33 05 05.43 - Mandrel Testing.pdf

PDF 212 KB Posted

Attached to
Contract 2026-01: Maintenance & Emergency Contract (Excavation) – Project No. 7297. 0444
Solicitation number
Not on record
Issued by
York County, Pennsylvania

About this file

This is a technical specification document for mandrel testing procedures related to Contract 2026-01, a Maintenance & Emergency Contract for excavation work issued by West Manchester Township in Pennsylvania. The specification establishes requirements for deflection testing of plastic sewer piping, including PVC and ABS materials, which must be performed after backfilling has remained in place for a minimum of 30 days but no longer than 12 months. Testing must be conducted in the presence of the Township or Township Representative using "go, no go" mandrel equipment, with allowable maximum deflection not exceeding five percent of the original vertical internal diameter. Prior to testing, contractors must submit testing procedures, test equipment lists, testing sequence schedules, water disposal provisions, test gage calibration certifications, and mandrel drawings with calculations. The specification also requires lamping operations to verify uniform line and grade installation, with rejected pipe sections requiring removal and reinstallation at no additional cost to the Township.

The specification establishes quality control standards that contractors must meet at their sole expense, including excavation and replacement of any pipe exceeding allowable deflection limits, along with surface restoration. Testing equipment requirements include pull/retrieval ropes and mandrels with diameters not less than 95 percent of the base or average internal diameter of the pipe, with dimensions verified in accordance with ASTM D2122 standards. All deflection testing must be performed without mechanical pulling devices. The document references related sections addressing sanitary sewerage gravity piping materials, submittals procedures, execution requirements, and quality requirements, establishing a comprehensive framework for ensuring the structural integrity of installed plastic sewer piping systems.

View the file

Other files

File Type Posted
32 92 19 - Seeding.pdf PDF
31 05 16 - Aggregates For Earthwork.pdf PDF
00 45 36 EEO Certificate.pdf PDF
01 22 00 - Unit Prices.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
00 01 01 - YO Cover.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
31 23 16 - Excavation.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
31 23 19 - Dewatering.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 01 10 - Table of Contents.pdf PDF
01 42 00 - References.pdf PDF
31 23 16.13 - Trenching.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
Sanitary and Storm Sewer Maintenance & Emergency Construction Details.pdf PDF
33 42 00 - Stormwater Conveyance.pdf PDF
31 10 00 - Site Clearing.pdf PDF
02 57 00 - Sinkhole Remediation.pdf PDF
33 31 11 - Public Sanitary Sewerage Gravity Piping.pdf PDF
03 20 00 - Concrete Reinforcing.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
00 63 13 - RFI Form.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 52 00 - Agmnt btw Own and Cntr for Const Con Stip Price.pdf PDF
31 23 23 - Fill.pdf PDF
33 05 61 - Concrete Manholes and Inlets.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
03 30 00 - Cast-in-Place Concrete.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
32 17 23 - Pavement Markings.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
31 05 13 - Soils For Earthwork.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
02 41 13.23 - Utility Line Removal.pdf PDF
33 05 05.41 - Air Testing.pdf PDF
33 31 23 - Sanitary Sewerage Force Main Piping.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
00 31 43 - Permit Applications.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
32 11 23 - Aggregate Base Courses.pdf PDF
00 63 36 - Work Order Form.pdf PDF
Show 40 more

Latest 50 of 69 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

33 05 05.43 - MANDREL TESTING

Herbert, Rowland & Grubic, Inc. 33 05 05.43 - 1 007297.0444

SECTION 33 05 05.43 - MANDREL TESTING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes: Deflection testing of plastic sewer piping.

B. Related Requirements:

1. Section 33 31 11 - Public Sanitary Sewerage Gravity Piping: Pipe materials, manholes, and accessories normally encountered with gravity sewerage piping.

1.2 REFERENCE STANDARDS

A. ASTM International:

1. ASTM D2122 - Standard Test Method for Determining Dimensions of

Thermoplastic Pipe and Fittings.

1.3 SUBMITTALS

A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.

B. Submit following items prior to start of testing:

1. Testing procedures.

2. List of test equipment.

3. Testing sequence schedule.

4. Provisions for disposal of flushing and test water.

5. Certification of test gage calibration.

6. Deflection mandrel drawings and calculations.

C. Test and Evaluation Reports: Indicate results of piping tests.

PART 2 - PRODUCTS

2.1 DEFLECTION TESTING

A. Equipment:

1. “Go, No Go" mandrel.

2. Pull/retrieval ropes.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Section 01 73 00 - Execution Requirements: Requirements for installation examination.

B. Verify that piping is ready for testing.

C. Verify that trenches are backfilled.

33 05 05.43 - MANDREL TESTING

Herbert, Rowland & Grubic, Inc. 33 05 05.43 - 2 007297.0444

3.2 PREPARATION

A. Section 01 73 00 - Execution Requirements: Requirements for preparation.

B. Lamping:

1. Lamp gravity piping after flushing and cleaning in the presence of the Township or Township Representative.

2. Perform lamping operation by shining light at one end of each pipe section between manholes.

3. The Township or Township Representative will observe the light at other end.

4. Pipe not installed with uniform line and grade will be rejected.

5. Remove and reinstall rejected pipe sections.

6. Clean and lamp until pipe section is installed to uniform line and grade.

C. Plugs:

1. Plug outlets, wye branches, and laterals.

2. Brace plugs to resist test pressures.

3.3 FIELD QUALITY CONTROL

A. Section 01 40 00 - Quality Requirements: Requirements for inspecting and testing.

B. Deflection Testing of Plastic Sewer Piping:

1. Perform vertical ring deflection testing on PVC and ABS sewer piping after backfilling has been in place for at least 30 days, but no longer than 12 months in the presence of the Township or Township Representative.

2. Allowable maximum deflection for installed plastic sewer pipe is no greater than five percent of original vertical internal diameter.

3. Perform deflection testing using "go, no go" mandrel.

4. Mandrel Diameter:

a. Not less than 95 percent of base or average ID of pipe.

b. Pipe Diameter: Comply with ASTM D2122.

5. Perform testing without mechanical pulling devices.

6. Pipe exceeding the allowable deflection shall be located, excavated, replaced, and retested at the sole expense of the Contractor, including surface restoration.

END OF SECTION