This is a Task Assignment (TA) document issued under the Florida Department of Environmental Protection (FDEP) Waste Cleanup Program (WCP) Contract Number HW687. The task assignment DC011A was executed between the State of Florida Department of Environmental Protection and Terracon Consultants, Inc., with Dean Cox serving as the Department Project Manager and Donna Cline as the Contractor's Project Manager. The work is performed at 60 Minute Cleaners (ERIC_4806), located at 1145 20th Place, Vero Beach, Florida, and is associated with a groundwater monitoring and remedial action project for an active PCE drycleaning facility.
The task assignment authorizes groundwater monitoring, related waste handling and disposal, sample shipping and analysis, and equipment procurement for a total fixed unit rate value of $11,547.76, comprising 63.50 hours of labor. Work activities include field preparation and groundwater sampling (35.5 hours), preparation of a groundwater monitoring report (24 hours), analytical testing costs ($1,710 for EPA 8260C analysis and $1,080 for dissolved gases testing), equipment and supplies ($1,968.10), travel expenses ($888), and industrial waste disposal ($110). The deliverable is a Groundwater Monitoring Report due July 15, 2022, with full invoice submission upon FDEP approval of the report by the completion date of September 30, 2022. Labor costs in the original proposal were reduced by 10%, resulting in an overall TA cost reduction of approximately $1,204.60. The task serves as a groundwater Remedial Action Management (NAM) update to evaluate plume location, contaminant concentrations, and dissolved gas results to determine the need for additional remedial action and assist in selecting a site closure path.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW687
DC011A Completion September 30, 2022
This task assignment (TA) authorizes costs associated with groundwater monitoring, related waste handling & disposal, sample shipping & analysis, and equipment. The total cost for this TA is $11,547.76 with 63.50 hours of labor. All costs are fixed unit rate.
Dean Cox 850-245-8969 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Terracon Consultants, Inc.
Terracon Consultants, Inc.
Donna Cline 813-321-0340
ERIC_4806
1145 20th Place, Vero Beach FL
60 Minute Cleaners
✔ $ 11,547.76
$ 11,547.76
Scope of Work
William E. Burns, Jr.
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2022.05.25 11:20:22 -04'00'
N/A dlcline Typewriter Donna Cline dlcline Typewriter Senior Remediation Engineer
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Groundwater Monitoring Report 07/15/2022
FDEP approval of Groundwater Monitoring Report (Subtask 1 Project Management and Subtask 2 Groundwater Monitoring and Subtask 3 Groundwater Monitoring Report)
$ 11,547.76
$ 11,547.76
HW687
DC011A
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Interim Secretary
Memorandum
TO: HW687 Contract File FROM: Dean Cox, Contract Manager SUBJECT: DC011A Groundwater Monitoring @ 60 Minute Cleaners (ERIC_4806)
DATE: 5/25/2022
This task assignment (TA) authorizes costs associated with groundwater monitoring, related waste handling & disposal, sample shipping & analysis, and equipment. The total cost for this TA is $11,547.76 with 63.50 hours of labor. All costs are fixed unit rate.
The labor costs in the contractor’s original proposal were reduced by 10%, resulting in a TA total cost reduction of approximately 10%, amounting to $1,204.60 lower cost.
This TA serves as a groundwater NAM update. Groundwater plume location and contaminant concentrations will be evaluated along with groundwater dissolved gases results to better determine the need for any additional remedial action. Results will also assist in choosing a site closure path, RMO I or RMO III.
The facility is an active PCE drycleaner. It has a potential buyer who plans to use petroleum based drycleaning solvent. The site access agreement was verified as valid.
FDEP COST ESTIMATE
Contractor: Terracon
Date: 5/24/2022 Task #: DC0011A SubTask 1 Project Management SubTask 6
Site: 60 Minute Cleaners ERIC_4806 SubTask 2 Groundwater Monitoring SubTask 7 Activity/Phase: GW Sampling and Monitoring Report SubTask 3 Groundwater Monitoring Report SubTask 8
Project Manager: Dean Cox SubTask 4 SubTask 9 SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$64.50 Project Manager Donna Cline 4.00 4.00 $0.00 Administrative 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Brownfield Consultant 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$22.25 CADD Specialist Andy Schifano 4.00 0.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Data Analyst & Visualization Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$24.75 Environmental Technician Pete Christianson 28.00 28.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Field Geologist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Field Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 GIS Technician 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Principal Consultant 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Project Geologist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Project Industrial Hygienist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$31.56 Project Scientist Laura Sebastian 9.00 4.00 5.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Engineer 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Geologist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior GIS Analyst 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Industrial Hygienist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$49.69 Senior Scientist Lydia Wing 18.50 3.50 15.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Staff Engineer 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Staff Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total Hours 63.50 4.00 35.50 24.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Direct Labor $2,243.40 $258.09 $993.16 $992.15 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 116.00% $2,602.34 $299.38 $1,152.07 $1,150.89 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 56.26% $1,262.13 $145.20 $558.75 $558.18 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $6,107.87 $702.67 $2,703.98 $2,701.22 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF TERRACON Page 1
FDEP COST ESTIMATEContractor: Terracon Date: 5/24/2022
Task #: DC0011A SubTask 1 Project Management SubTask 6 Site: 60 Minute Cleaners ERIC_4806 SubTask 2 Groundwater Monitoring SubTask 7
Activity/Phase: GW Sampling and Monitoring Report SubTask 3 Groundwater Monitoring Report SubTask 8 Project Manager: Dean Cox SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Travel
Vehicle Rental $480.00 480.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $408.00 $408.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $888.00 $888.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $100.00 100.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $10.00 $10.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $1,710.00 1,710.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $153.00 153.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $1,863.00 $1,863.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $120.00 120.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $1,412.10 1,412.10$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $100.00 100.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $336.00 336.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $1,968.10 $1,968.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $10,936.97 $702.67 $7,533.08 $2,701.22 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $610.79 $70.27 $270.40 $270.12 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $11,547.76 $772.94 $7,803.48 $2,971.34 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF TERRACON Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : 60 Minutes Cleaners ERIC_4806 SUBTASK 2: Annual Groundwater Monitoring and Reporting
PROPOSAL NO. PHD1227023
DATE: 5/24/2022
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Field Task Planning and Groundwater Sampling Senior Scientist/Geologist LW 1.00 Senior Scientist/Geologist LW 1.00 Senior Scientist/Geologist LW 1.00
Env Technician PC Load/unload 1.00 Env Technician PC Mobilization/Demobilization (from Winter Park) 3.50 Env Technician PC Access wells and replace locks and caps (14 wells) 1.00 Env Technician PC Collect groundwater levels (9 wells,10 minutes per well) 1.50 Env Technician PC Collect groundwater samples (13 total wells (9 wells, 4 injection wells) at 1.5 hours each) 19.50 Env Technician PC Containerize IDW in a central location 0.50 Env Technician PC Evaluate SVE system and document site conditions 1.00
Coordinate IDW T&D Senior Scientist/Geologist LW 0.50 Project Scientist LS 4.00
TOTAL LABOR 35.5
VEHICLE TYPE RATE UNIT USEAGE
Truck (groundwater sampling) 120 day 3 360.00$ Truck (IDW Coordination) 120 day 1 120.00$
TOTAL VEHICLE 480.00$
PER DIEM STAFF RATE UNIT USEAGE
PC $150.00 per night stay 2 300.00$ PC $36.00 per day 3 108.00$
TOTAL PER DIEM 408.00$
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE
Erwin Remediation IDW Disposal 100.00$ each 1 100.00$
Subcontractor Handling Fee 10% 0 10.00$
TOTAL SUBCONTRACTOR 110.00$
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC* #IDW TOTALS
Halocarbons (short list) EPA 8260 63.00$ 9 0 1 630.00$ Fe EPA 1610 13.50$ 0 -$ Na EPA 1610 13.50$ 0 -$ pH EPA 150.1 10.00$ 0 -$ Chloride SM4500-Cl 20.00$ 0 -$ Sulfate 375.2/300.0 31.00$ 0 -$
TDS SM2540C 16.00$ 0 -$
TOC SM5310C 30.00$ 0 -$
Color SM2120B 13.00$ 0 -$ Dissolved gasses RSK-175 180.00$ 6 1,080.00$ Sample Shipping Large Cooler (2 day) 70.00$ 2 140.00$ Sample Preparation Ice 6.50$ 2 13.00$
TOTAL LAB 1,863.00$
* No charge for trip blanks
Request sample kit Prepare Health and Safety Plan PreTask Planning, prepare field sampling SOW/coordinate site access
Prepare waste characterization/Generator Profile Coordinate IDW T&D: Mobilize to site, meet transporter to unlock secure area for pickup
SITE : 60 Minutes Cleaners ERIC_4806 SUBTASK 2: Annual Groundwater Monitoring and Reporting
PROPOSAL NO. PHD1227023
DATE: 5/24/2022
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Deep groundwater sampling k 415.00$ day 3 1,245.00$ Tubing, HDPE 0.30$ ft 417 125.10$ Tubing, silicon (3/16 x 3/8) 3.00$ ft 14 42.00$ Expendables 40.00$ day 3 120.00$ Lock, key operated 7.00$ ea 14 98.00$ well, cap 2" 17.00$ ea 14 238.00$ 55-gallon drum, new 100.00$ drum 1 100.00$
TOTAL EQUIPMENT 1,968.10$
SITE : 60 Minute Cleaners ERIC_4806 SUBTASK 3: Annual Groundwater Monitoring Report
PROPOSAL NO. PH1227140
DATE: 5/24/2022
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Report Deliverable Project Scientist LS Prepare report tables, draft groundwater elevation and analytical isoconcentration figures 4.00
Senior Scientist/Geologist LW Prepare report 7.00 Senior Scientist/Geologist LW QA/QC field and laboratory data 1.00 Senior Scientist/Geologist LW Summarize groundwater analytical results 2.00 Senior Scientist/Geologist LW Summarize groundwater geochemistry field results 1.00 Senior Scientist/Geologist LW Conclusions/Recommendations 4.00
Project Scientist LS Complete FDEP GIS / ADaPT tables 1.00
GIS Technician AS Prepare and update TetraTech base Figures and Exhibits 4.00 (3 groundwater flow and 1 concentration map)
TOTAL LABOR 24.0
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE -$
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM -$
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE
TOTAL SUBCONTRACTOR -$
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC* #IDW TOTALS
TOTAL LAB -$
* No charge for trip blanks
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT -$
Ranking by fee
Sub Solids non-haz 55-gal drum
Liquids non-haz
55-gal drum Additional pricing conditions
Minority Y/N
Regions* Contact Name Contact # email
1 Erwin Remediation 100.00$ 100.00$ all inclusive No All Johnathan Erwin 850-292-6511 erwinremediation@gmail.com
2 Clean Earth $63+$45=$108 $65+$45 =$110 15% EEI on total disposal, stop fee $100, 55% FSC of total transportation
No All Ryan Penfield 843-562-7481 rpenfield@harsco.com
3A Whatever Waste 150.00$ 150.00$ all included No North and
Central Florida
John 904-881-1957 John@whateverwaste.com
3B Whatever Waste 200.00$ 200.00$ all included No South Florida
John 904-881-1957 John@whateverwaste.com
* Regions that are specified with "All" of Florida, are not inclusive of the Keys
Erwin Remediation is the selected IDW Contractor
IDW Contractors, All of Florida (Except the Keys)
408 Ditmar Street
Pensacola, FL 32503
ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511
To: Mr. Sid O’Neal
Terracon
3559 Timberlane School Road
Tallahassee, FL 32312
March 4, 2022
Re: Non-Hazardous Drum Disposal – State of Florida
Mr. O’Neal:
The price for the transportation and disposal (T&D) of drums of non-hazardous soil, mud and water located in the State of Florida is listed below.
Non-Hazardous Chlorinated VOHs, Petroleum and Metals:
Description Rate Unit
T&D - Non-Haz Soil $ 100.00 Per Drum
T&D - Non-Haz Mud/Water $ 100.00 Per Drum
The prices listed are all inclusive without any additional fees or charges (fuel surcharge, low volume stop fee etc.) and are valid for all regions in the State of Florida except for the Florida
Keys. Pricing for sites located in the Florida Keys will be bid on a case-by-case basis dependent on the volume of drums and the location.
Respectfully, Jonathan Erwin
Erwin Remediation, Inc.
Email: ErwinRemediation@Gmail.com
Office: (850) 292-6511 mailto:Remediation@Gmail.com
Cline, Donna L
From: O'Neal, Sid L Sent: Wednesday, March 9, 2022 12:12 PM To: Cline, Donna L; Wing, Lydia; Lewis, Tom E Subject: FW: :EXTERNAL: RFQ - Non-Haz T&D
Here’s an email quote from Clean Earth. Should be the final one needed
Thanks, Sid O’Neal Senior Scientist I Environmental
3559 Timberlane School Road I Tallahassee, Florida 32312 D (850) 692-7189 I F (850) 692-7186 I M (229) 400-5108 sid.oneal@terracon.com I Terracon.com
From: Penfield, Ryan L <rpenfield@harsco.com> Sent: Wednesday, March 9, 2022 12:09 PM To: O'Neal, Sid L <Sid.O'neal@terracon.com> Subject: RE: :EXTERNAL: RFQ - Non-Haz T&D
Hello Sid, Non haz liquids (NH-L-20) $65 per drum Non haz solids (NH-S-10) $63 per drum 15% EEI on total disposal
Transportation (excluding the KEYS) Stop fee $100 Per Drum Trans $45 FSC based upon DOE currently 55% of total trans
This will be good for all of Florida except the keys.
Ryan Penfield
Environmental Specialist
M 843.562.7841 O 1.800.739.9156 rpenfield@harsco.com www.cleanearthinc.com
402 Webster Chapel Road, Glencoe , AL 35905
From: O'Neal, Sid L <Sid.O'neal@terracon.com> Sent: Wednesday, March 9, 2022 11:59 AM To: Penfield, Ryan L <rpenfield@harsco.com> Subject: :EXTERNAL: RFQ - Non-Haz T&D
Hi Larry, Was just following up from yesterday’s phone call in case you have my email wrong.
Need quote for Non-Haz Drum T&D – soil and gw waste for all Florida regions covering north, central, and south regions
Thanks, Sid O’Neal Senior Scientist I Environmental
3559 Timberlane School Road I Tallahassee, Florida 32312 D (850) 692-7189 I F (850) 692-7186 I M (229) 400-5108 sid.oneal@terracon.com I Terracon.com
Terracon provides environmental, facilities, geotechnical, and materials consulting engineering services delivered with responsiveness, resourcefulness, and reliability.
Private and confidential as detailed here (www.terracon.com/disclaimer). If you cannot access the hyperlink, please e-mail sender.
CAUTION : This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe.
You don't often get email from sid.o'neal@terracon.com. Learn why this is important
Whatever Waste, LLC 904.881.1957
3834 Mandarin Woods Dr. No.
Jacksonville, Florida
32223 United States
Overview RE: Non-hazardous Waste Drum Transport & Disposal LOC: North Florida (Jacksonville >< Pensacola) Central Florida (Greater Orlando >< Greater Tampa)
Good day Sid and Tom:
Whatever Waste appreciates the opportunity to price non-hazardous waste drums at facilities or sites throughout the North and Central Florida regions.
Overview Manifest, transport and dispose of non-hazardous petroleum contaminated soil, solids or liquids (including but not limited to PCW, IDW, groundwater, well drilling, and tank cleaning) in 55-gallon DOT shippable drums
Pricing
Prepared For Sid O'Neal Sr. Scientist
Terracon 3559 Timberlane School Road
Tallahassee, FL 32312
Proposal Number 030822.1
Proposal Date 03/08/2022
Description Rate Qty Line Total
Solids or Liquids Drums (each)
$150.00 1 $150.00
$0.00 1 $0.00
Notes Pricing includes assisting with waste profiling and analytical testing advisement unless the waste stream falls under a blanket profile.
Pricing and non-hazardous disposal acceptance of the drums is based on the waste being on-specification and RCRA non-hazardous. Required analytical testing data TBD based on disposal facility requirements DOT shippable drums must be on a hard surface and accessible location.
Drum pickup time frame can range from one week to several weeks based on location Whatever Waste also quotes hazardous waste drum transport and disposal
Terms
Whatever Waste will invoice actual amounts or volumes unless minimum quantities apply Due to pricing volatility in national and international energy sectors the non-hazardous waste drum transport and disposal rate will increase by $15.00 per drum for every $0.50 per gallon over $5.00 per gallon No-load stop fee if called off in transit or on-site $125.00 Payment is due in 30 days from email receipt of invoice
Sid O'Neal Sr. Scientist, Terracon
Subtotal
Tax
150.00
0.00
Proposal Total (USD) $150.00
Whatever Waste, LLC 904.881.1957
3834 Mandarin Woods Dr. No.
Jacksonville, Florida
32223 United States
Overview RE: Non-hazardous Waste Drum Transport & Disposal LOC: South Florida (south of Lake Okeechobee north end) Florida Keys
Good day Sid and Tom:
Whatever Waste appreciates the opportunity to price non-hazardous waste drums at facilities or sites throughout South Florida and the Florida Keys.
Overview Manifest, transport and dispose of non-hazardous petroleum contaminated soil, solids or liquids (including but not limited to PCW, IDW, groundwater, well drilling, and tank cleaning) in 55-gallon DOT shippable drums
Pricing
Prepared For Sid O'Neal Sr. Scientist
Terracon 3559 Timberlane School Road
Tallahassee, FL 32312
Proposal Number 030822.2
Proposal Date 03/08/2022
Description Rate Qty Line Total
Solids or Liquids Drums (each) (South Florida)
$200.00 1 $200.00
Solids or Liquid Drums (each) (Florida Keys)
$275.00 1 $275.00
Notes Pricing includes assisting with waste profiling and analytical testing advisement unless the waste stream falls under a blanket profile.
Pricing and non-hazardous disposal acceptance of the drums is based on the waste being on-specification and RCRA non-hazardous. Required analytical testing data TBD based on disposal facility requirements DOT shippable drums must be on a hard surface and accessible location.
Drum pickup time frame can range from one week to several weeks based on location Whatever Waste also quotes hazardous waste drum transport and disposal
Terms
Whatever Waste will invoice actual amounts or volumes unless minimum quantities apply Due to pricing volatility in national and international energy sectors the non-hazardous waste drum transport and disposal rate will increase by $15.00 per drum for every $0.50 per gallon over $5.00 per gallon No-load stop fee if called off in transit or on-site $175.00 Payment is due in 30 days from email receipt of invoice
Sid O'Neal Sr. Scientist, Terracon
Subtotal
Tax
475.00
0.00
Proposal Total (USD) $475.00
| DC011A.pdf |
| memo DC011A.pdf |
| DC011A CEF-LOE_FDEPedits220524.pdf |
| Cost Estimate |
| LOE Subtask 2 |
| LOE Subtask 3 |
| DC011Aproposal220520_Page_6.pdf |
| DC011Aproposal220520_Page_7.pdf |
| DC011Aproposal220520_Page_8.pdf |
| IDWbids.pdf |
| ErwinRemediation Quote - Terracon - Drum - All Regions - 03.04.2022 |