Contract 2026-01: Maintenance & Emergency Contract (Excavation) – Project No. 7297. 0444
Solicitation number
Not on record
Issued by
York County, Pennsylvania

About this file

This is a Requests for Interpretation specification document prepared by Herbert, Rowland & Grubic, Inc. for West Manchester Township's Contract 2026-01: Maintenance & Emergency Contract (Excavation) – Project No. 7297.0444 in Pennsylvania. The document establishes the procedures and requirements for Requests for Information/Interpretation (RFIs) that contractors may submit when clarification is needed on drawings or specifications during project execution. RFIs must be properly prepared with detailed written statements identifying specific drawings by number and location or specifications by section number, page, and paragraph. Contractors must submit RFIs using the designated RFI Form (Document 00 63 13) in consecutive numerical order via email, with all attachments properly numbered and labeled. RFIs from subcontractors or material suppliers must be reviewed and approved by the prime contractor before submission to the Engineer; those submitted directly to the Engineer will not be accepted. The Engineer will endeavor to respond to properly prepared RFIs in a timely manner, though the contractor must allow reasonable review and response time without guarantees for expedited replies.

RFIs may not be used to request approval of submittals, substitutions, changes involving cost or credit, or different work methods. Improperly prepared or frivolous RFIs—including those requesting information clearly shown in the Contract Documents—will be processed at the Engineer's standard hourly rate, with costs deducted from amounts due to the contractor. For coordination issues requiring clarification, contractors must submit suggested solutions with scaled drawings or sketches as part of the RFI or the request will be returned unanswered. The Engineer will respond to properly prepared RFIs directly on the RFI form or through a Request for Proposal, while improper RFIs will be returned with notification of processing fees or marked "Not Reviewed." The Engineer may retain RFIs for discussion during regularly scheduled project meetings with responses included in meeting minutes.

View the file

Other files

File Type Posted
32 92 19 - Seeding.pdf PDF
31 05 16 - Aggregates For Earthwork.pdf PDF
00 45 36 EEO Certificate.pdf PDF
01 22 00 - Unit Prices.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
00 01 01 - YO Cover.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
31 23 16 - Excavation.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
31 23 19 - Dewatering.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 01 10 - Table of Contents.pdf PDF
01 42 00 - References.pdf PDF
31 23 16.13 - Trenching.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
Sanitary and Storm Sewer Maintenance & Emergency Construction Details.pdf PDF
33 42 00 - Stormwater Conveyance.pdf PDF
31 10 00 - Site Clearing.pdf PDF
02 57 00 - Sinkhole Remediation.pdf PDF
33 31 11 - Public Sanitary Sewerage Gravity Piping.pdf PDF
33 05 05.43 - Mandrel Testing.pdf PDF
03 20 00 - Concrete Reinforcing.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
00 63 13 - RFI Form.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 52 00 - Agmnt btw Own and Cntr for Const Con Stip Price.pdf PDF
31 23 23 - Fill.pdf PDF
33 05 61 - Concrete Manholes and Inlets.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
03 30 00 - Cast-in-Place Concrete.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
32 17 23 - Pavement Markings.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
31 05 13 - Soils For Earthwork.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
02 41 13.23 - Utility Line Removal.pdf PDF
33 05 05.41 - Air Testing.pdf PDF
33 31 23 - Sanitary Sewerage Force Main Piping.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
00 31 43 - Permit Applications.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
32 11 23 - Aggregate Base Courses.pdf PDF
00 63 36 - Work Order Form.pdf PDF
Show 40 more

Latest 50 of 69 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 26 13 – REQUESTS FOR INTERPRETATION

Herbert, Rowland & Grubic, Inc. 01 26 13 - 1 007297.0444

SECTION 01 26 13 – REQUESTS FOR INTERPRETATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Requests For Interpretation.

B. Related Sections:

1. Document 00 60 00 – Project Forms.

2. Document 00 63 13 – RFI Form.

1.2 DEFINITIONS

A. Request For Information / Interpretation (RFI):

1. A properly prepared request for information / interpretation shall include a detailed written statement that indicates the specific Drawings or Specification in need of clarification and the nature of the clarification requested:

a. Drawings shall be identified by drawing number and location on the drawing sheet.

b. Specifications shall be identified by Section number, page and paragraph.

2. Requests for Information: Request made by Contractor concerning items not indicated on drawings or contained in Contract Documents that is required to properly perform the work.

B. Improper and Frivolous RFIs:

1. RFIs that are not properly prepared, or

2. RFIs that request information that is clearly shown on the Contract Documents.

3. Improper or Frivolous RFIs will be processed by the Engineer at the Engineer’s standard hourly rate and Engineer will charge the Owner, and such costs will be deducted from monies still due to the Contractor. The Contractor will be notified by the Engineer prior to the processing of improper RFIs.

1.3 CONTRACTOR'S REQUESTS FOR INFORMATION

A. Format: Use form Document 00 63 13 – RFI Form:

1. Forms shall be completely filled in, and if prepared by hand, shall be fully legible after photocopying or scanning.

2. RFIs shall be submitted in numerical order with no breaks in the consecutive numbering.

3. Each page of attachments to RFIs shall bear the RFI number and shall be consecutively numbered in chronological order.

4. Submit RFI via email.

B. When the Contractor is unable to determine from the Contract Documents, the material, process or system to be installed, the Engineer shall be requested to make a clarification of the indeterminate item.

01 26 13 – REQUESTS FOR INTERPRETATION

Herbert, Rowland & Grubic, Inc. 01 26 13 - 2 007297.0444

C. RFIs shall be originated by the Contractor:

1. RFIs from subcontractors or suppliers shall be submitted through, reviewed by, and approved by the Contractor prior to submittal to the Engineer.

2. RFIs from subcontractors or material suppliers sent directly to the Engineer shall not be accepted and will be returned unanswered.

D. In cases where RFIs are issued to request clarification of coordination issues, the Contractor shall fully lay out a suggested solution using drawings or sketches drawn to scale, and submit same with the RFI. RFIs which fail to include a suggested solution will be returned unanswered with a requirement that the Contractor submit a complete request.

E. RFIs shall not be used for the following purposes:

1. To request approval of submittals.

2. To request approval of substitutions.

3. To request changes which are known to entail additional cost or credit.

4. To request different methods of performing work.

F. Contractor shall allow a reasonable time for review and response time for RFIs:

1. The Engineer will endeavor to respond in a timely fashion to RFIs.

2. RFI shall state requested date/time for response, however, this requested date/time for response is not a guarantee that the RFI will be answered by that date/time if that date/time is too expeditious.

1.4 ENGINEER'S RESPONSE TO RFIs

A. Engineer will respond to RFIs on one of the following forms:

1. Properly prepared RFIs:

a. Response directly upon Request for Information / Interpretation form.

b. Request for Proposal.

2. Improper or Frivolous RFIs:

a. Notification of Processing Fee(s).

b. Unanswered RFIs will be returned with a notation: Not Reviewed.

3. Answers to properly prepared RFIs will be directly upon the RFI form as deemed appropriate by the Engineer.

B. Engineer may opt to retain RFIs for discussion during regularly scheduled project meetings for inclusion of responses in meeting minutes.

PART 2 - PRODUCTS - Not Used.

PART 3 - EXECUTION - Not Used.