This is a Task Assignment Change Order (TACO) No. 1 executed between the State of Florida Department of Environmental Protection (FDEP) and Terracon Consultants, Inc. under Contract No. HW687. The change order amends Task Assignment CSS03B for environmental site inspection activities at the Former Cal-Spray Chemical Co. facility located at 1715 Silver Star Road, Orlando, Orange County, Florida (Site ID ERIC_18464). The FDEP's project manager is Claire Field, and Terracon's project manager is Ralph Mongillo. The contract was originally executed on March 24, 2024, and the TACO became effective on May 16, 2025.

The TACO authorizes additional materials, equipment, analyses, and investigation-derived waste (IDW) disposal operations necessary to complete the site inspection work. The task assignment value increased from $48,751.83 to $50,113.85, reflecting a cost increase of $1,362.02. Cost adjustments across subtasks included: Subtask 1 (Project Management) decreased by $6.80; Subtask 2 (Site Investigation) increased by $541.00 to cover additional drums, casing materials for hand-installed monitoring wells, and TCLP analysis; Subtask 3 (IDW Management) increased by $880.00 for laboratory analysis and disposal costs of seven drums (five soil, two water); and Subtask 4 (Reporting) decreased by $52.18. The work is scheduled for completion by September 2, 2025, with deliverables including site inspection reports, field documentation, and IDW management confirmation. Invoice payments are structured upon departmental approval of each subtask deliverable.

View the file

Other files

File Type Posted
CN-370000-HW687-BF01ACO1.pdf PDF
CN-370000-HW687-BF03ACO1.pdf PDF
CN-370000-HW687-BIL01A.pdf PDF
CN-370000-HW687-BIL2ACO1.pdf PDF
CN-370000-HW687-BIL2BCO1.pdf PDF
CN-370000-HW687-BIL2CCO1.pdf PDF
CN-370000-HW687-BIL3ACO2.pdf PDF
CN-370000-HW687-BIO1ACO1.pdf PDF
CN-370000-HW687-DC001A.pdf PDF
CN-370000-HW687-DC003A.pdf PDF
CN-370000-HW687-DC003D.pdf PDF
CN-370000-HW687-DC005D.pdf PDF
CN-370000-HW687-DC006A.pdf PDF
CN-370000-HW687-DC006B.pdf PDF
CN-370000-HW687-DC008C.pdf PDF
CN-370000-HW687-DC010A.pdf PDF
CN-370000-HW687-DC010B.pdf PDF
CN-370000-HW687-DC011F.pdf PDF
CN-370000-HW687-DC011H.pdf PDF
CN-370000-HW687-DC012D.pdf PDF
CN-370000-HW687-DC013C.pdf PDF
CN-370000-HW687-DC015A.pdf PDF
CN-370000-HW687-DC015C.pdf PDF
CN-370000-HW687-DC019A.pdf PDF
CN-370000-HW687-DC01ACO2.pdf PDF
CN-370000-HW687-DC020A.pdf PDF
CN-370000-HW687-DC020B.pdf PDF
CN-370000-HW687-DC020C.pdf PDF
CN-370000-HW687-DC020D.pdf PDF
CN-370000-HW687-DC023C.pdf PDF
CN-370000-HW687-DC025B.pdf PDF
CN-370000-HW687-DC025C.pdf PDF
CN-370000-HW687-DC025F.pdf PDF
CN-370000-HW687-DC027B.pdf PDF
CN-370000-HW687-DC027C.pdf PDF
CN-370000-HW687-DC02BCO1.pdf PDF
CN-370000-HW687-DC02CCO2.pdf PDF
CN-370000-HW687-DC02DCO1.pdf PDF
CN-370000-HW687-DC02HCO1.pdf PDF
CN-370000-HW687-DC032A.pdf PDF
CN-370000-HW687-DC034A.pdf PDF
CN-370000-HW687-DC034C.pdf PDF
CN-370000-HW687-DC034D.pdf PDF
CN-370000-HW687-DC035F.pdf PDF
CN-370000-HW687-DC036A.pdf PDF
CN-370000-HW687-DC03CCO1.pdf PDF
CN-370000-HW687-DC041C.pdf PDF
CN-370000-HW687-DC041D.pdf PDF
CN-370000-HW687-DC048A.pdf PDF
CN-370000-HW687-DC048B.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number) Project Name:

4. There are no changes to the TA compensation.

The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. There are no changes to the TA Expiration Date.

The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. There are no changes to the Attachments.

Attachment ___ is replaced with Attachment -____.

7. No Additional Changes.

Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

Additional signatures attached on separate page.

CSS03B 1 HW687

This Task Assignment Change Order (TACO) authorizes additional materials during monitoring well installation, soil sampling analysis, and IDW disposal of 7 drums. This is being executed per the TACO request from Terracon received on May 7, 2025.

Claire Field 8502458970 Contractor Terracon Consultants, Inc. Contractor

Contractor Ralph Mongillo Contractor (904) 479-7415

ERIC_18464

Former Cal-Spray Chemical Co.

✔ $ 50,113.85 $ 48,751.83

$ 50,113.85 $ 48,751.83 ✔ Completion

Completion 0

✔ 1 1 1

Terracon Consultants, Inc.

Contractor Donna Cline

Senior Associate Digitally signed by Cline, Donna L DN: cn=Cline, Donna L, ou=General Users, email=Donna.Cline@terracon.com Date: 2025.05.16 13:35:03 -04'00'

Cline, Donna L

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2025.05.16 12:05:13 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

HW687

CSS03B

$ 50,113.85

Site Inspection Report and Project Management (Subtask 1 & 4)

Field Notes, lithological logs, well installation logs, photolog, and chain of custody documentation (Subtask 2)

Confirmation of IDW Management (Subtask 3)

Department Approval of Site Inspection Report and Project Management (Subtask 1 & 4)

Department Approval of Confirmation of IDW Management (Subtask 3)

Department Approval of Field Notes, lithological logs, well installation logs, photolog, and chain of custody documentation (Subtask 2)

06/02/2025

05/02/2025

05/23/2025

$ 42,032.21

$ 6,592.24

$ 1,489.40

FFLORIDAA DEPARTMENTT OF

EEnvironmentall Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ronn DDeSantiss Governor

Alexiss A.. Lambert Secretary

Terracon Consultants, Inc. HW687 Contract File

Claire Field, Contract Manager

May 15, 2025

Memorandum

TO:

FROM:

: Negotiation Summary – Change Order #1 - TA CSS03B C1 Former Cal- Spray Chemical Co. - Site ID # ERIC_18464 Site Inspection Activities

This Task Assignment Change Order (TACO) authorizes additional material, equipment, analyses, and defined IDW disposal operations that is needed to complete previous subtasks.

Specific changes are detailed below:

Subtask 1: Project Management This subtask is a percentage of the overall project and has been negotiated as a contract rate.

The change of specific man hours reduced from one person and redistributed to another resulted in an overall decrease in cost. This change resulted in a cost actual decrease of $ 6.80 .

Subtask 2: SI Site Investigation Activities This subtask, Terracon requested 3 additional 55-gallon drums and additional material for the hand installed monitoring well inside the crawl space inside the building. In addition, Terracon requested additional analysis of 2 soil IDW drum samples via TCLP extraction and OCP and RCRA metal analysis. This change resulted in a cost actual increase of $541.00.

Subtask 3: IDW Management The change in this subtask includes the actual cost of laboratory analysis of IDW samples and the disposal, transportation and manifest of the 7 drums of material collected (5 soil, 2 water). This change resulted in a cost actual increase of $880.00.

www.FloridaDEP.gov

Negotiation Summary – Change Order #1 TA CSS03B C1 Former Cal-Spray Chemical Co. ERIC_18464, Orlando, Orange County Site Inspection Activities and Report May 15, 2025

Subtask 4: Reporting This subtask includes labor hours associated with the preparation of Data Summary Tables/Figures and the SI Report. The change of specific man hours reduced from one person and redistributed to another resulted in an overall decrease in cost. This change resulted in a cost actual decrease of $ 52.18 .

Summary DEP’s CSS Project Manager and Terracon’s Project Manager have both agreed to the scope of work, associated costs, and above changes. All changes noted above represent a total overall cost increase of $1,362.0 , as shown in the Final LOE . Due to a rounding error in Excel, The changes were noted in the TACO Request received from Terracon on May 7, 2025. The final cost associated with this TA increased from $48,751.83 to $50,113.8 . Documentation of the changes is included in the attached TACO Request, the Delta LOE spreadsheet and the Final LOE spreadsheet, and the TACO form for CSS03B C1, prepared by the Department.

www.FloridaDEP.gov

FDEP COST ESTIMATE

Contractor: Terracon HW687

Date: 5/7/2025 PEQ257126 Task #: SubTask 1 Project Management

Site: Former Cal-Spray Chemical Co. SubTask 2 Site Investigation Activity/Phase: SI and SIR FINAL SubTask 3 IDW Management

Project Manager: Claire Field SubTask 4 Site Inspection Report SubTask 5

Totals 1 2 3 4 5 Labor Rate Category

$29.47 Project Manager Nicole Kovach 23.07 23.07 $78.85 Senior Geolgist Tom Lewis 0.00 0.00 0.00 0.00 0.00 $26.75 CADD Specialist Cali Mays 6.00 0.00 0.00 6.00 0.00 $29.10 Environmental Technician Pat Beers 39.50 37.50 2.00 0.00 0.00 $29.47 Staff Scientist Nicole Kovach 58.00 38.00 0.00 20.00 0.00 $70.14 Senior Engineer Donna Cline 31.50 19.00 1.50 11.00 0.00

Total Hours 158.07 23.07 94.50 3.50 37.00 0.00

Direct Labor $5,908.34 $679.72 $3,543.77 $163.41 $1,521.44 $0.00

Overhead 116.00% $6,853.68 $788.48 $4,110.77 $189.56 $1,764.87 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 56.263% $3,324.21 $382.43 $1,993.83 $91.94 $856.01 $0.00 Total Labor $16,086.23 $1,850.63 $9,648.37 $444.91 $4,142.32 $0.00

Travel Vehicle charge $920.00 800.00$ 120.00$ $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $222.00 222.00$ $0.00 $0.00 $0.00 Total Travel $1,142.00 $1,022.00 $120.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (DPT) - Action Environmental $8,330.00 8,330.00$ $0.00 $0.00 $0.00 IDW - Erwin Remediation $800.00 $0.00 800.00$ $0.00 $0.00 Geophysical - GPRS $700.00 700.00$ $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 Subcontractor Subtotal $9,830.00 $9,030.00 $800.00 $0.00 $0.00 Handling Fee $983.00 $903.00 $80.00 $0.00 $0.00 Total Subcontractor Cost $10,813.00 $9,933.00 $880.00 $0.00 $0.00

Laboratory Analytical Costs $18,215.00 $18,215.00 $0.00 $0.00 $0.00 Sample Shipping $300.00 $300.00 $0.00 $0.00 $0.00 Total Laboratory $18,515.00 $18,515.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $300.00 300.00$ $0.00 $0.00 $0.00 Expendables $146.00 146.00$ $0.00 $0.00 $0.00 Equipment (Drilling related) $48.00 48.00$ $0.00 $0.00 $0.00 Equipment (Analytical related) $1,230.00 1,230.00$ $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $225.00 225.00$ $0.00 $0.00 $0.00 Total Field Expenses $1,949.00 $1,949.00 $0.00 $0.00 $0.00

Subtotal $48,505.23 $1,850.63 $41,067.37 $1,444.91 $4,142.32 $0.00 Completion Fee $1,608.62 $185.06 $964.84 $44.49 $414.23 $0.00

Total Estimated Cost $50,113.85 $2,035.69 $42,032.21 $1,489.40 $4,556.55 $0.00

Original $48,751.83 $2,042.49 $41,491.21 $609.40 $4,608.73 Change $1,362.06 ($6.77) $541.00 $880.00 ($52.17) Original + change $50,113.89 $2,035.72 $42,032.21 $1,489.40 $4,556.56 Final $50,113.85 $2,035.69 $42,032.21 $1,489.40 $4,556.55 Check $0.04 $0.03 $0.00 $0.00 $0.01

REV: 02/03 CEF TERRACON Page 1

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Former Cal-Spray Chemical Co.

SUBTASK 2: Site Investigation

PROPOSAL NO. PEQ257126 FINAL

DATE: 5/5/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

PreTask Planning / Meeting / GPR Oversight / Prepare final Trip Report Senior Engineer DC 4.0

Staff Scientist NK 1.0 Senior Engineer DC 4.0 Staff Scientist NK 2.0

Field Activities - Soil Sampling and Temporary Well Installation (Driller estimated 1.5 day) Senior Engineer DC Kickoff meeting, project oversight and direct work logistics (2 hrs/day) 4.00 Staff Scientist PB Load/unload equipment (1 hr/day) 1.00 Staff Scientist NK Oversight and documentation of well installation, record lithological descriptions 15.00 Environmental Technician PB Collect soil samples for analysis during well installation 15.00 Environmental Technician PB Collect QA samples Staff Scientist NK Utilize Level C PPE to collect soil samples from below the floor slab 2.00 Environmental Technician PB Utilize Level C PPE to collect soil samples from below the floor slab (buddy system) 2.00 Environmental Technician PB Survey top of casing elevation at completion of temporary well installation 1.50 Environmental Technician NK Assist with surveying of temporary well installation 1.50 Environmental Technician NK GPS locations 1.00 Senior Engineer DC QA/QC of procedures and finalize field notes/lithological logs and survey at end of day (0.5 hr/day) 1.00

Field Activities - Temporary and Permanent Monitoring Well Sampling Environmental Technician PB Load/unload equipment (1 hr/day) 1.00 Environmental Technician PB DTW collection (10 minutes/well, 9 wells) 1.50 Environmental Technician PB Purge and groundwater sampling 5 monitoring wells (1.5 hours/well), includes equipment calibration 7.50 Staff Scientist NK Purge and groundwater sampling 4 monitoring wells (1.5 hours/well), includes equipment calibration 6.00 Senior Scientist/Geologist DC QA/QC of procedures and finalize field notes and groundwater sampling logs 2.00 Environmental Technician PB IDW staging, IDW sample collection (1 soil and 1 water drum) 1.50 Staff Scientist NK IDW staging, IDW sample collection (1 soil and 1 water drum) 1.50

Field Activities - Temporary Monitoring Well Abandonment Environmental Technician PB Oversee Florida liscened driller properly abandon the temporary monitoring wells 2.50

Mobilization / Demobilizations Senior Scientist/Geologist DC Preconstruction meeting (4 hour/day) 4.00 Staff Scientist NK Preconstruction meeting/oversee TMW install/ soil sampling/TOC survey (4 hour/event [overnight]) 4.00 Environmental Technician PB Oversee TMW install/ soil sampling/TOC survey (1 hour/day, 2 days) 2.00 Staff Scientist NK DTW, survey TOC, groundwater Sampling (4 hour/day) 4.00 Environmental Technician PB DTW, survey TOC, groundwater Sampling (1 hour/day) 1.00 Environmental Technician PB Oversee well abandonment (1 hour/day) 1.00

Personnel: DC NK PB Hours: 19.00 38.00 37.50 TOTAL LABOR 94.50

VEHICLE TYPE RATE UNIT USEAGE

Auto (Senior Engineer) 80.00$ day 1 80.00$ Truck (Staff Scientist) 120.00$ day 3 360.00$ Truck (Environmental Technician) 120.00$ days 3 360.00$

TOTAL VEHICLE 800.00$

PER DIEM STAFF RATE UNIT USEAGE

Per diem NK 36.00$ 2 72.00$ Hotel NK 150.00$ 1 150.00$

TOTAL PER DIEM 222.00$

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

GPRS 700.00$ lump sum 0 700.00$ Action Environmental 8,030.00$ lump sum 0 8,030.00$

Action Environmental 300.00$ lump sum 1 WCD1 300.00$

TOTAL SUBCONTRACTOR 8,730.00$

PreTask Field Planning, Site Safety, Schedule/Coordinate with Owner & FDEP lab, coordinate with GPR subcontractor, prepare soil boring logs, monitoring well construciton and development and groundwater sampling logs. Prepare for Level C soil sampling, acquiring necessary PPE.

PreTask meeting with owner, driller, geophysical subcontractor and FDEP (same day as drilling0 PreTask Meeting and flag soil boring location and oversight of GPRS Prepare trip report of field investigation activities at completion of work.

Geophysical Survey Installation of temporary monitoring wells, including well abandonment Extra over-casing (4-in) to get good sand pack from hand installed MW ($140) and for 2 drums ($160)

SUBTASK 2: Site Investigation

PROPOSAL NO. PEQ257126 FINAL

DATE: 5/5/2025

PARAMETER RATE # SAMPLES IDW Units Soil Analysis Total VOCs (PID/Hall Series) EPA 8260 110.00$ 19 2 $2,310.00 Total VOCs Prep EPA Method 5035 prep 7.00$ 19 2 $147.00 Organochlorine hydrocarbons EPA Method 8081 105.00$ 19 2 $2,205.00 Organo - N/P EPA Method 8141 170.00$ 19 2 $3,570.00 RCRA 7 EPA Method 6020 98.00$ 19 2 $2,058.00 RCRA Mercury EPA Method 7470/7471 28.00$ 19 2 $588.00 TCLP RCRA 8 EPA Method 1311/6010/7470 130.00$ 0 2 WCD2 $260.00 TCLP VOCs EPA Method 1311/8260 175.00$ 0 2 WCD2 $350.00 Sample Shipping Large Cooler (overnight) 150.00$ 1 $150.00 Groundwater Analysis $0.00 Total VOCs (PID/Hall Series) EPA 8260 110.00$ 13 1 $1,540.00 Organochlorine hydrocarbons EPA Method 8081 105.00$ 13 1 $1,470.00 Organochlorine hydrocarbons EPA Method 8081 105.00$ -1 0 p y VOCs ($105.00)

Organo - N/P EPA Method 8141 170.00$ 13 1 $2,380.00 Organo - N/P EPA Method 8141 170.00$ -1 0 ($170.00) RCRA 7 EPA Method 6020 98.00$ 13 1 $1,372.00 RCRA 7 EPA Method 6020 98.00$ -1 0 ($98.00) RCRA Mercury EPA Method 7470/7471 26.00$ 13 1 $364.00 RCRA Mercury EPA Method 7470/7471 26.00$ -1 0 ($26.00) Sample Shipping Large Cooler (overnight) 150.00$ 1 $150.00

TOTAL LAB $18,515.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Personnel Protection Level C 150.00$ Units-per man day 2 300.00$ Expendables Expendables 40.00$ day 3 120.00$

Ice (preservation of samples/2 per day) 6.50$ day 4 26.00$ Equipment (Soil/drilling) 12.00$ day 4 48.00$

11.00$ each 10 110.00$ 16.00$ day 10 160.00$

Equipment (Analytical) Monitoring Well Installation Kit 325.00$ day 2 650.00$

Shallow Groundwater Sampling Kit 290.00$ day 2 580.00$

IDW related (Drums provided by Driller) each 0

Equipment (other) Total Survey Station 50.00$ day 1 50.00$

GPS, Trimble 175.00$ day 1 175.00$

TOTAL EQUIPMENT 2,219.00$

TCLP/SPLP analysis will be submitted as WCD if required.

Hand auger (2 sets per day) Terra Core Sampler Encore Sampler

SUBTASK 3: IDW Management

PROPOSAL NO. PEQ257126 FINAL

DATE: 5/5/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION FINAL HOURS

IDW Management Senior Engineer DC 1.50 Environmental Technician PB 2.00

Personnel: DC PB Hours: 1.50 2.00 TOTAL LABOR 3.50

VEHICLE TYPE RATE UNIT USEAGE

Truck (Environmental Technician) 120.00$ days 1 120.00$

TOTAL VEHICLE 120.00$

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

Erwin Remediation 800.00$ 5 water & 2 soils WCD3 800.00$

TOTAL SUBCONTRACTOR 800.00$

LABORATORY COSTS

PARAMETER RATE # SAMPLES IDW QA/QC

Soil VOCs - Halocarbons EPA 8260 -$ 8 0 $0.00 IDW Encore Sampler -$ 8 $0.00 Soil VOCs - Halocarbons EPA 8260 -$ 5 0 $0.00

Sample Shipping Small Cooler (overnight) -$ $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Personnel Protection Level C 150.00$ Unit-per man day 0 -$ Expendables Expendables 40.00$ day 0 -$

Terra Core Sampler 11.00$ each 0 -$ IDW No IDW drummed each 0 Drilling Monitoring Well Installation Kit 325.00$ day 0 -$ Analytical Shallow Groundwater Sampling Kit 290.00$ day 0 -$

Tubing, HDPE 0.30$ ft 0 -$ Tubing, silicon (3/16 x 3/8) 5.00$ ft 0 -$

Other Total Survey Station 50.00$ day 0 -$

TOTAL EQUIPMENT -$

Prepare waste characterization/Generator Profile Coordinate IDW T&D: Mobilize to site, meet transporter to sign manifests

IDW Disposal of drums decon water, purgewater, drill cuttings)

Note all analytical samples will be analyzed by the FDEP Laboratory.

SUBTASK 4: Site Inspection Report

PROPOSAL NO. PEQ257126 FINAL

DATE: 5/5/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION FINAL HOURS

Staff Scientist NK 12.00 Staff Scientist NK 8.00 Senior Scientist/Geologist DC QA/QC field and laboratory data 2.00 Senior Scientist/Geologist DC Soil and Water Quality Parameters Summary Evaluation 2.00 Senior Scientist/Geologist DC Groundwater Analytical Results and Summary Evaluation 3.00 Senior Geologist DC Evaluate background calculations, cleanup target levels 2.00 Senior Geologist TL Provide conclusions, recommendation, Sign and Seal Investigation Report 2.00 Senior Geologist TL Provide conclusions, recommendation, Sign and Seal Investigation Report (2.00) Senior Engineer DC Provide conclusions, recommendation, Sign and Seal Investigation Report 2.00 CADD Specialist CM 6.00

Personnel: NK DC TL CM Hours: 20.00 11.00 0.00 6.00 TOTAL LABOR 37.00

Prepare draft summary tables and draft drawing for GIS Summarize field data and tabulate analytical data, prepare draft Exhibits

Prepare Exhibits (site setting, groundwater flow and concentrations maps and concentration maps, various Contaminants of Concern)

Date: 5/7/2025 PEQ257126 Task #: SubTask 1 Project Management

Site: Former Cal-Spray Chemical Co. SubTask 2 Site Investigation Activity/Phase: SI and SIR SubTask 3 IDW Management

Project Manager: Claire Field SubTask 4 Site Inspection Report SubTask 5

Totals 1 2 3 4 5 Labor Rate Category

$29.47 Project Manager Nicole Kovach -0.08 -0.08 $78.85 Senior Geolgist Tom Lewis -2.00 0.00 0.00 -2.00 0.00 $26.75 CADD Specialist Cali Mays 0.00 0.00 0.00 0.00 0.00 $29.10 Environmental Technician Pat Beers 0.00 0.00 0.00 0.00 0.00 $29.47 Staff Scientist Nicole Kovach 0.00 0.00 0.00 0.00 0.00 $70.14 Senior Engineer Donna Cline 2.00 0.00 0.00 2.00 0.00

Total Hours -0.08 -0.08 0.00 0.00 0.00 0.00

Direct Labor ($19.68) ($2.26) $0.00 $0.00 ($17.42) $0.00

Overhead 116.00% ($22.83) ($2.62) $0.00 $0.00 ($20.21) $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 56.263% ($11.07) ($1.27) $0.00 $0.00 ($9.80) $0.00 Total Labor ($53.58) ($6.15) $0.00 $0.00 ($47.43) $0.00

Travel Vehicle charge $0.00 -$ -$ $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 -$ $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (DPT) - Action Environmental $300.00 300.00$ $0.00 $0.00 $0.00 IDW - Erwin Remediation $800.00 $0.00 800.00$ $0.00 $0.00 Geophysical - GPRS $0.00 -$ $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 Subcontractor Subtotal $1,100.00 $300.00 $800.00 $0.00 $0.00 Handling Fee $110.00 $30.00 $80.00 $0.00 $0.00 Total Subcontractor Cost $1,210.00 $330.00 $880.00 $0.00 $0.00

Laboratory Analytical Costs $211.00 $211.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $211.00 $211.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 -$ $0.00 $0.00 $0.00 Expendables $0.00 -$ $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 -$ $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 -$ $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 -$ $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $1,367.42 ($6.15) $541.00 $880.00 ($47.43) $0.00 Completion Fee ($5.36) ($0.62) $0.00 $0.00 ($4.74) $0.00

Total Estimated Cost $1,362.06 ($6.77) $541.00 $880.00 ($52.17) $0.00

SUBTASK 2: Site Investigation

PROPOSAL NO. PEQ257126 DELTA

DATE: 5/5/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

PreTask Planning / Meeting / GPR Oversight / Prepare final Trip Report Senior Engineer DC 4.0

Staff Scientist NK 1.0 Senior Engineer DC 4.0 Staff Scientist NK 2.0

Field Activities - Soil Sampling and Temporary Well Installation (Driller estimated 1.5 day) Senior Engineer DC Kickoff meeting, project oversight and direct work logistics (2 hrs/day) 4.00 Staff Scientist PB Load/unload equipment (1 hr/day) 1.00 Staff Scientist NK Oversight and documentation of well installation, record lithological descriptions 15.00 Environmental Technician PB Collect soil samples for analysis during well installation 15.00 Environmental Technician PB Collect QA samples Staff Scientist NK Utilize Level C PPE to collect soil samples from below the floor slab 2.00 Environmental Technician PB Utilize Level C PPE to collect soil samples from below the floor slab (buddy system) 2.00 Environmental Technician PB Survey top of casing elevation at completion of temporary well installation 1.50 Environmental Technician NK Assist with surveying of temporary well installation 1.50 Environmental Technician NK GPS locations 1.00 Senior Engineer DC QA/QC of procedures and finalize field notes/lithological logs and survey at end of day (0.5 hr/day) 1.00

Field Activities - Temporary and Permanent Monitoring Well Sampling Environmental Technician PB Load/unload equipment (1 hr/day) 1.00 Environmental Technician PB DTW collection (10 minutes/well, 9 wells) 1.50 Environmental Technician PB Purge and groundwater sampling 5 monitoring wells (1.5 hours/well), includes equipment calibration 7.50 Staff Scientist NK Purge and groundwater sampling 4 monitoring wells (1.5 hours/well), includes equipment calibration 6.00 Senior Scientist/Geologist DC QA/QC of procedures and finalize field notes and groundwater sampling logs 2.00 Environmental Technician PB IDW staging, IDW sample collection (1 soil and 1 water drum) 1.50 Staff Scientist NK IDW staging, IDW sample collection (1 soil and 1 water drum) 1.50

Field Activities - Temporary Monitoring Well Abandonment Environmental Technician PB Oversee Florida liscened driller properly abandon the temporary monitoring wells 2.50

Mobilization / Demobilizations Senior Scientist/Geologist DC Preconstruction meeting (4 hour/day) 4.00 Staff Scientist NK Preconstruction meeting/oversee TMW install/ soil sampling/TOC survey (4 hour/event [overnight]) 4.00 Environmental Technician PB Oversee TMW install/ soil sampling/TOC survey (1 hour/day, 2 days) 2.00 Staff Scientist NK DTW, survey TOC, groundwater Sampling (4 hour/day) 4.00 Environmental Technician PB DTW, survey TOC, groundwater Sampling (1 hour/day) 1.00 Environmental Technician PB Oversee well abandonment (1 hour/day) 1.00

Personnel: DC NK PB Hours: 0.00 0.00 0.00 TOTAL LABOR 94.50

VEHICLE TYPE RATE UNIT USEAGE

Auto (Senior Engineer) 80.00$ day 0 -$ Truck (Staff Scientist) 120.00$ day 0 -$ Truck (Environmental Technician) 120.00$ days 0 -$

TOTAL VEHICLE -$

PER DIEM STAFF RATE UNIT USEAGE

Per diem NK 36.00$ 0 -$ Hotel NK 150.00$ 0 -$

TOTAL PER DIEM -$

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

GPRS 700.00$ lump sum 0 -$ Action Environmental 8,030.00$ lump sum 0 -$

Action Environmental 300.00$ lump sum 1 WCD1 300.00$

TOTAL SUBCONTRACTOR -$

Extra over-casing (4-in) to get good sand pack from hand installed MW ($140) and for 2 drums ($160)

Installation of temporary monitoring wells, including well abandonment

PreTask Field Planning, Site Safety, Schedule/Coordinate with Owner & FDEP lab, coordinate with GPR subcontractor, prepare soil boring logs, monitoring well construciton and development and groundwater sampling logs. Prepare for Level C soil sampling, acquiring necessary PPE.

PreTask meeting with owner, driller, geophysical subcontractor and FDEP (same day as drilling0 PreTask Meeting and flag soil boring location and oversight of GPRS Prepare trip report of field investigation activities at completion of work.

Geophysical Survey

SUBTASK 2: Site Investigation

PROPOSAL NO. PEQ257126 DELTA

DATE: 5/5/2025

PARAMETER RATE # SAMPLES IDW Units Soil Analysis Total VOCs (PID/Hall Series) EPA 8260 110.00$ 0 0 $0.00 Total VOCs Prep EPA Method 5035 prep 7.00$ 0 0 $0.00 Organochlorine hydrocarbons EPA Method 8081 105.00$ 0 0 $0.00 Organo - N/P EPA Method 8141 170.00$ 0 0 $0.00 RCRA 7 EPA Method 6020 98.00$ 0 0 $0.00 RCRA Mercury EPA Method 7470/7471 28.00$ 0 0 $0.00 TCLP RCRA 8 EPA Method 1311/6010/7470 130.00$ 0 2 WCD2 $260.00 TCLP VOCs EPA Method 1311/8260 175.00$ 0 2 WCD2 $350.00 Sample Shipping Large Cooler (overnight) 150.00$ 0 $0.00 Groundwater Analysis $0.00 Total VOCs (PID/Hall Series) EPA 8260 110.00$ 0 0 $0.00 Organochlorine hydrocarbons EPA Method 8081 105.00$ 0 0 $0.00 Organochlorine hydrocarbons EPA Method 8081 105.00$ -1 0 p y VOCs ($105.00)

Organo - N/P EPA Method 8141 170.00$ 0 0 $0.00 Organo - N/P EPA Method 8141 170.00$ -1 0 ($170.00) RCRA 7 EPA Method 6020 98.00$ 0 0 $0.00 RCRA 7 EPA Method 6020 98.00$ -1 0 ($98.00) RCRA Mercury EPA Method 7470/7471 26.00$ 0 0 $0.00 RCRA Mercury EPA Method 7470/7471 26.00$ -1 0 ($26.00) Sample Shipping Large Cooler (overnight) 150.00$ 0 $0.00

TOTAL LAB $211.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Personnel Protection Level C 150.00$ Units-per man day 0 -$ Expendables Expendables 40.00$ day 0 -$

Ice (preservation of samples/2 per day) 6.50$ day 0 -$ Equipment (Soil/drilling) 12.00$ day 0 -$

11.00$ each 0 -$ 16.00$ day 0 -$

Equipment (Analytical) Monitoring Well Installation Kit 325.00$ day 0 -$

Shallow Groundwater Sampling Kit 290.00$ day 0 -$

IDW related (Drums provided by Driller) each 0

Equipment (other) Total Survey Station 50.00$ day 0 -$

GPS, Trimble 175.00$ day 0 -$

TOTAL EQUIPMENT -$

TCLP/SPLP analysis will be submitted as WCD if required.

Hand auger (2 sets per day) Terra Core Sampler Encore Sampler

SUBTASK 3: IDW Management

PROPOSAL NO. PEQ257126 DELTA

DATE: 5/5/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION FINAL HOURS

IDW Management Senior Engineer DC 1.50 Environmental Technician PB 2.00

Personnel: DC PB Hours: 0.00 0.00 TOTAL LABOR 3.50

VEHICLE TYPE RATE UNIT USEAGE

Truck (Environmental Technician) 120.00$ days 0 -$

TOTAL VEHICLE -$

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

Erwin Remediation 800.00$ 5 water & 2 soils WCD3 800.00$

TOTAL SUBCONTRACTOR 800.00$

LABORATORY COSTS

PARAMETER RATE # SAMPLES IDW QA/QC

Soil VOCs - Halocarbons EPA 8260 -$ 0 0 $0.00 IDW Encore Sampler -$ 0 $0.00 Soil VOCs - Halocarbons EPA 8260 -$ 0 0 $0.00

Sample Shipping Small Cooler (overnight) -$ $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Personnel Protection Level C 150.00$ Unit-per man day 0 -$ Expendables Expendables 40.00$ day 0 -$

Terra Core Sampler 11.00$ each 0 -$ IDW No IDW drummed each 0 Drilling Monitoring Well Installation Kit 325.00$ day 0 -$ Analytical Shallow Groundwater Sampling Kit 290.00$ day 0 -$

Tubing, HDPE 0.30$ ft 0 -$ Tubing, silicon (3/16 x 3/8) 5.00$ ft 0 -$

Other Total Survey Station 50.00$ day 0 -$

TOTAL EQUIPMENT -$

Prepare waste characterization/Generator Profile Coordinate IDW T&D: Mobilize to site, meet transporter to sign manifests

IDW Disposal of drums decon water, purgewater, drill cuttings)

Note all analytical samples will be analyzed by the FDEP Laboratory.

SUBTASK 4: Site Inspection Report

PROPOSAL NO. PEQ257126 DELTA

DATE: 5/5/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION FINAL HOURS

Staff Scientist NK 0.00 Staff Scientist NK 0.00 Senior Scientist/Geologist DC QA/QC field and laboratory data 0.00 Senior Scientist/Geologist DC Soil and Water Quality Parameters Summary Evaluation 0.00 Senior Scientist/Geologist DC Groundwater Analytical Results and Summary Evaluation 0.00 Senior Geologist DC Evaluate background calculations, cleanup target levels 0.00 Senior Geologist TL Provide conclusions, recommendation, Sign and Seal Investigation Report 0.00 Senior Geologist TL Provide conclusions, recommendation, Sign and Seal Investigation Report (2.00) Senior Engineer DC Provide conclusions, recommendation, Sign and Seal Investigation Report 2.00 CADD Specialist CM 0.00

Personnel: NK DC TL CM Hours: 0.00 2.00 (2.00) 0.00 TOTAL LABOR 0.00

Prepare draft summary tables and draft drawing for GIS Summarize field data and tabulate analytical data, prepare draft Exhibits

Prepare Exhibits (site setting, groundwater flow and concentrations maps and concentration maps, Date: 4/29/2025 PEQ257126 Task #: SubTask 1 Project Management

Site: Former Cal-Spray Chemical Co. SubTask 2 Site Investigation Activity/Phase: SI and SIR ORIGINAL SubTask 3 IDW Management

Project Manager: Claire Field SubTask 4 Site Inspection Report SubTask 5

Totals 1 2 3 4 5 Labor Rate Category

$29.47 Project Manager Nicole Kovach 23.14 23.14 $78.85 Senior Geolgist Tom Lewis 2.00 0.00 0.00 2.00 0.00 $26.75 CADD Specialist Cali Mays 6.00 0.00 0.00 6.00 0.00 $29.10 Environmental Technician Pat Beers 39.50 37.50 2.00 0.00 0.00 $29.47 Staff Scientist Nicole Kovach 58.00 38.00 0.00 20.00 0.00 $70.14 Senior Engineer Donna Cline 29.50 19.00 1.50 9.00 0.00

Total Hours 158.14 23.14 94.50 3.50 37.00 0.00

Direct Labor $5,928.03 $681.99 $3,543.77 $163.41 $1,538.86 $0.00

Overhead 116.00% $6,876.52 $791.11 $4,110.77 $189.56 $1,785.08 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 56.263% $3,335.29 $383.71 $1,993.83 $91.94 $865.81 $0.00 Total Labor $16,139.84 $1,856.81 $9,648.37 $444.91 $4,189.75 $0.00

Travel Vehicle charge $920.00 800.00$ 120.00$ $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $222.00 222.00$ $0.00 $0.00 $0.00 Total Travel $1,142.00 $1,022.00 $120.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (DPT) - Action Environmental $8,030.00 8,030.00$ $0.00 $0.00 $0.00

IDW (WCD) $0.00 $0.00 $0.00 $0.00 $0.00

Geophysical - GPRS $700.00 700.00$ $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 Subcontractor Subtotal $8,730.00 $8,730.00 $0.00 $0.00 $0.00 Handling Fee $873.00 $873.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $9,603.00 $9,603.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $18,004.00 $18,004.00 $0.00 $0.00 $0.00 Sample Shipping $300.00 $300.00 $0.00 $0.00 $0.00 Total Laboratory $18,304.00 $18,304.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $300.00 300.00$ $0.00 $0.00 $0.00 Expendables $146.00 146.00$ $0.00 $0.00 $0.00 Equipment (Drilling related) $48.00 48.00$ $0.00 $0.00 $0.00 Equipment (Analytical related) $1,230.00 1,230.00$ $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $225.00 225.00$ $0.00 $0.00 $0.00 Total Field Expenses $1,949.00 $1,949.00 $0.00 $0.00 $0.00

Subtotal $47,137.84 $1,856.81 $40,526.37 $564.91 $4,189.75 $0.00 Completion Fee $1,613.99 $185.68 $964.84 $44.49 $418.98 $0.00

Total Estimated Cost $48,751.83 $2,042.49 $41,491.21 $609.40 $4,608.73 $0.00

SUBTASK 2: Site Investigation

PROPOSAL NO. PEQ257126 ORIGINAL

DATE: 4/29/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

PreTask Planning / Meeting / GPR Oversight / Prepare final Trip Report Senior Engineer DC 4.0

Staff Scientist NK 1.0 Senior Engineer DC 4.0 Staff Scientist NK 2.0

Field Activities - Soil Sampling and Temporary Well Installation (Driller estimated 1.5 day) Senior Engineer DC Kickoff meeting, project oversight and direct work logistics (2 hrs/day) 4.00 Staff Scientist PB Load/unload equipment (1 hr/day) 1.00 Staff Scientist NK Oversight and documentation of well installation, record lithological descriptions 15.00 Environmental Technician PB Collect soil samples for analysis during well installation 15.00 Environmental Technician PB Collect QA samples Staff Scientist NK Utilize Level C PPE to collect soil samples from below the floor slab 2.00 Environmental Technician PB Utilize Level C PPE to collect soil samples from below the floor slab (buddy system) 2.00 Environmental Technician PB Survey top of casing elevation at completion of temporary well installation 1.50 Environmental Technician NK Assist with surveying of temporary well installation 1.50 Environmental Technician NK GPS locations 1.00 Senior Engineer DC QA/QC of procedures and finalize field notes/lithological logs and survey at end of day (0.5 hr/day) 1.00

Field Activities - Temporary and Permanent Monitoring Well Sampling Environmental Technician PB Load/unload equipment (1 hr/day) 1.00 Environmental Technician PB DTW collection (10 minutes/well, 9 wells) 1.50 Environmental Technician PB Purge and groundwater sampling 5 monitoring wells (1.5 hours/well), includes equipment calibration 7.50 Staff Scientist NK Purge and groundwater sampling 4 monitoring wells (1.5 hours/well), includes equipment calibration 6.00 Senior Scientist/Geologist DC QA/QC of procedures and finalize field notes and groundwater sampling logs 2.00 Environmental Technician PB IDW staging, IDW sample collection (1 soil and 1 water drum) 1.50 Staff Scientist NK IDW staging, IDW sample collection (1 soil and 1 water drum) 1.50

Field Activities - Temporary Monitoring Well Abandonment Environmental Technician PB Oversee Florida liscened driller properly abandon the temporary monitoring wells 2.50

Mobilization / Demobilizations Senior Scientist/Geologist DC Preconstruction meeting (4 hour/day) 4.00 Staff Scientist NK Preconstruction meeting/oversee TMW install/ soil sampling/TOC survey (4 hour/event [overnight]) 4.00 Environmental Technician PB Oversee TMW install/ soil sampling/TOC survey (1 hour/day, 2 days) 2.00 Staff Scientist NK DTW, survey TOC, groundwater Sampling (4 hour/day) 4.00 Environmental Technician PB DTW, survey TOC, groundwater Sampling (1 hour/day) 1.00 Environmental Technician PB Oversee well abandonment (1 hour/day) 1.00

Personnel: DC NK PB Hours: 19.00 38.00 37.50 TOTAL LABOR 94.50

VEHICLE TYPE RATE UNIT USEAGE

Auto (Senior Engineer) 80.00$ day 1 80.00$ Truck (Staff Scientist) 120.00$ day 3 360.00$ Truck (Environmental Technician) 120.00$ days 3 360.00$

TOTAL VEHICLE 800.00$

PER DIEM STAFF RATE UNIT USEAGE

Per diem NK 36.00$ 2 72.00$ Hotel NK 150.00$ 1 150.00$

TOTAL PER DIEM 222.00$

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

GPRS 700.00$ lump sum 0 700.00$ Action Environmental 8,030.00$ lump sum 0 8,030.00$

TOTAL SUBCONTRACTOR 8,730.00$

PreTask Field Planning, Site Safety, Schedule/Coordinate with Owner & FDEP lab, coordinate with GPR subcontractor, prepare soil boring logs, monitoring well construciton and development and groundwater sampling logs. Prepare for Level C soil sampling, acquiring necessary PPE.

Prepare trip report of field investigation activities at completion of work.

PreTask Meeting and flag soil boring location and oversight of GPRS

Geophysical Survey Installation of temporary monitoring wells, including well abandonment

PreTask meeting with owner, driller, geophysical subcontractor and FDEP (same day as drilling0

SUBTASK 2: Site Investigation

PROPOSAL NO. PEQ257126 ORIGINAL

DATE: 4/29/2025

PARAMETER RATE # SAMPLES IDW Units Soil Analysis Total VOCs (PID/Hall Series) EPA 8260 110.00$ 19 2 $2,310.00 Total VOCs Prep EPA Method 5035 prep 7.00$ 19 2 $147.00 Organochlorine hydrocarbons EPA Method 8081 105.00$ 19 2 $2,205.00 Organo - N/P EPA Method 8141 170.00$ 19 2 $3,570.00 RCRA 7 EPA Method 6020 98.00$ 19 2 $2,058.00 RCRA Mercury EPA Method 7470/7471 28.00$ 19 2 $588.00 Sample Shipping Large Cooler (overnight) 150.00$ 1 $150.00 Groundwater Analysis $0.00 Total VOCs (PID/Hall Series) EPA 8260 110.00$ 13 1 $1,540.00 Organochlorine hydrocarbons EPA Method 8081 105.00$ 13 1 $1,470.00 Organo - N/P EPA Method 8141 170.00$ 13 1 $2,380.00 RCRA 7 EPA Method 6020 98.00$ 13 1 $1,372.00 RCRA Mercury EPA Method 7470/7471 26.00$ 13 1 $364.00 Sample Shipping Large Cooler (overnight) 150.00$ 1 $150.00

TOTAL LAB $18,304.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Personnel Protection Level C 150.00$ Units-per man day 2 300.00$ Expendables Expendables 40.00$ day 3 120.00$

Ice (preservation of samples/2 per day) 6.50$ day 4 26.00$ Equipment (Soil/drilling) 12.00$ day 4 48.00$

11.00$ each 10 110.00$ 16.00$ day 10 160.00$

Equipment (Analytical) Monitoring Well Installation Kit 325.00$ day 2 650.00$ Shallow Groundwater Sampling Kit 290.00$ day 2 580.00$

IDW related (Drums provided by Driller) each 0

Equipment (other) Total Survey Station 50.00$ day 1 50.00$

GPS, Trimble 175.00$ day 1 175.00$

TOTAL EQUIPMENT 2,219.00$

Terra Core Sampler Encore Sampler

Hand auger (2 sets per day)

TCLP/SPLP analysis will be submitted as WCD if required.

SUBTASK 3: IDW Management

PROPOSAL NO. PEQ257126 ORIGINAL

DATE: 4/29/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

IDW Management Senior Engineer DC 1.50 Environmental Technician PB 2.00

Personnel: DC PB Hours: 1.50 2.00 TOTAL LABOR 3.50

VEHICLE TYPE RATE UNIT USEAGE

Truck (Environmental Technician) 120.00$ days 1 120.00$

TOTAL VEHICLE 120.00$

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

IDW Contractor Work Change Directive

TOTAL SUBCONTRACTOR -$

LABORATORY COSTS

PARAMETER RATE # SAMPLES IDW QA/QC

Soil VOCs - Halocarbons EPA 8260 -$ 8 0 $0.00 IDW Encore Sampler -$ 8 $0.00 Soil VOCs - Halocarbons EPA 8260 -$ 5 0 $0.00

Sample Shipping Small Cooler (overnight) -$ $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Personnel Protection Level C 150.00$ Unit-per man day 0 -$ Expendables Expendables 40.00$ day 0 -$

Terra Core Sampler 11.00$ each 0 -$ IDW No IDW drummed each 0 Drilling Monitoring Well Installation Kit 325.00$ day 0 -$ Analytical Shallow Groundwater Sampling Kit 290.00$ day 0 -$

Tubing, HDPE 0.30$ ft 0 -$ Tubing, silicon (3/16 x 3/8) 5.00$ ft 0 -$

Other Total Survey Station 50.00$ day 0 -$

TOTAL EQUIPMENT -$

Prepare waste characterization/Generator Profile Coordinate IDW T&D: Mobilize to site, meet transporter to sign manifests

Note all analytical samples will be analyzed by the FDEP Laboratory.

IDW Disposal of drums decon water, purgewater, drill cuttings)

SUBTASK 4: Site Inspection Report

PROPOSAL NO. PEQ257126 ORIGINAL

DATE: 4/29/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Staff Scientist NK 12.00 Staff Scientist NK 8.00 Senior Scientist/Geologist DC QA/QC field and laboratory data 2.00 Senior Scientist/Geologist DC Soil and Water Quality Parameters Summary Evaluation 2.00 Senior Scientist/Geologist DC Groundwater Analytical Results and Summary Evaluation 3.00 Senior Geologist DC Evaluate background calculations, cleanup target levels 2.00 Senior Geologist TL Provide conclusions, recommendation, Sign and Seal Investigation Report 2.00 CADD Specialist CM 6.00

Personnel: NK DC TL CM Hours: 20.00 9.00 2.00 6.00 TOTAL LABOR 37.00

Prepare draft summary tables and draft drawing for GIS Summarize field data and tabulate analytical data, prepare draft Exhibits

Prepare Exhibits (site setting, groundwater flow and concentrations maps and concentration maps, G E

O P

H Y

S

IC

A L

S U

R V

E Y

S P

E C

IF

IC

A T

IO

N S it e a n d

A d d re ss

F or m er

C al

-S pr ay C he m ic al

C o, S ilv er S ta r

R oa d, O rl an do

O ra ng e

C ou nt y, F lo ri da

ER

IC

_1

It em o.

U n it o f

M ea su re

Es ti m at ed

Q u an ti ty

Lu m p

S um

Lu m p

S um

TO

TA

L N

O

D A

Y S

TO

TA

L

TO

TA

L

TO

TA

L

Lo w

B id

G P

R S

$6

.0

$3

.0

Ex te n d ed P ri ce

Ex te n d ed P ri ce

$4

.0

$3

.0

.0

.0

.0

C on ta ct or S pe ci fic

O th er

4-

1-

1 It em

D es cr ip ti on

P h on e:

1-

3-

4-

3-

Ex te n d ed P ri ce 45

0.

0.

M ob ili za ti on a nd

P er

D ie m

D em ob ili za ti on

C om p an y A d d re ss

S pa rr ow H aw k

R oa d Ja ck so nv ill e Ja ck so nv ill e

G en er al

I n fo rm at io n

T er ra co n is s ol ic it in g qu ot es f ro m t hr ee

3)

G

PR

s ub co nt ra ct or s, o n be ha lf of t he

F D

EP

fo r th e fo llo w in g sc op e of s er vi ce s.

T he su bc on tr ac to r w ill b e re sp on si bl e fo r al l n ec es sa ry p er m it s, p ub lic u ti lit y lo ca te s, e qu ip m en t an d pe rs on ne l t o co m pl et e th is s co pe o f w or k.

Th e su bc on tr ac to r sh ou ld b e aw ar e th at c ha ng es in s co pe m ay o cc ur o nc e th e w or k ha s be gu n.

om p an y N am e:

G eo

Te k

S er vi ce s, L

LC

G

PR

S

G eo

V ie w A ss oc ia te s In c.

Pa ge o f

D R

IL

LI

N G

S P

E C

IF

IC

A T

IO

N S

S h a ll o w

T e m p o ra ry

M o n it o ri n g

W e ll

I n st a ll a ti o n

S a n d A d d re ss

F or m er C al -S pr ay

C he m ic al C o, S ilv er S ta r

R oa d, O rl an do

O ra ng e

C ou nt y, F lo ri da

ER

IC

_1

It m o

U n it o f M e a su re E st im a te d a n ti ty

T o ta l

Li n e a r

Fe e t

U n it P ri ce

E x te n d ri ce

E st im a a n ti ty

T o ta l

Li n e a r

Fe e t

U n it P ri ce

E x te n d ce

E st im a a n ti ty

T o ta l

Li n e a r

Fe e t

U n it P ri ce

E x te n d ce

Lu m p

S um

0.

$5

.0

$2

,6

.0

$2 ,6

.0

D ay s

1.

$3

,2

.0

3, 0.

$1 ,7

.0

1, 0.

$2 ,2

.0

6, 0.

Ea ch

$3

.0

1, 0.

$1

,5

.0

9, 0.

$2

.0

1, 0.

D ru m

$8 0.

0.

$7 5.

0.

$8 5.

1, 0.

Lu m p

S um

0.

$1 ,3

.0

$1

,3

.0

1, 0.

L N

O

D A

Y S

1.

TO

TA

L 8, 0.

L

$1 2, 0.

TO

TA

L

$1 3, 0.

Lo w B

A ct io n E n vi ro n m en ta l

In st ll th o d

W ll te ri a l

T o ta l

D e p th S cr e

In rv a l

1 2 3 H an d

A ug er /D

PT

R is er

S C H

PV

C

S cr ee n

1" pr ep ac k

H

PV

(1 sl ot

4-

1" S

C H

PV

4 5 6 em ob ili za ti on

C on ta ct or S pe ci fic

O th er in cl ud e de sc ri pt io n be lo w

D ru m s fo r

ID

W

A ll so il w ill b e dr um m ed

A ll w at er w ill b e dr um m ed s ep ar at el y fr om s oi l.

D em ob ili za ti on t o in cl ud e st ag in g of d ru m s, r es to ra ti on o f pr op er ty an d cl ea nu p re qu ir ed f ro m e xp lo ra ti on a ct iv it ie s M on it or in g w el l a ba nd on m en t (r em ov e w el l m at er ia l a nd t re m ie g ro ut

C o n st ru ct io n D e ta il s

B a ck fi ll

I n te rv a l

M ob ili za ti on t o in cl ud e:

a ll eq ui pm en t ne ce ss ar y to c om pl et e th e id en ti fie d sc op e of w or k, in cl ud in g D

PT

d ri ll ri g, t oo lin g, t ru ck s, r es to ra ti on o r re pa ir o f da m ag ed s ur fa ce s

(e .g re pa ir o f co nc re te if da m ag ed b y dr ill r ig

S un sh in e ut ili ty lo ca te n um be r, 0-ho ur O

S H

A c er ti fic at es

S ix

6) s oi l b or in gs w ill b e ad va nc ed t o f ee t be lo w g ro un d su rf ac e

(b gs us in g ho llo w s te m a ug er

H

S A in st al la ti on

S oi l s am pl es w ill b e si m ul ta ne ou sl y co lle ct ed f ro m t w o in te rv al s (0

–1 f oo t bg s an d 1-fe et b gs

U po n re ac hi ng fe et b gs a te m po ra ry m on it or in g w el l w ill b e in st al le ea ch lo ca ti on w it h f ee t of

.0

-i nc h sl ot te d, p re pa ck ed s cr ee n an d

/6 si lic a sa nd

D ep th t o w at er is a pp ro xi m at el y fe et b gs

(0 -1

4'

0/ s an d

Lu m p su m w el l a ba nd on m en t, s ep ar at e m ob ili za ti on

IT

E

O It e m

S p e ci fi ca ti o n s

2-

7-m

D e sc ri p ti o n

M ob ili za ti on a nd

P er

D ie h o n e

7.

7.

4-

6-

G eo pr ob e D

PT

D ai ly

R ig

R at e

S ha llo w

M on it or in g

W el l M at er ia l/ In st al la ti on

D ru m s

(c on tr ac to r to e st im at e

ID

W b as ed o n sp ec s)

C o m p a n y A d d re ss

N

0t h S tr ee t, T am pa

FL

P ea ch tr ee

C ir cl e, D av ie

FL

S W th

P la ce

O ca la

FL

G en er al

I n fo rm at io n

T er ra co n is s ol ic it in g qu ot es f ro m t hr ee

3)

F lo ri da li ce ns ed w el l c on tr ac to rs on b eh al f of t he

F D

EP

f or t he f ol lo w in g sc op e of s er vi ce s.

he dr ill er w ill b e re sp on si bl e fo r al l n ec es sa ry p er m it s, p ub lic u ti lit y lo ca te s, e qu ip m en t an d pe rs on ne l t o co m pl et e th is s co pe o f w or k.

dr ill er s ho ul d be a w ar e th an ge s in s co pe m ay o cc ur o nc e th e w or k ha s be gu n.

co p e of

W or k:

In st al la ti on o f si x (6 so il bo ri ng s/

TM

W a dv an ce d to fe et b gs u si ng

D

PT

in st al la ti on

S oi l s am pl es c ol le ct ed f ro m t w o in te rv al s (0

–1 f oo t bg s an d 1-fe et b gs

TM

W w ill b e in st al le d at e ac h lo ca ti on w ith fe et o f 0.

6-in ch s lo tt ed pr ep ac ke d sc re en a nd

0/ s ili ca s d.

ec on ta m in at io n

A ll do w nh ol e to ol s w ill b e de co nt am in at ed p ri or t o an d be tw ee n ea ch s am pl e in te rv al lo ca ti on i.e ev er y fo ot d ur in g ha nd a ug er a dv an ce m en t an d ev er y fiv e fe et d ur in g m ac ro co re a dv an ce m en t)

S pe ci fic d ec on ta m in at io n pr oc ed ur es in cl ud e al co no x sc ru b an d st ea m w as h ap pl ie s fo r al l d ri lli ng e qu ip m en t an d do w nh ol e to ol s

(e .g t re m ie p ip e, h os es ec on ta m in at io n flu id s an d so lid s w ill b e co nt ai ne ri ze d se pa ra te ly

O ff er or ’s e qu ip m en t sh al l a rr iv e cl ea n an d fr ee o f so il or d ir t fr om it s pr ev io us w or k lo ca ti on

In ve st ig at io n

D er iv ed

W as te

ID

W an d T ra sh

S oi l c ut ti ng s, d ec on ta m in at io n w at er a nd s ol id s, a nd d ev el op m en t w at er

ID

W ge ne ra te d du ri ng w el l in st al la ti on w ill b e dr um m ed

T he D ri lle r w ill s up pl y a su ff ic ie nt n um be r of F

D O

T-ap pr ov ed

5-ga llo n st ee l d ru m s to c on ta in a ll

ID

W g en er at ed d ur in g si te a ct iv it ie s.

O ff er or w ill b e re qu ir ed t o co ns ol id at e th e

ID

W d ru m s in to o ne c en tr al lo ca ti on

D ri ll in g C on d it io s:

si te is n ot a n ac ti ve f ac ili ty

S om e va gr an t ac ti vi ty in t he a re a.

It s ho ul d be a ss um ed t ha t po ta bl e w at er a nd e le ct ri ci ty a re n ot a va ila bl e.

de pt h to w at er is e st im at ed a t

6.

fe et b gs

H ea lt h a n d S af et y:

W or k is e xp ec te d to b e pe rf or m ed in L ev el

D p er so na l p ro te ct iv e eq ui pm en t.

pr im ar y co nt am in an ts o f co nc er n at t he s it e ar e or ga no ch lo ri ne p es ti ci de s.

Pr op er s af et y pr oc ed ur es t o m in im iz e co nt ac t w it h co nt am in at ed s it e m ed ia is r eq ui re d.

S it e pe rs on ne l a re r eq ui re d to b e

-h ou r

O S H

A tr ai ne d.

Li n e it em s w ill b e in vo ic ed b as ed u po n ac tu al q ua nt it ie s/ de pt hs c om pl et ed in t he f ie ld

C o m p a n y N a m e

A ct io n

En vi ro nm en ta l

JA

EE

C as ca de

Pa ge o

Site Name: Site ID #:

Contract #: Contractor:

• Reason for Work Change Directive :

• Description of Work Change Directive :

• Attachments (if applicable, list documents supporting change):

• Costs (if negotiated unit costs, provide information below):

Authorized Contractor Signature:

Authorized FDEP Signature:

FDEP Supervisor Approval:

(if applicable)

Additional work is not authorized without prior FDEP approval as indicated by an approved Work Change Directive Form or Task Assignment Change Order Form. It is the Contractor's responsibility to ensure that additional costs associated with this WCD are resolved by a Task Assignment Change Order (TACO) prior to the completion date of the original Task Assignment or subsequent TACOs completed prior to the execution date of this WCD. Failure to do so will result in a loss of reimbursement for work associated with this WCD.

Task Assignment #: Work Change Directive #:

Maximum Estimated Increase in Task Amount:

Former Cal-Spray Chemical Co. ERIC_18464

HW687 Terracon

CSS03B 1

One of the monitoring wells will need to be installed by hand, since the drill rig cannot reach that location. In order to maximize on on getting an adequate sandpack around the hand installed well, the driller needs to purchase casing that they temporarily install during the well installation. Additionally 5 soil drums and we believe by the end of the project 3 water drums, a total of 8 drums will be generated. Only 5 drums were estimated in the proposal.

Three additional 55 gallon drums, and casing material for the hand installed monitoring well.

Action Environmental Subcontractor costs:

3 drums @ $80 = $240 Casing material = $200 10% markup = $44 Total = $484

$ 550.00

Digitally signed by Cline, Donna L DN: cn=Cline, Donna L, ou=General Users, email=Donna.Cline@terracon.com Date: 2025.04.02 11:00:24 -04'00'

Cline, Donna L

Claire Field Digitally signed by Claire Field Date: 2025.04.09 12:16:51 -04'00'

Scott L Sweeney

Digitally signed by Scott L Sweeney Date: 2025.04.09 13:57:07 -04'00'

• Reason for Work Change Directive :

• Description of Work Change Directive :

• Attachments (if applicable, list documents supporting change):

• Costs (if negotiated unit costs, provide information below):

Authorized Contractor Signature:

Authorized FDEP Signature:

FDEP Supervisor Approval:

(if applicable)

Additional work is not authorized without prior FDEP approval as indicated by an approved Work Change Directive Form or Task Assignment Change Order Form. It is the Contractor's responsibility to ensure that additional costs associated with this WCD are resolved by a Task Assignment Change Order (TACO) prior to the completion date of the original Task Assignment or subsequent TACOs completed prior to the execution date of this WCD. Failure to do so will result in a loss of reimbursement for work associated with this WCD.

Task Assignment #: Work Change Directive #:

Maximum Estimated Increase in Task Amount:

Former Cal-Spray Chemical Co. ERIC_18464

HW687 Terracon

CSS03B 2

For proper disposal of the IDW soil drums, based on the high concentrations of OCPs and RCRA metals in the soil samples, laboratory analysis of IDW soil samples for TCLP OCPs and TCLP RCRA metals is recommentded

Request the lab to analyze the 2 soil IDW drum samples for TCLP extraction and OCP and RCRA metal analysis of the extraction

TCLP metals, Method 1311/6010/7470, 2 samples @ $130.00 = $260.00 TCLP Organochlorine Pesticides, Method 1311/8081, 2 @ $175.00 = $350.00

$ 610.00

Digitally…