This is a Task Assignment (TA) document issued under Florida Department of Environmental Protection (FDEP) Contract Number HW687 between the State of Florida and Terracon Consultants, Inc. The task assignment is designated as CSS03B and pertains to site investigation activities at the Former Cal-Spray Chemical Co. facility located at 1715 Silver Star Road, Orlando, Orange County, Florida (Site ID: ERIC_18464). The work is being conducted using federal funds from the CERCLA Site Screening Program (CSS) cooperative agreement administered by DEP on behalf of the Environmental Protection Agency (EPA). The Department Project Manager is Claire Field, and Terracon's Project Manager is Ralph Mongillo.
Terracon Consultants, Inc. will conduct a CERCLA Site Inspection event and generate a Site Inspection Report in accordance with the cost proposal submitted March 14, 2025, revised March 20, 2025. The contract is structured as a fixed unit rate with a total task assignment value of $48,751.83. Work is divided into four subtasks: Subtask 1 (Project Management) at $2,042.49; Subtask 2 (Site Investigation Activities) at $41,491.21; Subtask 3 (IDW Management) at $609.40; and Subtask 4 (Site Inspection Report) at $4,608.73. The scope includes conducting soil borings, installing temporary monitoring wells, collecting soil and groundwater samples, managing investigative derived waste, and preparing a final Site Inspection Report. Deliverables include field notes, lithological logs, well installation logs, photolog, and chain of custody documentation due by May 2, 2025, with the final Site Inspection Report due by June 2, 2025. The task assignment is effective through September 2, 2025.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number) Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
Additional signatures attached on separate page.
HW687
CSS03B Completion September 2, 2025
Terracon Consultants, Inc. will conduct a CERCLA Site Inspection event, and generate a Site Inspection (SI) Report in accordance with the Cost Proposal/Level of Effort (CP/LOE) submitted on March 14, 2025, revised March 20, 2025.
Claire Field 8502458970 Contractor Terracon Consultants, Inc. Contractor
Contractor Ralph Mongillo Contractor (904) 479-7415
ERIC_18464
1715 Silver Star Road, Orlando, Orange County, Florida
Former Cal-Spray Chemical Co.
Contractor Contractor
✔ $ 48,751.83
$ 48,751.83
Scope of Work
Terracon Consultants, Inc.
Contractor Donna Cline
Senior Associate
3/24/2024
Digitally signed by Cline, Donna L DN: cn=Cline, Donna L, ou=General Users, email=Donna.Cline@terracon.com Date: 2025.03.24 10:03:31 -04'00'
Cline, Donna L
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2025.03.21 16:35:45 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WC TAFORM
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Site Inspection Report and Project Management (Subtask 1 & 4) 06/02/2025
Field Notes, lithological logs, well installation logs, photolog, and chain of custody documentation (Subtask 2) 05/02/2025
Confirmation of IDW Management (Subtask 3) 05/23/2025
Department Approval of Site Inspection Report and Project Management (Subtask 1 & 4) $ 6,651.22
Department Approval of Field Notes, lithological logs, well installation logs, photolog, and chain of custody documentation (Subtask 2) $ 41,491.21
Department Approval of Confirmation of IDW Management (Subtask 3) $ 609.40
$ 48,751.83
HW687
CSS03B
RRonn DDeSantiss Governor
AAlexiss A.. Lambert Secretary
Memorandum
TO:
FROM:
SUBJECT:
FFLORIDAA DEPARTMENTT OFF
Environmentall Protectionn
DATE:
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Terracon Consultants, Inc. HW687 Contract File
Claire Field, Contract Manager
March , 2025
Negotiation Summary – Task Assignment (TA) CSS03B Former Cal- Spray Chemical Co. - Site ID # ERIC_18464 Site Inspection Activities
This Task Assignment (TA) is intended for the preparation of conducting a CERCLA Site Screening event including field work, and a Site Inspection report for the Former Cal-Spray Chemical Co. The services are being conducted using federal funds from the CERCLA Site Screening Program (CSS) cooperative agreement that is administered by DEP on behalf of EPA.
Subtask 1: Project Management This subtask is a percentage of the overall project and has been negotiated as a contract rate. It includes project management, overhead, general, administrative, and fringe. The agreed upon cost of this subtask is $2,042.49.
Subtask 2:
This subtask includes pre- and post-drilling meetings, labor hours, travel, equipment costs, and subcontractor costs associated with the soil and groundwater sampling. Deliverables of this subtask include field notes, lithological logs, well installation logs, photolog, and chain of custody documentation, subcontractor receipts, and waste manifests from SI activities. The agreed upon cost of this subtask is $41,491.21.
Subtask 3: IDW Management This subtask includes labor hours and vehicle cost to identify IDW disposal costs after sampling and laboratory results have been received to determine if IDW is hazardous or non-hazardous.
The agreed upon cost of this subtask is $609.40.
www.FloridaDEP.gov
Negotiation Summary – Task Assignment (TA) CSS03B Former Cal-Spray Chemical Co. ERIC_18464, Orlando, Orange County Site Inspection Activities and Report May 2025
Subtask 4: Reporting This subtask includes labor hours associated with the preparation of Data Summary Tables/Figures and the SI Report. The deliverable will document field and laboratory findings to include soil and groundwater sampling forms, and soil and groundwater analytical results (tabulated and figures). Deliverables of this subtask will include both the Data Summary Tables/Figures and the SI Report. The agreed upon cost of this subtask is $4,608.73.
Summary DEP’s CSS Project Manager and Terracon’s Project Manager have both agreed to the scope of work and associated costs. The final cost associated with this TA is $48,751.83. Documentation of these costs is included in the Level of Effort/Cost Proposal (LOE-CP) Form and LOE-CP letter provided by Terracon on , as well as the Task Assignment Form for CSS03B prepared by DEP. The final deliverable must be received by DEP no later than September 2, 2025.
www.FloridaDEP.gov
FDEP COST ESTIMATE
Contractor: Terracon HW687
PEQ257126
Task #: SubTask 1 Project Management
Site: Former Cal-Spray Chemical Co. SubTask 2 Site Investigation Activity/Phase: SI and SIR SubTask 3 IDW Management
Project Manager: Claire Field SubTask 4 Site Inspection Report SubTask 5
Totals 1 2 3 4 5 Labor Rate Category
$29.47 Project Manager Nicole Kovach 23.14 23.14 $78.85 Senior Geolgist Tom Lewis 2.00 0.00 0.00 2.00 0.00 $26.75 CADD Specialist Cali Mays 6.00 0.00 0.00 6.00 0.00 $29.10 Environmental Technician Pat Beers 39.50 37.50 2.00 0.00 0.00 $29.47 Staff Scientist Nicole Kovach 58.00 38.00 0.00 20.00 0.00 $70.14 Senior Engineer Donna Cline 29.50 19.00 1.50 9.00 0.00
Total Hours 158.14 23.14 94.50 3.50 37.00 0.00
Direct Labor $5,928.03 $681.99 $3,543.77 $163.41 $1,538.86 $0.00
Overhead 116.00% $6,876.52 $791.11 $4,110.77 $189.56 $1,785.08 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 56.263% $3,335.29 $383.71 $1,993.83 $91.94 $865.81 $0.00 Total Labor $16,139.84 $1,856.81 $9,648.37 $444.91 $4,189.75 $0.00
Travel Vehicle charge $920.00 800.00$ 120.00$ $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $222.00 222.00$ $0.00 $0.00 $0.00 Total Travel $1,142.00 $1,022.00 $120.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (DPT) - Action Environmental $8,030.00 8,030.00$ $0.00 $0.00 $0.00
IDW (WCD) $0.00 $0.00 $0.00 $0.00 $0.00
Geophysical - GPRS $700.00 700.00$ $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 Subcontractor Subtotal $8,730.00 $8,730.00 $0.00 $0.00 $0.00 Handling Fee $873.00 $873.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $9,603.00 $9,603.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $18,004.00 $18,004.00 $0.00 $0.00 $0.00 Sample Shipping $300.00 $300.00 $0.00 $0.00 $0.00 Total Laboratory $18,304.00 $18,304.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $300.00 300.00$ $0.00 $0.00 $0.00 Expendables $146.00 146.00$ $0.00 $0.00 $0.00 Equipment (Drilling related) $48.00 48.00$ $0.00 $0.00 $0.00 Equipment (Analytical related) $1,230.00 1,230.00$ $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $225.00 225.00$ $0.00 $0.00 $0.00 Total Field Expenses $1,949.00 $1,949.00 $0.00 $0.00 $0.00
Subtotal $47,137.84 $1,856.81 $40,526.37 $564.91 $4,189.75 $0.00 Completion Fee $1,613.99 $185.68 $964.84 $44.49 $418.98 $0.00
Total Estimated Cost $48,751.83 $2,042.49 $41,491.21 $609.40 $4,608.73 $0.00
REV: 02/03 CEF TERRACON Page 1
Date: 3/21/2025
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Former Cal-Spray Chemical Co.
SUBTASK 2: Site Investigation
PROPOSAL NO. PEQ257126
DATE: 3/21/2025
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
PreTask Planning / Meeting / GPR Oversight / Prepare final Trip Report Senior Engineer DC 4.0
Staff Scientist NK 1.0 Senior Engineer DC 4.0 Staff Scientist NK 2.0
Field Activities - Soil Sampling and Temporary Well Installation (Driller estimated 1.5 day) Senior Engineer DC Kickoff meeting, project oversight and direct work logistics (2 hrs/day) 4.00 Staff Scientist PB Load/unload equipment (1 hr/day) 1.00 Staff Scientist NK Oversight and documentation of well installation, record lithological descriptions 15.00 Environmental Technician PB Collect soil samples for analysis during well installation 15.00 Environmental Technician PB Collect QA samples Staff Scientist NK Utilize Level C PPE to collect soil samples from below the floor slab 2.00 Environmental Technician PB Utilize Level C PPE to collect soil samples from below the floor slab (buddy system) 2.00 Environmental Technician PB Survey top of casing elevation at completion of temporary well installation 1.50 Environmental Technician NK Assist with surveying of temporary well installation 1.50 Environmental Technician NK GPS locations 1.00 Senior Engineer DC QA/QC of procedures and finalize field notes/lithological logs and survey at end of day (0.5 hr/day) 1.00
Field Activities - Temporary and Permanent Monitoring Well Sampling Environmental Technician PB Load/unload equipment (1 hr/day) 1.00 Environmental Technician PB DTW collection (10 minutes/well, 9 wells) 1.50 Environmental Technician PB Purge and groundwater sampling 5 monitoring wells (1.5 hours/well), includes equipment calibration 7.50 Staff Scientist NK Purge and groundwater sampling 4 monitoring wells (1.5 hours/well), includes equipment calibration 6.00 Senior Scientist/Geologist DC QA/QC of procedures and finalize field notes and groundwater sampling logs 2.00 Environmental Technician PB IDW staging, IDW sample collection (1 soil and 1 water drum) 1.50 Staff Scientist NK IDW staging, IDW sample collection (1 soil and 1 water drum) 1.50
Field Activities - Temporary Monitoring Well Abandonment Environmental Technician PB Oversee Florida liscened driller properly abandon the temporary monitoring wells 2.50
Mobilization / Demobilizations Senior Scientist/Geologist DC Preconstruction meeting (4 hour/day) 4.00 Staff Scientist NK Preconstruction meeting/oversee TMW install/ soil sampling/TOC survey (4 hour/event [overnight]) 4.00 Environmental Technician PB Oversee TMW install/ soil sampling/TOC survey (1 hour/day, 2 days) 2.00 Staff Scientist NK DTW, survey TOC, groundwater Sampling (4 hour/day) 4.00 Environmental Technician PB DTW, survey TOC, groundwater Sampling (1 hour/day) 1.00 Environmental Technician PB Oversee well abandonment (1 hour/day) 1.00
Personnel: DC NK PB Hours: 19.00 38.00 37.50 TOTAL LABOR 94.50
VEHICLE TYPE RATE UNIT USEAGE
Auto (Senior Engineer) 80.00$ day 1 80.00$ Truck (Staff Scientist) 120.00$ day 3 360.00$ Truck (Environmental Technician) 120.00$ days 3 360.00$
TOTAL VEHICLE 800.00$
PER DIEM STAFF RATE UNIT USEAGE
Per diem NK 36.00$ 2 72.00$ Hotel NK 150.00$ 1 150.00$
TOTAL PER DIEM 222.00$
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE
PreTask Field Planning, Site Safety, Schedule/Coordinate with Owner & FDEP lab, coordinate with GPR subcontractor, prepare soil boring logs, monitoring well construciton and development and groundwater sampling logs. Prepare for Level C soil sampling, acquiring necessary PPE.
Prepare trip report of field investigation activities at completion of work.
PreTask Meeting and flag soil boring location and oversight of GPRS PreTask meeting with owner, driller, geophysical subcontractor and FDEP (same day as drilling0
SUBTASK 2: Site Investigation
PROPOSAL NO. PEQ257126
DATE: 3/21/2025
GPRS 700.00$ lump sum 0 700.00$ Action Environmental 8,030.00$ lump sum 0 8,030.00$
TOTAL SUBCONTRACTOR 8,730.00$
PARAMETER RATE # SAMPLES IDW Units
Soil Analysis Total VOCs (PID/Hall Series) EPA 8260 110.00$ 19 2 $2,310.00 Total VOCs Prep EPA Method 5035 prep 7.00$ 19 2 $147.00 Organochlorine hydrocarbons EPA Method 8081 105.00$ 19 2 $2,205.00 Organo - N/P EPA Method 8141 170.00$ 19 2 $3,570.00 RCRA 7 EPA Method 6020 98.00$ 19 2 $2,058.00 RCRA Mercury EPA Method 7470/7471 28.00$ 19 2 $588.00 Sample Shipping Large Cooler (overnight) 150.00$ 1 $150.00 Groundwater Analysis $0.00 Total VOCs (PID/Hall Series) EPA 8260 110.00$ 13 1 $1,540.00 Organochlorine hydrocarbons EPA Method 8081 105.00$ 13 1 $1,470.00 Organo - N/P EPA Method 8141 170.00$ 13 1 $2,380.00 RCRA 7 EPA Method 6020 98.00$ 13 1 $1,372.00 RCRA Mercury EPA Method 7470/7471 26.00$ 13 1 $364.00 Sample Shipping Large Cooler (overnight) 150.00$ 1 $150.00
TOTAL LAB $18,304.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Personnel Protection Level C 150.00$ Units-per man day 2 300.00$ Expendables Expendables 40.00$ day 3 120.00$
Ice (preservation of samples/2 per day 6.50$ day 4 26.00$ Equipment (Soil/drilling) 12.00$ day 4 48.00$
11.00$ each 10 110.00$ 16.00$ day 10 160.00$
Equipment (Analytical) Monitoring Well Installation Kit 325.00$ day 2 650.00$ Shallow Groundwater Sampling Kit 290.00$ day 2 580.00$
IDW related (Drums provided by Driller) each 0
Equipment (other) Total Survey Station 50.00$ day 1 50.00$
GPS, Trimble 175.00$ day 1 175.00$
TOTAL EQUIPMENT 2,219.00$
Terra Core Sampler Encore Sampler
Hand auger (2 sets per day)
Geophysical Survey Installation of temporary monitoring wells, including well abandonment
TCLP/SPLP analysis will be submitted as WCD if required.
SUBTASK 3: IDW Management
PROPOSAL NO. PEQ257126
DATE: 3/21/2025
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
IDW Management Senior Engineer DC 1.50 Environmental Technician PB 2.00
Personnel: DC PB Hours: 1.50 2.00 TOTAL LABOR 3.50
VEHICLE TYPE RATE UNIT USEAGE
Truck (Environmental Technician) 120.00$ days 1 120.00$
TOTAL VEHICLE 120.00$
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE
IDW Contractor Work Change Directive
TOTAL SUBCONTRACTOR -$
LABORATORY COSTS
PARAMETER RATE # SAMPLES IDW QA/QC
Soil VOCs - Halocarbons EPA 8260 -$ 8 0 $0.00 IDW Encore Sampler -$ 8 $0.00 Soil VOCs - Halocarbons EPA 8260 -$ 5 0 $0.00
Sample Shipping Small Cooler (overnight) -$ $0.00
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Personnel Protection Level C 150.00$ Unit-per man day 0 -$ Expendables Expendables 40.00$ day 0 -$
Terra Core Sampler 11.00$ each 0 -$ IDW No IDW drummed each 0 Drilling Monitoring Well Installation Kit 325.00$ day 0 -$ Analytical Shallow Groundwater Sampling Kit 290.00$ day 0 -$
Tubing, HDPE 0.30$ ft 0 -$ Tubing, silicon (3/16 x 3/8) 5.00$ ft 0 -$
Other Total Survey Station 50.00$ day 0 -$
TOTAL EQUIPMENT -$
Prepare waste characterization/Generator Profile Coordinate IDW T&D: Mobilize to site, meet transporter to sign manifests
Note all analytical samples will be analyzed by the FDEP Laboratory.
IDW Disposal of drums decon water, purgewater, drill cuttings)
SUBTASK 4: Site Inspection Report
PROPOSAL NO. PEQ257126
DATE: 3/21/2025
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Staff Scientist NK 12.00 Staff Scientist NK 8.00 Senior Scientist/Geologist DC QA/QC field and laboratory data 2.00 Senior Scientist/Geologist DC Soil and Water Quality Parameters Summary Evaluation 2.00 Senior Scientist/Geologist DC Groundwater Analytical Results and Summary Evaluation 3.00 Senior Geologist DC Evaluate background calculations, cleanup target levels 2.00 Senior Geologist TL Provide conclusions, recommendation, Sign and Seal Investigation Report 2.00 CADD Specialist CM 6.00
Personnel: NK DC TL CM Hours: 20.00 9.00 2.00 6.00 TOTAL LABOR 37.00
Prepare draft summary tables and draft drawing for GIS Summarize field data and tabulate analytical data, prepare draft Exhibits
Prepare Exhibits (site setting, groundwater flow and concentrations maps and concentration maps, various Contaminants of Concern)
8001 Baymeadows Way, Suite 1 Jacksonville, FL 32256
P (904) 479-7415 Terracon.com
March 20, 2025
Florida Department of Environmental Protection CERCLA Site Screening Section Division of Waste Management 2600 Blair Stone Road Tallahassee, Florida 32399-2400
Attn: Ms. Claire Field, CERCLA Site Manager E: Claire.Field@FloridaDEP.gov W: 850-245-8970
Re: Proposal for Field Sampling Plan, Site Investigation and Reporting Former Cal-Spray Chemical Co.
1715 Silver Star Road Orlando, Orange County, Florida 32806
ERIC_18464
Task Assignment HW687 CSS03B Terracon Proposal No. PEQ257126
Dear Ms. Field:
Terracon Consultants, Inc. (Terracon) appreciates the opportunity to submit this proposal to the Florida Department of Environmental Program (FDEP) CERCLA Site Screening Section to prepare a perform site investigation (SI) activities and prepare a Site Inspection Report (SIR) pursuant to the approved Field Sampling Plan for the Former Cal-Spray Chemica Co. (ERIC_18464) facility located at 1715 Silver Star Road, Orlando, Orange County, Florida.
Scope of Services
Review the approved Field Sampling Plan (FSP) and Health and Safety Plan
Field preparation and oversite of geophysical investigation.
Mobilize to site and advance 8 soil borings with soil sampling and the installation of six shallow temporary monitoring wells to a depth of 12 feet below ground surface (bgs).
Collect soil samples 0-1, and 1-2 feet bgs from each soil boring and submit for laboratory analysis for volatile organic compounds (VOCs), organochlorine pesticides (OCPs), insecticides/herbicides and 8-RCRA metals
Perform groundwater sampling at the six temporary monitoring wells and the three existing monitoring wells for laboratory analysis of VOCs, OCPs, insecticide/herbicide and 8-RCRA metals, survey elevation of top of casings, and document water levels from the six temporary monitoring wells: MW001, MW002, MW003, MW004, MW005 and MW006 and the three permanent monitoring wells (MW012, MW011 and MW016). The temporary monitoring wells will be abandoned after groundwater activities are completed.
Proposal for Site Investigation and Reporting Former Cal-Spray Chemical Co., ERIC_18464 Orlando, FL March 20, 2025 Terracon Proposal No. PEQ257126
The investigative derived waste (soil and groundwater) will be containerized in 55-gallon drums and sampled for characterization once sampling is complete.
Review data and prepare the Site Inspection Report (SIR).
See attached LOE for details
Schedule
Deliverable of field notes, lithological logs, well installation logs, photolog, and chain-of-custody documentation within 5 business day of completion of field work.
Deliverable of SIR within 20 business days following receipt of laboratory results.
Compensation See attached CEF for details.
SCOPE OF SERVICES
Subtask 1: Project Management This scope is provided for in the template worksheets for project management.
Subtask 2: Site Investigation Terracon will coordinate a pre-drilling meeting with owner, drillers, geophysical survey subcontractor, and the FDEP.
Oversight of geophysical survey subcontractor Geoview for private utility locates.
Collection of soil samples at eight locations with sampling intervals of 0 to 1 feet below ground surface (bgs) and 1 to 2 feet bgs. Samples are to be submitted to the FDEP Laboratory for analysis for volatile organic compounds (VOCs) by EPA Method 8260, organochlorine pesticides (OCPs) by EPA Method 8081, insecticides/herbicides by EPA Method 8321B and 8- RCRA metals by EPA Method 6020/7471.
Supervise the installation of six temporary shallow monitoring wells at the soil boring locations; the temporary wells are constructed to 14 feet bgs, with 10 feet of 0.006-slotted prepacked screen and 30/65 silica sand.
Drilling services are provided by JAEE using direct push technology and hollow stem auger installation.
Terracon will create an arbitrary datum to survey the temporary monitoring well and the permanent monitoring well top of casings to provide groundwater elevation data and to assess groundwater flow direction.
Collection of depth to groundwater at the six temporary monitoring wells and 3 permanent monitoring wells to provide groundwater elevation data and evaluate shallow groundwater flow direction.
Collection of 6 groundwater samples from the temporary monitoring wells and an additional 3 groundwater samples from the three permanent monitoring wells for VOCs by EPA Method 8260, OCPs by EPA Method 8081, insecticides/herbicides by EPA Method 8321B and 8-RCRA metals by EPA Method 6020/7471. Groundwater sampling will occur a minimum of 24 hours after the temporary monitoring wells installation. The groundwater samples will be submitted to the FDEP Laboratory for analysis.
IDW generated from drilling and groundwater sampling activities will be collected and staged onsite in FDOT approved 55-gallond drums. Once field sampling is complete, samples will be collected from the IDW drums for waste characterization.
Proposal for Site Investigation and Reporting Former Cal-Spray Chemical Co., ERIC_18464 Orlando, FL March 20, 2025 Terracon Proposal No. PEQ257126
Once the IDW waste characterization laboratory results are received, and assessed whether hazardous or non-hazardous, then Terracon will solicit bids for IDW disposal.
Subtask 4: Prepare Site Inspection Report (SIR) Preparation of a SIR to include an evaluation of soil and groundwater data, establish site-specific background screening concentrations for soil and groundwater under investigation and compare environmental sample data results to USEPA and FDEP Cleanup Target Levels (CTLs).
SCHEDULE
Deliverable of field notes, lithological logs, well installation logs, groundwater sampling logs, photolog, and chain-of-custody documentation within 5 business days of completion of field work.
Deliverable of SIR within 20 business days following receipt of laboratory results.
CLOSING REMARKS
Terracon services will be conducted in accordance with the terms and conditions, contained within DEP Waste Cleanup Program (WCP) Contract No. HW687, executed January 5, 2022. It is understood that a Task Assignment will be issued to authorize us to perform this work.
We appreciate the opportunity to provide this proposal and look forward to working with you on this project. If you should have any questions or comments regarding this proposal, please contact either of the undersigned at (904) 470-2233 and (904) 479-7415.
Sincerely, Terracon Consultants, Inc.
Nicole Kovach Donna Cline, P.E.
Staff Scientist Senior Associate / Remediation Engineer
Attachments: Cost Spreadsheet Level of Effort
Subcontractor Quotes
TERRACON -
DENVER
Scope of Work
Equipment
Project Costs
General Terms & Conditions
Accepted and Agreed
Project-Speci c Assumptions
TOTAL NO. DAYS 1.5 TOTAL 8,030.00$ TOTAL $12,100.00 TOTAL $13,040.00
Low Bid: Action Environmental
General Information: Terracon is soliciting quotes from three (3) Florida licensed well contractors, on behalf of the FDEP , for the following scope of services. The driller will be responsible for all necessary permits, public utility locates, equipment and personnel to complete this scope of work. The driller should be aware that changes in scope may occur once the work has begun.
Scope of Work: Installation of six (6) soil borings/TMW advanced to 14 feet bgs using DPT installation. Soil samples collected from two intervals (0–1 foot bgs and 1-2 feet bgs).
TMW will be installed at each location with 10 feet of 0.006-inch slotted, prepacked screen and 30/65 silica sand.
Decontamination: All downhole tools will be decontaminated prior to and between each sample interval location (i.e. every foot during hand auger advancement and every five feet during macrocore advancement). Specific decontamination procedures include alconox scrub and steam wash applies for all drilling equipment and downhole tools (e.g., tremie pipe, hoses). Decontamination fluids and solids will be containerized separately. Offeror’s equipment shall arrive clean and free of soil or dirt from its previous work location.
Investigation Derived Waste (IDW) and Trash: Soil cuttings, decontamination water and solids, and development water (IDW) generated during well installation will be drummed. The Driller will supply a sufficient number of FDOT-approved 55-gallon steel drums to contain all IDW generated during site activities.
The Offeror will be required to consolidate the IDW drums into one central location.
Drilling Conditions: The site is not an active facility. Some vagrant activity in the area. It should be assumed that potable water and electricity are not available.
The depth to water is estimated at 6.0 feet bgs.
Health and Safety: Work is expected to be performed in Level D personal protective equipment. The primary contaminants of concern at the site are organochlorine pesticides. Proper safety procedures to minimize contact with contaminated site media is required. Site personnel are required to be 40-hour OSHA trained.
Line items will be invoiced based upon actual quantities/depths completed in the field.
TERRACON 2/28/2025
8001 Baymeadows Way, Suiote 1 199753 Jacksonville, Fl 32256
Project Name Commerciaol Site - Orlando, FL
Nicole Kovach Project Address 1715 Silver Star Road nicole.kovach@terracon.com Project City Orlando 407-770-9050 Project State Fl
Project Zip 32804
Cascade Rep Contact Information
Scope of Work
Quantity Unit Sales Price Subtotal
1 Lump Sum 1,300.00$ 1,300.00$
1 Lump Sum 1,300.00$ 1,300.00$
3 Day 2,250.00$ 6,750.00$
3 Day 450.00$ 1,350.00$
17 Each 4.00$ 68.00$
84 Foot 50.00$ 4,200.00$
6 Each 150.00$ 900.00$ 6 Each 70.00$ 420.00$ 12 Each 85.00$ 1,020.00$ 1 Lump Sum 70.00$ 70.00$
Pre-Tax Total
Tax Percentage
Taxes
Quote Total
Account Name Bid Date Address Quote Number
Quote Revision Date
Bill To Account
Contact Name Email Phone
Number
Prepared By Zachary Fordley, Project Manager Email zfordley@cascade-env.com
Cascade will provide a track mounted Geoprobe unit with a 2-man crew to provide the following.
- Collect continuous soil samples at Six (6) locations to 14' BLG.
- At each location install 2" PVC monitoring wells with 10' of prepacked .006 slot screen.
- Each well will be finished with a flush mount road box and developed using the surge and pump method.
- All soil and water will be drummed and stagged on site.
- This is NOT a prevailing wage site.
Description
$17,378.00
Mobilization
Demobilization
DPT Rig, Crew
Per diem
MC liners
2" well install - .006 slot prepacked screen Flush mount box Well development Drums Florida Permitting
$17,378.00
TERRACON 2/28/2025
8001 Baymeadows Way, Suiote 1 199753 Jacksonville, Fl 32256
Project Name Commerciaol Site - Orlando, FL
Nicole Kovach Project Address 1715 Silver Star Road nicole.kovach@terracon.com Project City Orlando 407-770-9050 Project State Fl
Project Zip 32804
Cascade Rep Contact Information
Account Name Bid Date Address Quote Number
Quote Revision Date
Bill To Account
Contact Name Email Phone
Number
Prepared By Zachary Fordley, Project Manager Email zfordley@cascade-env.com
Signature of Authorized Cascade Representative
Name & Title of Authorized Cascade Representative
Date Date
Cascade will perform the Work as described in this proposal subject to the terms and conditions posted at https://cascade-env.com/resources/other/terms-and-conditions/ unless MSA is already established between Cascade and Client in which case MSA takes precedence over the aforementioned terms and conditions. By signing this proposal, Client agrees that this proposal together with the terms and conditions referenced above constitute a Subcontract. Client acknowledges that Client has received and agrees with all such documents in the form provided by Cascade. Terms and Conditions are posted and accessible at the website location set forth above.
Name & Title of Authorized Representative and Company
This quote is based on information provided by you and is valid for 45 days from the bid date. Unless previously agreed, Cascade requires a 2-week notice prior to mobilization. Your firm is responsible for 1) Obtaining any site specific permits, 2) Locating and clearly marking underground installations or utilities, 3) Furnishing dig Alert numbers at least three working days prior to scheduled start date and proof of private locating services, 4) Obtaining access to site with no overhead wires within 20' of the holes. Cascade Drilling shall not be responsible for damages to underground improvements not clearly and accurately marked. If bedrock, cobbles, flowing sands or other adverse or unsafe drilling conditions are encountered, drilling may continue on a time and materials basis or be terminated at the discretion of Cascade. Additional costs may apply if scope is significantly changed. Well development by others may void some or all of Cascade warranties of workmanship and materials. Prices assume standard labor rates and no work hour restrictions.
Signature of Client/Owner Authorized Representative
File details come from the government source that posted it. Updated .