33 31 26 - Sanitary Pressure Sewer Piping.pdf
PDF 236 KB Posted
- Attached to
- Contract 2026-01: Maintenance & Emergency Contract (Excavation) – Project No. 7297. 0444
- Solicitation number
- Not on record
- Issued by
- York County, Pennsylvania
About this file
This is a technical specification document for sanitary pressure sewer piping issued by Herbert, Rowland & Grubic, Inc. for West Manchester Township (Project No. 007297.0444) in Pennsylvania. The specification establishes requirements for the installation of low-pressure sanitary sewer pipelines, service connections, air release valves, and associated components as part of the township's Maintenance & Emergency Contract (Contract 2026-01). The work includes polyethylene piping sized at 3-inch nominal and smaller, combination air valves rated 2-250 psig, forced sewer assemblies, and poly or stainless steel ball valves, all of which must comply with applicable ASTM and AASHTO standards. Installation requirements detail bedding placement, pipe laying to specified slopes, minimum 12-inch compacted bedding thickness, and proper backfilling and compaction procedures. The specification references related sections covering concrete, earthwork, trenching, fill materials, hydrostatic testing, and utility identification signage. Sealed bids for the contract were to be received by West Manchester Township online until 10:00 AM local time on Wednesday, May 20, 2026, with bid security required in the form of a Certified Check or Bid Bond in an amount not less than 10 percent.
The specification establishes product quality standards through manufacturer certifications and compliance with industry standards, requiring submittal of product data, manufacturer instructions, and field quality-control test results. Materials must include AASHTO No. 8 aggregate for bedding and cover, with soil backfill suitable per PENNDOT 2A specifications depending on trench location. Acceptable combination air valve manufacturers include H-TEC (Model 990-00), ARI (Model D-26), and APCO (Model ASU), while forced sewer assembly manufacturers include Lateral Connection Corp., E/One, or equals. Field quality control requires inspection prior to and immediately after bedding placement, with pressure testing conducted per specified hydrostatic testing requirements. The contract represents ongoing emergency and maintenance work for West Manchester Township's sanitary and storm sewer collection and conveyance systems, with specific scope and pricing established through individual Work Orders issued by the owner.
View the file
Other files
Show 40 more
Latest 50 of 69 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
33 31 26 - SANITARY PRESSURE SEWER PIPING
Herbert, Rowland & Grubic, Inc. 33 31 26 - 1 007297.0444
SECTION 33 31 26 - SANITARY PRESSURE SEWER PIPING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Sanitary sewer low-pressure pipelines.
2. Service connections.
3. Air release valves.
4. Valves.
5. Bedding and cover materials.
B. Related Requirements:
1. Section 03 30 00 - Cast-in-Place Concrete: Concrete material requirements.
2. Section 31 05 13 - Soils for Earthwork: Soil backfill from above pipe to finish grade.
3. Section 31 05 16 - Aggregates for Earthwork: Aggregate for basin backfill.
4. Section 31 23 16.13 - Trenching: Excavation, backfilling, compacting, and fill.
5. Section 31 23 23 - Fill: Requirements for fill.
6. Section 33 05 05.31 - Hydrostatic Testing: Pressure testing of completed pressure sewer piping.
7. Section 33 05 97 - Identification and Signage for Utilities: Pipe markers.
1.2 REFERENCE STANDARDS
A. American Association of State Highway and Transportation Officials:
1. AASHTO T 180 - Standard Method of Test for Moisture-Density Relations of Soils
Using a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop.
B. ASTM International:
1. ASTM D698 - Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Standard Effort (12,400 ft-lbf/ft3 (600 kN-m/m3).
2. ASTM D1557 - Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3 (2,700 kN-m/m3).
3. ASTM D1785 - Standard Specification for Poly(Vinyl Chloride) (PVC) Plastic Pipe, Schedules 40, 80, and 120.
4. ASTM D2241 - Standard Specification for Poly(Vinyl Chloride) (PVC) Pressure-
Rated Pipe (SDR Series).
5. ASTM D2321 - Standard Practice for Underground Installation of Thermoplastic
Pipe for Sewers and Other Gravity-Flow Applications.
6. ASTM D2466 - Standard Specification for Poly(Vinyl Chloride) (PVC) Plastic Pipe
Fittings, Schedule 40.
7. ASTM D2564 - Standard Specification for Solvent Cements for Poly(Vinyl Chloride)
(PVC) Plastic Piping Systems.
8. ASTM D3139 - Standard Specification for Joints for Plastic Pressure Pipes Using
Flexible Elastomeric Seals.
9. ASTM D6938 - Standard Test Method for In-Place Density and Water Content of
Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth).
Herbert, Rowland & Grubic, Inc. 33 31 26 - 2 007297.0444
10. ASTM F477 - Standard Specification for Elastomeric Seals (Gaskets) for Joining Plastic Pipe.
1.3 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Product Data: Submit manufacturer information indicating pipe material used, pipe accessories, valves, fittings, and combination air valves.
C. Manufacturer's Certificate: Certify that products meet or exceed specified requirements.
D. Manufacturer Instructions: Submit special procedures required to install specified products.
E. Field Quality-Control Submittals: Indicate results of Contractor-furnished tests and inspections.
1.4 DELIVERY, STORAGE, AND HANDLING
A. Section 01 61 00 - Product Requirements: Requirements for transporting, handling, storing, and protecting products.
B. Inspection: Accept materials on Site in manufacturer's original packaging and inspect for damage.
C. Storage:
1. Store materials according to manufacturer instructions.
2. Do not store materials on private property without written permission of property owner.
3. Do not stack pipe higher than recommended by pipe manufacturer.
D. Protection:
1. Protect materials from moisture and dust by storing in clean, dry location remote from construction operations areas.
2. Provide additional protection according to manufacturer instructions.
1.5 EXISTING CONDITIONS
A. Field Measurements:
1. Verify field measurements prior to fabrication.
2. Indicate field measurements on Shop Drawings.
PART 2 - PRODUCTS
2.1 LOW-PRESSURE SEWER PIPING
A. Polyethylene (PE) Piping:
1. Pipe:
Herbert, Rowland & Grubic, Inc. 33 31 26 - 3 007297.0444
a. Pipe Size 3-Inch Nominal Size and Smaller: Comply with ASTM D3035, DR- 11, IPS, for 200 psig pressure rating.
2. Materials:
a. Comply with ASTM D3350.
b. Minimum Cell Classification: 445574C.
c. Designation: PE 4710.
3. Fittings:
a. Comply with AWWA C901.
b. Style: Molded or fabricated.
4. Joints:
a. Fusion: Butt, Socket, and Electrofusion.
b. Threaded: NPT.
2.2 COMBINATION AIR VALVES FOR WASTEWATER SERVICE
A. Manufacturers:
1. H-TEC, Model 990-00.
2. ARI, Model D-26.
3. APCO, Model ASU.
4. Substitutions: As specified in Section 01 61 00 - Product Requirements.
B. Description:
1. Type:
a. Combination air release and air vacuum valve.
b. Automatic, float operated.
c. Body: Single.
2. Inlet and Outlet Size: 2 inch.
3. Suitable for sewage service.
4. Pressure Rating: 2 -250 psig.
5. Connection: Threaded.
6. Drain: Included with shutoff valve.
C. Materials:
1. Body and Cover: 316 Stainless Steel.
2. Float: 316 Stainless Steel or polypropylene.
3. Seals: Designed for intended service.
2.3 VALVES
A. Forced Sewer Assembly:
1. Description: Single body assembly consisting of curb stop valve and check valve.
2. Material: 316 stainless steel.
3. Size: 1.5-inch.
4. Pressure Rating: 200 psig.
5. Connections: Threaded NPT.
6. Curb Stop Valve operator: Service Key.
7. Manufacturers: Lateral Connection Corp., E/One, or equal.
8. Accessory: Operating Rod Extension.
Herbert, Rowland & Grubic, Inc. 33 31 26 - 4 007297.0444
B. Poly Ball Valves:
1. Full port design.
2. PE4710 polyethylene body, compatible with HDPE DR-11 pipe.
3. Pressure rating: 200 psig.
4. Designed for use with sewage.
5. Operating nut: 2-inch square.
6. Connections: butt fusion.
7. Meets requirements of ASTM D2513.
C. Stainless Steel Ball Valves:
1. Full port design.
2. 2-piece or 3-piece body.
3. Operating handle.
4. Pressure rating: 200 psig (min.).
5. Connections: Threaded NPT.
6. Material: 316 stainless steel.
2.4 MATERIALS
A. Bedding and cover.
1. Bedding and cover: AASHTO No. 8, as specified in Section 31 05 16 - Aggregates for Earthwork.
2. Soil Backfill from above Pipe to Finish Grade: Suitable Backfill and Embankment
Material as specified in Section 31 05 13 - Soils for Earthwork or PENNDOT 2A based on trench location.
3. Subsoil: No rocks more than 6 inches in diameter, frozen earth, or foreign matter.
B. Concrete: As specified in Section 03 30 00 - Cast-in-Place Concrete.
2.5 ACCESSORIES
A. Valve Boxes:
1. Manufacturers:
a. Tyler Union, Bingham & Taylor, or equal.
2. Valves 12 Inches and Smaller:
a. Type: Two-piece screw.
b. Material: Domestic cast iron.
3. Valves Larger Than 12 Inches:
a. Type: Three-piece screw.
b. Material: Domestic cast iron.
c. Base: Round.
4. Lid: Cast iron, inscribed with “SEWER”
B. Adjustable Valve Boxes:
1. Manufacturers:
a. Tyler Union, Bingham & Taylor, or equal.
2. Material: Cast Iron.
3. Bottom: Belled.
4. Configuration: Bell arched and flanged.
Herbert, Rowland & Grubic, Inc. 33 31 26 - 5 007297.0444
5. Adjustment: Screw.
6. Top Collar and Lid: Cast iron.
7. Inscription:
a. Cast with lid.
b. "SEWER."
C. Pipe Markers: As specified in Section 33 05 97 - Identification and Signage for Utilities.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Section 01 73 00 - Execution Requirements: Requirements for installation examination.
B. Verify that trench cut is ready to receive Work.
C. Verify that excavations, dimensions, and elevations are as indicated on Work Orders.
3.2 PREPARATION
A. Section 01 73 00 - Execution Requirements: Requirements for installation preparation.
B. Correct over-excavation with [fine aggregate] [coarse aggregate] [lean concrete].
C. Remove large stones or other hard matter that could damage pipe or impede consistent backfilling or compaction.
D. Protect pipe and aggregate cover from damage or displacement until backfilling operation is in progress.
3.3 INSTALLATION
A. Bedding:
1. Excavate pipe trench as specified in Section 31 23 16.13 - Trenching.
2. Place bedding material at trench bottom.
3. Level materials in continuous layer not exceeding 8 inches.
4. Maintain optimum moisture content of bedding material to attain required compaction density.
B. Piping:
1. Install pipe, fittings, and accessories according to ASTM D3035, and seal joints watertight.
2. Lay pipe to slope gradients as indicated on Work Orders.
3. Install bedding at sides and over top of pipe to minimum compacted thickness of
12 inches.
4. Backfilling and Compacting:
a. As specified in Section 31 23 16.13 - Trenching.
b. Do not displace or damage pipe while compacting.
Herbert, Rowland & Grubic, Inc. 33 31 26 - 6 007297.0444
5. Pipe Markers: As specified in Section 33 05 97 - Identification and Signage for Utilities.
C. Air Release Valves and Valves: Install at locations as indicated on Work Orders and according to manufacturer instructions.
D. Valves: Install at locations as indicated on Work Orders and according to manufacturer instructions.
E. Valve Boxes: Install at locations as indicated on Work Orders and according to manufacturer instructions.
3.4 FIELD QUALITY CONTROL
A. Section 01 40 00 - Quality Requirements: Requirements for inspecting and testing.
B. Inspection: Request inspection prior to and immediately after placement of bedding.
C. Pressure Testing: As specified in Section 33 05 05.31 - Hydrostatic Testing.
3.5 PROTECTION
A. Section 01 73 00 - Execution Requirements: Requirements for protecting finished Work.
B. Protect pipe and aggregate cover from damage or displacement until backfilling operation is in progress.
END OF SECTION