33 05 05.41 - Air Testing.pdf

PDF 216 KB Posted

Attached to
Contract 2026-01: Maintenance & Emergency Contract (Excavation) – Project No. 7297. 0444
Solicitation number
Not on record
Issued by
York County, Pennsylvania

About this file

This is a technical specification document for air testing procedures related to gravity sewer piping, prepared by Herbert, Rowland & Grubic, Inc. for West Manchester Township, Pennsylvania under Contract 2026-01 (Project No. 007297.0444). The specification outlines mandatory low-pressure air testing requirements for all gravity sewer piping within the township's sanitary sewer system unless otherwise approved. Before testing commences, contractors must submit testing procedures, equipment lists, testing sequence schedules, water disposal provisions, and pressure gage calibration certification. The specification requires lamping (internal visual inspection) of all pipe sections between manholes in the presence of township representatives to verify uniform line and grade installation. Testing utilizes air compressors, regulators, relief valves, calibrated pressure gages (±0.1 psi accuracy), plugs, and stopwatches to introduce air pressure slowly to approximately 4 psig, adjusted based on groundwater elevation above the pipe spring line, with maximum pressure not exceeding 10 psig.

The air testing methodology establishes specific minimum testing durations per 100 feet of pipe based on diameter, ranging from 3 minutes 46 seconds for 4-inch pipe to 51 minutes 17 seconds for 36-inch pipe, with minimum test times of 2.5, 4, and 5 minutes respectively for smaller diameter laterals. Test failure is defined as air pressure drop exceeding 1.0 psi during the testing period; any pressure drop of 1.0 psi or less indicates acceptable piping. The contractor bears responsibility for identifying leak sources through incremental stage testing, executing repairs, and retesting until successful results are achieved. All visible leaks must be repaired regardless of leakage quantity, and all laterals installed into manholes require individual air testing. Sealed bids for the overall maintenance and emergency contract were due by 10:00 AM on Wednesday, May 20, 2026, with bids received online through PennBID and publicly opened at that time.

View the file

Other files

File Type Posted
32 92 19 - Seeding.pdf PDF
31 05 16 - Aggregates For Earthwork.pdf PDF
00 45 36 EEO Certificate.pdf PDF
01 22 00 - Unit Prices.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
00 01 01 - YO Cover.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
31 23 16 - Excavation.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
31 23 19 - Dewatering.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 01 10 - Table of Contents.pdf PDF
01 42 00 - References.pdf PDF
31 23 16.13 - Trenching.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
Sanitary and Storm Sewer Maintenance & Emergency Construction Details.pdf PDF
33 42 00 - Stormwater Conveyance.pdf PDF
31 10 00 - Site Clearing.pdf PDF
02 57 00 - Sinkhole Remediation.pdf PDF
33 31 11 - Public Sanitary Sewerage Gravity Piping.pdf PDF
33 05 05.43 - Mandrel Testing.pdf PDF
03 20 00 - Concrete Reinforcing.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
00 63 13 - RFI Form.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 52 00 - Agmnt btw Own and Cntr for Const Con Stip Price.pdf PDF
31 23 23 - Fill.pdf PDF
33 05 61 - Concrete Manholes and Inlets.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
03 30 00 - Cast-in-Place Concrete.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
32 17 23 - Pavement Markings.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
31 05 13 - Soils For Earthwork.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
02 41 13.23 - Utility Line Removal.pdf PDF
33 31 23 - Sanitary Sewerage Force Main Piping.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
00 31 43 - Permit Applications.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
32 11 23 - Aggregate Base Courses.pdf PDF
00 63 36 - Work Order Form.pdf PDF
Show 40 more

Latest 50 of 69 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

33 05 05.41 - AIR TESTING

Herbert, Rowland & Grubic, Inc. 33 05 05.41 - 1 007297.0444

SECTION 33 05 05.41 - AIR TESTING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes: Low-pressure air testing of gravity sewer piping.

B. Related Requirements:

1. Section 33 31 11 - Public Sanitary Sewerage Gravity Piping: Pipe materials, manholes, and accessories normally encountered with gravity sewerage piping.

1.2 SUBMITTALS

A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.

B. Submit following items prior to start of testing:

1. Testing procedures.

2. List of test equipment.

3. Testing sequence schedule.

4. Provisions for disposal of flushing and test water.

5. Certification of test gage calibration.

1.3 REQUIREMENTS

A. Air testing shall be performed on all gravity sewer piping unless approved otherwise.

B. The Contractor shall determine and correct the causes of test failure and retest until successful test results are achieved.

PART 2 - PRODUCTS

2.1 AIR TESTING

A. Equipment:

1. Air compressor.

2. Air supply line.

3. Shutoff valves.

4. Pressure regulator.

5. Pressure relief valve.

6. Stopwatch.

7. Plugs.

8. Pressure Gage: Calibrated to 0.1 psi.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Section 01 73 00 - Execution Requirements: Requirements for installation examination.

Herbert, Rowland & Grubic, Inc. 33 05 05.41 - 2 007297.0444

B. Verify that piping is ready for testing.

C. Verify that trenches are backfilled.

3.2 PREPARATION

A. Section 01 73 00 - Execution Requirements: Requirements for preparation.

B. Lamping:

1. Lamp gravity piping after flushing and cleaning in the presence of the Township.

2. Perform lamping operation by shining light at one end of each pipe section between manholes.

3. The Township will observe the light at other end.

4. Pipe not installed with uniform line and grade will be rejected.

5. Remove and reinstall rejected pipe sections.

6. Clean and lamp until pipe section is installed to uniform line and grade.

C. Plugs:

1. Plug outlets, wye branches, and laterals.

2. Brace plugs to resist test pressures.

3.3 FIELD QUALITY CONTROL

A. Section 01 40 00 - Quality Requirements: Requirements for inspecting and testing.

B. Low-Pressure Air Testing:

1. Test each reach of gravity sewer piping between manholes.

2. Introduce air pressure slowly to approximately 4 psig.

3. Determine ground water elevation above spring line of piping.

4. For every foot of ground water above spring line of piping, increase starting air test pressure by 0.43 psi.

5. Do not increase pressure above 10 psig.

6. Allow pressure to stabilize for at least five minutes.

7. Adjust pressure to 3.5 psig or to increased test pressure as determined above when ground water is present.

8. Do not make allowance for laterals.

9. Minimum Testing Duration in Minutes Per 100 Feet:

a. Pipe Size 4 Inches: 3:46.

b. Pipe Size 6 Inches: 5:40.

c. Pipe Size 8 Inches: 7:34.

d. Pipe Size 10 Inches: 9:26.

e. Pipe Size 12 Inches: 11:20.

f. Pipe Size 15 Inches: 14:10.

g. Pipe Size 18 Inches: 17:00.

h. Pipe Size 21 Inches: 19:50.

i. Pipe Size 24 Inches: 22:47.

j. Pipe Size 27 Inches: 28:51.

k. Pipe Size 30 Inches: 35:37.

l. Pipe Size 36 Inches: 51:17.

Herbert, Rowland & Grubic, Inc. 33 05 05.41 - 3 007297.0444

m. Pipe Size 42 Inches: 69:48.

10. Record drop in pressure during testing period.

11. If air pressure drops more than 1.0 psi during testing period, piping has failed.

12. If 1.0-psi air pressure drop has not occurred during testing period, piping is acceptable; discontinue testing.

13. If piping fails, test reach of piping in incremental stages until leaks are isolated, repair leaks, and retest entire reach between manholes.

14. If unsatisfactory testing results are achieved, make necessary repairs and retest until result meets criteria.

15. Repair visible leaks regardless of quantity of leakage.

16. All laterals installed into manholes shall be air tested. Regardless of pipe length, the minimum test times for 4-inch diameter, 6-inch diameter, and 8-inch diameter pipes are 2.5, 4 and 5 minutes, respectively.

END OF SECTION