CN-370000-HW683-DC05BCO1.pdf

PDF 3 MB Posted

Attached to
Master Agreement FL|HW683|90e8124b5a65e607dedb86d39c72016e
Contract number
HW683
Issued by
Florida

View the file

Other files

File Type Posted
CN-370000-HW683-BF01A.pdf PDF
CN-370000-HW683-BF01B.pdf PDF
CN-370000-HW683-BF02A.pdf PDF
CN-370000-HW683-BF02ACO2.pdf PDF
CN-370000-HW683-BF04A.pdf PDF
CN-370000-HW683-BF04BCO1.pdf PDF
CN-370000-HW683-BF2BCO1.pdf PDF
CN-370000-HW683-BIL01A.pdf PDF
CN-370000-HW683-CSS02.pdf PDF
CN-370000-HW683-CSS02A.pdf PDF
CN-370000-HW683-DC002F.pdf PDF
CN-370000-HW683-DC004B.pdf PDF
CN-370000-HW683-DC004E.pdf PDF
CN-370000-HW683-DC005D.pdf PDF
CN-370000-HW683-DC005E.pdf PDF
CN-370000-HW683-DC007A.pdf PDF
CN-370000-HW683-DC007B.pdf PDF
CN-370000-HW683-DC008A.pdf PDF
CN-370000-HW683-DC008B.pdf PDF
CN-370000-HW683-DC008D.pdf PDF
CN-370000-HW683-DC009A.pdf PDF
CN-370000-HW683-DC009B.pdf PDF
CN-370000-HW683-DC009G.pdf PDF
CN-370000-HW683-DC010C.pdf PDF
CN-370000-HW683-DC011B.pdf PDF
CN-370000-HW683-DC011C.pdf PDF
CN-370000-HW683-DC011D.pdf PDF
CN-370000-HW683-DC012B.pdf PDF
CN-370000-HW683-DC016B.pdf PDF
CN-370000-HW683-DC017A.pdf PDF
CN-370000-HW683-DC018B.pdf PDF
CN-370000-HW683-DC019A.pdf PDF
CN-370000-HW683-DC019B.pdf PDF
CN-370000-HW683-DC019C.pdf PDF
CN-370000-HW683-DC019D.pdf PDF
CN-370000-HW683-DC01ACO1.pdf PDF
CN-370000-HW683-DC025B.pdf PDF
CN-370000-HW683-DC026B.pdf PDF
CN-370000-HW683-DC029A.pdf PDF
CN-370000-HW683-DC029E.pdf PDF
CN-370000-HW683-DC02ACO1.pdf PDF
CN-370000-HW683-DC02E.pdf PDF
CN-370000-HW683-DC031C.pdf PDF
CN-370000-HW683-DC032A.pdf PDF
CN-370000-HW683-DC032C.pdf PDF
CN-370000-HW683-DC035A.pdf PDF
CN-370000-HW683-DC036B.pdf PDF
CN-370000-HW683-DC037B.pdf PDF
CN-370000-HW683-DC038A.pdf PDF
CN-370000-HW683-DC039A.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number) Project Name:

4. ☐ There are no changes to the TA compensation.

☐ The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO ☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. ☐ There are no changes to the TA Expiration Date.

☐ The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. ☐ There are no changes to the Attachments.

☐ Attachment ___ is replaced with Attachment -____.

7. ☐ No Additional Changes.

☐ Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

DC005B 1 HW683

This Task Assignment Change Order reconciles labor associated with ADaPT deliverable data tables.

Evan Miller 850-245-8928 Contractor Contractor

Contractor Contractor

Contractor

Geosyntec James Mills 813-379-4389

ERIC_4783

Walker Plaza

✔ $ 17,872.57 $ 19,182.77

$ 17,872.57 $ 19,182.77 ✔ Completion

Completion 0

✔ 1 1 1

Geosyntec Consultants

Todd Kafka

Contract Manager

Todd Kafka, P.G. Digitally signed by Todd Kafka, P.G.

Date: 2022.07.11 17:53:49 -04'00'

William E. Burns, Jr.

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2022.07.11 15:36:48 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 01_18

Contract Number:

Task Assignment #:

Change Order #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

HW683

DC005B

$ 17,872.57

Subtask 2- Submittal of Q2 field deliverable, ADaPT files, and GIS data tables

Subtask 3- Submittal of Q3 field deliverable, ADaPT files, and GIS data tables

Subtask 4- Submittal of Q4 field deliverable, ADaPT files, and GIS data tables

Subtask 5- Submittal of PARM Report

Subtask 1,6- Submittal of Final IDW manifest; Project Management

Subtask 2- FDEP receipt and approval of Q2 field deliverable, ADaPT files, and GIS data tables

Subtask 4- FDEP receipt and approval of Q4 field deliverable, ADaPT files, and GIS data tables

Subtask 5- FDEP receipt and approval of PARM Report

Subtask 1,6- FDEP receipt and approval of Final IDW manifest; Project Management

Subtask 3- FDEP receipt and approval of Q3 field deliverable, ADaPT files, and GIS data tables

09/30/2022

12/30/2022

03/31/2023

04/28/2023

05/26/2023

$ 4,241.69

$ 4,241.69

$ 4,311.70

$ 3,218.68

$ 1,858.81

Printed on recycled paper.

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Secretary

To: HW683 Contract Negotiation File Walker Plaza

Plant City, Hillsborough County

ERIC_4783

From: Evan Miller, Project Manager Date: July 11, 2022 Subject: Negotiation Summary

HW683 DC005B-1

This Task Assignment Change Order reconciles labor associated with ADaPT deliverable data tables. Per email guidance from the FDEP on 1 July 2022, ADaPT data tables/files should not be submitted for review.

Subtask 1: Project Management An automatic calculation based upon total direct labor hours determines the labor hours within this subtask.

Subtask 2 – Quarter 2 PARM Sampling (June – August 2022) TACO-1 removes labor associated with submitting ADaPT data/tables to the FTP site for review.

TACO-1 includes effort to use ADaPT to QA/QC all analytical data and perform required data checks/review to satisfy QA/QC requirements.

Subtask 3 – Quarter 3 PARM Sampling (September – November 2022) TACO-1 removes labor associated with submitting ADaPT data/tables to the FTP site for review.

TACO-1 includes effort to use ADaPT to QA/QC all analytical data and perform required data checks/review to satisfy QA/QC requirements.

Subtask 4 – Quarter 4 PARM Sampling (December 2022 – February 2023) TACO-1 removes labor associated with submitting ADaPT data/tables to the FTP site for review.

TACO-1 includes effort to use ADaPT to QA/QC all analytical data and perform required data checks/review to satisfy QA/QC requirements.

Subtask 5 – PARM Report No Change

Subtask 6 - IDW Management No Change

The cost decrease related to this change order is $1,310.20.

Negotiation Summary Walker Plaza July 11, 2022 Page Two

The FDEP project manager agrees to the scope of work and final cost associated with this Task Assignment Change Order. The final cost for this Task Assignment Change Order is $17,872.57with 126 labor hours.

Geosyntec may invoice following the schedule established in the Deliverables and Invoice Schedule Attachment, which accompanies the Task Assignment Change Order Notification Form.

FDEP COST ESTIMATEContractor: Geosyntec Consultants

Date: 7/5/2022

Task #: DC005B SubTask 1 Project Management SubTask 6 IDW Management

Site: Walker Plaza SubTask 2 PARM Sampling (Jun - Aug 22) SubTask 7

Activity/Phase: PARM Sampling SubTask 3 PARM Sampling (Sept - Nov 22) SubTask 8

Project Manager: James Mills SubTask 4 PARM Sampling (Dec 22 - Feb 23) SubTask 9

SubTask 5 PARM Report SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$39.42 Project Manager J. Mills 13 12.7 $68.75 Principal T. Kafka 2 0 0 0 2 0 0 0 0 0 $46.15 Project Professional M. Hensley 6 0 0 0 6 0 0 0 0 0 $39.42 Professional J. Mills 35 6 6 6 16 1 0 0 0 0 $32.21 Senior Staff Professional A. Langteau 3 1 1 1 0 0 0 0 0 0 $29.33 Staff Professional A. Lamore 66 22 22 22 0 0 0 0 0 0 $27.88 Administrative Assistant A. Acosta 1 0 0 0 1 0 0 0 0 0

Total Hours 126 13 29 29 29 25 1 0 0 0 0

Direct Labor $4,355.46 $501.07 $913.99 $913.99 $913.99 $1,073.00 $39.42 $0.00 $0.00 $0.00 $0.00

Overhead 172.70% $7,521.88 $865.35 $1,578.46 $1,578.46 $1,578.46 $1,853.07 $68.08 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $11,877.34 $1,366.42 $2,492.45 $2,492.45 $2,492.45 $2,926.07 $107.50 $0.00 $0.00 $0.00 $0.00

Travel Vehicle Rental $720.00 $240.00 $240.00 $240.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $720.00 $240.00 $240.00 $240.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $125.00 $0.00 $0.00 $0.00 $0.00 $125.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $125.00 $0.00 $0.00 $0.00 $0.00 $125.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $12.50 $0.00 $0.00 $0.00 $0.00 $12.50 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $137.50 $0.00 $0.00 $0.00 $0.00 $137.50 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $1,540.00 $490.00 $490.00 $560.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $330.00 $110.00 $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $1,870.00 $600.00 $600.00 $670.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $240.00 $80.00 $80.00 $80.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $1,740.00 $580.00 $580.00 $580.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $100.00 $0.00 $0.00 $0.00 $0.00 $100.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $2,080.00 $660.00 $660.00 $660.00 $0.00 $100.00 $0.00 $0.00 $0.00 $0.00

Subtotal $16,684.84 $1,366.42 $3,992.45 $3,992.45 $4,062.45 $2,926.07 $345.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $1,187.75 $136.64 $249.25 $249.25 $249.25 $292.61 $10.75 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $17,872.57 $1,503.07 $4,241.69 $4,241.69 $4,311.69 $3,218.68 $355.75 $0.00 $0.00 $0.00 $0.00

Original $19,182.77 $1,653.80 $4,628.18 $4,628.18 $4,698.18 $3,218.68 $355.75 Delta #1 ($1,310.20) ($150.73) ($386.49) ($386.49) ($386.49) $0.00 $0.00

Rounding error $0.00 Total $17,872.57 $1,503.07 $4,241.69 $4,241.69 $4,311.69 $3,218.68 $355.75

ST 1 & 6 $1,858.82

REV: 02/03 CEF ARCADIS Page 1

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Walker Plaza SUBTASK: PARM Sampling (Jun - Aug 22)

DATE: 7/5/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Professional J. Mills 6

Senior Staff Professional A. Langteau 1.0

Staff Professional A. Lamore

TOTAL LABOR 29

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 Day 2 $240.00 Subtotal $240.00

TOTAL VEHICLE $240.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOCs 7 wells $70.00 7 $490.00

Subtotal $490.00 Shipping

Small Cooler (0 to 25 lbs) $110.00 1 $110.00 Subtotal $110.00

TOTAL LAB $600.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Analytical Related

Groundwater Sampling Kit $290.00 Day 2 $580.00 Subtotal $580.00

Expendables $40.00 Day 2 $80.00

Subtotal $80.00

TOTAL EQUIPMENT $660.00

RPO coordination and logistics to access interior wells (2 hr); Update data tables and prepare field package (4 hr)

TACO-1 - ADaPT QA/QC of analytical data (0.5 hr)

Field preparation (2 hr); mobe/demob (2 d @ 2hr/d = 4 hr); collect 12 water levels from MWs not sampled (2 hr); sample 7 monitoring wells (7 @ 1.5 hr/well = 11 hr); equipment calibration (2 d @ 0.5 hr/d = 1 hr); IDW management (1 hr); sample management (1 hr)

FINAL --7/24/96

SUBTASK: PARM Sampling (Sept - Nov 22)

DATE: 7/5/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Professional J. Mills 6

Senior Staff Professional A. Langteau 1

Staff Professional A. Lamore

TOTAL LABOR 29

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 Day 2 $240.00 Subtotal $240.00

TOTAL VEHICLE $240.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOCs 7 wells $70.00 7 $490.00

Subtotal $490.00 Shipping

Small Cooler (0 to 25 lbs) $110.00 1 $110.00 Subtotal $110.00

TOTAL LAB $600.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Analytical Related

Groundwater Sampling Kit $290.00 Day 2 $580.00 Subtotal $580.00

Expendables $40.00 Day 2 $80.00

Subtotal $80.00

TOTAL EQUIPMENT $660.00

RPO coordination and logistics to access interior wells (2 hr); Update data tables and prepare field package (4 hr)

TACO-1 - ADaPT QA/QC of analytical data (0.5 hr)

Field preparation (2 hr); mobe/demob (2 d @ 2hr/d = 4 hr); collect 12 water levels from MWs not sampled (2 hr); sample 7 monitoring wells (7 @ 1.5 hr/well = 11 hr); equipment calibration (2 d @ 0.5 hr/d = 1 hr); IDW management (1 hr); sample management (1 hr)

SUBTASK: PARM Sampling (Dec 22 - Feb 23)

DATE: 7/5/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Professional J. Mills 6

Senior Staff Professional A. Langteau 1

Staff Professional A. Lamore

TOTAL LABOR 29

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 Day 2 $240.00 Subtotal $240.00

TOTAL VEHICLE $240.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOCs 7 wells, 1 IDW $70.00 8 $560.00

Subtotal $560.00 Shipping

Small Cooler (0 to 25 lbs) $110.00 1 $110.00 Subtotal $110.00

TOTAL LAB $670.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Analytical Related

Groundwater Sampling Kit $290.00 Day 2 $580.00 Subtotal $580.00

Expendables $40.00 Day 2 $80.00

Subtotal $80.00

TOTAL EQUIPMENT $660.00

RPO coordination and logistics to access interior wells (2 hr); Update data tables and prepare field package (4 hr)

TACO-1 - ADaPT QA/QC of analytical data (0.5 hr)

Field preparation (2 hr); mobe/demob (2 d @ 2hr/d = 4 hr); collect 12 water levels from MWs not sampled (2 hr); sample 7 monitoring wells (7 @ 1.5 hr/well = 11 hr); equipment calibration (2 d @ 0.5 hr/d = 1 hr); IDW management (1 hr); sample management (1 hr)

SUBTASK: PARM Report

DATE: 7/5/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Principal T. Kafka 2

Project Professional M. Hensley 6

Professional J. Mills 16

Administrative Assistant A. Acosta 1

TOTAL LABOR 25

Report assembly and PDF compilation (1 hr)

Data evaluation/interpretation and PG certification on report (2 hr)

Prepare 6 report figures (6 hr)

Prepare annual groundwater monitoring report (16 hr)

SUBTASK: IDW Management

DATE: 7/5/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Professional J. Mills 1

TOTAL LABOR 1

SUBCONTRACTOR COSTS

NAME PURPOSE COST

IDW

T&D - UES 1 drum $125.00 $125.00

Subtotal $125.00

TOTAL SUB $125.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

IDW Related

Drum $100.00 Each 1 $100.00 Subtotal $100.00

TOTAL EQUIPMENT $100.00

Prepare IDW manifest (1 hr)

FDEP COST ESTI MATEContractor: Geosyntec Consultants

Date: 7/5/2022

Task #: DC005B SubTask 1 Project Management SubTask 6 IDW Management

Site: Walker Plaza SubTask 2 PARM Sampling (Jun - Aug 22) SubTask 7

Activity/Phase: PARM Sampling SubTask 3 PARM Sampling (Sept - Nov 22) SubTask 8

Project Manager: James Mills SubTask 4 PARM Sampling (Dec 22 - Feb 23) SubTask 9

SubTask 5 PARM Report SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$39.42 Project Manager J. Mills -1 -1.3 $68.75 Principal T. Kafka 0 0 0 0 0 0 0 0 0 0 $46.15 Project Professional M. Hensley 0 0 0 0 0 0 0 0 0 0 $39.42 Professional J. Mills 0 0 0 0 0 0 0 0 0 0 $32.21 Senior Staff Professional A. Langteau -12 -4 -4 -4 0 0 0 0 0 0 $29.33 Staff Professional A. Lamore 0 0 0 0 0 0 0 0 0 0 $27.88 Administrative Assistant A. Acosta 0 0 0 0 0 0 0 0 0 0

Total Hours -13 -1 -4 -4 -4 0 0 0 0 0 0

Direct Labor ($436.77) ($50.25) ($128.84) ($128.84) ($128.84) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 172.70% ($754.31) ($86.78) ($222.51) ($222.51) ($222.51) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor ($1,191.08) ($137.03) ($351.35) ($351.35) ($351.35) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Travel Vehicle Rental $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal ($1,191.08) ($137.03) ($351.35) ($351.35) ($351.35) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee ($119.12) ($13.70) ($35.14) ($35.14) ($35.14) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost ($1,310.20) ($150.73) ($386.49) ($386.49) ($386.49) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

ST 1 & 6 ($150.73)

SUBTASK: PARM Sampling (Jun - Aug 22)

DATE: 7/5/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Staff Professional A. Langteau

-4

TOTAL LABOR -4

TACO-1 - subtract [ADaPT & GIS table updates (19 water levels, 8 samples = 27 data points @ 8 min/point = ~4 hr); GIS data table checker and submittal (1 hr)] ADaPT QA/QC of analytical data (0.5 hr)

SUBTASK: PARM Sampling (Sept - Nov 22)

DATE: 7/5/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Staff Professional A. Langteau

-4

TOTAL LABOR -4

TACO-1 - subtract [ADaPT & GIS table updates (19 water levels, 8 samples = 27 data points @ 8 min/point = ~4 hr); GIS data table checker and submittal (1 hr)] ADaPT QA/QC of analytical data (0.5 hr)

SUBTASK: PARM Sampling (Dec 22 - Feb 23)

DATE: 7/5/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Staff Professional A. Langteau

-4

TOTAL LABOR -4

TACO-1 - subtract [ADaPT & GIS table updates (19 water levels, 8 samples = 27 data points @ 8 min/point = ~4 hr); GIS data table checker and submittal (1 hr)] ADaPT QA/QC of analytical data (0.5 hr)

FDEP COST ESTIMATEContractor: Geosyntec Consultants

Date: 5/31/2022

Task #: DC005B SubTask 1 Project Management SubTask 6 IDW Management

Site: Walker Plaza SubTask 2 PARM Sampling (Jun - Aug 22) SubTask 7

Activity/Phase: PARM Sampling SubTask 3 PARM Sampling (Sept - Nov 22) SubTask 8

Project Manager: James Mills SubTask 4 PARM Sampling (Dec 22 - Feb 23) SubTask 9

SubTask 5 PARM Report SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$39.42 Project Manager J. Mills 14 14.0 $68.75 Principal T. Kafka 2 0 0 0 2 0 0 0 0 0 $46.15 Project Professional M. Hensley 6 0 0 0 6 0 0 0 0 0 $39.42 Professional J. Mills 35 6 6 6 16 1 0 0 0 0 $32.21 Senior Staff Professional A. Langteau 15 5 5 5 0 0 0 0 0 0 $29.33 Staff Professional A. Lamore 66 22 22 22 0 0 0 0 0 0 $27.88 Administrative Assistant A. Acosta 1 0 0 0 1 0 0 0 0 0

Total Hours 139 14 33 33 33 25 1 0 0 0 0

Direct Labor $4,792.23 $551.32 $1,042.83 $1,042.83 $1,042.83 $1,073.00 $39.42 $0.00 $0.00 $0.00 $0.00

Overhead 172.70% $8,276.19 $952.13 $1,800.97 $1,800.97 $1,800.97 $1,853.07 $68.08 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $13,068.42 $1,503.45 $2,843.80 $2,843.80 $2,843.80 $2,926.07 $107.50 $0.00 $0.00 $0.00 $0.00

Travel Vehicle Rental $720.00 $240.00 $240.00 $240.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $720.00 $240.00 $240.00 $240.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $125.00 $0.00 $0.00 $0.00 $0.00 $125.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $125.00 $0.00 $0.00 $0.00 $0.00 $125.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $12.50 $0.00 $0.00 $0.00 $0.00 $12.50 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $137.50 $0.00 $0.00 $0.00 $0.00 $137.50 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $1,540.00 $490.00 $490.00 $560.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $330.00 $110.00 $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $1,870.00 $600.00 $600.00 $670.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $240.00 $80.00 $80.00 $80.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $1,740.00 $580.00 $580.00 $580.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $100.00 $0.00 $0.00 $0.00 $0.00 $100.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $2,080.00 $660.00 $660.00 $660.00 $0.00 $100.00 $0.00 $0.00 $0.00 $0.00

Subtotal $17,875.92 $1,503.45 $4,343.80 $4,343.80 $4,413.80 $2,926.07 $345.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $1,306.85 $150.35 $284.38 $284.38 $284.38 $292.61 $10.75 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $19,182.77 $1,653.80 $4,628.18 $4,628.18 $4,698.18 $3,218.68 $355.75 $0.00 $0.00 $0.00 $0.00

ST 1 & 6 $2,009.55

Funding Information:

Org. Code E.O.

Object Code

Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department

Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature)

Date:

Additional signatures attached on separate page.

HW683

DC005B August 26, 2023

This Task Assignment authorizes Geosyntec to conduct post active remediation monitoring (PARM) at the Walker Plaza site in accordance with the Geosyntec scope of work, cost estimate, and schedule received on 31 May 2022.

Evan Miller 850-245-8928 Geosyntec

James Mills 813-379-4389

ERIC_4783

603 – 617 North Maryland Avenue Plant City, Florida

Walker Plaza

$ 19,182.77

$ 19,182.77

Scope of Work

Geosyntec

Todd Kafka

Contract Manager

Todd Kafka, P.G. Digitally signed by Todd Kafka, P.G.

Date: 2022.06.01 09:36:45 -04'00'

William E. Burns, Jr.

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2022.06.01 07:27:18 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WC TAFORM

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

12802 Tampa Oaks Blvd, Suite 151 Tampa, Florida 33637

PH 813.558.0990

FAX 813.558.9726

www.geosyntec.com

FR8633/Walker Plaza (ERIC_4783)_SOW_PARM Sampling_TACO-1_July 2022

31 May 2022 (Revised 8 July 2022)

Mr. Evan Miller Florida Department of Environmental Protection Waste Cleanup Program 2600 Blair Stone Road Tallahassee, FL 32399-2400

Subject: SOW/LOE – Post Active Remediation Monitoring – TACO 1 Walker Plaza (ERIC_4783) 603 – 617 North Maryland Avenue Plant City, Florida

Dear Mr. Miller:

Geosyntec Consultants, Inc. (Geosyntec) has prepared the following scope of work (SOW) and proposed level of effort (LOE) to perform post active remediation monitoring (PARM) at the Walker Plaza site (herein, the “Site”) located in Plant City, Florida. The objective of this SOW is to collect three quarters of groundwater samples from seven existing monitoring wells to evaluate the effectiveness of soil vapor extraction (SVE) remediation activities conducted on-Site pursuant to Chapter 62-780.750, Florida Administrative Code on groundwater concentrations of volatile organic halocarbons (VOHs). Based on comments from the Florida Department of Environmental Protection (FDEP) memorandum, dated 20 April 2022 and addressing the Annual Groundwater Monitoring Report, it is assumed that the groundwater sampling event conducted in March 2022 will serve as the first of four quarters (i.e., Quarter 1) of PARM.

Task Assignment Change Order 1 (TACO 1) reconciles labor associated with ADaPT deliverable data tables. Per email guidance from the FDEP on 1 July 2022, ADaPT data tables/files should not be submitted for review. Revisions to the original scope of work are provided in red font.

SOW ELEMENTS

Geosyntec will collect three quarters (groundwater sampling event from March 2022 will serve as Quarter 1) of groundwater samples from two on-Site monitoring wells (i.e., MW002 and MW006) and five off-Site monitoring wells (i.e., MW010 to MW012, MW013, and MW016). The rationale for the locations (see Figure 2 and Figure 3) is as follows:

Mr. Evan Miller 31 May 2022 (Revised 8 July 2022)

FR2711/Walker Plaza (ERIC_4783)_SOW_PARM Sampling_TACO-1_July 2022

MW002 (2.8-12.8 ft) Source area on-Site, PCE above GCTL MW012 (65-75 ft) cDCE detection, off-Site

MW006 (0.7-10.7ft) Source area on-Site, historical PCE impacts MW013 (3-13 ft) No VOH impacts, off-Site downgradient property line

MW010 (3-13 ft) PCE above GCTL, off-Site MW016 (3-13 ft) TCE above GCTL, off-Site downgradient property line

MW011 (27-32 ft) PCE and TCE above GCTLs, off-Site

Notes: PCE indicates tetrachloroethene; TCE indicates trichloroethene; cDCE indicates cis-1,2-dichloroethene;

GCTL indicates Groundwater Cleanup Target Level.

Prior to each quarterly groundwater sampling event, Geosyntec will gauge and record the depth-to-water (DTW) from 19 monitoring wells (this excludes MW008, MW009D, and UMW001) within a 24-hour period, including from 12 wells that are not anticipated to be sampled on the first day of field activities. Geosyntec will collect a total of 7 groundwater samples per quarterly event (28 samples total) using a peristaltic pump. Field activities will be conducted in accordance with the FDEP Standard Operating Procedures. Groundwater samples will be submitted under chain of custody protocol for laboratory analysis of VOHs by Environmental Protection Agency Method 8260B.

Action levels for the wells listed above will be as follows:

• The FDEP Groundwater Cleanup Target Level (GCTL) for tetrachloroethene (PCE) or 3 micrograms per liter (µg/L), where current PCE concentrations are less than its GCTL (i.e., MW006, MW012, MW013, and MW016)

• The FDEP GCTL for trichloroethene (TCE) or 3 µg/L, where TCE concentrations are less than its GCTL (i.e., MW002, MW006, MW010, MW012, and MW013).

• The FDEP Natural Attenuation Default Concentration (NADC) for PCE or 300 µg/L, where current PCE concentrations are greater than its GCTL but less than its NADC (i.e., MW002, MW010, and MW011)

• The FDEP NADC for TCE or 300 µg/L, where current TCE concentrations are greater than its GCTL but less than its NADC (i.e., MW016).

• The TCE action level at MW011 will be 1.5 times the 95% upper confidence level for historical TCE results (742 µg/L) at MW011 or 1,113 µg/L.

If analyses of groundwater samples indicate that concentrations of PCE or TCE exceed the action levels above, then a change order will be submitted and the well or wells exceeding the action levels will be resampled no later than 30 days after receipt of the analytical results for the corresponding quarter.

Based on previous sampling events, it is estimated that purge water generated during sampling activities will be containerized in one, 55-gallon drum. Geosyntec will collect one sample for VOHs during the last quarterly sampling event to update the waste characterization analytical results for disposal (see Subtask 6).

LOE SUBTASKS

Subtask 1 – Project Management

James Mills will serve as the Project Manager for the proposed SOW. Costs associated with this subtask are directly computed.

Subtask 2 – Quarter 2 PARM Sampling (June – August 2022)

Geosyntec will conduct one quarterly groundwater sampling event as outlined above, prepare and update the FDEP GIS Data Tables/ADaPT files electronically, and submit one field deliverable to the FDEP with groundwater sampling forms, laboratory analytical results, updated groundwater analytical results and DTW tables, and a Site Map figure. TACO-1 removes labor associated with submitting ADaPT data/tables to the FTP site for review. TACO-1 includes effort to use ADaPT to QA/QC all analytical data and perform required data checks/review to satisfy QA/QC requirements.

Subtask 3 – Quarter 3 PARM Sampling (September – November 2022)

Geosyntec will conduct one quarterly groundwater sampling event as outlined above, prepare and update the FDEP GIS Data Tables/ADaPT files electronically, and submit one field deliverable to the FDEP with groundwater sampling forms, laboratory analytical results, updated groundwater analytical results and DTW tables, and a Site Map figure. TACO-1 removes labor associated with submitting ADaPT data/tables to the FTP site for review. TACO-1 includes effort to use ADaPT to QA/QC all analytical data and perform required data checks/review to satisfy QA/QC requirements.

Subtask 4 – Quarter 4 PARM Sampling (December 2022 – February 2023)

Geosyntec will conduct one quarterly groundwater sampling event as outlined above, collect one IDW sample, prepare and update the FDEP GIS Data Tables/ADaPT files electronically, and submit one field deliverable to the FDEP with groundwater sampling forms, laboratory analytical results, updated groundwater analytical results and DTW tables, and a Site Map figure. TACO-1 removes labor associated with submitting ADaPT data/tables to the FTP site for review. TACO- 1 includes effort to use ADaPT to QA/QC all analytical data and perform required data checks/review to satisfy QA/QC requirements.

Subtask 5 – PARM Report

Approximately 60 days after receipt of the final quarter (i.e., Quarter 4) of groundwater analytical results, Geosyntec will submit one PARM Report that will be signed and sealed by a licensed Florida engineer or geologist and include analytical results, field forms, and updated tables and figures summarizing the four quarterly sampling events. The field forms will consist of groundwater sampling, calibration, DTW, and drum logs generated during quarterly sampling activities. The tables will include (i) DTW measurements, (ii) groundwater analytical results for VOHs, and (iii) geochemical field parameters. The figures will include (i) Site location Plan, (ii) Site map, (iii) groundwater elevation contours in the surficial aquifer, (iv) groundwater elevation contours in the intermediate aquifer, (v) groundwater analytical results in the surficial aquifer, and

(vi) groundwater analytical results in the intermediate aquifer.

Subtask 6 - IDW Management

This subtask includes generation and management of groundwater investigation-derived waste (IDW), which is estimated to include one drum. IDW will be staged inside the gated enclosure containing the SVE skid at the Site. Universal Environmental Solutions, LLC. is the lowest cost provider of transportation and disposal services per drum. Geosyntec will review the generation of a waste characterization profile as well as prepare the IDW manifest. IDW transportation and disposal quotes are provided in Attachment A. Field oversight of the final IDW pickup is not required.

Invoice and Deliverable Schedule

Please note the following schedule is contingent on FDEP review and approval of this SOW/LOE within two weeks of submittal. We have tentatively scheduled groundwater sampling for the week of 6/13/2022. TACO-1 results in a decrease of $1,310.20.

Subtask Deliverable Deliverable Date Invoice Amount 2 Q2 field deliverable, ADaPT files, and GIS data tables 09/30/2022 $4,241.69 3 Q3 field deliverable, ADaPT files, and GIS data tables 12/30/2022 $4,241.69 4 Q4 field deliverable, ADaPT files, and GIS data tables 03/31/2023 $4,311.70 5 Submittal of PARM Report 04/28/2023 $3,218.68

1, 6 Submittal of Final IDW manifest 05/26/2023 $1,858.81 Total $17,872.57

CLOSURE

As always, it is a pleasure to work with the FDEP. If you require any additional information or have any questions, please contact us at 813.558.0990.

Sincerely, James C. Mills, M.S.

Professional

Todd K. Kafka, P.G.

Senior Principal Hydrogeologist

Attachments Figures Attachment A – IDW Subcontractor Bids

LOE

Note, Figure 1 and Attachment A are not related to TACO-1 and are not provided.

Final CEF.pdf
Final Estimate
Final LOEs.pdf
Subtask 2
Subtask 3
Subtask 4
Subtask 5
Subtask 6
Delta CEF.pdf
TACO 1 Estimate
Delta LOEs.pdf
Subtask 2-CO1
Subtask 3-CO1
Subtask 4-CO1
Original CEF.pdf
Original Estimate
Walker Plaza (ERIC_4783)_SOW_PARM Sampling_TACO-1_July 2022.pdf
SOW ELEMENTS
LOE SUBTASKS
Subtask 1 – Project Management
Subtask 2 – Quarter 2 PARM Sampling (June – August 2022)
Subtask 3 – Quarter 3 PARM Sampling (September – November 2022)
Subtask 4 – Quarter 4 PARM Sampling (December 2022 – February 2023)
Subtask 5 – PARM Report
Subtask 6 - IDW Management
Invoice and Deliverable Schedule
CLOSURE
FIGURES
ATTACHMENT A

File details come from the government source that posted it. Updated .