32 12 16 - Asphalt Paving.pdf

PDF 223 KB Posted

Attached to
Contract 2026-01: Maintenance & Emergency Contract (Excavation) – Project No. 7297. 0444
Solicitation number
Not on record
Issued by
York County, Pennsylvania

About this file

This is a technical specifications document for asphalt paving work under Contract 2026-01: Maintenance & Emergency Contract (Excavation) issued by West Manchester Township in Pennsylvania. The project encompasses asphalt paving restoration including aggregate subbase installation, base course placement, and wearing course application for streets, driveways, parking areas, and other surfaces disturbed during utility maintenance and emergency work. Work will be performed on an as-needed basis through Work Orders issued by the Owner, with sealed bids due by 10:00 AM on Wednesday, May 20, 2026. The specifications require compliance with PennDOT standards and publications, including use of PG 64S-22 asphalt cement and Superpave mixture designs for both base and wearing courses. Existing pavement must be saw-cut equidistant from trench centerlines and removed to a width equal to maximum excavation width plus one foot on each side. The contractor is responsible for temporary surfacing maintenance if permanent pavement cannot be placed due to weather, with permanent surfacing required within ten days of base course installation or temporary pavement placement as conditions allow.

The contractor must obtain all asphalt and aggregate materials from the same source throughout the project and submit product data, mix designs with laboratory test results, and material certifications from PennDOT-registered and approved manufacturers. Daily surface maintenance is mandatory during construction, including street sweeping and dust control measures, with failure to maintain conditions subject to backcharging of corrective work costs. The contractor shall maintain all completed paving work for twelve months following the Owner's approval of the final Completion Certificate at no additional compensation, including repair or replacement of failed sections or damaged areas. Bid security in the form of a Certified Check or Bid Bond is required in an amount not less than 10%. Bidding documents are available through PennBID at https://pennbid.bonfirehub.com/, with no pre-bid conference scheduled.

View the file

Other files

File Type Posted
32 92 19 - Seeding.pdf PDF
31 05 16 - Aggregates For Earthwork.pdf PDF
00 45 36 EEO Certificate.pdf PDF
01 22 00 - Unit Prices.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
00 01 01 - YO Cover.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
31 23 16 - Excavation.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
31 23 19 - Dewatering.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 01 10 - Table of Contents.pdf PDF
01 42 00 - References.pdf PDF
31 23 16.13 - Trenching.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
Sanitary and Storm Sewer Maintenance & Emergency Construction Details.pdf PDF
33 42 00 - Stormwater Conveyance.pdf PDF
31 10 00 - Site Clearing.pdf PDF
02 57 00 - Sinkhole Remediation.pdf PDF
33 31 11 - Public Sanitary Sewerage Gravity Piping.pdf PDF
33 05 05.43 - Mandrel Testing.pdf PDF
03 20 00 - Concrete Reinforcing.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
00 63 13 - RFI Form.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 52 00 - Agmnt btw Own and Cntr for Const Con Stip Price.pdf PDF
31 23 23 - Fill.pdf PDF
33 05 61 - Concrete Manholes and Inlets.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
03 30 00 - Cast-in-Place Concrete.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
32 17 23 - Pavement Markings.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
31 05 13 - Soils For Earthwork.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
02 41 13.23 - Utility Line Removal.pdf PDF
33 05 05.41 - Air Testing.pdf PDF
33 31 23 - Sanitary Sewerage Force Main Piping.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
00 31 43 - Permit Applications.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
32 11 23 - Aggregate Base Courses.pdf PDF
00 63 36 - Work Order Form.pdf PDF
Show 40 more

Latest 50 of 69 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

32 12 16 - ASPHALT PAVING

Herbert, Rowland & Grubic, Inc. 32 12 16 - 1 007297.0444

SECTION 32 12 16 - ASPHALT PAVING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Aggregate subbase.

2. Aggregate base and wearing course.

B. Related Requirement:

1. Section 31 23 23 - Fill: Compacted subbase for paving.

2. Section 32 11 23 - Aggregate Base Courses: Compacted subbase for paving.

1.2 REFERENCE STANDARDS

A. Pennsylvania Department of Transportation:

1. Publication 19 – Field and Laboratory Test Methods, latest edition.

2. Publication 408 - Specifications, latest edition, as amended.

3. Publication 72M (Roadway Construction Standards) latest edition, as amended.

1.3 SUBMITTALS

A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.

B. Product Data:

1. Submit product information for asphalt and aggregate materials.

2. Submit mix design with laboratory test results supporting design.

C. Material Slips: Furnish certification of the amount of materials utilized from the producer in accordance with PennDOT specifications.

1.4 QUALITY ASSURANCE

A. Manufacturer Qualifications: A paving-mix manufacturer registered with and approved by PennDOT.

B. Obtain materials from same source throughout.

C. Perform Work in accordance with West Manchester Township Construction and Materials Specifications Manual.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Asphalt Materials:

1. Asphalt Cement: PG 64S-22 conforming to PennDOT Bulletin 25.

2. Asphalt Rubber Sealing Compound: Conforming to PennDOT Bulletin 25.

Herbert, Rowland & Grubic, Inc. 32 12 16 - 2 007297.0444

3. Superpave Wearing Course Asphalt Mixture Design: In accordance with PennDOT Publication 408, Section 413.

4. Superpave Base Course Asphalt Mixture Design: In accordance with PennDOT Publication 408, Section 313.

5. Asphalt Tack Coat: In accordance with PennDOT Publication 408, Section 460.2.

B. Aggregate Subbase: Type C or better, No. 2A, Section 703.2, placement per Section 350.

C. Aggregate Subbase Repair: AASHTO No. 1, in accordance with PennDOT 408, Section 703.2.

PART 3 - EXECUTION

3.1 PREPARATION

A. Existing Pavement Removal:

1. Saw cut existing pavement using a mechanical saw to neat lines equidistant from the centerline of the trench.

2. Remove pavement to width equal to maximum excavated trench width plus not less than one foot on each side of the trench. If roadway is removed or disturbed for a greater width without written authorization of the Engineer, the Owner will require the Contractor to replace such pavement without compensation.

3.2 EXAMINATION

A. Section 01 73 00 - Execution Requirements: Requirements for installation examination.

B. Verify utilities indicated under paving are installed with excavations and trenches backfilled and compacted.

C. Verify compacted subgrade subbase is dry and ready to support paving and imposed loads.

D. Verify gradients and elevations of base are correct.

E. Verify manhole frames are installed in correct position and elevation.

3.3 INSTALLATION

A. General: Restore streets, shoulders, driveways, parking areas and other areas according to the Work Order. All work shall conform to PennDOT Publication 408 for materials, placement, and compaction.

B. Temporary Surfacing:

1. Temporary pavement shall be installed as directed by the Engineer in the event where permanent pavement cannot be placed due to the weather limitations set forth herein for the placing of asphalt material for the permanent base and surface courses. The temporary surface shall be as specified in the Work Order.

2. Temporary surfacing shall be maintained in a safe, drivable condition at all times.

Herbert, Rowland & Grubic, Inc. 32 12 16 - 3 007297.0444

3. Contractor shall be responsible for the removal and disposal of the temporary surfacing to the grade required for the placement of the final sub-base, base, and surface at the specified depths.

C. The Contractor shall be responsible for the maintenance and protection of all surfacing, as well as manholes, frame and covers, valve boxes, and other facilities or structures located within the areas of the roadway reconstruction until such time that the permanent pavement or surface can be placed. Permanent surfacing must be placed no later than ten (10) days following the placement of base course paving unless otherwise approved by Owner or Engineer. In the event that environmental conditions do not allow for placement of permanent surfacing within the ten days specified, temporary pavement must be placed as soon as conditions allow.

D. Prior to placement of final surfacing, the Contractor, Owner, and Engineer shall inspect all areas to be restored. The Contractor shall be responsible for any replacement of material, regrading, or addition of material deemed necessary by the Engineer in any areas found to be unacceptable for receipt of final surfacing.

E. The Contractor shall be responsible for any necessary adjustments to grade for manholes, frame and covers, and other facilities or structures prior to final surfacing.

F. Asphalt Materials:

1. Superpave Wearing Course Asphalt Mixture Design, placement, and compaction:

In accordance with PennDOT Publication 408, Section 413.

2. Superpave Base Course Asphalt Mixture Design, placement, and compaction: In accordance with PennDOT Publication 408, Section 313.

3. Asphalt Tack Coat: In accordance with PennDOT Publication 408, Section 460.3.

4. Aggregate Subbase: Construct and place in accordance with the requirements of

PennDOT Section 350.3:

a. Install on prepared subgrade as specified in PennDOT Section 210.

b. Install subbase to underside of base course as specified.

c. Subgrade shall be proof rolled and unstable areas undercut as directed by Engineer.

5. Asphalt Rubber Sealing Compound: Apply according to PennDOT Bulletin 25. Use to seal joints between existing and new pavements, new pavement and curbing, and new pavement and manhole frame and covers, valve boxes, etc.

3.4 CLEAN UP

A. During construction, surfaces of all areas including, but not limited to, roads, streets, and driveways shall be maintained on a daily basis to produce a safe, desirable, and convenient condition:

1. Streets shall be swept and flushed after backfilling, and recleaned as dust, mud, stones and debris caused by the work, or related to the work again accumulates.

2. Failure of the Contractor to perform this work shall be cause for the Engineer to order the work to be done by others, and backcharge all costs to the Contractor.

B. Repair or Correction of Unsatisfactory Conditions: All unsatisfactory conditions resulting from the work shall be corrected.

Herbert, Rowland & Grubic, Inc. 32 12 16 - 4 007297.0444

C. Dust Control: Provide effective dust control by sprinkling water, by the use of calcium chloride or by any other methods approved by Engineer. Use dust control measures where, when and in a manner required by Engineer.

3.5 MAINTENANCE

A. Continuously maintain temporary paving without additional compensation until it is replaced with permanent paving.

B. Maintain without additional compensation, such work of this Section done under this Contract for a period of twelve (12) months after the date of Owner’s approval of the final Completion Certificate issued by Engineer, including the repair or removal and replacement of such work which has failed or has been damaged or wherever surface depressions have been developed. Materials and methods used to repair or replace such work shall conform to the applicable requirements of this Section.

C. Should Contractor fail to perform required maintenance or repairs within three days after written notice from Owner or Engineer, the Owner may perform such maintenance or repairs and deduct the cost thereof from any monies due or to become due Contractor.

3.6 RESTORATION SCHEDULE – See Work Order.

END OF SECTION