This is a Warranties specification document (Section 01 78 36) prepared by Herbert, Rowland & Grubic, Inc. for West Manchester Township's Contract 2026-01: Maintenance & Emergency Contract (Excavation) – Project No. 7297.0444 in Pennsylvania. The document establishes comprehensive warranty requirements for all products and work performed under the contract. Warranty documentation must be submitted to the Owner and Engineer within 10 days following the Date of Substantial Completion or Partial Utilization, with individual item warranties due within 10 days of acceptance. The specification requires both standard product warranties from manufacturers and special warranties as needed, with all warranties written in the Owner's name and becoming valid upon issuance of the Certificate of Substantial Completion. For work delayed beyond substantial completion, contractors must provide updated schedules within 10 days of acceptance, with the acceptance date marking the warranty start.

The warranty requirements impose significant obligations on the Contractor, who remains responsible for all warranted work regardless of manufacturer disclaimers or limitations. Upon failure of warranted work, the Contractor must remove, replace, or rebuild defective components and restore any damaged work, bearing all replacement and remediation costs without regard to the Owner's prior use or benefit from the work. Warranties must be reinstated through written endorsement when work covered by warranty fails, with reinstated warranties equal to original terms adjusted equitably for depreciation. The specification explicitly states that written warranties supplement rather than limit implied warranties or the Owner's legal remedies, ensuring comprehensive protection for the township's sanitary sewer and storm sewer infrastructure improvements and maintenance work.

View the file

Other files

File Type Posted
32 92 19 - Seeding.pdf PDF
31 05 16 - Aggregates For Earthwork.pdf PDF
00 45 36 EEO Certificate.pdf PDF
01 22 00 - Unit Prices.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
00 01 01 - YO Cover.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
31 23 16 - Excavation.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
31 23 19 - Dewatering.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 01 10 - Table of Contents.pdf PDF
01 42 00 - References.pdf PDF
31 23 16.13 - Trenching.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
Sanitary and Storm Sewer Maintenance & Emergency Construction Details.pdf PDF
33 42 00 - Stormwater Conveyance.pdf PDF
31 10 00 - Site Clearing.pdf PDF
02 57 00 - Sinkhole Remediation.pdf PDF
33 31 11 - Public Sanitary Sewerage Gravity Piping.pdf PDF
33 05 05.43 - Mandrel Testing.pdf PDF
03 20 00 - Concrete Reinforcing.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
00 63 13 - RFI Form.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 52 00 - Agmnt btw Own and Cntr for Const Con Stip Price.pdf PDF
31 23 23 - Fill.pdf PDF
33 05 61 - Concrete Manholes and Inlets.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
03 30 00 - Cast-in-Place Concrete.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
32 17 23 - Pavement Markings.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
31 05 13 - Soils For Earthwork.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
02 41 13.23 - Utility Line Removal.pdf PDF
33 05 05.41 - Air Testing.pdf PDF
33 31 23 - Sanitary Sewerage Force Main Piping.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
00 31 43 - Permit Applications.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
32 11 23 - Aggregate Base Courses.pdf PDF
Show 40 more

Latest 50 of 69 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 78 36 – WARRANTIES

Herbert, Rowland & Grubic, Inc. 01 78 36 - 1 007297.0444

SECTION 01 78 36 – WARRANTIES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Product warranty manuals.

2. Warranty requirements.

B. Related Sections:

1. Individual Sections for specific requirements for Project Record Documents of the

Work in those Sections.

1.2 PRODUCT WARRANTIES

A. Warranties specified in individual Sections shall be in addition to, and run concurrent with, other warranties required by the Contract Documents. Manufacturer's disclaimers and limitations on product warranties do not relieve Contractor of obligations under requirements of the Contract Documents. Warranties shall be written in Owner’s name:

1. Standard Product Warranties are preprinted written warranties published by individual manufacturers for particular products and are specifically endorsed by the manufacturer to Owner.

2. Special Warranties are written warranties required by or incorporated into Contract Documents, either to extend time limits provided by standard warranties or to provide greater rights for Owner.

B. Submission requirements:

1. Submit documents to Owner and Engineer within 10 days following Date of

Substantial Completion or Partial Utilization. For item accepted after Date of Substantial Completion, submit documents within 10 days following each individual acceptance:

a. When special warranty is required to be executed by Contractor, or

Contractor and a subcontractor, supplier or manufacturer, prepare a written document that contains appropriate terms and identification, ready for execution by required parties. Submit a draft to Owner.

2. Submit information electronically on Owner and Engineer.

1.3 WARRANTY REQUIREMENTS

A. Written warranties made to Owner are in addition to implied warranties and shall not limit duties, obligations, right and remedies otherwise available under Jaw, nor shall warranty periods be interpreted as limitations on time in which Owner can enforce such other duties, obligations, rights, or remedies.

B. Manufacturer's disclaimers and limitations on product warranties shall not relieve Contractor of warranty on Work that incorporates products, nor shall it relieve suppliers, manufacturers, and subcontractors required to countersign special warranties with Contractor.

01 78 36 – WARRANTIES

Herbert, Rowland & Grubic, Inc. 01 78 36 - 2 007297.0444

C. Special Warranties: Prepare a written document that contains appropriate terms and identification, ready for execution. Submit a draft for approval before final execution:

1. Manufacturer's Standard Form: Modified to include Project-specific information and properly executed.

2. Specified Form: When specified forms are included with the Specifications, prepare a written document using appropriate form properly executed.

3. Refer to Sections for specific content requirements and particular requirements for submitting special warranties.

D. Warranties shall become valid and operative upon issuance of Certificate of Substantial Completion.

E. For items of Work delayed beyond Date of Substantial Completion, provide an updated schedule within 10 days after acceptance, listing date of acceptance as start of warranty.

F. Related Damages and Losses: When correcting warranted Work that has failed, remove and replace other Work that has been damaged as a result of such failure or that needs to be removed and replaced to provide access for correction of warranted Work.

G. Reinstatement of Warranty: In event of Work covered by warranty has failed, correct by replacement or rebuilding. Reinstate warranty by written endorsement. Reinstated warranty shall be equal to original warranty with an equitable adjustment for depreciation.

H. Replacement Cost:

1. Upon determining that Work covered by a warranty has failed replace or rebuild

Work to an acceptable condition in compliance with requirements of Contract Documents.

2. Contractor shall be responsible for cost of replacing or rebuilding defective Work regardless of whether Owner has benefited from use of Work through a portion of its anticipated useful service life.

PART 2 - PRODUCTS - Not Used.

PART 3 - EXECUTION - Not Used.

END OF SECTION