Summary

This is a Task Assignment (TA) document under Contract Number HW683 issued by the State of Florida Department of Environmental Protection (FDEP) to Geosyntec Consultants, Inc. for conducting annual groundwater monitoring activities at the Magic Cleaners remedial site (ERIC_4604) located at 5850 San Juan Avenue, Jacksonville, Duval County, Florida. The task assignment was executed on June 24, 2025, with a completion date of February 27, 2026. The Department Project Manager is Safa Shariat (850-245-8788), and the Contractor's Project Manager is Blaine Dawson (904-450-4271).

The scope of work authorizes Geosyntec to conduct annual groundwater monitoring for volatile organic halocarbons (VOHs) and per- and polyfluoroalkyl substances (PFAS) at the site. The work is structured into four subtasks: Subtask 1 covers project management; Subtask 2 involves collection of seven groundwater samples and depth-to-water measurements using EPA Method 8260B analysis; Subtask 3 requires preparation of a comprehensive Groundwater Monitoring Report with figures and tables; and Subtask 4 includes PFAS sampling and reporting from five monitoring wells. The total contract value is $11,690.27, with a fixed unit rate payment structure. Invoice payments are scheduled as follows: $5,105.11 upon FDEP review and approval of groundwater monitoring field notes and investigation-derived waste (IDW) manifest (due October 3, 2025), and $6,585.16 upon submission and approval of the Groundwater Monitoring Report (due November 7, 2025). The total labor commitment is 67 hours. Supporting documentation includes cost estimates, level-of-effort worksheets, subcontractor quotes for IDW disposal services, and site maps indicating monitoring well locations and groundwater flow directions.

View the file

Other files

File Type Posted
CN-370000-HW683-BF02A.pdf.crdownload CRDOWNLOAD file
CN-370000-HW683-BF02ACO1.pdf PDF
CN-370000-HW683-BF02B.pdf PDF
CN-370000-HW683-BF04CCO2.pdf PDF
CN-370000-HW683-BIL01B.pdf PDF
CN-370000-HW683-BIL01C.pdf PDF
CN-370000-HW683-BIL03A.pdf PDF
CN-370000-HW683-CSS01.pdf PDF
CN-370000-HW683-CSS02B.pdf PDF
CN-370000-HW683-DC002B.pdf PDF
CN-370000-HW683-DC002C.pdf PDF
CN-370000-HW683-DC003D.pdf PDF
CN-370000-HW683-DC003F.pdf PDF
CN-370000-HW683-DC005A.pdf PDF
CN-370000-HW683-DC005B.pdf PDF
CN-370000-HW683-DC005C.pdf PDF
CN-370000-HW683-DC008C.pdf PDF
CN-370000-HW683-DC009D.pdf PDF
CN-370000-HW683-DC010B.pdf PDF
CN-370000-HW683-DC014B.pdf PDF
CN-370000-HW683-DC015A.pdf PDF
CN-370000-HW683-DC017B.pdf PDF
CN-370000-HW683-DC017D.pdf PDF
CN-370000-HW683-DC018A.pdf PDF
CN-370000-HW683-DC019E.pdf PDF
CN-370000-HW683-DC01ACO2.pdf PDF
CN-370000-HW683-DC01B.pdf PDF
CN-370000-HW683-DC020D.pdf PDF
CN-370000-HW683-DC025A.pdf PDF
CN-370000-HW683-DC025C.pdf PDF
CN-370000-HW683-DC028B.pdf PDF
CN-370000-HW683-DC028C.pdf PDF
CN-370000-HW683-DC029C.pdf PDF
CN-370000-HW683-DC029F.pdf PDF
CN-370000-HW683-DC029G.pdf PDF
CN-370000-HW683-DC02ECO2.pdf PDF
CN-370000-HW683-DC030A.pdf PDF
CN-370000-HW683-DC030B.pdf PDF
CN-370000-HW683-DC031A.pdf PDF
CN-370000-HW683-DC032B.pdf PDF
CN-370000-HW683-DC034A.pdf PDF
CN-370000-HW683-DC036C.pdf PDF
CN-370000-HW683-DC037A.pdf PDF
CN-370000-HW683-DC042B.pdf PDF
CN-370000-HW683-DC043B.pdf PDF
CN-370000-HW683-DC044C.pdf PDF
CN-370000-HW683-DC048A.pdf PDF
CN-370000-HW683-DC04A.pdf PDF
CN-370000-HW683-DC04ACO1.pdf PDF
CN-370000-HW683-DC05BCO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O.

Object Code

Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bas s, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department

Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature)

Date:

Additional signatures attached on separate page.

HW683

DC019D February 27, 2026

This TA authorizes Geosyntec to conduct Annual Groundwater Monitoring for VOHs and PFAS at the Magic Cleaners site in accordance with the Geosyntec scope of work, cost estimate, and schedule received on June 9, 2025.

Safa Shariat 850-245-8788 Geosyntec

Blaine Dawson 904-450-4271

ERIC_4604

5850 San Juan Avenue Jacksonville, Duval County, Florida

Magic Cleaners (ERIC_4604)

$ 11,690.27

$ 11,690.27

Scope of Work

Geosyntec

Todd Kafka

Contract Manager

Joseph Applegate Digitally signed by Joseph Applegate Date: 2025.06.24 12:02:47 -04'00'

Mubeen Darji

Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.

Date: 2025.06.24 11:48:40 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Secretary

Memorandum

TO:

FROM:

SUBJECT: Negotiation Summary

DATE:

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Magic Cleaners SUBTASK : Groundwater Sampling

DATE: 6/8/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Professional

B. Dawson 4

Senior Staff Professional D. McGill

TOTAL LABOR 25

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 Day 2 $240.00

Subtotal $240.00

TOTAL VEHICLE $240.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

IDW

Hulls $206.00 $206.00

Subtotal $206.00

TOTAL SUB $206.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOHs $73.00 7 0 $511.00

Subtotal $511.00

Shipping

Large Cooler (25 to 50 lbs) $150.00 1 $150.00

Subtotal $150.00

TOTAL LAB $661.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Analytical Related

Groundwater Sampling Kit $290.00 Day 2 $580.00

Subtotal $580.00

IDW Related

Drum $100.00 Drum 1 $100.00

Subtotal $100.00

Expendables

$40.00 Day 2 $80.00

Subtotal $80.00

TOTAL EQUIPMENT $760.00

Property owner notification (1 hr); Evaluating and interpreting field data (1 hr); Prepare field package (1 hr); Prepare and sign IDW manifest (1 hr)

Field preparation (1 hr); Mobe 2 days @ 1 hr/day (2 hrs); Collect DTW measurements (2 hrs); Calibration of equipment (0.5 hr/day x 2 day = 1 hr); Sampling 7 monitoring wells @

1.5 hrs each (11 hrs); Sample management/shipping (2 hrs); IDW Management (1 hr);

Prepare field notes (1 hr)

6/16/2025 Page 3 of 5 Subtask 2

SUBTASK : GMR

DATE: 6/8/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Principal

T. Kafka 1

Senior Professional

B. Dawson 12

Professional C. Saville 4

Senior Staff Professional

D. McGill 3

Administrative Assistant

P. Gallagher 1

TOTAL LABOR 21

Report formatting and PDF compilation

Develop recommendations and path forward

Preparation of Groundwater Monitoring Report

Prepare 2 GIS figures (Groundwater contours and groundwater results)

Prepare tables, draft contour figures, assemble appendices

6/16/2025 Page 4 of 5 Subtask 3

SUBTASK : PFAS Sampling and Reporting

DATE: 6/8/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Principal

T. Kafka 1

Senior Professional

B. Dawson 3

Professional

C. Saville 3

Senior Staff Professional D. McGill

TOTAL LABOR 14

Data evaluation and path forward recommendation

Prepare PFAS evaluation in GMR

PFAS groundwater results figures

Sample 5 wells for PFAS including additional decon procedures (5 wells @ 0.5 hr/well = 3 hrs). IDW management (1 hr). Sample management for FDEP lab (1 hr); Prepare GW results table (2 hrs).

6/16/2025 Page 5 of 5 Subtask 4

ERIC_4604 - Magic Cleaners - Annual Monitoring SOW_2025

1200 Riverplace Boulevard, Suite 710 Jacksonville, Florida 32207

PH 904.858.1818

FAX 904.396.1143

www.geosyntec.com

8 June 2025

Ms. Sarah Aduwa Florida Department of Environmental Protection Waste Site Cleanup Section 2600 Blair Stone Road Tallahassee, FL 32399-2400

Subject: Scope of Work/Level of Effort Annual Groundwater Monitoring Magic Cleaners (ERIC_4604) 5850 San Juan Avenue Jacksonville, Duval County, Florida

Dear Ms. Aduwa, Geosyntec Consultants, Inc. has prepared the following Scope of Work (SOW) and Level of Effort (LOE) for annual groundwater monitoring activities at the Magic Cleaners (ERIC_4604, the Site) located in Jacksonville, FL. A copy of the CEF and LOE is provided as Attachment A. Annual volatile organic halocarbon (VOH) monitoring proposed in this SOW is consistent with the recommendations provided in the August 2023 Site Assessment Report (SAR).

On 30 May 2025, Geosyntec confirmed the Site Access Agreement (SAA) was executed with Enat Injera, Inc., on 14 June 2022, as the real property owner of the Magic Cleaners Site (ERIC_4604) located at the above address. The Duval County Property Appraiser database indicates the property owner since 15 August 2018 is �Enat Injera, Inc.,� and that the property has not changed ownership since then. As a result, Geosyntec believes the current SAA remains in force.

Subtask 1 � Project Management

Blaine Dawson, Senior Geologist, will be the project manager (PM), and his PM hours are directly computed.

Subtask 2 � Annual Groundwater Monitoring

Geosyntec will collect seven (7) groundwater samples from the current monitoring well network per the recommendations in the August 2023 SAR. Depth to water measurements will be collected within a 24-hour period from the monitoring well network. Each of the seven monitoring wells

Ms. Sarah Aduwa 8 June 2025

ERIC_4604 - Magic Cleaners - Annual Monitoring SOW_2025

(MW-1 through MW-7) will be conventionally sampled using a peristaltic pump. The seven groundwater samples will be analyzed by a fixed-based lab for volatile organic halocarbons (VOHs) by Environmental Protection Agency (EPA) Method 8260B. We have estimated the activities can be performed by one senior staff professional over a two-day period.

Purge water generated during sampling activities will be placed in a 55-gallon drum and manifested for off-Site disposal. Investigation derived waste (IDW) will be staged in the rear of the facility. Historical analytical results (VOHs and PFAS) indicate IDW has been non-hazardous;

however, to verify applicability with the current waste profile, Geosyntec proposes the collection of a liquid IDW sample for analysis of PFAS. Geosyntec has assumed disposal of the IDW drum as non-hazardous; however, if concentrations in the waste profiling sample indicate exceedance of hazardous limits, a change order will be submitted for the additional disposal costs. Bid costs prepared by the waste disposal companies are included in Attachment A.

Subtask 3 � Groundwater Monitoring Report

Geosyntec will prepare an Annual Groundwater Monitoring Report documenting the results of the depth to groundwater measurements and chlorinated solvent concentrations. The report will contain tables summarizing field/laboratory groundwater data, one figure showing groundwater flow direction(s), one groundwater results figure, and a summary of the groundwater monitoring event. The report will be signed and sealed by a Florida-licensed professional geologist. A final signed waste manifest for IDW transport and disposal will also be included in the Groundwater Monitoring Report.

Subtask 4 � PFAS Sampling and Reporting

Geosyntec will conduct PFAS groundwater monitoring activities concurrently with those described in Subtask 2. These sampling activities are proposed to evaluate the PFAS groundwater impacts observed during initial PFAS screening activities in August 2023. Exceedances of the provisional groundwater cleanup target level for the summation of PFOA and PFOS was observed at monitoring wells MW-2 (101 nanograms per liter [ng/L] and MW-4 (155 ng/L). Due to the concentrations observed during initial screening activities, continued monitoring for PFAS has been included in Subtask 2 and includes sample collection from five monitoring wells (MW-1 through MW-5) to evaluate current PFAS concentrations.

PFAS samples will be collected using low-flow purging via a peristaltic pump in accordance with draft SOPs for PFAS sampling developed by FDEP and the SOPs for PFAS sampling prepared by

ERIC_4604 - Magic Cleaners - Annual Monitoring SOW_2025

Geosyntec for use at FDEP�s Site Investigation Section firefighting training facilities. PFAS free water will used to decontaminate the water level meter between sampling wells.

Geosyntec understands that the FDEP laboratory will analyze the five (5) groundwater samples for PFAS constituents, and the FDEP will ship the sampling kits to Geosyntec. Based on the location of the Site, Geosyntec anticipates shipping the samples to the FDEP laboratory. Geosyntec assumes that the FDEP laboratory will provide return shipping labels with the sampling kits.

The PFAS analytical results will be presented within the annual groundwater monitoring report included in Subtask 3.

ERIC_4604 - Magic Cleaners - Annual Monitoring SOW_2025

Invoice and Deliverable Schedule:

Subtask Deliverable Deliverable Date Invoice Amount

Submittal of groundwater sampling field notes and IDW manifest

3 October 2025 $5,105.11

1, 3, 4 Submittal of Groundwater Monitoring Report 7 November 2025 $6,585.16

Total $11,690.27

As always, it is a pleasure to work with the FDEP. If you require any additional information or have any questions, please contact Blaine Dawson at 904.450.4271.

Sincerely, Blaine Dawson, P.G.

Senior Geologist

Todd K. Kafka, P.G.

Sr. Principal Hydrogeologist

Attachments A � Subcontractor Cost Evaluation and Quotes

1 Drum $206 1 Profile Fee (PFAS) $350 1 Drum $105 1 Drum $195 1 Transportation $425

Note: The selected subcontractor is highlighted in yellow.

* indicates requires PFAS profiling and disposal if any present or historical detections

Subcontractor Evaluation: Magic Cleaners, Jacksonville, Florida

WRI/Moran

$206.00 $545.00 $530.00

IDW DISPOSAL

Hulls Erwin Remedation*

408 Ditmar Street Pensacola, FL 32503

ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562

(850) 292-6511

To: Ms. Maria Lemes Geosyntec Consultants, Inc.

19321 US Highway 19 North Clearwater, FL 33764

December 16, 2024

Re: Non-Hazardous Drum Disposal of PFOS/PFAS Impacted Materials

Ms. Lemes:

The price for the transportation and disposal (T&D) of 55-gallon drums of non-hazardous soil, mud, and water is listed below:

Impacted with Non-Hazardous Petroleum or Chlorinated Solvents:

Description Rate Unit

T&D - Non-Haz Soil $ 110.00 Per Drum

T&D - Non-Haz Mud/Water $ 125.00 Per Drum

Impacted with Non-Hazardous PFAS/PFOS:

Description Rate Unit

Profile Fee (Charged once per site) $ 350.00 Per Site

T&D - Non-Haz PFOS/PFAS Impacted Soil $ 195.00 Per Drum

T&D - Non-Haz PFOS/PFAS Impacted Mud/Water $ 195.00 Per Drum

Dry cleaning sites will require 8260-VOH lab analysis and PFAS sites will require the full FDEP lab analysis for IDW waste characterization.

This quote is valid for 120 days.

Respectfully, Jonathan Erwin Erwin Remediation, Inc.

Email: ErwinRemediation@Gmail.com Office: (850) 292-6511

Profile Fee (Charged once per site) $ 350.00 Per Site

T&D - Non-Haz PFOS/PFAS Impacted Mud/Water $ 1$ 195.00 Per Drum

Proposal No.

Date

: 2 -AK0

: /3 /202

PROPOSAL & SHORT FORM AGREEMENT FOR WASTE DISPOSAL SERVICES

Additional Terms:

Drums must be labeled, securely closed and free of leaks.

All Services subject to a minimum charge of $195 Standby to be charged at an additional $145/hr Water treatment loads containing equal to or greater than 2% solids will be assessed a solids surcharge of $0.68/gallon, applies to the solids portion of the load only.

Payment Terms: [NET 30 Days] In addition to the charges above, Customer shall reimburse Water Recovery for any tariff, permit or approval fees, tax surcharges or sales, or use or any other applicable fees related to the performance of the Services.

Proposal is based upon accuracy of information provided by Customer; any changes to the waste stream data or site conditions may result in additional charges.

Prior to commencement of Services, Water Recovery must r - Hazardous Waste Stream Profile and inventory (if applicable).

This Proposal, the attached General Terms and Conditions, and any documentation referenced above shall constitute the entire agreement between Water Recovery and Customer with respect to the waste handling, transportation, and/or disposal of the waste identified above. By signing below, the undersigned represents his/her authority to bind Customer and generator (if different than Customer) to the terms and conditions herein. Water Recovery may withdraw this Proposal prior to acceptance, at any time.

Dated this 3 day of , 202 .

WATER RECOVERY CUSTOMER

(Signature)

(Signature)

WATER RECOVERY CUSTOMER

Company : Water Recovery, LLC Company :

Contact : Amanda Kimball Contact :

Street : 1819 Albert St. Street :

City, State, Zip : Jacksonville, FL 32202 City, State, Zip :

Phone : 904-475-9320 Phone :

E-mail : akimball@wrijax.com E-mail :

Geosyntec Consultants

Blvd.

FL

@geosyntec.com

WASTE AND SERVICES INFORMATION

Generator : Various (as manifested) Waste Description : Non-hazardous industrial waste Waste Location : Various (as manifested) Anticipated Volume : Various Anticipated Frequency : As Needed Disposal Quote : Water Treatment Non-hazardous waste - $0.18/gallon

Solidification Non-hazardous waste - $0.68/gallon Non-hazardous drum disposal - $105/drum PFAS Rate varies, please call for quote

Transportation : Local (Jacksonville)- $425/load, plus fuel surcharge (currently 8.5%) Brunswick, GA- $595/load, plus fuel surcharge (currently 8.5%) Orlando/Titusville, FL- $1,025/load, plus fuel surcharge (currently 8.5%)

Description of Services : Transportation and disposal of non-hazardous waste.

Documentation : Proposal No.: 2 -AK0 and General Terms and Conditions

Non-hazardous drum disposal - $105/drum

Local (Jacksonville)- $425/load, plus fuel surcharge (currently 8.5%)

Printed Name/Title

Printed Name/Title

GENERAL TERMS AND CONDITIONS

1. Agreement. These General Terms and Conditions and attached Proposal (including any documentation referenced transportation, and/or management services identified on the attach identified on the Proposal and any applicable waste profile form(s) submitted by Customer and approved by Water this Agreement and

2. Nonconforming Waste. Any waste, substance, and/or material tendered or delivered by Customer to Water Recovery (in any manner) that is not in strict conformance with the description or information on the applicable Waste Profile, as well as any substance or waste considered hazardous under any applicable federal, state, or local statute, regulation, or ordinance or by any governing agency, shall be deeme

3. Customer Warranties. Customer hereby represents and warrants the following: (i) the wasted tendered to or received by Water Recovery pursuant to this Agreement is not considered Nonconforming Waste; (ii) Customer and its subcontractors (of any tier), shall comply with all applicable laws, ordinances, regulations, orders, permits, or other legal requirements executing this Agreement on behalf of another party (including but not limited to the generator of the waste) Customer represents and warrants that it has authority to bind the other party to the terms and conditions of this Agreement and if not, shall remain responsible to Water Recovery for the same.

4. Water Recovery Warranties. Water Recovery represents and warrants that it will perform the Services in a safe and workmanlike manner, consistent with reasonable industry standards, and in accordance with all applicable federal, state, and local laws, ordinances, orders, rules, and regulations.

5. Term of Agreement. This Agreement shall commence upon the effective date indicated on the Proposal and shall terminate upon the completion of Services unless otherwise terminated earlier by Water Recovery. Water Recovery may terminate this Agreement for convenience by providing Customer with thirty (30) days written notice or immediately in the event Customer is in material breach of this Agreement which shall to timely pay any amounts owed to Water Recovery; (ii) any actual or alleged violation of any applicable federal, state, or local statute, regulation, ordinance, permit, or regulatory agency directive by Customer, its subcontractors (of any tier), or any entity or personnel whom Customer is responsible for; (iii) any attempt to or actual tender of Nonconforming Waste to Water Recovery (in any manner whatsoever); and (iv) any breach of Section 9 below.

6. Inspection/Rejection of Waste. Title to and liability of the waste shall remain with Customer and/or the generator at all discretion, it i cost and expense: (i) reject and return the waste to Customer; (ii) require Customer to remove and dispose of the Nonconforming Waste; (iii) elect to handle the Nonconforming Waste as described in Section 7 below; (iv) or any other course of action deemed necessary to comply with applicable federal, state, or local statutes, laws, regulations, ordinances, permits, or regulatory agency directives, guidance, or orders. Customer shall be responsible for any additional forth herein.

7. Special Handling; Nonconforming Waste. If Water Recovery elects to handle any Nonconforming Waste, Water Recovery shall have the right to manage the same in a manner deemed appropriate by Water Recovery and Customer shall be responsible for any and all related additional expenses as set forth in Section 6 above.

8. Indemnification. To the fullest extent allowable by law, the parties shall be responsible for the following allocations of liability:

a. Water Recovery. Water Recovery shall defend, indemnify, and hold harmless Customer from and against any and all claims, liabil fault including but not limited to negligence, strict liability, breach of its warranty obligations in Section 4 above, or obligations will not apply to occurrences involving Nonconforming Waste.

b. Customer. Customer shall defend, indemnify, and hold harmless Water Recovery and its parent, subsidiary, and from and against any and all Claims arising from or related to this Agreement or the Services provided hereunder and this Agreement (including Section 3 above), or any other legal theory of liability attributable to Customer or its other subcontractors of any tier in the performance of this Agreement.

c. Waiver of Immunity. In furtherance of the foregoing indemnity obligations, Customer and Water Recovery agree to waive any immunity afforded to it under workers compensation or similar law.

9. Facility Access -loading waste in the manner directed by Water Recovery. Customer and its subcontractors (of any tier) shall comply with all rules of the facility and directions given by Water Recovery personnel. Water Recovery may revoke or deny Customer (or its subcontractors of any tier) access to the facility in the event Customer, or its subcontractors (of any tier), fail to follow any such directives, rules, or regulations, and Water Recovery shall not be responsible for any expenses related to such removal.

10. Charges and Payments. Payment to Water Recovery shall be deemed earned as Services are performed and Customer shall make payment to Water Recovery without offset or deduction the earlier of: (i) the payment term indicated on the Proposal or (ii) if no payment term is expressly indicated, within net thirty (30) da invoice. Late payments shall earn interest at the rate of 1.5% per month, or the maximum amount permitted by law, whichever is less. Customer shall be responsible for and shall reimburse Water Recovery for any and all costs and

11. Consequential Damages. Neither party shall be responsible for any consequential, incidental, punitive, or special damages whatsoever (including but not limited to, business interruption, extra expense, loss of use of any property, or delay) arising out of or relating to the Services and/or this Agreement, howsoever caused and regardless of whether the same results from the negligence of a party, or otherwise and even if the possibility of such was or could have been foreseeable.

Force Majuere. Except for the obligation to make payments hereunder, neither party shall be in default for its failure to perform or delay in performance caused by events beyond its reasonable control, including, but not limited to, strikes, riots, imposition of laws or governmental orders, fires, acts of God, and inability to obtain equipment, and the affected party shall be excused from performance during the occurrence of such events

12. Counterparts and Facsimile Signatures. This Agreement may be executed in two or more counterparts, each of which will be deemed an original and all of which together will constitute the same agreement. Facsimile or email signatures and/or acknowledgement and acceptance shall be considered valid.

13. Severability. The partial or complete invalidity of any one or more provisions of this Agreement shall not affect the validity or continuing force and effect of any other provision. If any provision is invalid, in whole or in part, the balance of the provisions shall be considered reformed to reflect the intent of the parties to the greatest extent possible consistent with applicable law.

Governing Law, Venue and Legal Fees. The interpretation and performance of this Agreement shall be governed by the laws of the state of Florida which the Services are performed and any litigation or dispute arising in connection with this Agreement shall be settled by arbitration administered by the American Arbitration Association in accordance with its commercial arbitration rules, and judgment on the award entered by the arbitrator(s) may be entered into any court having jurisdiction thereof. The substantially prevailing party shall be entitled to its legal fees and costs with respect to any litigation or dispute arising pursuant to this Agreement.

14. Entire Agreement, Neutral Construction and Headings. This Agreement constitutes the entire agreement between the parties and expressly supersedes and negates any prior or contemporaneous agreements, whether written or oral. This Agreement may not be modified or amended except by a writing signed by both parties. The parties agree that each has had the opportunity to review the terms of this Agreement and to request any desired changes or clarifications and this Agreement shall be construed neutrally, and as the commemoration of the mutual assent of both parties, rather than for or against either party. The title of this Agreement and headings used herein are for reference only and shall not be construed to give any substantive meaning.

File details come from the government source that posted it. Updated .