This is a technical specification document for aggregates used in earthwork operations for West Manchester Township's Maintenance & Emergency Contract (Excavation), Project No. 7297.0444, located in Pennsylvania. The specification outlines requirements for coarse and fine aggregate materials to be supplied for the project, which encompasses emergency and maintenance work on the township's sanitary sewer and storm sewer collection and conveyance systems. Coarse aggregate materials specified include PennDOT 2A, AASHTO No. 57, AASHTO No. 8, AASHTO No. 3, and Select Granular Material (2RC), all meeting PennDOT Publication 408 standards. Fine aggregate materials include Bituminous Concrete Sand Type B, Mortar Sand, Sieve Size #1, #3, and Filler Type C, with detailed gradation requirements specified across multiple sieve sizes. All aggregate materials must originate from PennDOT-approved sources and be furnished from a single source throughout the work. The sealed bid submission deadline is 10:00 AM local time on Wednesday, May 20, 2026, with bids to be received and publicly opened online through PennBID. No pre-bid conference is scheduled for this project.

Bid security in the form of a Certified Check or Bid Bond is required in an amount not less than 10% of the bid submission. All aggregate materials must be certified by manufacturers to meet or exceed specified requirements, with materials source documentation required as part of the submittal process. Stockpiling requirements mandate that materials be stored at locations directed by the township, with different aggregate types separated to prevent mixing and surface water directed away from stockpile sites to prevent erosion or deterioration. Upon project completion, all stockpiles must be removed and the site restored to a clean, neat condition with proper grading to prevent standing surface water. The specification references PennDOT standards, AASHTO guidelines, and ASTM International test methods to ensure material quality and compliance with established construction standards.

View the file

Other files

File Type Posted
32 92 19 - Seeding.pdf PDF
00 45 36 EEO Certificate.pdf PDF
01 22 00 - Unit Prices.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
00 01 01 - YO Cover.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
31 23 16 - Excavation.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
31 23 19 - Dewatering.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 01 10 - Table of Contents.pdf PDF
01 42 00 - References.pdf PDF
31 23 16.13 - Trenching.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
Sanitary and Storm Sewer Maintenance & Emergency Construction Details.pdf PDF
33 42 00 - Stormwater Conveyance.pdf PDF
31 10 00 - Site Clearing.pdf PDF
02 57 00 - Sinkhole Remediation.pdf PDF
33 31 11 - Public Sanitary Sewerage Gravity Piping.pdf PDF
33 05 05.43 - Mandrel Testing.pdf PDF
03 20 00 - Concrete Reinforcing.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
00 63 13 - RFI Form.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 52 00 - Agmnt btw Own and Cntr for Const Con Stip Price.pdf PDF
31 23 23 - Fill.pdf PDF
33 05 61 - Concrete Manholes and Inlets.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
03 30 00 - Cast-in-Place Concrete.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
32 17 23 - Pavement Markings.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
31 05 13 - Soils For Earthwork.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
02 41 13.23 - Utility Line Removal.pdf PDF
33 05 05.41 - Air Testing.pdf PDF
33 31 23 - Sanitary Sewerage Force Main Piping.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
00 31 43 - Permit Applications.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
32 11 23 - Aggregate Base Courses.pdf PDF
00 63 36 - Work Order Form.pdf PDF
Show 40 more

Latest 50 of 69 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

31 05 16 - AGGREGATES FOR EARTHWORK

Herbert, Rowland & Grubic, Inc. 31 05 16 - 1 007297.0444

SECTION 31 05 16 - AGGREGATES FOR EARTHWORK

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Coarse aggregate materials.

2. Fine aggregate materials.

B. Related Sections:

1. Section 31 05 13 - Soils for Earthwork: Fill and grading materials.

2. Section 31 23 16.13 - Trenching.

3. Section 31 23 23 - Fill.

4. Section 32 11 23 - Aggregate Base Courses.

5. Section 33 31 11 - Public Sanitary Sewerage Gravity Piping.

6. Section 33 31 23 - Sanitary Sewerage Force Main Piping.

7. Section 33 31 26 - Sanitary Pressure Sewer Piping.

8. Section 33 42 00 - Stormwater Conveyance.

1.2 REFERENCES

A. Pennsylvania Department of Transportation (PennDOT):

1. American Association Publication 19 – Field and Laboratory Test Methods, latest edition.

2. Publication 408 - Specifications, latest edition, as amended.

B. American Association of State Highway and Transportation Officials:

1. AASHTO M147 - Standard Specification for Materials for Aggregate and Soil-

Aggregate Subbase, Base and Surface Courses.

2. AASHTO T180 - Standard Specification for Moisture-Density Relations of Soils

Using a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop.

C. ASTM International:

1. ASTM C136 - Standard Test Method for Sieve Analysis of Fine and Coarse

Aggregates.

2. ASTM D698 - Standard Test Method for Laboratory Compaction Characteristics of

Soil Using Standard Effort (12,400 ft-lbf/ft3 (600 kN-m/m3).

3. ASTM D1557 - Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3 (2,700 kN-m/m3).

4. ASTM D2487 - Standard Classification of Soils for Engineering Purposes (Unified

Soil Classification System).

5. ASTM D4318 - Standard Test Method for Liquid Limit, Plastic Limit, and Plasticity

Index of Soils.

1.3 SUBMITTALS

A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.

Herbert, Rowland & Grubic, Inc. 31 05 16 - 2 007297.0444

B. Materials Source: Submit name of imported materials suppliers.

C. Manufacturer's Certificate: Certify Products meet or exceed specified requirements.

1.4 QUALITY ASSURANCE

A. Furnish each aggregate material from single source throughout the Work.

B. All aggregate must originate from a source approved by PennDOT meeting according to PennDOT standards.

PART 2 - PRODUCTS

2.1 COARSE AGGREGATE MATERIALS

A. PennDOT 2A: consisting of naturally or artificially graded mixture of natural or crushed gravel, crushed stone, or crushed slag meeting the requirements of PennDOT Publication 408, Section 703.2 for No. 2A, type C.

B. AASHTO No. 57: Open-graded, free-draining coarse aggregate meeting the requirements of PennDOT Publication 408, Section 703.2 for AASHTO No. 57.

C. AASHTO No. 8: Open-graded, free-draining coarse aggregate meeting the requirements of PennDOT Publication 408, Section 703.2 for AASHTO No. 8.

D. AASHTO No. 3: Open-graded, free-draining coarse aggregate meeting the requirements of PennDOT Publication 408, Section 703.2 for AASHTO No. 3.

E. Select Granular Material: Select Granular Material conforming to PennDOT Publication 408 Section 703.3 for 2RC.

2.2 FINE AGGREGATE MATERIALS

A. Fine Aggregates: Conforming to PennDOT’s standards as follows:

Bituminous Concrete Sand Type B

Mortar Sand

Sieve Size #1 #3 Filler Type C

3/8 inch 100 100 -- --

No. 4 95-100 80-100 -- 100

No. 8 70-100 65-100 -- 95-100

No. 16 40-80 40-80 -- --

No. 30 20-65 20-65 100 --

No. 50 7-40 7-40 95-100 --

No. 100 2-20 2-20 90-100 0-25

No. 200 0-10 0-10 70-100 0-10

Herbert, Rowland & Grubic, Inc. 31 05 16 - 3 007297.0444

PART 3 - EXECUTION

3.1 STOCKPILING

A. Stockpile materials on site at locations as directed.

B. Stockpile in sufficient quantities to meet Project schedule and requirements.

C. Separate different aggregate materials with dividers or stockpile individually to prevent mixing.

D. Direct surface water away from stockpile site to prevent erosion or deterioration of materials.

3.2 STOCKPILE CLEANUP

A. Remove stockpile, leave area in clean and neat condition. Grade site surface to prevent free standing surface water.

B. When borrow area is indicated, leave area in clean and neat condition. Grade site surface to prevent free standing surface water.

END OF SECTION