31 10 00 - Site Clearing.pdf

PDF 211 KB Posted

Attached to
Contract 2026-01: Maintenance & Emergency Contract (Excavation) – Project No. 7297. 0444
Solicitation number
Not on record
Issued by
York County, Pennsylvania

About this file

This is a Scope of Work document prepared by Herbert, Rowland & Grubic, Inc. for West Manchester Township's Maintenance & Emergency Contract (Project No. 7297.0444) in Pennsylvania. The document outlines site clearing services required for the township's utility infrastructure projects. The scope of work includes removal of surface debris, designated paving and curbs, trees, shrubs, and other plant life, abandoned utilities, and topsoil excavation. Work must comply with all applicable environmental codes and disposal regulations. Contractors must call Local Utility Line Information services at least three working days before beginning work to locate and mark underground utilities. The contract allows for work to be issued on an as-needed basis through Work Orders from the Owner. Sealed bids were to be received by West Manchester Township online until 10:00 AM local time on Wednesday, May 20, 2026, with bids publicly opened on PennBID. No pre-bid conference was scheduled for this project.

The specification requires contractors to protect designated trees, plant growth, survey control points, and existing structures from damage during clearing operations. All debris, rock, and extracted plant material must be removed from the site and disposed of at locations outside the Owner's property in compliance with applicable laws; burning or burying materials on site is prohibited. Topsoil must be excavated separately without mixing with foreign materials, stockpiled to a maximum depth of eight feet in a designated site location, and retained on site for finish grading purposes. Bid security in the form of a Certified Check or Bid Bond equal to at least ten percent of the bid amount was required. Prospective bidders were instructed to register on PennBID and obtain all bidding documents from the designated website, as the Owner and Engineer would not be responsible for documents obtained from other sources.

View the file

Other files

File Type Posted
32 92 19 - Seeding.pdf PDF
31 05 16 - Aggregates For Earthwork.pdf PDF
00 45 36 EEO Certificate.pdf PDF
01 22 00 - Unit Prices.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
00 01 01 - YO Cover.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
31 23 16 - Excavation.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
31 23 19 - Dewatering.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 01 10 - Table of Contents.pdf PDF
01 42 00 - References.pdf PDF
31 23 16.13 - Trenching.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
Sanitary and Storm Sewer Maintenance & Emergency Construction Details.pdf PDF
33 42 00 - Stormwater Conveyance.pdf PDF
02 57 00 - Sinkhole Remediation.pdf PDF
33 31 11 - Public Sanitary Sewerage Gravity Piping.pdf PDF
33 05 05.43 - Mandrel Testing.pdf PDF
03 20 00 - Concrete Reinforcing.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
00 63 13 - RFI Form.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 52 00 - Agmnt btw Own and Cntr for Const Con Stip Price.pdf PDF
31 23 23 - Fill.pdf PDF
33 05 61 - Concrete Manholes and Inlets.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
03 30 00 - Cast-in-Place Concrete.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
32 17 23 - Pavement Markings.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
31 05 13 - Soils For Earthwork.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
02 41 13.23 - Utility Line Removal.pdf PDF
33 05 05.41 - Air Testing.pdf PDF
33 31 23 - Sanitary Sewerage Force Main Piping.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
00 31 43 - Permit Applications.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
32 11 23 - Aggregate Base Courses.pdf PDF
00 63 36 - Work Order Form.pdf PDF
Show 40 more

Latest 50 of 69 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

31 10 00 - SITE CLEARING

Herbert, Rowland & Grubic, Inc. 31 10 00 - 1 007297.0444

SECTION 31 10 00 - SITE CLEARING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Removing surface debris.

2. Removing designated paving and curbs.

3. Removing designated trees, shrubs, and other plant life.

4. Removing abandoned utilities.

5. Excavating topsoil.

B. Related Sections:

1. Section 31 23 16.26 - Rock Removal.

2. Section 31 25 00 - Erosion and Sedimentation Controls.

1.2 DEFINITIONS

A. Clearing is defined as the removal of trees, brush, down timber, rotten wood, rubbish, any other vegetation, and other material at or above original ground elevation not designated to be saved. Clearing also includes removal and replacement of fences, walls, guideposts, guide rail, signs, and other obstructions interfering with the proposed work.

B. Grubbing is defined as the removal from below the surface of the natural ground of stumps, roots and stubs, brush, topsoil, organic materials and debris.

1.3 SUBMITTALS

A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.

B. Product Data: Submit data for herbicide. Indicate compliance with applicable codes for environmental protection.

C. Permits for Disposal of Debris:

1. Arrange for disposal of debris to locations outside the Owner's property, permanent easement, or right of way. Comply with all applicable laws.

2. Submit two copies of any agreement with each property owner releasing the

Owner from responsibility in connection with the disposal of the debris.

1.4 QUALITY ASSURANCE

A. Conform to applicable code for environmental requirements, disposal of debris, burning debris on site, and use of herbicides.

B. Perform Work in accordance with Public Work's standard.

Herbert, Rowland & Grubic, Inc. 31 10 00 - 2 007297.0444

PART 2 - PRODUCTS

2.1 MATERIALS

A. Herbicide: broad-spectrum type, approved by authority having jurisdiction.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Section 01 73 00 - Execution Requirements: Verification of existing conditions before starting work.

B. Verify existing plant life designated to remain is tagged or identified.

3.2 PREPARATION

A. Call Local Utility Line Information service not less than three working days before performing Work.

1. Request underground utilities to be located and marked within and surrounding construction areas.

3.3 PROTECTION

A. Locate, identify, and protect utilities indicated to remain, from damage.

B. Protect trees, plant growth, and features designated to remain, as final landscaping.

C. Protect bench marks, survey control points, and existing structures from damage or displacement.

3.4 CLEARING

A. Clear areas required for access to site and execution of Work to minimum depth of 6 inches.

B. Remove trees and shrubs as indicated. Remove stumps, main root ball, and surface rock.

C. Clear undergrowth and deadwood, without disturbing subsoil.

D. Apply herbicide to remaining stumps to inhibit growth.

3.5 REMOVAL

A. Remove debris, rock, and extracted plant life from site.

B. Remove paving, curbs, and fencing as indicated on Work Order. Neatly saw cut edges at right angle to surface.

C. Remove abandoned utilities. Indicated removal termination point for underground

Herbert, Rowland & Grubic, Inc. 31 10 00 - 3 007297.0444 utilities on Record Documents.

D. Continuously clean-up and remove waste materials from site. Do not allow materials to accumulate on site.

E. Do not burn or bury materials on site. Leave site in clean condition.

3.6 TOPSOIL EXCAVATION

A. Excavate topsoil from areas to be further excavated, relandscaped, or regraded, without mixing with foreign materials for use in finish grading.

B. Do not excavate wet topsoil.

C. Stockpile in area designated on site to depth not exceeding 8 feet and protect from erosion.

D. Do not remove topsoil from site.

END OF SECTION