CN-370000-HW683-BF01A.pdf
PDF 1 MB Posted
- Contract number
- HW683
- Issued by
- Florida
About this file
This is a Task Assignment (TA) document for Contract Number HW683 between the State of Florida Department of Environmental Protection (FDEP) and Geosyntec Consultants. The task assignment was executed on August 24, 2022, and pertains to environmental assessment services at the Former Biscayne Chemical Site (Site ID BF139801015) located at 690 NW 13th Street, Miami, Miami-Dade County. The work is being conducted using federal funds from the State & Tribal Response Program (SRP) cooperative agreement administered by FDEP on behalf of the U.S. Environmental Protection Agency (EPA). The Department Project Manager is Megan Johnson, and the Contractor's Project Manager is Andrew Galvin of Geosyntec Consultants.
The task assignment covers two subtasks for preparing a Quality Assurance Project Plan (QAPP) Workplan to support additional soil and groundwater assessment activities. Subtask 1 involves project management, overhead, general and administrative costs, and fringe benefits totaling $1,024.22. Subtask 2 encompasses preparation of the QAPP Workplan, including project planning elements, data generation and acquisition, quality assurance, data validation, and proposed additional soil and groundwater assessment, totaling $7,878.62. The combined Total Task Assignment Value is $8,902.84 on a fixed unit rate basis. The primary deliverable is the Quality Assurance Project Plan (QAPP) Workplan with a due date of September 23, 2022. Payment is contingent upon Department approval of the project management and QAPP Workplan components. The TA completion date is October 31, 2022.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW683
BF01A Completion October 31, 2022
The Department approves this Task Assignment (TA), based upon the Cost Proposal and Level of Effort (CP/LOE), to prepare the Quality Assurance Project Plan (QAPP) Workplan for additional assessment activities at the below project site, submitted to the Department on August 18, 2022 by Geosyntec Consultants.
Megan Johnson 850.245.8994 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Geosyntec Consultants
Geosyntec Consultants
Andrew Galvin 561.922.1033
BF139801015
690 NW 13th Street, Miami, Miami-Dade County
Former Biscayne Chemical Site
✔ $ 8,902.84
$ 8,902.84
Scope of Work
Joseph Applegate, P.G.
Senior Principal Hydrogeologist
Joseph Applegate Digitally signed by Joseph Applegate Date: 2022.08.24 11:22:30 -04'00'
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2022.08.24 08:35:55 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Quality Assurance Project Plan (QAPP) Workplan 09/23/2022
Department approval of Project Management and Quality Assurance Project Plan (QAPP) Workplan (Subtasks 1 and 2) $ 8,902.84
$ 8,902.84
HW683
BF01A
www.FloridaDEP.gov
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: Geosyntec Consultants, HW683 Contract File
FROM: Megan Johnson, Contract Manager
DATE: August 23, 2022
SUBJECT: Negotiation Summary – SRP18 Task Assignment (TA) BF01A
Former Biscayne Chemical – Site ID # BF139801015 Quality Assurance Project Plan (QAPP) Workplan
This TA is intended for preparing the Quality Assurance Project Plan (QAPP) Workplan for additional assessment activities at the Former Biscayne Chemical site, located at 690 NW 13th Street, Miami, Miami-Dade County. The services under this task are being conducted using federal funds from the State & Tribal Response Program (SRP) cooperative agreement that is administered by the Department on behalf of the U.S.
Environmental Protection Agency (EPA).
Subtask 1: Project Management This subtask is a percentage of the overall project fees and has been negotiated as a contract rate. It includes project management, overhead, general and administrative, and fringe. The agreed upon cost of this subtask is $1,024.22.
Subtask 2: Quality Assurance Project Plan (QAPP) Workplan In accordance with an EPA directive, this subtask includes the completion of a Quality Assurance Project Plan (QAPP) Workplan for future additional assessment activities. The QAPP Workplan will provide information on project planning elements, data generation and acquisition, quality assurance, data validation, and proposed additional soil and groundwater assessment. Sampling tables and figures will be prepared that show the number and locations of additional soil borings for chlorinated volatile organic compounds (CVOCs) delineation as well as monitoring wells and analyses for both CVOCs and iron/manganese. The agreed upon cost of this subtask is $7,878.62.
Summary The Department’s SRP Contract Manager and Geosyntec’s Contract Manager have both agreed to the scope of work and associated costs. The final cost associated with this TA is $8,902.84. Documentation of these costs is included in the Cost Proposal/Level of Effort (CP/LOE) Form and CP/LOE narrative provided by Geosyntec on August 18, 2022, and the TA Form for BF01A prepared by the Department. The final deliverable for this TA must be received by the Department no later than September 23, 2022.
http://www.floridadep.gov/
2039 Centre Pointe Blvd, Suite 301 Tallahassee, Florida 32308
PH 850-556-8419
www.geosyntec.com
Former Biscayne Chemical_ASA Work Plan
17 August 2022
Ms. Kelly Crain and Megan R. Johnson Brownfields and CERCLA Administration Florida Department of Environmental Protection 2600 Blair Stone Road, MS 4535 Room 310-D Tallahassee, FL 32399-2400
Subject: Proposal and Level of Effort/Cost Estimate Form Additional Soil and Groundwater Assessment Former Biscayne Chemical 690 NW 13th Street Miami, Florida 33032 FDEP Brownfield Site ID# BF139801015
Dear Ms. Crain and Ms. Johnson:
We are pleased to submit this attached Cost Estimate Form and proposed Level of Effort (CEF/LOE) for the Former Biscayne Chemical Site (“the Site”). The Site is in a critical redevelopment stage and the purpose of this project is to prepare a work plan to conduct additional site assessment activities to help support site closure for soil and groundwater impacts to the property being redeveloped under a Brownfield Site Rehabilitation Agreement (BSRA) into affordable housing. The intent of the proposed additional assessment is to: (i) characterize residual soil concentrations above the leachability limit for chlorinated volatile organic compounds (CVOCs) associated with the previous source area removal,(ii) characterize the vertical and horizontal extent of iron and manganese exceedances in groundwater, and (iii) potentially collect additional background groundwater samples for iron to support the ongoing background study for iron at the Site.
This work is being conducted so that portions of the property may be redeveloped by KTLC Biscayne, LLC for the conditional closure of the property with allowance for future residential use. Work will be conducted under the State and Tribal Response Program (SRP) grant administered by FDEP. The associated scope of work consists of the following tasks.
Ms. Crain and Ms. Johnson
Former Biscayne Chemical ASA Work Plan
Subtask 1 – Project Management
Subtask 2 – Prepare Quality Assurance Project Plan for Additional Assessment Activities
Geosyntec Consultants (Geosyntec) conducted a supplemental interim source removal for CVOC impacted soils in the source area between January 25, 2021, and February 19, 2021. In general, portions of the existing concrete slab were removed and soils within the limits of excavation were excavated to depths between 2 feet (ft) below land surface (bls) and the water table ( approximately 9 ft bls ). A total of approximately 45 tons of concrete and 541 tons of soil were excavated and disposed off-Site as non-hazardous waste. The excavated areas were backfilled with clean fill material, and the Site was restored to conditions like those prior to the excavation.
TEA Inc. (TEA) prepared a Remedial Action Plan and submitted to the Miami-Dade Division of Environmental Resource Management (DERM) in October 2020 and included conducting soil and groundwater remediation. The Site-wide RAP was prepared and submitted to DERM on October 27, 2020. Review comments were received, and responses were submitted on November 24, 2020;
December 30, 2021; and January 27, 2021. Subsequently, the Site-wide groundwater RAP activities were implemented in March and April 2021. The Remedial Action Plan Implementation Report (RAPIR) was submitted on July 7, 2021 and described the implementation activities and the results of the 1-week, 2-week, 3-week, and 1-month monitoring activities. Analysis and interpretation of the results from these monitoring events were provided in the RAPIR and indicated that all RAP components were successfully implemented and several monitoring events post-RAP had been completed. These early monitoring events post-RAP showed that the RAP implementation activities were in the initial stages of meeting project goals and objectives which included the reduction in COC concentrations in groundwater, the enhancement of anaerobic and reducing environments in the subsurface, and the production of methane, ethane and ethene.
The 2-Month monitoring event was conducted on June 18 and 19, 2021 and the 3-Month monitoring event was conducted on July 20 and 21, 2021. The results of these events indicated that significant progress had been made toward reaching remedial goals in a short period of time (post-remediation). After three months post-remediation, there was only one well remaining with a concentration of parent compound PCE exceeding the Groundwater Cleanup Target Level (GCTL) (5.3 micrograms per liter (µg/L) at MW-231). No wells had GCTL exceedances of trichloroethylene (TCE) or cis-dicloroethene (DCE). Vinyl Chloride (VC) was observed to have decreased in aerial extent from the one-month results, as expected, and was being converted to ethene and ethane. Biogeochemical results from the field parameters as well as gas production
Former Biscayne Chemical ASA Work Plan
(methane, ethane, ethene) showed sustained conditions that were amenable to the reductive dechlorination process.
In addition to the significant chemical and biogeochemical results observed following the 1- Month, 2-Month and 3-Month monitoring events, robust statistical investigations were undertaken on the RAP monitoring well results following the 3-Month event. Mann-Kendall evaluation of the data was conducted using the GSI Environmental (GSI) Mann-Kendall Toolkit (Version 1.0).
These analyses were performed as an additional line of evidence to demonstrate COC plume stability or attenuation. Multiple review comments on the Post Active Remediation Monitoring (PARM) 3 report have been provided by DERM and several teleconferences between TEA, KTLC Biscayne, LLC Green Reuse Site, and DERM have been held to discuss PARM data which has shown elevated concentrations of iron and manganese in groundwater at the Site, apparently caused by the injection of zero valent iron to treat chlorinated VOCs, which has been overall successful in reducing CVOC concentrations in groundwater. However, iron/manganese (MG) concentrations have increased off-site and possibly vertically on-site. Based on data provided by TEA, it is expected as the geochemistry returns to normal conditions, that iron/MG concentrations will also decrease. TEA has also provided data that indicates that there are elevated background concentrations of iron that could also contribute to elevated iron/MG concentrations. DERM has requested additional delineation of iron/MG vertically and horizontally on and off-site as well as additional background data as well.
Pursuant to United States Environmental Protection Agency (USEPA)’s applicable requirements, Geosyntec will prepare a Quality Assurance Project Plan (QAPP) specific to this Site and the proposed activities. The QAPP will include information on project planning elements, data generation and acquisition, quality assurance, data validation, and proposed additional soil and groundwater assessment. Sampling tables and figures will be prepared that show the number and locations of additional soil borings for CVOCs delineation as well as additional monitoring wells and analyses for both CVOCs and iron/MG.
This work plan will focus on providing additional site assessment requested by DERM for vertical and horizontal delineation of iron/MG, as well as the collection of additional iron/MG groundwater data to support the background study. Based on recent redevelopment plans and schedule of this property redevelopment under the Florida Brownfields program, it is anticipated that multiple existing monitoring wells will need to be abandoned and/or relocated as a part of ongoing PARM and assessment that will proceed as the property is redeveloped. Geosyntec and the developer’s consultant will review future site plans to determine the number of needed well abandonments and replacements and will include this information in the work plan and obtain concurrence from DERM prior to moving forward.
Former Biscayne Chemical ASA Work Plan
The work plan will also provide additional soil assessment for residual CVOC soil that exceeds leachability concentrations for PCE, TCE, Cis, 1-2 DCE, and VC. During the January and February 2021 excavation, soil below R-SCTLs but above L-SCTLs was left in place as illustrated in the Remedial Construction Report (September 2021). The work plan will propose soil sampling locations to refine the extent of residual soil exceedances and to estimate remaining volume for additional excavation. Based on this additional soil delineation, Geosyntec will identify and prepare approximate excavation areas of residual soil that was left in place that exceeded L-SCTLs.
Based on the soil characterization of the CVOCs, Geosyntec will prepare a future QAPP Work Plan Addendum to the previous QAPP Work Plan/Interim Source Removal, 8 January 2021 that will be tasked separately from the assessment work plan so that assessment and source removal efforts can be tasked and tracked separately.
Invoice and Deliverable Schedule:
Subtask Deliverable Deliverable Due Date Invoice Amount
Additional Site Assessment QAPP Work Plan 23 September 2022 $7,878.62
1 Project Management 31 October 2021 $1,024.22 Total: $8,902.84
A copy of associated CEF has been included with this proposal.
As always, we appreciate the opportunity to conduct this project for the FDEP and for the benefit of the KTLC Biscayne, LLC. Please contact Adrian Smith at 561.922.1094 or Joe Applegate at
850.556.8419 if you have any questions.
Sincerely, Adrian Smith, P.E. (FL) Project Engineer
Joseph L. Applegate, P.G. (FL) Senior Principal Hydrogeologist
Attachment(s): LOE Cost Estimate Form
FDEP COST ESTIMATEContractor: Geosyntec Consultants
Date: 8/16/2022
Task #: HW683 SubTask 1 Project Management SubTask 6
Site: Biscayne Chemical SubTask 2 QAPP Work Plan Development SubTask 7
Activity/Phase: QAPP Work Plan (Assessment) SubTask 3 SubTask 8
Project Manager: A. Galvin/Applegate SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$38.46 Project Manager A. Galvin 9 8.9 $84.13 Sr. Principal J. Applegate 6 6 0 0 0 0 0 0 0 0 $56.30 Sr. Engineer A.Smith 12 12 0 0 0 0 0 0 0 0 $38.46 Sr. Staff Engineer A. Galvin 34 34 0 0 0 0 0 0 0 0 $46.15 Project Professional Melissa Hensley 3 3 0 0 0 0 0 0 0 0
Total Hours 64 9 55 0 0 0 0 0 0 0 0
Direct Labor $2,967.91 $341.44 $2,626.47 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 172.70% $5,125.58 $589.67 $4,535.91 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $8,093.49 $931.11 $7,162.38 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cost Estimate Page 1 of 3 Cost Estimate
FDEP COST ESTIMATEContractor: Geosyntec Consultants
Date: 8/16/2022
Task #: HW683 SubTask 1 Project Management SubTask 6
Site: Biscayne Chemical SubTask 2 QAPP Work Plan Development SubTask 7
Activity/Phase: QAPP Work Plan (Assessment) SubTask 3 SubTask 8
Project Manager: A. Galvin/Applegate SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Subcontractor (Services Procurement)
Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utility locate $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $8,093.49 $931.11 $7,162.38 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $809.35 $93.11 $716.24 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $8,902.84 $1,024.22 $7,878.62 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cost Estimate Page 2 of 3 Cost Estimate
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Biscayne Chemical SUBTASK: QAPP Work Plan Development
DATE: 8/16/2022
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Principal Evaulate and Interpret Field Data (2 hrs), Scope development with TEA and KTLC (3 hrs), call with FDEP (1)
J. Applegate 6
SR Engineer Adrian 12
Sr. Staff A Galvin 34
Project Professional Figures (3 hrs) 3 M. Hensley
TOTAL LABOR 55
VEHICLE TYPE RATE UNIT USEAGE
Car $80.00 Day 0 $0.00 Truck $480.00 Week 0 $0.00
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
Meals (standard per diem) $36.00 Day 0 $0.00 Lodging (4 nights) $130.00 Day 0 $0.00 Meals (standard per diem) $36.00 Day 0 $0.00 Lodging (3 nights) $130.00 Day 0 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Drilling (Conventional)
0 0 $0.00 $0.00 $0.00 $0.00
Other 0 0 $0.00 $0.00 0 0 $0.00 $0.00
Subtotal $0.00
TOTAL SUB $0.00
LABORATORY COSTS
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Drilling Related
0 $175.00 Day 0 $0.00 Subtotal $0.00
Analytical Related Groundwater Sampling Kit (One set for J. Udavardy and one set for K. Starling) $290.00 Day 0 $0.00 Water Level Meter (one for J. Udavardy and one for K. Starling) $25.00 Day 0 $0.00 In-line Filters $21.00 Filter 0 $0.00
Subtotal $0.00 IDW Related
Drum $100.00 Drum 0 $0.00 Subtotal $0.00
Expendables $40.00 Day 0 $0.00
Subtotal $0.00
Other GPS Station $150.00 Day 0 $0.00 Survey Station $50.00 Day 0 $0.00
Subtotal $0.00
TOTAL EQUIPMENT $0.00
QAPP Work Plan Preparation (4), Historical review ( 2) Scope development with TEA and KTLC (5 hrs), call with FDEP (1)
QAPP Work Plan Preparation, Text (18 hrs) Tables (8 hrs) and Figures (4 hrs); HASP (2 hrs); Historical review (2)
8/23/2022 Page 3 of 3 Subtask 2