CN-370000-HW683-DC011D.pdf
PDF 5 MB Posted
- Contract number
- HW683
- Issued by
- Florida
About this file
This is a Task Assignment (TA) document under Contract Number HW683 between the State of Florida Department of Environmental Protection (FDEP) and Geosyntec Consultants, Inc. The TA authorizes environmental investigation and monitoring services at Scott's Custom Cleaners, Inc., a contaminated site located at 2454 McMullen Booth Road, Suite 205, Clearwater, Florida (ERIC Project 5307). The document is dated November 30, 2024, with a completion date of November 30, 2024. Key personnel include Sarah Aduwa as the FDEP Project Manager and Nick Barnes as Geosyntec's Project Manager.
Geosyntec will conduct groundwater and expanded Per- and Polyfluoroalkyl Substances (PFAS) monitoring in accordance with the contractor's scope of work, cost estimate, and schedule submitted May 3, 2024. The work encompasses five subtasks: (1) Project Management; (2) Groundwater Sample Collection from 12 monitoring wells for volatile organic compound testing and 10 wells for PFAS analysis; (3) Annual Groundwater Monitoring Report preparation; (4) Expanded PFAS Monitoring Summary Letter with Conceptual Site Model evaluation; and (5) Interdicted Drill Water (IDW) disposal through Erwin Remediation. The total TA value is $17,664.14 on a fixed unit rate basis, with invoice deliverables scheduled as follows: Field Deliverable ($8,268.49) due July 29, 2024; Groundwater Monitoring Report ($4,311.95) due August 30, 2024; and Expanded PFAS Monitoring Summary Letter and IDW Manifest ($5,083.70) due September 30, 2024. The work requires 96 labor hours and includes laboratory analysis costs, equipment rental, vehicle usage, and waste disposal services.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O.
Object Code
Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department
Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature)
Date:
Additional signatures attached on separate page.
HW683
DC011D November 30, 2024
This Task Assignment authorizes Geosyntec to conduct groundwater and expanded
PFAS monitoring at Scott’s Custom Cleaners site in accordance with Geosyntec scope of work, cost estimate and schedule received on May 3, 2024
Sarah Aduwa 850-245-8973 Geosyntec
Nick Barnes 813-557-1165
ERIC 5307
2454 McMullen Booth Road, Suite 205 Clearwater, Florida
Scott’s Custom Cleaners, Inc.
$ 17,664.14
$ 17,664.14
Scope of Work
Geosyntec
Todd Kafka
Contract Manager
Todd Kafka, P.G. Digitally signed by Todd Kafka, P.G.
Date: 2024.05.28 12:27:23 -04'00'
Mubeen Darji
Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.
Date: 2024.05.28 11:05:58 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WC TAFORM
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
To: HW683 Contract Negotiation File Scotts Custom Cleaners, Inc Clearwater, Florida
ERIC_5307
From: Sarah Aduwa, Project Manager Date: May 6, 2024 Subject: Negotiation Summary
HW683_DC011D
This Task Assignment authorizes Geosyntec to conduct groundwater and expanded PFAS monitoring at Scott’s Custom Cleaners site in accordance with Geosyntec scope of work, cost estimate and schedule received on May 3, 2024
Subtask 2: Groundwater Sample Collection VOHs - Geosyntec will collect a total of 12 groundwater samples from monitoring wells
MW002, MW-7, MW-8, MW-9, MW-10, MW-11, MW-13, MW-14, MW-16, MW-17, MW-18,
and MW-19. PFAS monitoring is proposed at MW002, MW-8, MW-9, MW-10, MW-11, MW- 12, MW-13, MW-14, MW-17, and MW-21. Purge water generated during the groundwater monitoring activities will be stored in a 55-gallon drum onsite.
Subtask 3: Annual Groundwater Monitoring Report (VOHs) Geosyntec will prepare a Groundwater Monitoring Report documenting the VOH results of the groundwater monitoring event.
Subtasks 4: Expanded PFAS Monitoring Summary Letter Geosyntec will prepare an Expanded PFAS Monitoring Summary Letter documenting the results of the groundwater monitoring event. This letter will include a summary of field activities, groundwater sampling field forms, flow directions figures, analytical results and a PFAS conceptual site model.
Subtask 5 – IDW Disposal Geosyntec recommends selecting Erwin Remediation to haul and dispose of IDW generated during the groundwater monitoring activities.
The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost is $17,664.14 with 96 labor hours.
Printed on recycled paper.
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Scott's Custom Cleaners SUBTASK: Groundwater Sample Collection
DATE: 5/3/2024
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Professional N. Barnes 3
Senior Staff Professional O. Hollingsworth 24
Senior Staff Professional M. Mohr
TOTAL LABOR 47
VEHICLE TYPE RATE UNIT USEAGE
Truck Mohr $120.00 day 2 $240.00 Truck Hollingsworth $120.00 Day 2 $240.00
Subtotal $480.00
TOTAL VEHICLE $480.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
IDW
Subtotal $0.00
TOTAL SUB $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOHs 12 MWs & IDW $73.00 13 0 $949.00 BTEX IDW Composite $70.00 1 0 $70.00 Arsenic IDW Composite $14.00 1 0 $14.00 Barium IDW Composite $14.00 1 0 $14.00 Cadmium IDW Composite $14.00 1 0 $14.00 Chromium IDW Composite $14.00 1 0 $14.00 Lead IDW Composite $14.00 1 0 $14.00 Mercury IDW Composite $26.00 1 0 $26.00 Selenium IDW Composite $14.00 1 0 $14.00 Silver IDW Composite $14.00 1 0 $14.00 PFAS Subtotal $1,143.00 Shipping
Large Cooler (25 to 50 lbs) $150.00 1 $150.00 Subtotal $150.00
TOTAL LAB $1,293.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Analytical Related Shallow Groundwater Sampling Kit $290.00 Day 4 $1,160.00
Subtotal $1,160.00 IDW Related
Drum $100.00 Drum 1 $100.00 Subtotal $100.00
Expendables $40.00 Day 2 $80.00
Subtotal $80.00
TOTAL EQUIPMENT $1,340.00
Prepare Field Package and RPO/tenant notifications (2 hr). Evaluate field data (0.5 hr/day x 2 days = 1 hr).
Field preparation (1 hr). Round trip mobilization (2 hr/day x 2 days = 4 hr). Locate and collect depth-to-groundwater measurements from 16 montoring wells (1.5 hr). Calibration of instruments (0.5 hr/day x 2 days = 1 hr). Sample 7 monitoring wells (1.5 hr/well x 7 wells = 10.5 hr). Extra time for PFAS SOPs (2 hr). Sample management (3 hr). Compile field notes and documentation (1 hr).
Field preparation (1 hr). Round trip mobilization (2 hr/day x 2 days = 4 hr). Locate and collect depth-to-groundwater measurements from 16 montoring wells (1.5 hr). Calibration of instruments (0.5 hr/day x 2 days - 1 hr). Sample 7 monitoring wells (1.5 hr/well x 7 wells = 10.5 hr). Extra time for PFAS SOPs (2 hr).
5/6/2024 Page 3 of 6 Subtask 2
SUBTASK: Annual Groundwater Monitoring Report (VOHs)
DATE: 5/3/2024
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Principal T. Kafka 2
Senior Professional
Project Professional M. Hensley 8
Project Professional N. Barnes 14
TOTAL LABOR 24
Evaluating and interpreting groundwater data, develop conclusions and recommendations
Prepare figure package for Groundwater Monitoring Report
Prepare Groundwater Monitoring Report and sign/seal Groundwater Monitoring Report
5/6/2024 Page 4 of 6 Subtask 3
SUBTASK: Expanded PFAS Monitoring Summary Letter
DATE: 5/3/2024
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Principal T. Kafka 1
Senior Professional
Project Professional M. Hensley 3
Project Professional N. Barnes 10
TOTAL LABOR 14
SUBCONTRACTOR COSTS
NAME PURPOSE COST
IDW
Subtotal
TOTAL SUB $0.00
Evaluating and interpreting groundwater data, develop conclusions and recommendations
Prepare figure package for PFAS Investigation Report
Preliminary PFAS CSM evaluation, prepare PFAS Summary Letter Report and sign/seal PFAS Summary Letter
5/6/2024 Page 5 of 6 Subtask 4
SUBTASK: IDW Disposal
DATE: 5/3/2024
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Professional Waste profile and IDW manifesting (2 hr).
N. Barnes 2
TOTAL LABOR 2
SUBCONTRACTOR COSTS
NAME PURPOSE COST
IDW
Erwin Remediation Profile Fee $350.00 $350.00 Erwin Remediation PFAS-Impacted Waste ($195/drum) $195.00 $195.00
Subtotal $545.00
TOTAL SUB $545.00
5/6/2024 Page 6 of 6 Subtask 5
12802 Tampa Oaks Blvd.
Suite 151
Tampa, Florida 33764 Ph. 813-558-0990 www.geosyntec.com
May 3, 2024
Ms. Sarah Aduwa Florida Department of Environmental Protection Waste Site Cleanup Section 2600 Blair Stone Road, MS 4520 Tallahassee, Florida 32399-2400
Subject: Scope of Work and Level of Effort Annual Groundwater Monitoring and Expanded PFAS Monitoring Scott’s Custom Cleaners, Inc.
2454 McMullen Booth Road, Suite 205 Clearwater, Florida FDEP Site ID No. ERIC_5307
Dear Ms. Aduwa, Geosyntec Consultants, Inc. (Geosyntec) has prepared this Scope of Work (SOW), Cost Estimating Form (CEF), and Level of Effort (LOE) to conduct annual groundwater monitoring concurrent with expanded PFAS monitoring at the former Scott’s Custom Cleaners, Inc. facility (herein, the “Site”) located in Clearwater, Florida. A description of task breakdown for groundwater sampling activities and report preparation is provided below. A copy of the CEF/LOE is included in Attachment A.
Subtask 1 – Project Management
Costs associated with this subtask are directly computed.
Subtask 2 – Groundwater Sample Collection
VOHs
Geosyntec will collect a total of 12 groundwater samples from monitoring wells MW002, MW-7, MW-8, MW-9, MW-10, MW-11, MW-13, MW-14, MW-16, MW-17, MW-18, and MW-19. Prior to groundwater sampling, Geosyntec will gauge and record the depth-to-water (DTW) from 16 surficial aquifer monitoring wells within a 24-hour period, including from 2 wells that are not anticipated to be sampled during this event (MW-1 and MW-20). A copy of the 2023 groundwater monitoring results figure is provided as Attachment B, along with a proposed sampling schedule.
Geosyntec assumes that a peristaltic pump will be used to collect groundwater samples from the monitoring wells, consistent with previous sampling events. Field activities will be conducted in
Ms. Sarah Aduwa February 8, 2024 accordance with the FDEP Standard Operating Procedures. Groundwater samples will be submitted under chain of custody protocol for laboratory analysis of volatile organic halocarbons (VOHs) by Environmental Protection Agency Method 8260.
PFAS
Per- and polyfluoroalkyl substances (PFAS) were previously detected in Site monitoring wells during the screening conducted in October 2022, with exceedances of the Provisional Groundwater Cleanup Target Levels (PGCTLs) within MW002, MW-9, and MW-14. In accordance with FDEP guidance, expanded PFAS monitoring is proposed from these wells and seven additional monitoring wells. Accordingly, PFAS monitoring is proposed at MW002, MW-8, MW-9, MW- 10, MW-11, MW-12, MW-13, MW-14, MW-17, and MW-21. Geosyntec assumes that the PFAS samples will be analyzed by the FDEP Central Laboratory.
Geosyntec understands that the FDEP laboratory will analyze up to ten (10) groundwater samples for PFAS, provide 1 liter of PFAS-free water for an equipment blank, and ship the sampling kits to Geosyntec. Based on the location of the Site, Geosyntec anticipates shipping the samples to the FDEP laboratory. Geosyntec assumes that the FDEP laboratory will provide return shipping labels with the sampling kits.
Purge water generated during the groundwater monitoring activities will be stored in a 55-gallon drum onsite. A sample will be collected for PFAS, Volatile Organic Halogens (VOHs) and BTEX, and the 8 Resource Conservation and Recovery Act (RCRA) metals for analysis to characterize the waste.
Subtask 3 – Annual Groundwater Monitoring Report (VOHs)
Geosyntec will prepare a Groundwater Monitoring Report documenting the VOH results of the groundwater monitoring event. The report will contain a summary of the field activities completed, tables summarizing field and laboratory groundwater data, figures showing groundwater flow direction(s) and groundwater analytical results, and conclusions. The report will be signed and sealed by a Florida-licensed professional geologist or engineer.
Subtask 4 – Expanded PFAS Monitoring Summary Letter
Following receipt and review of the analytical data, Geosyntec will prepare an Expanded PFAS Monitoirng Summary Letter documenting the results of the groundwater monitoring event. The letter will include:
A summary of the field activities;
Groundwater sampling field forms;
Figures of the groundwater flow direction and the PFAS analytical results;
Ms. Sarah Aduwa February 8, 2024
The FDEP analytical laboratory report; and A preliminary evaluation of the PFAS Conceptual Site Model (CSM) and recommendations for further courses of action as necessary. The letter will be signed and sealed by a Florida-licensed professional geologist or engineer.
Subtask 5 – IDW Disposal
IDW disposal quotes prepared by waste disposal companies are included in Attachment A. Based on the quotes, Geosyntec recommends selecting Erwin Remediation to haul and dispose of IDW generated during the groundwater monitoring activities. Based on prior screening activities, it is expected that the IDW will need to be disposed of as PFAS-containing waste and will require a new waste profile. Bid costs prepared by waste disposal companies are included in Attachment C. Based on the bids, Geosyntec recommends selecting Erwin Remediation to haul and dispose of IDW generated during the groundwater monitoring activities.
Deliverable and Invoicing Schedule:
Subtask Deliverable Due Date Invoice Amount
2 Field Deliverable – Groundwater Monitoring
July 29, 2024 $8,268.49
3 Groundwater Monitoring Report August 30, 2024 $4,311.95
1, 4, 5 Expanded PFAS Monitoring Summary Letter and IDW Manifest
September 30, 2024 $5,083.70
Total $17,664.14
The above schedule assumes the Task Assignment is received in May 2024.
Geosyntec appreciates the opportunity to provide this proposal and cost estimate to you and the FDEP. Please contact us if you have any questions or require additional information.
Sincerely, Nicholas S. Barnes P.E. (FL) Todd K. Kafka, P.G. (FL, TN)
Project Engineer Senior Principal Hydrogeologist
Attachments: Attachment A – CEF/LOE Attachment B – February 2023 Groundwater Monitoring Results and Proposed Sampling Plan Attachment C – IDW Quotes
ATTACHMENT A
ATTACHMENT B
Well ID Screen
Interval (ft BLS)
VOHs PFAS
MW002 3-13 X X
MW-7 18.5-28.5 X
MW-8 2-12 X X
MW-9 2-12 X X
MW-10 2-12 X X
MW-11 2-12 X X
MW-12 5-15 X
MW-13 14-19 X X
MW-14 3-13 X X
MW-16 4-9 X
MW-17 15-20 X X
MW-18 3-13 X
MW-19 15-20 X
MW-21 15-20 X
No. of Wells 14
12 10
- Water levels to be collected from MW-1, MW002, MW-
7, MW-8, MW-9, MW-10, MW-11, MW-12, MW-13, MW-
14, MW-16, MW-17, MW-18, MW-19, MW-20, and MW-
Attachment B - Proposed Sampling Schedule Scott's Custom Cleaners