About this file
This document package consists of a Task Assignment (TA) under Contract Number HW687 between the State of Florida Department of Environmental Protection (FDEP) and Terracon Consultants, Inc. The TA, numbered DC011C, authorizes work at the 60 Minute Cleaners facility located at 1145 20th Place, Vero Beach, Indian River County, Florida (ERIC_4806). The Department Project Manager is Dean Cox, and the Contractor's Project Manager is Donna Cline. The task assignment is effective as of June 16, 2023, with a completion date of October 31, 2023.
The Task Assignment authorizes costs associated with replacement of the Soil Vapor Extraction (SVE) system electrical panel and exhaust fan, and upgrade of system telemetry at the 60 Minute Cleaners site. The total TA value is $11,146.16 on a fixed unit rate basis. Work includes panel, subpanel, and swingout panel replacement (with existing electrical components and wiring reused), installation of a new Sensaphone Sentinel telemetry system, and replacement of the inoperable exhaust fan motor. The cost breakdown includes Terracon labor ($3,401.17), vehicle rental ($360.00), subcontractor costs for equipment procurement ($1,544.87 for the exhaust fan), subcontractor costs for services including RSI Inc. control panel repair ($5,060.00), field expenses ($440.00), and completion fees ($340.12). Deliverables are due by July 31, 2023, and include photographs, major component replacement documentation, and property reporting forms. Payment of the full $11,146.16 is due upon FDEP approval of all deliverables and documentation.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW687
DC011C Completion October 31, 2023
This TA authorizes costs associated with replacement of SVE system electrical panel & exhaust fan, and upgrade of system telemetry. The total cost of this TA is $11,146.16 and this entire cost is fixed unit rate.
Dean Cox 850-245-8969 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Terracon Consultants, Inc.
Terracon Consultants, Inc.
Donna Cline 813-321-0340
ERIC_4806
1145 20th Place, Vero Beach (Indian River County)
60 Minute Cleaners
✔ $ 11,146.16
$ 11,146.16
Scope of Work
Kelly Crain
Kelly Crain Digitally signed by Kelly Crain Date: 2023.06.16 14:23:36 -04'00'
N/A
Cline, Donna L Typewriter Donna Cline
Sr. Remediation Engineer
06/16/23
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Photos of panel, telemetry, & fan before & after replacement, with photos of the property# on the new panel, fan, & telemetry. Major Component Replacement docs and Property Reporting Form listing panel, telemetry & fan with applicable parts lists.
07/31/2023
DEP approval of panel, telemetry, & fan before & after replacement and property# photos, and Major Component Replacement docs and Property Reporting Form with applicable docs (ST 1 Proj. Mgmt. and ST 2 Panel, Fan & Telemetry Replacement).
$ 11,146.16
$ 11,146.16
HW687
DC011C
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Interim Secretary
Memorandum
TO: HW687 Contract File FROM: Dean Cox, Contract Manager SUBJECT: DC011C SVE Panel & Exhaust Fan Replacement and Telemetry Upgrade
DATE: 5/30/23
This TA authorizes costs associated with replacement of SVE system electrical panel & exhaust fan, and upgrade of system telemetry. The total cost of this TA is $11,146.16 and this entire cost is fixed unit rate. Site access was confirmed.
The exhaust fan will be replaced by Terracon, while the panel replacement and telemetry upgrade will be completed by a subcontractor (RSI). The panel is corroded, warped, and is partially exposed to the elements. The panel replacement includes panel, subpanel and swingout panel replacement – existing electrical components/wiring will be reused. The exhaust fan is inoperable – the motor was confirmed to be the problem during an O&M visit by Terracon. The telemetry software is old and not compatible with current computer operating systems – upgrade will allow remote system monitoring & shutdown.
FDEP COST ESTIMATE
Contractor: Terracon
Date: 5/23/2023 Task #: HW687 DC011 SubTask 1 Project Management SubTask 6
Site: 60 Minute Cleaners ERIC_4806 SubTask 2 System Control panel upgrade, telemtry and exhaust fan SubTask 7 Activity/Phase: System Control Panal Repair, Telemetry and Exhaust Fan SubTask 3 SubTask 8
Project Manager: Dean Cox SubTask 4 SubTask 9 SubTask 5 SubTask 10
Totals 1 2 4 5 6 7 8 9 Labor Rate Category
$67.74 Project Manager Donna Cline 2.12 2.12 $0.00 Administrative 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 Brownfield Consultant 0.00 0.00 0.00 0.00 0.00 0 0 0 0
$32.50 CADD Specialist Chelsea Fugate 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 Data Analyst & Visualization Specialist 0.00 0.00 0.00 0.00 0.00 0 0 0 0
$33.00 Environmental Technician Billy Phillips 21.00 21.00 0.00 0.00 0.00 0 0 0 0 $0.00 Field Geologist 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 Field Scientist 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 GIS Technician 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 Principal Consultant 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 Project Geologist 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 Project Industrial Hygienist 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 Project Scientist 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 Project Scientist/Engineer 0.00 0.00 0.00 0.00 0.00 0 0 0 0
$50.00 Senior Geologist Shawn Ouellette 8.25 8.25 0.00 0.00 0.00 0 0 0 0 $0.00 Senior GIS Analyst 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 Senior Industrial Hygienist 0.00 0.00 0.00 0.00 0.00 0 0 0 0
Senior Scientist 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 Staff Engineer 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 Staff Scientist 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 0.00 0.00 0.00 0.00 0.00 0 0 0 0
Total Hours 31.37 2.12 29.25 0.00 0.00 0.00 0 0 0 0
Direct Labor $1,249.22 $143.72 $1,105.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 116.00% $1,449.10 $166.72 $1,282.38 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 56.263% $702.85 $80.86 $621.99 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $3,401.17 $391.30 $3,009.87 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF TERRACON Page 1
FDEP COST ESTIMATEContractor: Terracon Date: 5/23/2023
Task #: HW687 DC011 SubTask 1 Project Management SubTask 6 Site: 60 Minute Cleaners ERIC_4806 SubTask 2 System Control panel upgrade, telemtry and exhaust fan SubTask 7
Activity/Phase: System Control Panal Repair, Telemetry and Exhaust Fan SubTask 3 SubTask 8 Project Manager: Dean Cox SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 4 5 6 7 8 9 Travel
Vehicle Rental $360.00 360.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $360.00 $360.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) Exhaust Fan + Shipping $1,404.43 $1,404.43 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $1,404.43 $1,404.43 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $140.44 $140.44 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $1,544.87 $1,544.87 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 -$ $0.00 $0.00 $0.00 $0.00 $0.00 Initiation Fee $0.00 $0.00 $0.00 -$ $0.00 $0.00 $0.00 $0.00 $0.00 RSI Control Panel Repair Bid $4,600.00 $4,600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $4,600.00 $4,600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $460.00 $460.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $5,060.00 $5,060.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $80.00 80.00$ -$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $360.00 360.00$ -$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $440.00 $440.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $10,806.04 $391.30 $10,414.74 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $340.12 $39.13 $300.99 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $11,146.16 $430.43 $10,715.73 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF TERRACON Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : 60 Minute Cleaners , ERIC_4806
SUBTASK 2: SVE SYSTEM REPAIR
PROPOSAL NO. PHB237006
DATE: 5/23/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Field Task Planning SVE REPAIR Senior Geologist SO 5.00 Senior Geologist SO 1.25 Environmental Tech BP Load/unload 1.00 Environmental Tech BP Mobilization/Demobilization (from PSL) 2.00 Environmental Tech BP Provide Oversite of SVE Repairs (2 Days @ 9 hours) 18.00 Senior Geologist SO Submit Documentation of Repairs and New Equipment Inventory 2.00
Personnel: SO BP Hours: 8.25 21.00 TOTAL LABOR 29.25
VEHICLE TYPE RATE UNIT USEAGE
Truck (Exhaust Fan Repair) 120 day 1 120.00$ Truck (System Control Panel Repair) 120 day 2 240.00$
TOTAL VEHICLE 360.00$
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE
RSI Inc SVE System Repair Control Panel Replacement 4,600.00$ each 1 4,600.00$ Handling Fee 10% each 460.00$
TOTAL 5,060.00$
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables 40.00$ day 2 80.00$ Analytical Related Construction / O&M / Pilot Test Kit ( Verify system flows and 360.00$ day 1 360.00$ consistent with pre-repair conditions) Exhaust Fan and Replacment Filters 1,404.43$ Each 1 1,404.43$
TOTAL EQUIPMENT 1,844.43$
Replace and rewire system exhaust fan PreTask Planning, prepare field sampling
February 9, 2023
Shawn Ouellette
Senior Geologist, P.G. Environmental Division
Terracon
645 NW Enterprise Drive Suite 107
Port St Lucie, FL 34986
Subject: Quote for Controls Enclosure replacement and Installation of Telemetry
60 Minutes Cleaners 1145 NW 2oth Place
Vero Beach FL
Dear Shawn, Remedial Systems Integrated, LLC (RSI) is pleased to provide Terracon, with this cost proposal to replace Controls Enclosure and to Install Telemetry to system in Vero Beach. Onsite work to include:
replacement of 30X24X8 control panel enclosure, sub panel, and swing out panel. (All components and wires are to be reused that are currently within panel), installation of a new Sensaphone Sentinel telemetry system, including wiring to panel. All work to be performed on-site.
Cost project described above including labor and mob: $4,600.00
NOTE: Above Pricing is good for 60 days.
Partnership for a Cleaner Tomorrow
12/19/2022
Equipment Proposal For:
60 Minutes Cleaners
Vero Beach, FL
Proposal Number:
MR121522-01
Prepared for:
Terracon
645 I NW Enterprise Drive Suite 107
Port St Lucie, FL 34986
D: (561) 689-4299
F: (561) 689-5955
M: (772) 408-2959
Shawn.ouellette@terracon.com
Prepared By:
Matthew Rivera
Remediation Project Manager
ESD Waste2Water, Inc.
12/19/2022 60 Minute Cleaners
CP Housing Replacement and Sentinel Telemetry System
Dear Mr. Ouellette, ESD is pleased to provide the following detailed Technical Cost Proposal for your Project.
CP Housing Replacement and Telemetry System Install
To include the replacement of 30” x 24” x 8” Control Panel Enclosure Top include the Installation of new Sensaphone Sentinel Telemetry System (1 year of Service included) To include all the labor and associated parts for the above work
Pricing to assume that the work is to be complete on-site in Vero Beach, FL one ESD Job #11545 Not to include installation or replacement of any other parts not mentioned above
To include appropriate and applicable PPE To Include Lodging, Travel and Per Diem
Sub-Total $ 11,844.00
Tax $ TBD
Total $ 11,844.00
From: Ouellette, Shawn Sent: Tuesday, December 6, 2022 2:13 PM To: jziegler@engineeredenvironmental.com Subject: 2100 45th Street West Palm Beach Florida Village Cleaners ERIC_5205
Joe, We have a site in WPB that you may have been involved with the restart of.
Donna Cline wanted me to reach out to see if you could quote us for replacing the blower and making any improvements you see fit to the system.
Attached is a summary of the recent system history and Terracon recommendations and troubleshooting efforts.
Additionally, there is a site in Vero Beach where we need a control panel replacement. Please contact us so we can provide the information for pricing.
Thanks, Senior Geologist, P.G. Environmental Division
645 I NW Enterprise Drive Suite 107 I Port St Lucie, FL 34986 D (561) 689-4299 I F (561) 689-5955 I M (772) 408-2959 Shawn.ouellette@terracon.com http://www.terracon.com/
Quote Date
5/15/2023
Quote No.
Name / Address
Terracon 645 NW Enterprise Dr Suite 107 Port St Lucie FL 34986
Ship To
TBD
Enviro-Equipment Inc.
Payment Terms
Credit Card
Estimated Lead Time
2 WEEKS ARO
Signature
Total
Subtotal
Sales Tax (7.25%)
10120 Industrial Drive Pineville, NC 28134 Phone 704-556-7723
Fax 704-556-7228
This estimate is subject to the "Enviro-Equipment Estimate Terms and Conditions", "Enviro-Equipment Invoice Terms and Conditions", "Enviro-Equipment Rental/Service
Agreement Terms and Conditions" and the "Enviro-Equipment New and Used Purchased Remediation Equipment Warranty and Returns Policy". It is the responsibility of the buyer to request and review these applicable terms and conditions. Acceptance of this estimate by the buyer shall be deemed as acceptance of all of these terms. All prices valid for 30 days unless otherwise specified. All equipment is subject to availability which may change without notice.
All prices are in US dollars and do not include shipping costs unless otherwise specified.
Part No. Description Qty Cost Total
Part Stoddard F8-109 Filter Element 1 66.43 66.43 23N613 Canarm 12" Shutter Mounted Hazardous Location Exhaust Fan, 1/3HP, 115VAC, 1640 CFM
1 1,265.00 1,265.00
235P Solberg 235P Filter Element 1 73.00 73.00
$1,404.43
$1,404.43
$0.00
645 NW Enterprise Drive, Suite 107 Port St Lucie, FL 34986
P (561) 689-4299 F (561) 689-5955
Terracon.com
May 22, 2023
Florida Department of Environmental Protection Waste Cleanup Program Waste Management Division 2600 Blair Stone Road Tallahassee, Florida 32399-2400
Attn: Mr. Dean Cox, Environmental Consultant E: Dean.Cox@FloridaDep.gov W: 850-245-8969 M: 727-686-6502
Re: TASK ASSIGNEMNT CHANGE ORDER REQUEST 60 Minute Cleaners 1145 20th Place Vero Beach, Indian River County, Florida
ERIC_4806
Task Assignment HW687 DC011 Terracon Proposal No. PHB237006
Dear Mr. Cox:
Terracon Consultants, Inc. (Terracon) is requesting a task assignment (TA) under Terracon’s Florida Department of Environmental Program (FDEP) Waste Cleanup Program Contract HW_687 to provide an additional task for the 60 Minute Cleaners Site ERIC_4806 to repair the corroded control panel, add telemetry to the system and replace a damaged system exhaust fan.
Scope of Services
Subtask 1 - The charges associated with this subtask are calculated automatically at 12.5% of the change in the direct labor costs of the remaining subtasks.
Subtask 2- This is a new subtask to authorize costs for the installation of a new control panel, system telemetry and a replacement exhaust fan. The costs to perform the additional work are $11,146.16 which includes labor, T/L, PM, parts ($1404.43) subcontractor costs of ($4,600.00) and handling fees.to perform the additional work See attached CEF and LOEs for details
Schedule
Deliverable to include an email summary with photo documentation, FDEP reporting forms, along with field notes and other backup documentation within 20 business days following the system repairs. We suggest executing this TA ASAP to get the exhaust fan replaced.
Compensation See attached CEF for details.
Proposal for SVE Operation for Methane Mitigation 60 Minute Cleaners, ERIC_4806 ■ Vero Beach, FL May 22, 2023 ■ Terracon Proposal No. HB237006
SCHEDULE
It is estimated that system repairs, including control panel replacement, telemetry upgrades and replacement exhaust fan, will occur in June 2023, depending on TA authorization date.
CLOSING REMARKS
Terracon services will be conducted in accordance with the terms and conditions, contained within DEP Waste Cleanup Program (WCP) Contract No. HW687, executed January 5, 2022. It is understood that a Task Assignment change order will be issued to authorize us to perform this work.
We appreciate the opportunity to provide this proposal and look forward to working with you on this project. If you should have any questions or comments regarding this proposal, please contact either of the undersigned at 772-343-9787.
Sincerely, Terracon Consultants, Inc.
Shawn Ouellette, P.G. Donna Cline, P.E.
Senior Geologist Senior Remediation Engineer
Attachments: Level of Effort Cost Spreadsheet Subcontractor Quotes
| DC011C.pdf |
| DC011C memo.pdf |
| DC011C CEFLOE&proposal.pdf |
| DC011C CEF-LOE proposed.pdf |
| CEF |
| LOE Subtask 2 |
| DC011C proposal.pdf |
| MR121522-01 Terracon CP Housing and Sentinel |
| Proposal for Vero Beach Panel replacement and Telemetry |
| RFP Village and 60 Minutes |
| HW-687 60 Min PHB237006 TEXT.pdf |
| Schedule |
| closing remarks |
File details come from the government source that posted it. Updated .