This document comprises multiple Task Assignment Change Orders (TACOs) between the State of Florida Department of Environmental Protection (FDEP) and Terracon Consultants, Inc. for work under Contract Number HW687. The contract involves environmental site cleanup and assessment services across multiple sites in Florida, with project management overseen by Dean Cox for FDEP and Donna Cline for Terracon.

The document details two primary change orders: TACO #5 and TACO #4. TACO #5, effective November 29, 2023, adds $7,811.29 as a fixed unit rate for a site review meeting, bringing the total task value to $42,951.58. This cost addition was negotiated to be $892.85 (10%) less than originally proposed. TACO #4, effective May 13, 2023, adjusts the task compensation to $35,140.29, representing a $4,500 increase from the prior value of $30,640.29, also structured as fixed unit rate pricing. Deliverables include site status table updates, field notes and photos, PRAC meeting attendance documentation, site review meeting summary notes, and documentation of critical response site activities. The invoicing structure requires FDEP approval of each deliverable component before payment, with invoice amounts ranging from $1,359.88 to $22,280.41 across various approved activities. Cost estimates detail labor expenses for senior-level staff (geologists, scientists, and project managers), vehicle charges, lodging, and per diem, with completion fees included in the total pricing.

View the file

Other files

File Type Posted
CN-370000-HW687-BF01ACO1.pdf PDF
CN-370000-HW687-BF03ACO1.pdf PDF
CN-370000-HW687-BIL01A.pdf PDF
CN-370000-HW687-BIL2ACO1.pdf PDF
CN-370000-HW687-BIL2BCO1.pdf PDF
CN-370000-HW687-BIL2CCO1.pdf PDF
CN-370000-HW687-BIL3ACO2.pdf PDF
CN-370000-HW687-BIO1ACO1.pdf PDF
CN-370000-HW687-DC001A.pdf PDF
CN-370000-HW687-DC003A.pdf PDF
CN-370000-HW687-DC003D.pdf PDF
CN-370000-HW687-DC005D.pdf PDF
CN-370000-HW687-DC006A.pdf PDF
CN-370000-HW687-DC006B.pdf PDF
CN-370000-HW687-DC008C.pdf PDF
CN-370000-HW687-DC010A.pdf PDF
CN-370000-HW687-DC010B.pdf PDF
CN-370000-HW687-DC011F.pdf PDF
CN-370000-HW687-DC011H.pdf PDF
CN-370000-HW687-DC012D.pdf PDF
CN-370000-HW687-DC013C.pdf PDF
CN-370000-HW687-DC015A.pdf PDF
CN-370000-HW687-DC015C.pdf PDF
CN-370000-HW687-DC019A.pdf PDF
CN-370000-HW687-DC01ACO2.pdf PDF
CN-370000-HW687-DC020A.pdf PDF
CN-370000-HW687-DC020B.pdf PDF
CN-370000-HW687-DC020C.pdf PDF
CN-370000-HW687-DC020D.pdf PDF
CN-370000-HW687-DC023C.pdf PDF
CN-370000-HW687-DC025B.pdf PDF
CN-370000-HW687-DC025C.pdf PDF
CN-370000-HW687-DC025F.pdf PDF
CN-370000-HW687-DC027B.pdf PDF
CN-370000-HW687-DC027C.pdf PDF
CN-370000-HW687-DC02BCO1.pdf PDF
CN-370000-HW687-DC02CCO2.pdf PDF
CN-370000-HW687-DC02DCO1.pdf PDF
CN-370000-HW687-DC02HCO1.pdf PDF
CN-370000-HW687-DC032A.pdf PDF
CN-370000-HW687-DC034A.pdf PDF
CN-370000-HW687-DC034C.pdf PDF
CN-370000-HW687-DC034D.pdf PDF
CN-370000-HW687-DC035F.pdf PDF
CN-370000-HW687-DC036A.pdf PDF
CN-370000-HW687-DC03CCO1.pdf PDF
CN-370000-HW687-DC041C.pdf PDF
CN-370000-HW687-DC041D.pdf PDF
CN-370000-HW687-DC048A.pdf PDF
CN-370000-HW687-DC048B.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number) Project Name:

4. ☐ There are no changes to the TA compensation.

☐ The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO ☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. ☐ There are no changes to the TA Expiration Date.

☐ The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. ☐ There are no changes to the Attachments.

☐ Attachment ___ is replaced with Attachment -____.

7. ☐ No Additional Changes.

☐ Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

DC001A 5 HW687

This TACO adds $7,811.29 for a site review meeting. This entire amount is fixed unit rate.

Dean Cox 850-245-8969 Contractor Contractor

Contractor Contractor

Contractor

Terracon Consultants, Inc.

Donna Cline 813-321-0340 multiple multiple

✔ $ 42,951.58 $ 35,140.29

$ 42,951.58 $ 35,140.29 ✔ Completion

Completion 0

✔ 1 1 5

Kelly Crain

Digitally signed by Jennifer Farrell Date: 2023.11.29 12:16:21 -05'00'

N/A

Cline, Donna L Typewriter Donna Cline

Senior Associate

11/29/2023

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 01_18

Contract Number:

Task Assignment #:

Change Order #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

HW687

DC001A

$ 42,951.58

Sites Status Table update, along with any new owner or property information related to any need for site access authorization or offsite notification.

Two signatures each by two contractor staff - one signature each on the daily PRAC meeting sign-in & sign-out sheet(s) for each of the two meeting days.

Field notes and photos for Hurricane Ian SVE system shutdowns/disconnections.

Signatures by at least two contractor staff per day - one signature per staff member in attendance on each of the daily PRAC meeting sign-in & sign-out sheet(s).

Site review meeting summary notes.

Documentation of as-needed critical response site activities requested by the Waste Site Cleanup Section.

DEP approval of Sites Status Table update, along with any new owner or property information related to any need for site access authorization or offsite notification.

DEP approval of field notes and photos for Hurricane Ian SVE system shutdowns/disconnections.

DEP approval of signatures by at least two contractor staff - one signature per staff member on each of the daily PRAC meeting sign-in & sign-out sheet(s).

DEP approval of documentation of as-needed critical response site activities requested by the Waste Site Cleanup Section.

DEP approval of site review meeting summary notes (Subtask 1 Project Management and Subtask 2 Site Review Meeting Travel & Attendance).

DEP approval of two signatures each by two contractor staff - one signature each on the daily PRAC meeting sign-in & sign-out sheet(s) for each of the two meeting days.

04/15/2022

08/31/2022

10/31/2022

05/24/2023

01/04/2027

12/31/2023

$ 4,500.00

$ 22,280.41

$ 1,359.88

$ 4,500.00

$ 7,811.29

$ 2,500.00

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Interim Secretary

Negotiation Summary

TO: HW687 Contract File FROM: Dean Cox, Contract Manager SUBJECT: DC001A-5 Site Review Meeting

DATE: 11/17/23

This TACO adds $7,811.29 for a site review meeting. This entire amount is fixed unit rate. The total task cost is now $42,951.58 and this entire cost is fixed unit rate. This TA was negotiated - the total cost is $892.85 or 10% less than originally proposed.

This cost addition is for a standard site review meeting, conducted periodically during the contract. Terracon did not submit their TA proposal in time to execute a TA for the meeting, so the cost was approved by a WCD to the Critical Response TA DC001A.

FDEP COST ESTIMATE

Contractor: Terracon

Date: 11/17/2023 Task #: SubTask 1 Site Review Meeting - Travel & Attendance SubTask 6

Site: Multiple Site SubTask 2 SubTask 7 Activity/Phase: Site Review Meeting SubTask 3 SubTask 8

Project Manager: Dean Cox SubTask 4 SubTask 9 SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$67.74 Project Manager Donna Cline 3.90 3.90 $0.00 Administrative 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Brownfield Consultant 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 CADD Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Data Analyst & Visualization Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Field Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Field Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Field Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Staff Engineer 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Principal Consultant 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Staff Engineer 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Project Industrial Hygienist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Project Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Engineer 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$50.00 Senior Geologist Shawn Ouellette 14.00 14.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior GIS Analyst 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Industrial Hygienist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$51.97 Senior Scientist/Geologist Lydia Wing 14.00 14.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Staff Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$43.27 Senior Project Manager/E Michael Mui 14.00 14.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total Hours 45.90 3.90 42.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Direct Labor $2,297.70 $264.34 $2,033.36 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 116.00% $2,665.33 $306.63 $2,358.70 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 56.26% $1,292.69 $148.72 $1,143.97 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $6,255.72 $719.69 $5,536.03 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF TERRACON Page 1

FDEP COST ESTIMATEContractor: Terracon Date: 11/17/2023

Task #: SubTask 1 Site Review Meeting - Travel & Attendance SubTask 6 Site: Multiple Site SubTask 2 SubTask 7

Activity/Phase: Site Review Meeting SubTask 3 SubTask 8 Project Manager: Dean Cox SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Travel

Vehicle charge $480.00 480.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $450.00 450.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $930.00 $930.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) - GPI/EDS $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying - SSMC $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 IDW - Erwin Remediation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Geoview $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Camera Line (Sunshine) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $7,185.72 $719.69 $6,466.03 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $625.57 $71.97 $553.60 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $7,811.29 $791.66 $7,019.63 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF TERRACON Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Multiple SUBTASK 1: Site Review Meeting - Travel & Attendance

PROPOSAL NO.

DATE: 11/17/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Field Task Planning Senior Geologist SO 6.00 Senior Scientist/Geologis LW 6.00 Senior PM/Engineer MM Site Review Meeting 6.00

Mobilization / Demobilizations Senior Geologist SO 8.00 Senior Scientist/Geologis LW 8.00 Senior PM/Engineer MM Roundtrip travel from Tampa 8.00

Personnel: SO LW MM NK CN Hours: 14.00 14.00 14.00 0.00 0.00 TOTAL LABOR 42.00

VEHICLE TYPE RATE UNIT USEAGE

Shawn Car 80.00$ day 2 160.00$ Lydia Car 80.00$ days 2 160.00$ Mike Car 80.00$ days 2 160.00$

TOTAL VEHICLE 480.00$

PER DIEM STAFF RATE UNIT USEAGE

Lodging Shawn Ouellette $150.00 days 1 150.00$ Meals Shawn Ouellette $36.00 days 0 -$ Lodging Lydia Wing $150.00 days 1 150.00$ Meals Lydia Wing $36.00 days 0 -$ Lodging Michael Mui $150.00 days 1 150.00$ Meals Michael Mui $36.00 days 0 -$

TOTAL PER DIEM 450.00$

Roundtrip travel from Port St. Lucie

Site Review Meeting Site Review Meeting

Roundtrip travel from Winter Park

DC001A-5.pdf
DC001A-5 NS.pdf
CEF LOE Site Review Meeting_DEPcomments231116.pdf
Cost Estimate
LOE 1 Meeting
WCD1.pdf
HW687 DC001A-4_Page_1.pdf
HW687 DC001A-4_Page_2.pdf

File details come from the government source that posted it. Updated .