AutoCAD and hard copies on Mylar) X Final + 7

26 Completion of DD1354 X Final + 7