This is a Task Assignment (TA) document executed between the State of Florida Department of Environmental Protection (FDEP) and Terracon Consultants, Inc. under Contract Number HW687. The task is designated as BF03A and is effective through July 14, 2023. The project involves environmental assessment work at the Broward County School Board Property located at the southeast corner of Broward Boulevard and South Hiatus Road in Plantation, Broward County, Florida. The work is funded through the State & Tribal Response Program (SRP) cooperative agreement administered by FDEP on behalf of the U.S. Environmental Protection Agency (EPA).
The contract requires Terracon to perform three subtasks: Project Management ($981.72), File Review ($3,834.12), and QAPP/Workplan and Health and Safety Plan (HASP) preparation ($3,717.53), for a total task assignment value of $8,533.37. Deliverables include a File Review Letter of Findings due May 17, 2023, and a QAPP/Workplan and HASP due June 14, 2023. Invoicing is contingent upon departmental approval of the respective deliverables, with the File Review Letter payment triggered by approval of Subtask 2 and the remaining payment triggered by approval of Subtasks 1 and 3 combined. All services are conducted under the fixed unit rate payment method using federal SRP funding.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW687
BF03A Completion July 14, 2023
The Department approves this Task Assignment (TA) based upon the Cost Proposal and Level of Effort (CP/LOE) to prepare a File Review Letter of Findings and a QAPP/Workplan and HASP submitted to the Department on April 13, 2023, by Terracon Consultants, Inc., for the below referenced site. The final deliverable will be a QAPP/Workplan and HASP received by the Department no later than June 14, 2023.
Megan Johnson 850.245.8994 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Terracon Consultants, Inc.
Terracon Consultants, Inc.
Shawn Ouellette 561.689.4299
ERIC_18360
SE Corner of Broward Blvd. and South Hiatus Road, Broward County
Broward County School Board Property - Plantation
✔ $ 8,533.37
$ 8,533.37
Scope of Work
Donna Cline, P.E.
Senior Remediation Engineer
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2023.04.18 08:36:00 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
File Review Letter of Findings 05/17/2023
QAPP/Work Plan and HASP; Project Management 06/14/2023
Department approval of File Review Letter of Findings (Subtask 2) $ 3,834.12
Department approval of Project Management and QAPP/Work Plan and HASP (Subtasks 1 and 3) $ 4,699.25
$ 8,533.37
HW687
BF03A
www.FloridaDEP.gov
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: Terracon Consultants, Inc., HW687 Contract File
FROM: Megan Johnson, Contract Manager
DATE: April 17, 2023
SUBJECT: Negotiation Summary – SRP18 Task Assignment (TA) BF03A
Broward County School Board Property – Site ID # ERIC_18360 File Review Letter of Findings, QAPP/Workplan and HASP
This TA is intended to prepare a File Review Letter of Findings and a Quality Assurance Project Plan (QAPP)/Workplan and Health and Safety Plan (HASP) at the Broward County School Board Property site, located at the southeast corner of Broward Boulevard and South Hiatus Road, Plantation, Broward County, Florida. The services under this task are being conducted using federal funds from the State & Tribal Response Program (SRP) cooperative agreement that is administered by the Department on behalf of the U.S. Environmental Protection Agency (EPA).
Subtask 1: Project Management This subtask is a percentage of the overall project fees and has been negotiated as a contract rate.
It includes project management, overhead, general and administrative, and fringe. The agreed upon cost of this subtask is $981.72.
Subtask 2: File Review Under this subtask Terracon will conduct a file review of the two subject parcels, which includes review of available historical records, regulatory file review of onsite and surrounding parcels, and site reconnaissance. The deliverable for this subtask will be a Letter of Findings submitted to the Department. The agreed upon cost of this subtask is $3,834.12.
Subtask 3: QAPP/Workplan and HASP In accordance with an EPA directive, this subtask includes the completion of a QAPP/Work Plan and a HASP. The QAPP/Work Plan will provide a brief summary of the scope of work, tables and figures showing the proposed sampling locations, and laboratory and field quality assurance measures and procedures. The agreed upon cost of this subtask is $3,717.53.
Summary The Department’s SRP Contract Manager and Terracon’s Contract Manager have both agreed to the scope of work and associated costs. The final cost associated with this TA is $8,533.37.
Documentation of these costs is included in the Cost Proposal/Level of Effort (CP/LOE) Form and CP/LOE narrative provided by Terracon on April 13, 2023, and the Task Assignment Form for BF03A prepared by the Department. The final deliverable must be received by the Department no later than June 14, 2023.
http://www.floridadep.gov/
5371 NW 33 Avenue, Suite 201
Fort Lauderdale, FL 33309
P (954) 703-1866 F (561) 692-7186
Terracon.com
Florida Department of Environmental Protection Waste Cleanup Program-Waste Management Division 2600 Blair Stone Road Tallahassee, Florida 32399-2400
Attn: Ms. Megan R. Johnson, Environmental Consultant Brownfields and CERCLA Site Screening Section E: Megan.R.Johnson@floridadep.gov W: 850-245-8994
Re: Proposal for Preliminary File Review, HASP, QAPP and Workplan Preparation
School Board of Broward County Plantation Site SE Corner of Hiatus Road and Broward Blvd Plantation, Broward County, Florida Terracon Proposal No. 34237088
Dear Ms. Johnson:
Terracon Consultants, Inc. (Terracon) appreciates the opportunity to submit this proposal to the Florida Department of Environmental Protection (FDEP) Waste Cleanup Section to conduct a preliminary file review and then preparing a HASP, QAPP and Work Plan for the School Board of Broward County Plantation site located at the SE corner of Broward Blvd and Hiatus Road in Plantation, Florida. Based on correspondence with the FDEP and Broward County, it was requested that the adjacent parcel to the north also be incorporated into the project site. According to the Broward County Property Appraiser Website, the site encompasses two parcels, Broward County Parcel identification number 504107010140 (Parcel 1, north) owned by the Old Plantation Water Control District and Broward County Parcel identification number 504107150020 (Parcel 2, south) owned by the School Board of Broward County. The site activities will be performed as approved by both FDEP and the U.S. Environmental Protection Agency (U.S. EPA) for utilizing Targeted Brownfield Assessment/Site Specific Activities (TBA/SSA) federal funding administered by FDEP.
Scope of Services
Conduct a preliminary file review of the subject properties.
develop a Workplan / Quality Assurance Project Plan (QAPP) and Health and Safety Plan (HASP) for the site.
See attached LOE for details
Schedule
Deliverable of HASP, Workplan and QAPP within 20 business days of completion of File Review;
Compensation
See attached CEF for details.
mailto:Megan.R.Johnson@floridadep.gov
Proposal for Preliminary File Review and QAPP Workplan Preparation BCSB Plantation Site ■ Plantation, FL April 13, 2023 ■ Terracon Proposal No. 34237088
PROJECT INFORMATION
The north parcel (Parcel 1) is currently owned by the Old Plantation Water Control District and is currently comprised of cleared and vacant land. Past uses of the Site included a drainage canal across the parcel during the late 1940s to early 2000s. A review of aerial photographs confirmed the construction and renovation of S. Hiatus Road and the intersection of S. Hiatus Road and W. Broward Boulevard on adjoining properties located immediately west and northwest of the Site, respectively, beginning in the early 2000s.
The south parcel (Parcel 2) is currently owned by the School Board of Broward County and is currently comprised of cleared and vacant land. Past uses of the Site included agricultural operations which took place from the late 1950s to mid-1990s, a suspected maintenance building/barn was previously located on the northwestern portion of the Site.
On March 22, 20223, FDEP approved the School Boards application for Targeted Brownfields Assessment and Site-Specific Activities for further assessment and cleanup of this site. The following scope has been prepared to provide a path forward and potential next steps on the parcels as it pertains to future development. The goal of this study is to identify and summarize the assessment and remedial work that has been completed to date and identify any data gaps which need to be addressed prior to any future remedial design or implementation.
SCOPE OF SERVICES
Based on prior discussions on phone and email, the proposed scope of services consists of three subtasks involving Project Management, conducting a file review, and developing a Workplan / QAPP and HASP.
Subtask Description
Subtask 1: Project Management This scope is provided for in the template worksheets
Subtask 2: File Review
Terracon will conduct a file review of the 2 subject parcels 504107010140 (Parcel 1) and 504107150020 (Parcel 2) which includes review of available historical records such (aerial photos, city directories, and topographic maps), regulatory file review of onsite and surrounding parcels using FDEP Map Direct, and site reconnaissance. At completion of the review, a Letter of Findings of the review will be submitted to FDEP for comment and approval.
Subtask 3:
Workplan/QAPP/HASP
After approval of the File Review Letter of Findings, Terracon will develop a Workplan and Quality Assurance Project Plan and Health and Safety Plan prior to field work for approval by FDEP
SCHEDULE
It is estimated that the file review Letter of Findings can be submitted within 20 business days of authorization and the QAPP, workplan, and updated HASP can be submitted within 20 business days of approval of the Letter of Findings.
Proposal for Preliminary File Review and QAPP Workplan Preparation BCSB Plantation Site ■ Plantation, FL April 13, 2023 ■ Terracon Proposal No. 34237088
CLOSING REMARKS
Terracon services will be conducted in accordance with the terms and conditions, contained within DEP Waste Cleanup Program (WCP) Contract No. HW687, executed January 5, 2022. It is understood that a Task Assignment will be issued to authorize us to perform this work.
We appreciate the opportunity to provide this proposal and look forward to working with you on this project. If you should have any questions or comments regarding this proposal, please contact Tom Lewis at 850-692-7194 or Shawn Ouellette at .
Sincerely, Terracon Consultants, Inc.
Shawn Ouellette, P.G. Tom Lewis, P.G.
Senior Geologist Principal
Attachments: Exhibit 1 Cost Spreadsheet Level of Effort
FDEP COST ESTIMATE
Contractor: Terracon
Date: 4/17/2023 Task #: HW687_ SubTask 1 Project Management SubTask 6
Site: School Board Of Broward County Plantation Site SubTask 2 File Review SubTask 7 Activity/Phase: File Review, Workplan Generation SubTask 3 HASP, Work Plan, QAPP SubTask 8
Project Manager: Megan Johnson SubTask 4 SubTask 9 SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$48.08 Project Manager Shawn Ouellette 6.82 6.82 $0.00 Administrative 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$72.12 Brownfield Consultant Tom Lewis 3.00 0.00 3.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $31.25 CADD Specialist Chelsea Fugate 7.00 3.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$0.00 Data Analyst & Visualization Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Environmental Technician 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Field Geologist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Field Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 GIS Technician 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$72.12 Principal Consultant Tom Lewis 2.00 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Project Geologist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Project Industrial Hygienist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$26.92 Project Scientist Gabrielle Skelton 52.50 28.00 24.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $48.08 Senior Geologist Shawn Ouellette 11.00 6.00 5.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$0.00 Senior Geologist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior GIS Analyst 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Industrial Hygienist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$40.87 Staff Engineer 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Staff Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total Hours 82.32 6.82 39.00 36.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Direct Labor $2,849.33 $327.80 $1,280.23 $1,241.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 116.00% $3,305.23 $380.25 $1,485.07 $1,439.91 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 56.26% $1,603.04 $184.42 $720.26 $698.36 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $7,757.60 $892.47 $3,485.56 $3,379.57 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF TERRACON Page 1
FDEP COST ESTIMATEContractor: Terracon Date: 4/17/2023
Task #: HW687_ SubTask 1 Project Management SubTask 6 Site: School Board Of Broward County Plantation Site SubTask 2 File Review SubTask 7
Activity/Phase: File Review, Workplan Generation SubTask 3 HASP, Work Plan, QAPP SubTask 8 Project Manager: Megan Johnson SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Travel
Vehicle Rental $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $7,757.60 $892.47 $3,485.56 $3,379.57 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $775.77 $89.25 $348.56 $337.96 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $8,533.37 $981.72 $3,834.12 $3,717.53 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF TERRACON Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : SBOBC Plantation Site SUBTASK 2: File Review
PROPOSAL NO. P34237088
DATE: 4/17/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Conduct File Review of 2 Parcels
Principal Geologist TL Review File Review Summary, Review Remedial Recomendations 2.0 Senior Geologist GS Conduct File Review North Parcel Broward Parcel ID 504107010140 14.0 Senior Geologist GS Conduct File Review South Parcel Broward Parcel ID 504107150020 14.0 Project Scientist SO Conduct File Review Summary and Site Visit 6.0
Cadd Support CF Preparation of File Review Figures 3.0 Personnel: TL SO CF GS
Hours: 2.00 6.00 3.00 28.00
TOTAL LABOR 39.0
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : SBOBC Plantation Site SUBTASK 3: HASP, Workplan and QAPP
PROPOSAL NO. P34237088
DATE: 4/17/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
HASP
Senior Geologist SO Review and Finalize HASP 1.0 Project Scientist GS Prepare HASP 2.5
QAPP Work Plan Senior Scientist/Engineer SO Review and Finalize QAPP and Work Plan 4.0 Project Scientist GS Prepare QAPP and Workplan 22.0
Senior Brown Field Consultant TL Site Specs for QAPP and Workplan, Recommendations 3.0
Cadd Support CF Preparation of Workplan Drawings 4.0 Personnel: TL SO CF GS
Hours: 3.00 5.00 4.00 24.50
TOTAL LABOR 36.5