This document is a Task Assignment (TA) issued by the State of Florida, Department of Environmental Protection (FDEP), Waste Cleanup Program, to Terracon Consultants, Inc. for remedial system work at the Village Cleaners site located at 2100 45th Street, Unit B8, West Palm Beach, Florida (ERIC_5205). The TA is issued under Contract Number HW687 and designated as TA Number DC002B. Dean Cox serves as the FDEP Project Manager, while Donna Cline represents Terracon as the contractor's project manager.
The scope of work authorizes costs for soil vapor extraction (SVE) operation and maintenance (O&M) for a four-month period, including system restart with capacitor replacement, sampling and analysis, and system evaluation reporting. The total TA value is $9,826.05, comprised of a fixed unit rate of $7,826.05 and cost reimbursement of $2,000.00 for utilities. Labor costs total $3,878.77, including project management and three months of O&M activities performed by environmental technicians, staff engineers, and senior engineers. Additional costs include $480.00 for vehicle rental, $1,502.00 for laboratory analytical services and sample shipping, and $1,497.41 for field equipment and expendables, including two motor capacitors ($46.07 and $26.34). The deliverables include monthly O&M checklists and field notes, laboratory reports for two system sampling events, O&M tables updates, and system evaluation recommendations, with a completion date of May 31, 2023.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW687
DC002B Completion May 31, 2023
This TA authorizes costs for SVE O&M, inluding restart system sampling & analysis and system evaluation/reporting. The total cost for this TA is $9,826.05. Cost reimbursement accounts for $2,000 of the total cost.
Dean Cox 850-245-8969 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Terracon Consultants, Inc.
Terracon Consultants, Inc.
Donna Cline 813-321-0340
ERIC_5205
2100 45th Street, Unit B8 West Palm Beach
Village Cleaners (former)
✔ $ 7,826.05 ✔ $ 2,000.00
$ 9,826.05
Scope of Work
Tom Lewis
Principal
Lewis, Tom E Digitally signed by Lewis, Tom E Date: 2022.10.18 11:15:17 -04'00'
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2022.10.18 07:46:21 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Monthly O&M checklists and field notes, lab reports for two system sampling events, O&M tables update, and system evaluation email with recommendations. (Subtask 1 Project Management and Subtask 2 Three Months O&M)
03/31/2023
FDEP approval of monthly O&M checklists and field notes, lab reports for two system sampling events, O&M tables update, and system eval email with recommendations.
(Subtask 1 Project Management and Subtask 2 Three Months O&M)
$ 7,746.05
FDEP receipt of utility invoices - Utilities Cost Reimbursement not to exceed $2000;
Utilities Handling Fee $80 (Subtask 3 Utilities) $ 2,080.00
$ 9,826.05
HW687
DC002B
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Interim Secretary
Memorandum
TO: HW687 Contract File FROM: Dean Cox, Contract Manager SUBJECT: SVE O&M DC002B for Village Cleaners ERIC_5205
DATE: 10/14/2022
This TA authorizes costs for SVE O&M, including system restart sampling & analysis and system evaluation/reporting, based on the Terracon TA proposal letter and cost estimate dated 9/27/22. The total cost for this TA is $9,826.05. Cost reimbursement accounts for $2,000 of the total cost.
The cost of this TA was negotiated. The total cost is $848.02 less than originally proposed. Negotiation resulted in a cost savings of approximately 8%.
The system has been operational since January 2019, but the capacitors failed sometime between the May and June O&M visits. Recent contaminant recovery has been relatively low, but high enough to continue running – only VEW-3 and VEW-4 will be on, which has been the situation for a few months (per WSCS PE 7/19/22 email). The other wells had not been recovering contamination.
The capacitors will be replaced and a “pulse/shutdown evaluation” will be completed (per WSCS PE 7/19/22 email, FDEP guidelines, and WSCS PE verbal guidance [purge volume evacuation not to exceed one hour]) when the system is re-started on the first O&M visit (wells & influent sampling). Two additional O&M visits will be completed, with an operational verification visit (no O&M) in-between. The system wells and influent will also be sampled during the third O&M visit (four months from the first visit). Site access has been confirmed – the agreement is current/accurate.
FDEP COST ESTIMATE
Contractor: Terracon
Date: 9/27/2022 Task #: HW687 DC002B SubTask 1 Project Management SubTask 6
Site: Village Cleaners ERIC_5205 SubTask 2 Three Months SVE O&M, 4 months operation SubTask 7 Activity/Phase: SVE O&M, 4 months operation SubTask 3 Utilities SubTask 8
Project Manager: Dean Cox SubTask 4 SubTask 9 SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$64.50 Project Manager Donna Cline 2.54 2.54 $0.00 Administrative 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Brownfield Consultant 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$21.25 CADD Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Data Analyst & Visualization Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$24.75 Environmental Technician Pete Christianson 30.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Field Geologist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Field Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 GIS Technician 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Principal Consultant 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$32.00 Project Geologist Joshua Feltner 2.00 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Project Industrial Hygienist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Project Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$64.50 Senior Engineer Donna Cline 5.00 5.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Geologist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior GIS Analyst 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Industrial Hygienist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$29.28 Staff Engineer Eddy Leon 4.50 4.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Staff Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total Hours 44.04 2.54 41.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Direct Labor $1,424.66 $163.90 $1,260.76 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 116.00% $1,652.60 $190.12 $1,462.48 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 56.26% $801.51 $92.21 $709.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $3,878.77 $446.23 $3,432.54 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF TERRACON Page 1
FDEP COST ESTIMATEContractor: Terracon Date: 9/27/2022
Task #: HW687 DC002B SubTask 1 Project Management SubTask 6 Site: Village Cleaners ERIC_5205 SubTask 2 Three Months SVE O&M, 4 months operation SubTask 7
Activity/Phase: SVE O&M, 4 months operation SubTask 3 Utilities SubTask 8 Project Manager: Dean Cox SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Travel
Vehicle Rental $480.00 480.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $480.00 $480.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $2,000.00 $0.00 2,000.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $2,000.00 $0.00 $2,000.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $80.00 $0.00 80.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $2,080.00 $0.00 $2,080.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $1,398.00 1,398.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $104.00 104.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $1,502.00 $1,502.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $120.00 120.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $1,377.41 1,377.41$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $1,497.41 $1,497.41 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $9,438.18 $446.23 $6,911.95 $2,080.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $387.87 $44.62 $343.25 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $9,826.05 $490.85 $7,255.20 $2,080.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF TERRACON Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Village Cleaners ERIC_5205 SUBTASK 2: 3 Months of O&M
PROPOSAL NO. PH4227314
DATE: 9/27/2022
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Month 1 O&M, Restart/Pulse Staff Engineer EL 0.5 Staff Engineer EL 0.5 Environmental Technician PC Load/unload 1.0 Environmental Technician PC Mobilization (from Winter Park) 5.0 Environmental Technician PC Replace capacitors 1.0 Environmental Technician PC System O&M, Optimization, collect samples from SVE001, SVE002 and influent 4.0 Staff Engineer EL Monthly recording of system data and laboratory data into the operational tables 1.5 Senior Engineer DC
1.5
Month 2 O&M (approximately 30 days after Month 1 O&M visit) Environmental Technician PC Load/unload 1.0 Environmental Technician PC Mobilization (from Winter Park) 5.0 Environmental Technician PC O&M, optimize performance 3.0 Staff Engineer EL Monthly recording of system data into the operational tables 1.0 Senior Engineer DC Evaluate O&M Checklist, field notes, and operational tables 1.0
Month 3 Visit (verify system operation) Project Geologist JF Mobilization (from West Palm Office) 1.0 Project Geologist JF Verify system operation, record hour meter reading, restart sytem if necessary 1.0
Month 4 O&M (approximately 60 days after Month 2 O&M visit) Environmental Technician PC Load/unload 1.0 Environmental Technician PC Mobilization (from Winter Park) 5.0 Environmental Technician PC O&M, optimize, collect samples from SVE001, SVE002 and system influent 4.0 Staff Engineer EL Monthly recording of system and lab data into the operational tables 1.0 Senior Engineer DC 2.5
TOTAL LABOR 41.5
VEHICLE TYPE RATE UNIT USEAGE
Truck (Environmental Technician) 120 day 3 360.00$ Truck (Project Geologist) 120 day 1 120.00$
TOTAL VEHICLE 480.00$
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC* #IDW TOTALS
VOCs TO-15 (VEW-1, -2, total) 200.00$ 6 1,200.00$
Summa Canister 33.00$ 6 198.00$ Sample Shipping Small Cooler (2 day) 52.00$ 2 104.00$
TOTAL LAB 1,502.00$
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Construction / O&M / Pilot Test Kit 360.00$ day 3 1,080.00$ Construction / O&M Supplies 75.00$ day 3 225.00$ 20UD64 Motor Run Capacitor 46.07$ each 1 46.07$ 4UHC7 Motor Start Capacitor 26.34$ each 1 26.34$ Expendables 40.00$ day 3 120.00$
TOTAL EQUIPMENT 1,497.41$
Request sample kit PreTask Planning, prepare field sampling SOW/coordinate site access
Submit O&M Checklist, field notes, operational tables, and email evaluation/recommendations
Evaluate O&M Checklist, field notes, operational tables, and lab data - provide update to FDEP
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Village Cleaners ERIC_5205 SUBTASK 3: Utilities
PROPOSAL NO. PH4227314
DATE: 9/27/2022
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
TOTAL LABOR 0.0
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE -$
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM -$
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE
FP&L Initiation Fee 225.00$ lump sum 0 -$ FP&L Electric 500.00$ Month 4 2,000.00$
Subcontractor Handling Fee 20.00$ Month 4 80.00$
TOTAL SUBCONTRATOR 2,080.00$
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC* #IDW TOTALS
TOTAL LAB -$
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT -$
5463 West Waters Avenue, Suite 830
Tampa, FL 33584
P (813) 221-0050
F (813) 221-0051
Terracon.com
September 27, 2022
Florida Department of Environmental Protection
Waste Cleanup Program
Waste Management Division
2600 Blair Stone Road
Tallahassee, Florida 32399-2400
Attn: Mr. Dean Cox, Environmental Consultant
E: Dean.Cox@FloridaDep.gov
W: 850-245-8969
M: 727-686-6502
Re: Proposal for SVE Shutdown Evaluation and 4 Months of System Operation
Village Cleaners
2100 45th Street, Unit B8
West Palm Beach, Palm Beach County, Florida
ERIC_5205
Task Assignment HW687 DC002B
Terracon Proposal No. PH4227314
Dear Mr. Cox:
Terracon Consultants, Inc. (Terracon) appreciates the opportunity to submit this proposal to the
Florida Department of Environmental Program (FDEP) Waste Cleanup Program (WCP) to perform remedial system shutdown evaluation on the soil vapor extraction (SVE) system at Village Cleaners.
Scope of Services
◼ Initial site visit (after a brief period of non-operation) includes troubleshooting and system repairs (replacing capacitors);
◼ The system will operate for a period of 4 months;
◼ Perform first, second, and fourth month of system Operation and
Maintenance (O&M) with operation of SVE001 and SVE002 only;
◼ Collect air samples for laboratory analysis at initial site visit and at the fourth month of O&M;
◼ The initial site visit will include an evaluation for system shutdown, with air sample collection after the removal of 1 pore volume of air (approximately 1 hour of operation);
◼ Submit O&M checklist, field notes, operational tables, lab data, and email evaluation / recommendations.
See attached LOE for details
Schedule
◼ System troubleshoot, to include replacing capacitors, and system restart by October 2022, depending on issuance of TA
◼ Submit e-mail summary at completion of 4 months of operation to include O&M checklists and field notes, laboratory analytical data, O&M tables, and email summary with system performance evaluation and recommendations by February 2023.
GRAINGER ..
11 Ill · · Cl ick : www.grainger.com I Call : 1-80
WW GRAINGER DC
8001 FORSHEE D R IVE
JAC J<SON V ILLE FL 322 19-5338
fShip To I
TERRACON
1675 LEE RD
W INTER PARK FL 32789-2207
ATTN :
~old To
TERRACON
1675 LEE RD
WINTER PARK FL 32789-2207
,1NGER (4 72-4643)
PACKING LIST
Include Stuffers
BOX ID 2021685~2
PO Number PETER CHRISTENSON
Delivery Number 6553731820 Account Number 835850892
Caller PETER CHRISTENSON PO Release Number Project/Job Number
Department Order Date 06/15/2022
Ship Date Requisi tioner
Employee Contact BR3C1 L Carrier FOX GROUND
Order Type SH Debit/Credit Code MRCD Cartons Shipped
SPECIAL INSTRUCTIONS Please reference DELIVERY NUMBER 6553731 820 on all remittance and correspondence.
PO Line Item# Item Description
20UD64 Motor Run Capacitor,60 MFD,4 11 /32" H
4UHC7 Motor Start Capacitor,645-774 MFD,Round
Your Order Number is : 1450222949
Quantity Shipped
Shipped from other location
Back ordered Tax Unit Price
0 T 43.25
0 0.00
Subtotal Tax Stand. Parcel Shipping Other Shipping
Total
W e'd love to hear your feedback about this order. Go to www.grainger.com/survey and tell us what you think.
Total
43.25
0.00
43.25 2.82 0.00 0.00
46.07
THIS PURCHASE IS GOVERNED EXCLUSIVELY BY GRAINGER'S TERMS OF SALE, INCLUDING (i ) DISPUTE RESOLUTION REMEDIES, AND (ii ) CERTAIN WARRANTY AND DAMAGES LIMITATIONS AND DISCLAIMERS IN EFFECT AT THE TIME OF THE ORDER, WHICH ARE INCORPORATED BY REFERENCE HEREIN. GRAINGER'S TERMS OF
SALE ARE AVAILABLE AT WWW.GRAINGER.COM
PRODUCT RETURN INSTRUCTIONS ARE AVAILABLE AT WWW.GRAINGER.COM/RETURNS
L
THESE ITEMS ARE SOLD FOR DOMESTIC CONSUMPTION IN THE UNITED STATES. IF EXPORTED, PURCHASER
ASSUMES FULL RESPONSIBILITY FOR COMPLIANCE WITH US EXPORT CONTROLS.
Ill 1111111111111111111111111111111111
SOLD TO ACCOUNT 835850892
TERRACON
1675 LEE RD
WINTER PARK FL 32789-2207
CALLER
PETER CHRISTENSON
TELEPHONE NUMBER
4075094127
SHIP TO
TERRACON
1675 LEE RD
WINTER PARK FL 32789-2207
ATTENTION
ITEM DESCRIPTION
Motor Start Capacitor,645-774 MFD,Round
THIS PURCHASE IS GOVERNED EXCLUSIVELY BY GRAINGER'S
TERMS OF SALE, INCLUDING: {i) DISPUTE RESOLUTION REMEDIES, AND (ii) CERTAIN WARRANTY AND DAMAGES
LIMITATIONS ANO DISCLAIMERS IN EFFECT AT THE TIME OF THE
ORDER, W'HICH ARE INCORPORATED BY REFERENCE HEREIN
GRAINGER'S TERMS OF SALE ARE AVAILABLE AT
WWW.GRAINGER.COM
PRODUCT RETURN INSTRUCTIONS ARE AVAltABLE AT
WWW.GRAINGER.COM/RETURNS
PURCHASE ORDER NUMBER
PETER CHRISTENSON
I L.IL. I n.1'\l1Y1L.1 l'\I UIVlOl:.I
REQUISITIONER
PROJECT/JOB NUMBER
PO RELEASE NUMBER
SPECIAL INSTRUCTIONS
CARRIER NAME
NONE
ITEM NUMBER SHIP QTY
4UHC7
GRAINGER®
/II IJl'i#-!-IWJ-/ iii iil·ldiiii·M ti
SAP DELIVERY
6553731819
PACKING LIST
DELIVERY DATE AND TIME EMPLOYEE I PAGE
06/15/2022 12:45 BR3C1L 1 OF 1
DBTfCROCOOE I SALES ORDER NUMBER DELIVERY
MRCD 1450222949 6553731819
BRANCH ADDRESS
4180 LB MCLEOD
ORLANDO FL 32811-5695
407-843-3220 CHECK NUMBER I CHECK AMOUNT I CASH REC'D/PAID f g;;Ns TYPE
INVUICE WILL ~uL:LOW
SALES TERMS AND CONDITIONS ON REVERSE SIDE
THANK YOU FOR YOUR ORDER
I# Of BOXES I FREIGKT TERMS
PPP
BACKORDER MESSAGE TAX
T
I certify lhat if I am purchasing lhe maleria~s) as •materiaLs of trade· as defined in the Hazardous Materias RegUations in Title 49 of the Code of Federal Regulations. I intend to use the materia(s) in direct support ofmy principal business (....tich is not transportation), and I do not irtend to resell the material, or transport them in a vehicle other than my O'Ml.
I DA1E SHIPPED/PICKED UP
UNIT PRICE
24.74
Stand. Parcel Shipping Other Shipping Tax Total
Vi.sit our web site @ www.grainger.rom
TOTAL
24.74
0.00 0.00 1.60
26.34
These items are sold for domestic ooosurrl)C.On in the United States. If exp;:111ed, pudlaser assumes ful resp:,l"ISlb.lity for oo!'l"Piance 'Mth US exlX)rt oontrols. I llllll 111111111111111 1111111111 1111111111 11111 1111111111111
GRAINGER.
I I WUlilli·ilil llfoi1H Ii
4180 LB MCLEOD
ORLANDO FL 32811-5695
TO:
TERRACON
1675LEERD
WINTER PARK FL 32789-2207
4075094127
06/15/2022 Delivery# 6553731819
TELEPHONE#
PO NUMBER
ATTENTION
PROJECT/JOB#
DEPARTMENT#
PO RELEASE
PETER CHRISTENSON
CALLER PETER CHRISTENSON
GRAINGER.
l/1--Nl-liili-iiil I -liiili-·111
4180 LB MCLEOD
ORLANDO FL 32811-5695
TO:
TERRACON
1675LEERD
WINTER PARK FL 32789-2207
4075094127
06/15/2022 Delivery# 6553731819
TELEPHONE#
PO NUMBER
ATTENTION
PROJECT/JOB#
DEPARTMENT #
PO RELEASE
PETER CHRISTENSON
CALLER PETER CHRISTENSON
| DC002B.pdf |
| DC002B memo.pdf |
| Pages from DC0002BproposalFinal220927.pdf |
| DC0002BproposalFinal220927_Page_6.pdf |
| Pages from DC0002BproposalFinal220927-2.pdf |
{"type":"Imported Receipt","isBackSide":false,"languages":["en-us"],"usedOnDeviceOCR":true}
{"type":"Imported Receipt","isBackSide":false,"languages":["en-us"],"usedOnDeviceOCR":true}
File details come from the government source that posted it. Updated .