CN-370000-HW687-BF1BCO2.pdf

PDF 14 MB Posted

Attached to
Master Agreement FL|HW687|519929c0c8a00e44396dc1d8f5fa086b
Contract number
HW687
Issued by
Florida

About this file

Summary

This document package consists of Task Assignment Change Orders (TACO) issued by the State of Florida Department of Environmental Protection (FDEP) to Terracon Consultants, Inc. under Contract HW687. The work involves supplemental site assessment activities at the Former Rose Printing Company facility (Site ID ERIC_18047) located in Tallahassee, Florida. The primary parties include FDEP with Project Manager Megan Johnson and Terracon with Project Manager Tom Lewis, P.G., and Senior Remediation Engineer Donna Cline, P.E.

TACO #1 authorizes a time extension only, extending the task completion date from June 28, 2024 to August 16, 2024 (49 additional days) with no cost changes to the total task value of $68,527.53. TACO #2 authorizes additional labor, analytical costs, and disposal expenses for sampling two additional monitoring wells and disposal of six additional investigation-derived waste (IDW) drums, increasing the total task value from $68,527.53 to $70,145.90—a cost increase of $1,618.37. The increase includes $42.85 for additional project management labor in Subtask 1 and $1,575.52 for supplemental site assessment activities in Subtask 3, which encompassed increased labor hours, analytical costs, and IDW drum disposal, partially offset by a reduction in laboratory costs. Deliverables include a Field Sampling Plan/QAPP and HASP, field notes with photographic documentation and chain of custody records, and a Supplemental Site Assessment Report with project management documentation, with invoice requirements tied to departmental approvals of each deliverable component.

View the file

Other files

File Type Posted
CN-370000-HW687-BF01ACO1.pdf PDF
CN-370000-HW687-BF03ACO1.pdf PDF
CN-370000-HW687-BIL01A.pdf PDF
CN-370000-HW687-BIL2ACO1.pdf PDF
CN-370000-HW687-BIL2BCO1.pdf PDF
CN-370000-HW687-BIL2CCO1.pdf PDF
CN-370000-HW687-BIL3ACO2.pdf PDF
CN-370000-HW687-BIO1ACO1.pdf PDF
CN-370000-HW687-DC001A.pdf PDF
CN-370000-HW687-DC003A.pdf PDF
CN-370000-HW687-DC003D.pdf PDF
CN-370000-HW687-DC005D.pdf PDF
CN-370000-HW687-DC006A.pdf PDF
CN-370000-HW687-DC006B.pdf PDF
CN-370000-HW687-DC008C.pdf PDF
CN-370000-HW687-DC010A.pdf PDF
CN-370000-HW687-DC010B.pdf PDF
CN-370000-HW687-DC011F.pdf PDF
CN-370000-HW687-DC011H.pdf PDF
CN-370000-HW687-DC012D.pdf PDF
CN-370000-HW687-DC013C.pdf PDF
CN-370000-HW687-DC015A.pdf PDF
CN-370000-HW687-DC015C.pdf PDF
CN-370000-HW687-DC019A.pdf PDF
CN-370000-HW687-DC01ACO2.pdf PDF
CN-370000-HW687-DC020A.pdf PDF
CN-370000-HW687-DC020B.pdf PDF
CN-370000-HW687-DC020C.pdf PDF
CN-370000-HW687-DC020D.pdf PDF
CN-370000-HW687-DC023C.pdf PDF
CN-370000-HW687-DC025B.pdf PDF
CN-370000-HW687-DC025C.pdf PDF
CN-370000-HW687-DC025F.pdf PDF
CN-370000-HW687-DC027B.pdf PDF
CN-370000-HW687-DC027C.pdf PDF
CN-370000-HW687-DC02BCO1.pdf PDF
CN-370000-HW687-DC02CCO2.pdf PDF
CN-370000-HW687-DC02DCO1.pdf PDF
CN-370000-HW687-DC02HCO1.pdf PDF
CN-370000-HW687-DC032A.pdf PDF
CN-370000-HW687-DC034A.pdf PDF
CN-370000-HW687-DC034C.pdf PDF
CN-370000-HW687-DC034D.pdf PDF
CN-370000-HW687-DC035F.pdf PDF
CN-370000-HW687-DC036A.pdf PDF
CN-370000-HW687-DC03CCO1.pdf PDF
CN-370000-HW687-DC041C.pdf PDF
CN-370000-HW687-DC041D.pdf PDF
CN-370000-HW687-DC048A.pdf PDF
CN-370000-HW687-DC048B.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number) Project Name:

4. ☐ There are no changes to the TA compensation.

☐ The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO ☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. ☐ There are no changes to the TA Expiration Date.

☐ The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. ☐ There are no changes to the Attachments.

☐ Attachment ___ is replaced with Attachment -____.

7. ☐ No Additional Changes.

☐ Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

BF01B 2 HW687

Megan Johnson 850.245.899 Contractor Contractor

Contractor Contractor

Contractor

Terracon Consultants, Inc.

Tom Lewis, P.G. 850.692.7194

ERIC_18047

Former Rose Printing Company

✔ $ 70,145.90 $ 68,527.53

$ 70,145.90 $ 68,527.53 ✔ Completion

Completion 0

✔ 1 1 1

Terracon Consultants, Inc.

Donna Cline, P.E.

Senior Remediation Engineer Digitally signed by Cline, Donna L DN: cn=Cline, Donna L, ou=General Users, email=Donna.Cline@terracon.com Date: 2024.05.30 04:29:03 -04'00'

Cline, Donna L

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2024.05.28 11:51:48 -04'00'

This Task Assignment Change Order authorizes additional labor time needed to sample two additional monitoring wells, the analytical costs associated with two additional monitoring wells, and six additional IDW drums that were generated. There was also a reduction in laboratory costs.

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 01_18

Contract Number:

Task Assignment #:

Change Order #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

HW687

BF01B

$ 70,145.90

Field Sampling Plan/QAPP and HASP.

Field notes, photographic log, chain of custody, and sampling logs.

Supplemental Site Assessment Report; Project Management.

Department approval of Field Sampling Plan/QAPP and HASP (Subtask 2)

Department approval of Project Management and Supplemental Site Assessment Report (Subtasks 1 and 4)

Department approval of field notes, photographic log, chain of custody, and sampling logs (Subtask 3)

04/03/2024

05/17/2024

06/28/2024

$ 58,872.69

$ 2,058.45

$ 9,214.76 www.FloridaDEP.gov

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Secretary

Memorandum

TO: Terracon Consultants, Inc. HW687 Contract File

FROM: Megan Johnson, Contract Manager

DATE: May 22, 2024

SUBJECT: Negotiation Summary – SRP28

Task Assignment (TA) Change Order #2 – TA BF01BC2 Former Rose Printing Company – Site ID # ERIC_18047 Supplemental Site Assessment activities

This Task Assignment Change Order (TACO) authorizes additional labor time needed to sample two additional monitoring wells, the analytical costs associated with two additional monitoring wells, and the disposal of six additional IDW drums that were generated. There was also a reduction in laboratory costs. Specific changes are detailed below:

Subtask 1: Project Management The increase of overall task labor hours produced a change associated with Project Management.

This change resulted in a cost actual increase of $42.85.

Subtask 2: QAPP/Work Plan and HASP No cost changes associated with this Subtask.

Subtask 3: Supplemental Site Assessment Activities Terracon was able to locate two additional monitoring wells not previously abandoned by the former consultant. The Department approved the sampling of these two additional wells. This increased the labor time, analytical costs, and IDW generated during the supplemental site assessment activities. There was also a reduction in laboratory costs for encore samplers and SPLP work. These changes resulted in a cost actual increase of $1,575.52.

Subtask 4: Supplemental Site Assessment Report No cost changes associated with this Subtask.

Summary The Department’s SRP Contract Manager and Terracon’s Contract Manager have both agreed to the above changes. All changes noted above represent a total overall cost increase of $1,618.37, as shown in the Cost Actual LOE. Due to a rounding error in Excel, the Delta LOE shows a cost increase of $1,618.35, but this was corrected in the Cost Actual LOE. The changes were noted in the TACO Request received from Terracon on May 13, 2024. The final cost associated with this TA increased from $68,527.53 to $70,145.90. Documentation of the changes is included in the attached TACO Request, the Delta LOE spreadsheet and the Cost Actual LOE spreadsheet, and the TACO form for BF01BC2 prepared by the Department.

http://www.floridadep.gov/

FDEP COST ESTIMATE

Contractor: Terracon

Date: 5/13/2024 Task #: TACO#2 SubTask 1 Project Management SubTask 6

Site: Former Rose Printing Company TBA SubTask 2 QAPP and HASP SubTask 7 Activity/Phase: TBA and Reporting SubTask 3 Monitoring Well Installations/Soil and Groundwater Assessment SubTask 8

Project Manager: Megan Johnson SubTask 4 Site Assessment Report SubTask 9 SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$75.48 Project Manager Tom Lewis 14 13.8 $23.50 Administrative Ashley Miller 1 1 0 0 0 0 0 0 0 0 $0.00 Brownfield Consultant Belinda Richard 0 0 0 0 0 0 0 0 0 0

$32.50 CADD Specialist Chelsea Fugate 10 0 0 10 0 0 0 0 0 0 $0.00 Data Analyst & Visualization Specialist 0 0 0 0 0 0 0 0 0 0 $0.00 Environmental Technician 0 0 0 0 0 0 0 0 0 0 $0.00 Field Geologist 0 0 0 0 0 0 0 0 0 0 $0.00 Field Scientist 0 0 0 0 0 0 0 0 0 0 $0.00 GIS Technician 0 0 0 0 0 0 0 0 0 0 $0.00 Principal Consultant 0 0 0 0 0 0 0 0 0 0 $0.00 Project Geologist 0 0 0 0 0 0 0 0 0 0 $0.00 Project Industrial Hygienist 0 0 0 0 0 0 0 0 0 0

$26.92 Project Scientist 0 0 0 0 0 0 0 0 0 0 $0.00 Senior Engineer 0 0 0 0 0 0 0 0 0 0

$75.48 Senior Geologist Tom Lewis 7 1 0 6 0 0 0 0 0 0 $0.00 Senior GIS Analyst 0 0 0 0 0 0 0 0 0 0 $0.00 Senior Industrial Hygienist 0 0 0 0 0 0 0 0 0 0

$47.60 Senior Scientist Sid O'Neal 95 1 72.5 21 0 0 0 0 0 0 $0.00 Staff Engineer 0 0 0 0 0 0 0 0 0 0

$25.75 Env Technician Rodney Twiss 103 21 71.5 10 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 229 14 24 144 47 0 0 0 0 0 0

Direct Labor $9,056.32 $1,041.88 $687.33 $5,292.13 $2,034.98 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 116.00% $10,505.33 $1,208.58 $797.30 $6,138.87 $2,360.58 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 56.26% $5,095.08 $586.16 $386.69 $2,977.35 $1,144.88 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $24,656.73 $2,836.62 $1,871.32 $14,408.35 $5,540.44 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF TERRACON Page 1

Final Cost Actual CEF and LOE

FDEP COST ESTIMATEContractor: Terracon Date: 5/13/2024

Task #: TACO#2 SubTask 1 Project Management SubTask 6 Site: Former Rose Printing Company TBA SubTask 2 QAPP and HASP SubTask 7

Activity/Phase: TBA and Reporting SubTask 3 Monitoring Well Installations/Soil and Groundwater Assessment SubTask 8 Project Manager: Megan Johnson SubTask 4 Site Assessment Report SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Travel

Vehicle Rental $480.00 $0.00 $480.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $480.00 $0.00 $480.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) EDS $28,220.00 $0.00 $28,220.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $5,280.00 $0.00 $5,280.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $33,500.00 $0.00 $33,500.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $3,350.00 $0.00 $3,350.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $36,850.00 $0.00 $36,850.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $3,749.00 $0.00 $3,749.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $3,749.00 $0.00 $3,749.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $227.50 $0.00 $227.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $260.00 $0.00 $260.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $1,457.00 $0.00 $1,457.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $1,944.50 $0.00 $1,944.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $67,680.23 $2,836.62 $1,871.32 $57,431.85 $5,540.44 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $2,465.67 $283.66 $187.13 $1,440.84 $554.04 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $70,145.90 $3,120.28 $2,058.45 $58,872.69 $6,094.48 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF TERRACON Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Former Rose Printing SUBTASK 2: QAPP and Updated HASP

PROPOSAL NO. PHF237020

DATE: 10/24/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

HASP

Senior Scientist SO 1.00 Staff Scientist RT 3.00

QAPP

Field Scientist RT 18.00 Senior Geologist TL 1.00

Admin Admin AM Project files set-up 1

Staff Total hours

TL 1

SO 1

RT 21

AM 1 TOTAL LABOR 24

VEHICLE TYPE RATE UNIT USEAGE

0 $0.00 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT $0.00

Review Prepare Updated Health and Safety Plan

Prepare QAPP Review

SUBTASK 2: Monitoring Well Installations/Soil and Groundwater Assessment

PROPOSAL NO. PHF237020

DATE: 10/24/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Field Task Planning and Monitoring Well Installations with Soil Sampling Senior Scientist SO 1.00 Staff Scientist RT 4 days loading/unload mobilization 4.00 Senior Scientist SO 4 days loading/unload mobilization 4.00 Staff Scientist RT 4 days of well installation oversight with soil sampling at 7 locations 40.00 Senior Scientist SO 4 days of well installation oversight with soil sampling at 7 locations 40.00

Survey Monitoring Well Top of Casing Senior Scientist SO 2.00 Field Scientist RT 2.00

Coordinate IDW T&D Senior Scientist SO 1.00 Field Scientist RT 2.00

Monitoring Well Groundwater Sampling Senior Scientist SO 1.00 Staff Scientist RT 2.5 days loading/unload mobilization 2.00 Senior Scientist SO 2.5 days loading/unload mobilization 2.00 Staff Scientist RT 2.5 days of monitoring welll sampling at 19 locations 20.00 Staff Scientist RT monitoring welll sampling at 2 locations 1.50 Senior Scientist SO 2.5 days of monitoring well sampling at 19 locations 20.00 Senior Scientist SO monitoring welll sampling at 2 locations 1.50

Staff Total hours

TL 0

SO 72.5

RT 71.5

TOTAL LABOR 144

VEHICLE TYPE RATE UNIT USEAGE

Truck (Well Installation/ sampling) 480 week 1 $480.00 Truck (IDW pickup) 120 day 0 $0.00

TOTAL VEHICLE $480.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

Erwin Remediation IDW Disposal 110.00$ each 42 $4,620.00 Erwin Remediation IDW Disposal 110.00$ each 6 $660.00 PDS Sonic 27,800.00$ LS 1 $27,800.00 PDS Sonic 420.00$ LS 1 $420.00

TOTAL $33,500.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

Aromatic VOCs EPA 8260D (soil) 60.00$ 4 0 0 $240.00 Encore Sampler each 16.00$ 4 $64.00 Encore Sampler each 16.00$ -4 ($64.00) Sample Shipping Large Cooler (2 day) 70.00$ 2 $140.00

SPLP Bottle Extraction 1311/1312 45.00$ -4 0 0 ($180.00) SPLP Bottle Extraction 1311/1312 45.00$ 4 0 0 $180.00 Aromatic VOCs EPA 8260D/SPLP (groundwater) 60.00$ -4 0 0 ($240.00)

PreTask Planning, prepare field sampling SOW/coordinate site access, kit

PreTask Planning, prepare field sampling SOW/coordinate site access, kit

Survey new monitoring wells (7) Survey new monitoring wells (7)

Prepare waste characterization/Generator Profile Coordinate IDW T&D: Meet transporter to unlock secure area for pickup

SUBTASK 2: Monitoring Well Installations/Soil and Groundwater Assessment

PROPOSAL NO. PHF237020

DATE: 10/24/2023

Aromatic VOCs EPA 8260D/SPLP (groundwater) 60.00$ 4 0 0 $240.00 Aromatic VOCs EPA 8260D (groundwater) 60.00$ 19 0 0 $1,140.00 Aromatic VOCs EPA 8260D (groundwater) 60.00$ 2 0 0 $120.00 PAHS EPA 8270 (groundwater) 110.00$ 7 $770.00 PAHS EPA 8270 (groundwater) 110.00$ 2 $220.00 TRPH FL PRO (groundwater) 88.00$ 7 $616.00 TRPH FL PRO (groundwater) 88.00$ 2 $176.00 Lead 6010 (groundwater) 13.00$ 7 $91.00 Lead 6010 (groundwater) 13.00$ 2 $26.00 Sample Shipping Large Cooler (2 day) 70.00$ 3 $210.00

TOTAL LAB $3,749.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables 40.00$ day 6.5 $260.00 Personal Protection 35.00$ day 6.5 $227.50 Photoionization Meter 352.00$ week 1 $352.00 Shallow groundwater sampling kit 290.00$ day 2.5 $725.00 Tubing, HDPE 0.30$ ft 1000 $300.00 Tubing, silicon (3/16 x 3/8) 3.00$ ft 10 $30.00 Multimeter (YSI ProPlus) 105.00$ day 0 $0.00 Turbidimeter (Hach) 27.00$ day 0 $0.00 water level indicator 25.00$ day 0 $0.00 Pump, peristaltic 30.00$ day 0 $0.00 Total Survey Station 50.00$ day 1 $50.00 55-gallon drum, new 100.00$ drum 0 $0.00

$0.00

TOTAL EQUIPMENT $1,944.50

SUBTASK 3: SSA Report

PROPOSAL NO. PHF237020

DATE: 10/24/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Field Task Planning Senior Scientist SO 2.00 Senior Geologist TL 2.00

Deliverable Field Scientist RT 10.00 Senior Scientist/Geologist SO Review and Summarize Water Quality Parameters 3.00 Senior Scientist/Geologist SO Review and Summarize Groundwater Analytical Results 4.00 Senior Scientist SO 12.00

QA/QC and Review Senior Scientist/Geologist TL Review and Seal Report 4.00

CADD

Project Scientist CF Create updated exhibits 10.00 Staff Total hours

TL 6

SO 21

RT 10

CF 10 TOTAL LABOR 47.00

VEHICLE TYPE RATE UNIT USEAGE

TOTAL VEHICLE -$

PER DIEM STAFF RATE UNIT USEAGE

$0.00 -$

TOTAL PER DIEM -$

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

TOTAL -$

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC* #IDW TOTALS

* No charge for trip blanks, only one duplicate

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT -$

Review data

Data reduction/evaluation/Tables

Prep of Report

Date: 5/13/2024 Task #: TACO#2 SubTask 1 Project Management SubTask 6

Site: Former Rose Printing Company TBA SubTask 2 QAPP and HASP SubTask 7 Activity/Phase: TBA and Reporting SubTask 3 Monitoring Well Installations/Soil and Groundwater Assessment SubTask 8

Project Manager: Megan Johnson SubTask 4 Site Assessment Report SubTask 9 SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$75.48 Project Manager Tom Lewis 0 0.2 $23.50 Administrative Ashley Miller 0 0 0 0 0 0 0 0 0 0 $0.00 Brownfield Consultant Belinda Richard 0 0 0 0 0 0 0 0 0 0

$32.50 CADD Specialist Chelsea Fugate 0 0 0 0 0 0 0 0 0 0 $0.00 Data Analyst & Visualization Specialist 0 0 0 0 0 0 0 0 0 0 $0.00 Environmental Technician 0 0 0 0 0 0 0 0 0 0 $0.00 Field Geologist 0 0 0 0 0 0 0 0 0 0 $0.00 Field Scientist 0 0 0 0 0 0 0 0 0 0 $0.00 GIS Technician 0 0 0 0 0 0 0 0 0 0 $0.00 Principal Consultant 0 0 0 0 0 0 0 0 0 0 $0.00 Project Geologist 0 0 0 0 0 0 0 0 0 0 $0.00 Project Industrial Hygienist 0 0 0 0 0 0 0 0 0 0

$26.92 Project Scientist 0 0 0 0 0 0 0 0 0 0 $0.00 Senior Engineer 0 0 0 0 0 0 0 0 0 0

$75.48 Senior Geologist Tom Lewis 0 0 0 0 0 0 0 0 0 0 $0.00 Senior GIS Analyst 0 0 0 0 0 0 0 0 0 0 $0.00 Senior Industrial Hygienist 0 0 0 0 0 0 0 0 0 0

$47.60 Senior Scientist Sid O'Neal 2 0 1.5 0 0 0 0 0 0 0 $0.00 Staff Engineer 0 0 0 0 0 0 0 0 0 0

$25.75 Env Technician Rodney Twiss 2 0 1.5 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 3 0 0 3 0 0 0 0 0 0 0

Direct Labor $124.33 $14.30 $0.00 $110.03 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 116.00% $144.22 $16.59 $0.00 $127.63 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 56.26% $69.95 $8.05 $0.00 $61.90 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $338.50 $38.94 $0.00 $299.56 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Delta CEF and LOE

Date: 5/13/2024

Task #: TACO#2 SubTask 1 Project Management SubTask 6 Site: Former Rose Printing Company TBA SubTask 2 QAPP and HASP SubTask 7

Activity/Phase: TBA and Reporting SubTask 3 Monitoring Well Installations/Soil and Groundwater Assessment SubTask 8 Project Manager: Megan Johnson SubTask 4 Site Assessment Report SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Travel

Vehicle Rental $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) EDS $420.00 $0.00 $420.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $660.00 $0.00 $660.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $1,080.00 $0.00 $1,080.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $108.00 $0.00 $108.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $1,188.00 $0.00 $1,188.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $58.00 $0.00 $58.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $58.00 $0.00 $58.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $1,584.50 $38.94 $0.00 $1,545.56 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $33.85 $3.89 $0.00 $29.96 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $1,618.35 $42.83 $0.00 $1,575.52 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

SUBTASK 2: QAPP and Updated HASP

PROPOSAL NO. PHF237020

DATE: 10/24/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

HASP

Senior Scientist SO 0.00 Staff Scientist RT 0.00

QAPP

Field Scientist RT 0.00 Senior Geologist TL 0.00

Admin Admin AM Project files set-up 0

Staff Total hours

TL 0

SO 0

RT 0

AM 0 TOTAL LABOR 0

VEHICLE TYPE RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT $0.00

Review Prepare Updated Health and Safety Plan

Prepare QAPP

SUBTASK 3: Monitoring Well Installations/Soil and Groundwater Assessment

PROPOSAL NO. PHF237020

DATE: 10/24/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Field Task Planning and Monitoring Well Installations with Soil Sampling Senior Scientist SO 0.00 Staff Scientist RT 4 days loading/unload mobilization 0.00 Senior Scientist SO 4 days loading/unload mobilization 0.00 Staff Scientist RT 4 days of well installation oversight with soil sampling at 7 locations 0.00 Senior Scientist SO 4 days of well installation oversight with soil sampling at 7 locations 0.00

Survey Monitoring Well Top of Casing Senior Scientist SO 0.00 Field Scientist RT 0.00

Coordinate IDW T&D Senior Scientist SO 0.00 Field Scientist RT 0.00

Monitoring Well Groundwater Sampling Senior Scientist SO 0.00 Staff Scientist RT 2.5 days loading/unload mobilization 0.00 Senior Scientist SO 2.5 days loading/unload mobilization 0.00 Staff Scientist RT 2.5 days of monitoring welll sampling at 19 locations 0.00 Staff Scientist RT monitoring welll sampling at 2 locations 1.50 Senior Scientist SO 2.5 days of monitoring well sampling at 19 locations 0.00 Senior Scientisit SO monitoring welll sampling at 2 locations 1.50

Staff Total hours

TL 0

SO 1.5

RT 1.5

TOTAL LABOR 3

VEHICLE TYPE RATE UNIT USEAGE

Truck (Well Installation/ sampling) 480 week 1 $0.00 Truck (IDW pickup) 120 day 0 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

Erwin Remediation IDW Disposal 110.00$ each 0 $0.00 Erwin Remediation IDW Disposal 110.00$ each 6 $660.00 PDS Sonic 27,800.00$ LS 0 $0.00 PDS Sonic 420.00$ LS 1 $420.00

TOTAL $1,080.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

Aromatic VOCs EPA 8260D (soil) 60.00$ 0 0 0 $0.00 Encore Sampler each 16.00$ -4 ($64.00) Sample Shipping Large Cooler (2 day) 70.00$ 0 $0.00

SPLP Bottle Extraction 1311/1312 45.00$ -4 0 0 ($180.00) Aromatic VOCs EPA 8260D/SPLP (groundwater) 60.00$ -4 0 0 ($240.00) Aromatic VOCs EPA 8260D (groundwater) 60.00$ 0 0 0 $0.00 Aromatic VOCs EPA 8260D (groundwater) 60.00$ 2 0 0 $120.00

PreTask Planning, prepare field sampling SOW/coordinate site access, kit

PreTask Planning, prepare field sampling SOW/coordinate site access, kit

Survey new monitoring wells (7) Survey new monitoring wells (7)

Prepare waste characterization/Generator Profile

SUBTASK 3: Monitoring Well Installations/Soil and Groundwater Assessment

PROPOSAL NO. PHF237020

DATE: 10/24/2023

PAHS EPA 8270 (groundwater) 110.00$ 0 $0.00 PAHS EPA 8270 (groundwater) 110.00$ 2 $220.00 TRPH FL PRO (groundwater) 88.00$ 0 $0.00 TRPH FL PRO (groundwater) 88.00$ 2 $176.00 Lead 6010 (groundwater) 13.00$ 0 $0.00 Lead 6010 (groundwater) 13.00$ 2 $26.00 Sample Shipping Large Cooler (2 day) 70.00$ 0 $0.00

TOTAL LAB $58.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables 40.00$ day 6.5 $0.00 Personal Protection 35.00$ day 6.5 $0.00 Photoionization Meter 352.00$ week 1 $0.00 Shallow groundwater sampling kit 290.00$ day 2.5 $0.00 Tubing, HDPE 0.30$ ft 1000 $0.00 Tubing, silicon (3/16 x 3/8) 3.00$ ft 10 $0.00 Multimeter (YSI ProPlus) 105.00$ day 0 $0.00 Turbidimeter (Hach) 27.00$ day 0 $0.00 water level indicator 25.00$ day 0 $0.00 Pump, peristaltic 30.00$ day 0 $0.00 Total Survey Station 50.00$ day 1 $0.00 55-gallon drum, new 100.00$ drum 0 $0.00

$0.00

TOTAL EQUIPMENT $0.00

SUBTASK 4: SSA Report

PROPOSAL NO. PHF237020

DATE: 10/24/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Field Task Planning Senior Scientist SO 0.00 Senior Geologist TL 0.00

Field Scientist RT 0.00 Senior Scientist/Geologist SO Review and Summarize Water Quality Parameters 0.00 Senior Scientist/Geologist SO Review and Summarize Groundwater Analytical Results 0.00 Senior Scientist SO 0.00

QA/QC and Review Senior Scientist/Geologist TL Review and Seal Report 0.00

CADD

Project Scientist CF Create updated exhibits 0.00 Staff Total hours

TL 0

SO 0

RT 0

CF 0 TOTAL LABOR 0.00

VEHICLE TYPE RATE UNIT USEAGE

TOTAL VEHICLE -$

PER DIEM STAFF RATE UNIT USEAGE

$0.00 -$

TOTAL PER DIEM -$

SUBCONTRACTOR COSTS

PARAMETER RATE # SAMPLES #QAQC* #IDW TOTALS

* No charge for trip blanks, only one duplicate

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT -$

Date: 1/12/2024 Task #: SubTask 1 Project Management SubTask 6

Site: Former Rose Printing Company TBA SubTask 2 QAPP and HASP SubTask 7 Activity/Phase: TBA and Reporting SubTask 3 Monitoring Well Installations/Soil and Groundwater Assessment SubTask 8

Project Manager: Megan Johnson SubTask 4 Site Assessment Report SubTask 9 SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$75.48 Project Manager Tom Lewis 14 13.6 $23.50 Administrative Ashley Miller 1 1 0 0 0 0 0 0 0 0 $0.00 Brownfield Consultant Belinda Richard 0 0 0 0 0 0 0 0 0 0

$32.50 CADD Specialist Chelsea Fugate 10 0 0 10 0 0 0 0 0 0 $0.00 Data Analyst & Visualization Specialist 0 0 0 0 0 0 0 0 0 0 $0.00 Environmental Technician 0 0 0 0 0 0 0 0 0 0 $0.00 Field Geologist 0 0 0 0 0 0 0 0 0 0 $0.00 Field Scientist 0 0 0 0 0 0 0 0 0 0 $0.00 GIS Technician 0 0 0 0 0 0 0 0 0 0 $0.00 Principal Consultant 0 0 0 0 0 0 0 0 0 0 $0.00 Project Geologist 0 0 0 0 0 0 0 0 0 0 $0.00 Project Industrial Hygienist 0 0 0 0 0 0 0 0 0 0

$26.92 Project Scientist 0 0 0 0 0 0 0 0 0 0 $0.00 Senior Engineer 0 0 0 0 0 0 0 0 0 0

$75.48 Senior Geologist Tom Lewis 7 1 0 6 0 0 0 0 0 0 $0.00 Senior GIS Analyst 0 0 0 0 0 0 0 0 0 0 $0.00 Senior Industrial Hygienist 0 0 0 0 0 0 0 0 0 0

$47.60 Senior Scientist Sid O'Neal 93 1 71 21 0 0 0 0 0 0 $0.00 Staff Engineer 0 0 0 0 0 0 0 0 0 0

$25.75 Env Technician Rodney Twiss 101 21 70 10 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 226 14 24 141 47 0 0 0 0 0 0

Direct Labor $8,931.98 $1,027.57 $687.33 $5,182.10 $2,034.98 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 116.00% $10,361.10 $1,191.98 $797.30 $6,011.24 $2,360.58 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 56.26% $5,025.13 $578.11 $386.69 $2,915.45 $1,144.88 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $24,318.21 $2,797.66 $1,871.32 $14,108.79 $5,540.44 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Original CEF and LOE

Date: 1/12/2024

Task #: SubTask 1 Project Management SubTask 6 Site: Former Rose Printing Company TBA SubTask 2 QAPP and HASP SubTask 7

Activity/Phase: TBA and Reporting SubTask 3 Monitoring Well Installations/Soil and Groundwater Assessment SubTask 8 Project Manager: Megan Johnson SubTask 4 Site Assessment Report SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Travel

Vehicle Rental $480.00 $0.00 $480.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $480.00 $0.00 $480.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) EDS $27,800.00 $0.00 $27,800.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $4,620.00 $0.00 $4,620.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $32,420.00 $0.00 $32,420.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $3,242.00 $0.00 $3,242.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $35,662.00 $0.00 $35,662.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $3,691.00 $0.00 $3,691.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $3,691.00 $0.00 $3,691.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $227.50 $0.00 $227.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $260.00 $0.00 $260.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $1,457.00 $0.00 $1,457.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $1,944.50 $0.00 $1,944.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $66,095.71 $2,797.66 $1,871.32 $55,886.29 $5,540.44 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $2,431.82 $279.77 $187.13 $1,410.88 $554.04 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $68,527.53 $3,077.43 $2,058.45 $57,297.17 $6,094.48 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

SUBTASK 2: QAPP and Updated HASP

PROPOSAL NO. PHF237020

DATE: 10/24/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

HASP

Senior Scientist SO 1.00 Staff Scientist RT 3.00

QAPP

Field Scientist RT 18.00 Senior Geologist TL 1.00

Admin Admin AM Project files set-up 1

Staff Total hours

TL 1

SO 1

RT 21

AM 1 TOTAL LABOR 24

VEHICLE TYPE RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT $0.00

Review Prepare Updated Health and Safety Plan

Prepare QAPP

SUBTASK 3: Monitoring Well Installations/Soil and Groundwater Assessment

PROPOSAL NO. PHF237020

DATE: 10/24/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Field Task Planning and Monitoring Well Installations with Soil Sampling Senior Scientist SO 1.00 Staff Scientist RT 4 days loading/unload mobilization 4.00 Senior Scientist SO 4 days loading/unload mobilization 4.00 Staff Scientist RT 4 days of well installation oversight with soil sampling at 7 locations 40.00 Senior Scientist SO 4 days of well installation oversight with soil sampling at 7 locations 40.00

Survey Monitoring Well Top of Casing Senior Scientist SO 2.00 Field Scientist RT 2.00

Coordinate IDW T&D Senior Scientist SO 1.00 Field Scientist RT 2.00

Monitoring Well Groundwater Sampling Senior Scientist SO 1.00 Staff Scientist RT 2.5 days loading/unload mobilization 2.00 Senior Scientist SO 2.5 days loading/unload mobilization 2.00 Staff Scientist RT 2.5 days of monitoring welll sampling at 19 locations 20.00 Senior Scientist SO 2.5 days of monitoring well sampling at 19 locations 20.00

Staff Total hours

TL 0

SO 71

RT 70

TOTAL LABOR 141

VEHICLE TYPE RATE UNIT USEAGE

Truck (Well Installation/ sampling) 480 week 1 $480.00 Truck (IDW pickup) 120 day 0 $0.00

TOTAL VEHICLE $480.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

Erwin Remediation IDW Disposal 110.00$ each 42 $4,620.00 PDS Sonic 27,800.00$ LS 1 $27,800.00

TOTAL $32,420.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

Aromatic VOCs EPA 8260D (soil) 60.00$ 4 0 0 $240.00 Encore Sampler each 16.00$ 4 $64.00 Sample Shipping Large Cooler (2 day) 70.00$ 2 $140.00

SPLP Bottle Extraction 1311/1312 45.00$ 4 0 0 $180.00 Aromatic VOCs EPA 8260D/SPLP (groundwater) 60.00$ 4 0 0 $240.00 Aromatic VOCs EPA 8260D (groundwater) 60.00$ 19 0 0 $1,140.00 PAHS EPA 8270 (groundwater) 110.00$ 7 $770.00 TRPH FL PRO (groundwater) 88.00$ 7 $616.00 Lead 6010 (groundwater) 13.00$ 7 $91.00 Sample Shipping Large Cooler (2 day) 70.00$ 3 $210.00

Survey new monitoring wells (7) Survey new monitoring wells (7)

PreTask Planning, prepare field sampling SOW/coordinate site access, kit

PreTask Planning, prepare field sampling SOW/coordinate site access, kit

Prepare waste characterization/Generator Profile

SUBTASK 3: Monitoring Well Installations/Soil and Groundwater Assessment

PROPOSAL NO. PHF237020

DATE: 10/24/2023

TOTAL LAB $3,691.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables 40.00$ day 6.5 $260.00 Personal Protection 35.00$ day 6.5 $227.50 Photoionization Meter 352.00$ week 1 $352.00 Shallow groundwater sampling kit 290.00$ day 2.5 $725.00 Tubing, HDPE 0.30$ ft 1000 $300.00 Tubing, silicon (3/16 x 3/8) 3.00$ ft 10 $30.00 Multimeter (YSI ProPlus) 105.00$ day 0 $0.00 Turbidimeter (Hach) 27.00$ day 0 $0.00 water level indicator 25.00$ day 0 $0.00 Pump, peristaltic 30.00$ day 0 $0.00 Total Survey Station 50.00$ day 1 $50.00 55-gallon drum, new 100.00$ drum 0 $0.00

$0.00

TOTAL EQUIPMENT $1,944.50

SUBTASK 4: SSA Report

PROPOSAL NO. PHF237020

DATE: 10/24/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Field Task Planning Senior Scientist SO 2.00 Senior Geologist TL 2.00

Field Scientist RT 10.00 Senior Scientist/Geologist SO Review and Summarize Water Quality Parameters 3.00 Senior Scientist/Geologist SO Review and Summarize Groundwater Analytical Results 4.00 Senior Scientist SO 12.00

QA/QC and Review Senior Scientist/Geologist TL Review and Seal Report 4.00

CADD

Project Scientist CF Create updated exhibits 10.00 Staff Total hours

TL 6

SO 21

RT 10

CF 10 TOTAL LABOR 47.00

VEHICLE TYPE RATE UNIT USEAGE

TOTAL VEHICLE -$

PER DIEM STAFF RATE UNIT USEAGE

$0.00 -$

TOTAL PER DIEM -$

SUBCONTRACTOR COSTS

PARAMETER RATE # SAMPLES #QAQC* #IDW TOTALS

* No charge for trip blanks, only one duplicate

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT -$

Invoice

Date

5/17/2024

Invoice #

TC202

Terracon Attn: Sid O'Neal 645 NW Enterprise Drive, Suite 107 Port Saint Lucie, FL 34986 APInvoices@terracon.com

P.O. Box 884 Gulf Breeze, FL 32562

(850) 292-6511 ErwinRemediation@gmail.com

Site City

Tallahassee

Proj #HF237109

Site Name

Rose Printing

Total

Quantity Rate AmountDate Item

48 110.00 5,280.005/13/2024 Drum Disposal Petro Cont Soil

$5,280.00

From: O"Neal, Sid L To: Johnson, Megan R Cc: Lewis, Tom E; Brown, Julie A.; Cline, Donna L Subject: RE: Former Rose Printing Company, ERIC_18047; TA B Date: Friday, May 17, 2024 2:45:50 PM Attachments: image003.png image004.png image005.png image006.png image007.png image008.png image009.png Terracon Invoice - TC202.pdf Rose Printing LOE and CE_2024.05.13DRAFT.xlsx Terracon Manifest - Rose Printing - Tallahassee - 05.13.2024.pdf EDS - Inv 10124 Terracon Rose Printing Tally.pdf Rose Printing, ERIC_18047 - Subtask 3 Deliverable.pdf

EXTERNAL MESSAGE

This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.

Happy Friday Megan!

Attached is the waste manifest/disposal tckt and invoice (Erwin and EDS) for the extra drums. I’ve also attached the TACO that covers the costs for additional 2 wells sampled and extra 6 drums.

Also, see attached Deliverable Subtask 3 for your review. Let me know if you need anything else for processing.

Thanks, Sid O’Neal Senior Scientist I Environmental

3559 Timberlane School Road I Tallahassee, Florida 32312 D (850) 692-7189 I F (850) 692-7186 I M (229) 400-5108 sid.oneal@terracon.com I Terracon.com

From: O'Neal, Sid L Sent: Monday, May 13, 2024 5:41 PM To: Johnson, Megan R <Megan.R.Johnson@FloridaDEP.gov> Cc: Lewis, Tom E <Tom.Lewis@terracon.com> Subject: FW: Former Rose Printing Company, ERIC_18047; TA B

Hi Megan, Following up to previous email. Attached is the Draft TACO and EDS’s invoice for the 6 extra drums mailto:Sid.O"neal@terracon.com mailto:Megan.R.Johnson@floridadep.gov mailto:Tom.Lewis@terracon.com mailto:Julie.Brown@terracon.com mailto:Donna.Cline@terracon.com mailto:name@terracon.com http://secure-web.cisco.com/1lSdfy0Piig9R5HtUE1L1XUoDEFkrYavR6PM9DJNTLYw0ecvnGQaax1hKc2K8vAWm8eASLfPIWoK22QTMVtZvIGyzuJyMUGVv-93ztkFSsSx7BeW6mHfJyHUvsNbf0ozD42DaGklPhwargTCRbYILdAA6WgovdmBseZv89p-g8sNfwRJr3h6ya-FxFHtseh_M22MlyW06nAL6chXveQBm-IbYQ3O_VUTFH7mjWjt3pgdOnEQkrfJXcGyZB3rFWr11O3v2Bxtv8fMHg80iEPmrwhcpkYKE3fPxOjqMkTCnhk9GQDGp9opTPJ2Kt0SpSAQs/http%3A%2F%2Fwww.terracon.com%2F https://secure-web.cisco.com/1ET7lbhvgSnXsbmgL05iN68pqme8s6_w8KN6FTMT6c89onMBtkgGMq5pxNz5W2fHlVlTHtrMUyuR6NIrhV2ZqmNC5Ady2z1zWG3hRpOQ9MkXPu5VwCZIq1KnU8MfuumI349IsENIOo5tt_loZFkAGdF35495tDcB0x3S8SUgYkS6VNZnsLvU6Iiy2C452-ieVtXLBI9nj7e0rRjnT8efofXIZ3306cNnawlhYTjxeKDlzpSeyJhX9NklN6_jUoiueOowz6xDKbf3wRS6-0JVamRfWnE5_LGx3UNQ_VbdVkm4pJ6pvVHmOJgwRHcIzzWuM/https%3A%2F%2Fwww.facebook.com%2Fterracon%2F https://secure-web.cisco.com/1BtSNiWZN5DmTTk_HAq05opN0GImP6-DPZg-wTWz1_srZvhFX4dy3muB3elZANQy1_tBAsBLritj3uZTxyiJLhhrv2jxdePWO4cGFSkKNOUQ_DichiWQ-grtMicX1XYOGVXKk6UW-QOFTgXdS3D8ew43rIq22TY4tBM41QsjsAYlcf18-2pD2FHP8KNx7o5qFSqmuTKs0hZy03ZvNzgG13eiQUfQKo6J39XJqDJW8F-5WtuL20Y48D9eFtwI9a19-Z-AwXdxE2rCSIjlAG3rqyysb5TGRRtNNFEyJEGCqqc3sOuOXFVC3oOJaeq-j2Uab/https%3A%2F%2Ftwitter.com%2Fterraconlife https://secure-web.cisco.com/1u12pev6Taku08Q1vDTQ2qHjdAuf5SeOK4yYr471ET2X8EgL0uTdJSlvbgxFu_e-IiEkpqtmYBIHC_ZJR9Rw9AUp8JyRbtA8gMjcUKPFzIo3ddZ3JGo6Ql24941paxWuIAtyAuQK9rqCPFsIT3eMy97l1Bs313Oxpb4PGl6xfRt20yOQOSTAIsQbg2tZrQN00V4p78UTzr59iW7hu7rCBP6yE7ZpZ0YYQf20IcYlXI-4wk_bmcc1WBCXAVptEMd4BHTHI4kpYX9OEbPVeN40RL8TKjFHxNF1WwTiiCsnmSdIbvXqtPzIf02ydDokILCTZn2J-Ph0ijoi4JzEB7tpgcg/https%3A%2F%2Fwww.linkedin.com%2Fcompany%2Fterracon%2Fmycompany%2F https://secure-web.cisco.com/1oEhyu5FlNA29ebBGvajmw-jyzSOOK2GAUT6-2veeL8Wmvip2lsZNabN3KG7M-6Ia6CWhorAMxG5qw_1ri9yqjT0uiy4s1rTx6n2u2V0W121_glmBCFQC5rzsz1h0tszyPnBTN3oOQcy0RMuD2wz0GofArCNwsQQCuoanxXzwVi1uxM5SsbftpxMDPyvQG-D8bvgbzgubDeXNvqxFphyDwMiBSBseKR3FkORMo0xwUIUfooz1J9OIMrSRcqiSTeB89zB-OaSUHNNe0NCRT65th8SEQoWp6H3wNXHSRrMiTW3ZX-S0mKYmMDO9pB30DZUk61cyPdUXX5PvQMmT-gVkeQ/https%3A%2F%2Fwww.instagram.com%2Fterraconlife%2F https://secure-web.cisco.com/1SciioURVmZkVBX0o_XoOTw6DlR5ZZBX9KZNM1vN2Ho_y1Fg9jPCLewAAaKcuVrYgtEPZGTwiIm6-bw3Dy0ypjJcMB2dENvfP1Ag4dwYNWVUaa4QEF8NzbI-WcVkUjSEVoOqVlz7Rdhl8Kup7RWf147pjLVWEMMu7jFx8o24-_JRILJnOIi8tybc1g9tyYTSt6G7gSsWVJv1LJnzONl41UYZFXuIRq8ZLg9fLyhJzoLWdErHqsgGGWkpo4gtcBZbk9KdLC7D2x4fvOMwW4FgTWmFirrB4oJRVaF0Rnbm1-YKB5vPmScMNP3dwGN2W_MLt_OytkBkq3PlryaHk0-jb2w/https%3A%2F%2Fwww.youtube.com%2Fchannel%2FUCnME_jcG0b6CH5xxwdrtDZw

Invoice

Date

5/17/2024

Invoice #

TC202

Terracon Attn: Sid O'Neal 645 NW Enterprise Drive, Suite 107 Port Saint Lucie, FL 34986 APInvoices@terracon.com

P.O. Box 884 Gulf Breeze, FL 32562

(850) 292-6511 ErwinRemediation@gmail.com

Site City

Tallahassee

Proj #HF237109

Site Name

Rose Printing

Total

Quantity Rate AmountDate Item

48 110.00 5,280.005/13/2024 Drum Disposal Petro Cont Soil

$5,280.00

Original-Cost Estimate

Contractor: Terracon

Date: 1/12/24

Task #: SubTask 1 Project Management SubTask 6

Site: Former Rose Printing Company TBA SubTask 2 QAPP and HASP SubTask 7

Activity/Phase: TBA and Reporting SubTask 3 Monitoring Well Installations/Soil and Groundwater Assessment SubTask 8

Project Manager: Megan Johnson SubTask 4 Site Assessment Report SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10

Labor Rate Category IK LW JB

$75.48 Project Manager Tom Lewis 14 13.6

$23.50 Administrative Ashley Miller 1 1 0 0 0 0 0 0 0 0 4 8 1 12

$0.00 Brownfield Consultant Belinda Richard 0 0 0 0 0 0 0 0 0 0

$32.50 CADD Specialist Chelsea Fugate 10 0 0 10 0 0 0 0 0 0

$0.00 Data Analyst & Visualization Specialist 0 0 0 0 0 0 0 0 0 0

$0.00 Environmental Technician 0 0 0 0 0 0 0 0 0 0

$0.00 Field Geologist 0 0 0 0 0 0 0 0 0 0

$0.00 Field Scientist 0 0 0 0 0 0 0 0 0 0

$0.00 GIS Technician 0 0 0 0 0 0 0 0 0 0

$0.00 Principal Consultant 0 0 0 0 0 0 0 0 0 0

$0.00 Project Geologist 0 0 0 0 0 0 0 0 0 0

$0.00 Project Industrial Hygienist 0 0 0 0 0 0 0 0 0 0

$26.92 Project Scientist 0 0 0 0 0 0 0 0 0 0

$0.00 Senior Engineer 0 0 0 0 0 0 0 0 0 0

$75.48 Senior Geologist Tom Lewis 7 1 0 6 0 0 0 0 0 0

$0.00 Senior GIS Analyst 0 0 0 0 0 0 0 0 0 0

$0.00 Senior Industrial Hygienist 0 0 0 0 0 0 0 0 0 0

$47.60 Senior Scientist Sid O'Neal 93 1 71 21 0 0 0 0 0 0

$0.00 Staff Engineer 0 0 0 0 0 0 0 0 0 0

$25.75 Env Technician Rodney Twiss 101 21 70 10 0 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 226 14 24 141 47 0 0 0 0 0 0

Direct Labor $8,931.98 $1,027.57 $687.33 $5,182.10 $2,034.98 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 116.00% $10,361.10 $1,191.98 $797.30 $6,011.24 $2,360.58 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Fringe 56.26% $5,025.13 $578.11 $386.69 $2,915.45 $1,144.88 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Labor $24,318.21 $2,797.66 $1,871.32 $14,108.79 $5,540.44 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Travel

Vehicle Rental $480.00 $0.00 $480.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Travel $480.00 $0.00 $480.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement)

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement)

Drilling (Conventional) EDS $27,800.00 $0.00 $27,800.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $4,620.00 $0.00 $4,620.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $32,420.00 $0.00 $32,420.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Handling Fee $3,242.00 $0.00 $3,242.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Subcontractor Cost $35,662.00 $0.00 $35,662.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory

Analytical Costs $3,691.00 $0.00 $3,691.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Sample Shipping $70.00 $0.00 $ 70.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Laboratory $3,761.00 $0.00 $3,761.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses

Personal Protection $227.50 $0.00 $227.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Expendables $260.00 $0.00 $260.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Other) $1,457.00 $0.00 $1,457.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Field Expenses $1,944.50 $0.00 $1,944.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $66,165.71 $2,797.66 $1,871.32 $55,956.29 $5,540.44 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Completion Fee $2,431.82 $279.77 $187.13 $1,410.88 $554.04 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $68,597.53 $3,077.43 $2,058.45 $57,367.17 $6,094.48 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

&"Verdana,Bold"&10FDEP COST ESTIMATE

&"Verdana,Bold"&8REV: 02/03 &"Verdana,Bold"&8CEF TERRACON &"Verdana,Bold"&8Page &P

Original-LOE Subtask 2

SITE : Former Rose Printing

SUBTASK 2: QAPP and Updated HASP

PROPOSAL NO. PHF237020

DATE: 10/24/23

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON SO KP TL AM

STAFF-TITLE WORK DESCRIPTION HOURS

HASP

Senior Scientist SO Review 1.00 1 3

Staff Scientist RT Prepare Updated Health and Safety Plan 3.00

QAPP

Field Scientist RT Prepare QAPP 18.00 18 1

Senior Geologist TL Review 1.00

Admin

Admin AM Project files set-up 1 1

Staff Total hours

TL 1

SO 1

RT 21 1 21 1 1

AM 1 TOTAL LABOR 24

VEHICLE TYPE RATE UNIT USEAGE

0 $0.00

$0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00

$0.00

$0.00

$0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT $0.00

$ 240.00

&"Verdana,Bold"&10LEVEL OF EFFORT/EXPENSE WORKSHEET

&"Verdana,Regular"&8Page &P

Original-LOE Subtask 3

SITE : Former Rose Printing

SUBTASK 3: Monitoring Well Installations/Soil and Groundwater Assessment

PROPOSAL NO. PHF237020

DATE: 10/24/23

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS SO RT

Field Task Planning and Monitoring Well Installations with Soil Sampling

Senior Scientist SO PreTask Planning, prepare field sampling SOW/coordinate site access, kit 1.00 1

Staff Scientist RT 4 days loading/unload mobilization 4.00 3

Senior Scientist SO 4 days loading/unload mobilization 4.00 3

Staff Scientist RT 4 days of well installation oversight with soil sampling at 7 locations 40.00 30

Senior Scientist SO 4 days of well installation oversight with soil sampling at 7 locations 40.00 30

Survey Monitoring Well Top of Casing

Senior Scientist SO Survey new monitoring wells (7) 2.00 2

Field Scientist RT Survey new monitoring wells (7) 2.00 2

Coordinate IDW T&D

Senior Scientist SO Prepare waste characterization/Generator Profile 1.00 1

Field Scientist RT Coordinate IDW T&D: Meet transporter to unlock secure…

This is the start of the file's text. The full file is on GovTribe.