This document is a Task Assignment Change Order (TACO) #1 between the State of Florida Department of Environmental Protection (FDEP) and Geosyntec Consultants, Inc. under Contract Number HW683. The change order amends Task Assignment BF02B for additional site assessment activities at Jackson Square in Marianna, Jackson County, Florida (Site ID ERIC_18453). The project is managed by Megan Johnson for FDEP and Kevin Warner for Geosyntec Consultants, with the authorized signatories being Jennifer Farrell (Secretary or Designee) for the Department and Joseph L. Applegate, P.G. (Senior Principal Hydrogeologist) for the Contractor. The change order was executed on June 10, 2025, and became effective upon the last date signed.

The TACO reduces the total task assignment cost from $9,732.29 to $9,594.79, representing a decrease of $137.50. This reduction results from one Indirectly Disposed Waste (IDW) drum going missing from the site, eliminating the disposal cost of one drum ($125.00) plus the associated handling fee ($12.50). The task assignment includes four subtasks: Project Management ($975.56), Groundwater Sampling and Analysis ($3,697.07), SAR Addendum Letter Report ($4,473.34), and IDW Disposal ($448.82). Invoice requirements are tied to departmental approval of deliverables including field forms and lab reports, IDW disposal confirmation, and the SAR Addendum Letter Report, with a completion date of June 27, 2025. No changes were made to the task assignment expiration date, and Attachment 1 was replaced with Attachment 1-1 to reflect the cost adjustment.

View the file

Other files

File Type Posted
CN-370000-HW683-BF01A.pdf PDF
CN-370000-HW683-BF01B.pdf PDF
CN-370000-HW683-BF02A.pdf PDF
CN-370000-HW683-BF02ACO2.pdf PDF
CN-370000-HW683-BF04A.pdf PDF
CN-370000-HW683-BF04BCO1.pdf PDF
CN-370000-HW683-BIL01A.pdf PDF
CN-370000-HW683-CSS02.pdf PDF
CN-370000-HW683-CSS02A.pdf PDF
CN-370000-HW683-DC002F.pdf PDF
CN-370000-HW683-DC004B.pdf PDF
CN-370000-HW683-DC004E.pdf PDF
CN-370000-HW683-DC005D.pdf PDF
CN-370000-HW683-DC005E.pdf PDF
CN-370000-HW683-DC007A.pdf PDF
CN-370000-HW683-DC007B.pdf PDF
CN-370000-HW683-DC008A.pdf PDF
CN-370000-HW683-DC008B.pdf PDF
CN-370000-HW683-DC008D.pdf PDF
CN-370000-HW683-DC009A.pdf PDF
CN-370000-HW683-DC009B.pdf PDF
CN-370000-HW683-DC009G.pdf PDF
CN-370000-HW683-DC010C.pdf PDF
CN-370000-HW683-DC011B.pdf PDF
CN-370000-HW683-DC011C.pdf PDF
CN-370000-HW683-DC011D.pdf PDF
CN-370000-HW683-DC012B.pdf PDF
CN-370000-HW683-DC016B.pdf PDF
CN-370000-HW683-DC017A.pdf PDF
CN-370000-HW683-DC018B.pdf PDF
CN-370000-HW683-DC019A.pdf PDF
CN-370000-HW683-DC019B.pdf PDF
CN-370000-HW683-DC019C.pdf PDF
CN-370000-HW683-DC019D.pdf PDF
CN-370000-HW683-DC01ACO1.pdf PDF
CN-370000-HW683-DC025B.pdf PDF
CN-370000-HW683-DC026B.pdf PDF
CN-370000-HW683-DC029A.pdf PDF
CN-370000-HW683-DC029E.pdf PDF
CN-370000-HW683-DC02ACO1.pdf PDF
CN-370000-HW683-DC02E.pdf PDF
CN-370000-HW683-DC031C.pdf PDF
CN-370000-HW683-DC032A.pdf PDF
CN-370000-HW683-DC032C.pdf PDF
CN-370000-HW683-DC035A.pdf PDF
CN-370000-HW683-DC036B.pdf PDF
CN-370000-HW683-DC037B.pdf PDF
CN-370000-HW683-DC038A.pdf PDF
CN-370000-HW683-DC039A.pdf PDF
CN-370000-HW683-DC039B.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number) Project Name:

4. There are no changes to the TA compensation.

The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

There are no changes to the TA Expiration Date.

The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. There are no changes to the Attachments.

Attachment ___ is replaced with Attachment -____.

7. No Additional Changes.

Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

Additional signatures attached on separate page.

BF02B 1 HW683

Megan Johnson 850.245.899 Contractor Geosyntec Consultants, Inc. Contractor

Contractor Kevin Warner Contractor 850.528.2269

ERIC_18453

Jackson Square

✔ $ 9,594.79 $ 9,732.29

$ 9,594.79 $ 9,732.29 ✔ Completion

Completion 0

✔ 1 1 1

Geosyntec Consultants, Inc.

Contractor Joseph L. Applegate, P.G.

Sr. Principal Hydrogeologist

Joseph Applegate Digitally signed by Joseph Applegate Date: 2025.06.10 14:54:42 -04'00'

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2025.06.10 14:31:03 -04'00'

This Task Assignment Change Order reduces the IDW disposal cost due to one drum going missing from the site, per the TACO request from Geosyntec received on June 3, 2025.

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

HW683

BF02B

$ 9,594.79

Field forms and lab reports

IDW Disposal Confirmation

SAR Addendum Letter Report; Project Management

Department approval of field forms and lab reports (Subtask 2)

Department approval of Project Management and SAR Addendum Letter Report (Subtasks 1 and 3)

Department approval of IDW Disposal Confirmation (Subtask 4)

04/15/2025

06/01/2025

05/15/2025

$ 448.82

$ 3,697.07

$ 5,448.90 www.FloridaDEP.gov

FFLORIDAA DEPARTMENTT OF

EEnvironmentall Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ronn DeSantis Governor

Alexiss A.. Lambert

Secretary

Memorandum TO: Geosyntec Consultants, Inc. HW683 Contract File

FROM: Megan Johnson, Contract Manager

DATE: June 10, 2025

SUBJECT: Negotiation Summary – SRP28 Task Assignment (TA) Change Order #1 – TA BF02B C1 Jackson Square, City of Marianna – Site ID # ERIC_18453 Additional Site Assessment activities

This Task Assignment Change Order (TACO) reduces the cost of IDW disposal due to one IDW drum going missing from the site. Specific changes are detailed below:

Subtask 1: Project Management No changes associated with this subtask.

Subtask 2: Groundwater Sampling and Analyses No changes associated with this subtask.

Subtask 3: SAR Addendum Letter Report No changes associated with this subtask.

Subtask 4: IDW Disposal When Geosyntec traveled to the site to oversee the IDW pickup by the subcontractor, it was discovered that one IDW drum was missing from the site. This resulted in the reduction of costs for one IDW drum disposal plus handling fee. This change resulted in a cost actual decrease of ($137.50).

Summary The Department’s SRP Contract Manager and Geosyntec’s Contract Manager have both agreed to the above changes. All changes noted above represent a total overall cost decrease of ($137.50), as shown in the Cost Actual LOE. The changes were noted in the TACO Request received from Geosyntec on June 3, 2025. The final cost associated with this TA decreased from $9,732.29 to $9,594.79. Documentation of the changes is included in the attached TACO Request, the Delta LOE spreadsheet and the Cost Actual LOE spreadsheet, and the TACO form for BF02B C1 prepared by the Department.

FDEP COST ESTIMATEContractor: Geosyntec Consultants

Date: 6/3/2025

Task #: BF02B_TACO 1 Final SubTask 1 Project Management SubTask 6

Site: Jackson Square SubTask 2 Groundwater Sampling and Analysis SubTask 7

Activity/Phase: Additional GW sampling and SAR Add. SubTask 3 SAR Addendum Letter Report SubTask 8

Project Manager: K. Warner SubTask 4 IDW Disposal SubTask 9

SubTask 5 SubTask 10

TTotals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$80.14 PProject Manager Warner 4 4.1 $80.14 Principal Warner 10 2 8 0 0 0 0 0 0 0 $36.54 Senior Staff Professiona T. Barnett 29 11 15 3 0 0 0 0 0 0 $44.20 Project Professional M. Hensley 6 0 6 0 0 0 0 0 0 0 $42.32 Senior Engineering Tech K. Starling 8 8 0 0 0 0 0 0 0 0 $36.84 Admin Assist T. Hampton 1 0 1 0 0 0 0 0 0 0

Total Hours 64 4 21 36 3 0 0 0 0 0 0

Direct Labor $2,826.88 $325.22 $900.78 $1,491.26 $109.62 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 172.70% $4,882.02 $561.65 $1,555.65 $2,575.41 $189.31 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $7,708.90 $886.87 $2,456.43 $4,066.67 $298.93 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Travel Vehicle Rental $240.00 $120.00 $0.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $240.00 $120.00 $0.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) 0 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $210.00 $210.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $320.00 $320.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $415.00 $415.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $555.00 $555.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $8,823.90 $886.87 $3,451.43 $4,066.67 $418.93 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $770.89 $88.69 $245.64 $406.67 $29.89 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Cost Estimate Page 1 of 5 Cost Estimate

Final

Task #: BF02B_TACO 1 Final SubTask 1 Project Management SubTask 6

Site: Jackson Square SubTask 2 Groundwater Sampling and Analysis SubTask 7

Activity/Phase: Additional GW sampling and SAR Add. SubTask 3 SAR Addendum Letter Report SubTask 8

Project Manager: K. Warner SubTask 4 IDW Disposal SubTask 9

SubTask 5 SubTask 10

TTotals 1 2 3 4 5 6 7 8 9 10 TTotal Estimated Cost $9,594.79 $975.56 $3,697.07 $4,473.34 $448.82 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Cost from Prior CEF: Manual Entry Cost from Delta CEF; Manual Entry

Cost (Prior + Delta): $0.00 Auto-Calculated Rounding Error: $9,594.79 Auto-Calculated

FFinal Total Cost: $9,594.79 Auto-Calculated

Cost Estimate Page 2 of 5 Cost Estimate

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Jackson Square SUBTASK 2: Groundwater Sampling and Analysis

DATE: 6/3/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Principal K. Warner 2

Senior Staff Professional T. Barnett 11

Senior Engineering Technician K. Starling 8

TOTAL LABOR 21

VEHICLE TYPE RATE UNIT USEAGE

Truck $480.00 Week $0.00 Truck $120.00 Day 1 $120.00

Subtotal $120.00

TOTAL VEHICLE $120.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOCs $70.00 2 1 $210.00 VOHs $73.00 0 0 $0.00 VOAs $60.00 0 0 $0.00

RCRA-8 $14.00 0 0 $0.00

TOC $30.00 0 0 $0.00

TDS $16.00 0 0 $0.00

TRPH $88.00 0 0 $0.00

PFAS $315.00 0 0 $0.00

Subtotal $210.00 Fast Turnaround Charges Percent

24 Hours 110% $0.00 0 $0.00 3 Days 65% $0.00 0 $0.00 1 Week 20% $0.00 0 $0.00

Subtotal $0.00 Shipping

Large Cooler (25 to 50 lbs) $150.00 0 $0.00 Small Cooler (0 to 25 lbs) $110.00 1 $110.00

Subtotal $110.00

TOTAL LAB $320.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Drilling Related

Monitoring Well Installation Kit $325.00 Day 0 $0.00 Soil Assessment Kit $175.00 Day 0 $0.00 Soil Sampling Kit (Through Concrete) $235.00 Day 0 $0.00

Subtotal $0.00 Analytical Related

$1,660.00 Week 0 $0.00

$415.00 Day 1 $415.00 YSI 556 MPS $105.00 Day 0 $0.00

Subtotal $415.00 IDW Related

Drum $100.00 Drum 1 $100.00 Subtotal $100.00

Expendables $40.00 Day 1 $40.00

Subtotal $40.00

Other $0.00 Day 0 $0.00

Subtotal $0.00

TOTAL EQUIPMENT $555.00

Deep Groundwater Sampling Kit

Deep Groundwater Sampling Kit

Complete pre-field work and field preparation activities (1 hr). Round trip mobilization from Tallahassee to Marianna (2hr). Collect depth-to-water measurements, 2 monitoring well samples, and manage IDW 5 hr.

Field Staff Prepation and Data review

Complete pre-field work and field preparation activities (2 hr). Round trip mobilization from Tallahassee to Marianna (2hr). Collect depth-to-water measurements, 2 monitoring well samples, and manage IDW 5 hr. Finalize and organize field notes (2 hr).

6/10/2025 Page 3 of 5 Subtask 2

SUBTASK 3: SAR Addendum Letter Report

DATE: 6/3/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Principal K. Warner 8

Professional M. Hensley 6

Senior Staff Professional T. Barnett 15

Project Professional M. Hensley 6

Administrative Assistant T. Hampton 1

TOTAL LABOR 36

Preparing and Revising Figures

Senior level revew and P.G. approval

Preparing and revising Figures

Data tabulation, Figures development, and Letter Report Prepartion

6/10/2025 Page 4 of 5 Subtask 3

SUBTASK 4: IDW Disposal

DATE: 6/3/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Staff Professional T. Barnett 3

TOTAL LABOR 3

VEHICLE TYPE RATE UNIT USEAGE

Car $80.00 Day 0 $0.00 Truck $120.00 Day 1 $120.00 Van $120.00 Day 0 $0.00

Subtotal $120.00

Mileage $0.59 Mile 0 $0.00 Subtotal $0.00

Air Fare $0.00 Round Trip 0 $0.00 Subtotal $0.00

TOTAL VEHICLE $120.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

IDW

Erwin Remediation 1 drum @ $125/drum - Minus one drum disposal ($125.00) $0.00 $0.00 $0.00

Subtotal $0.00

TOTAL SUB $0.00

Mobilize to site (2 hours), IDW oversite/handling (3 hours)

6/10/2025 Page 5 of 5 Subtask 4

Task #: BF02B_TACO 1 DELTA SubTask 1 Project Management SubTask 6

Site: Jackson Square SubTask 2 Groundwater Sampling and Analysis SubTask 7

Activity/Phase: Additional GW sampling and SAR Add. SubTask 3 SAR Addendum Letter Report SubTask 8

Project Manager: K. Warner SubTask 4 IDW Disposal SubTask 9

SubTask 5 SubTask 10

TTotals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$80.14 PProject Manager Warner 0 0.0 $80.14 Principal Warner 0 0 0 0 0 0 0 0 0 0 $36.54 Senior Staff Professiona T. Barnett 0 0 0 0 0 0 0 0 0 0 $44.20 Project Professional M. Hensley 0 0 0 0 0 0 0 0 0 0 $42.32 Senior Engineering Tech K. Starling 0 0 0 0 0 0 0 0 0 0 $36.84 Admin Assist T. Hampton 0 0 0 0 0 0 0 0 0 0

Total Hours 0 0 0 0 0 0 0 0 0 0 0

Direct Labor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 172.70% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Travel Vehicle Rental $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) 0 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW ($125.00) $0.00 $0.00 ($125.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal ($125.00) $0.00 $0.00 ($125.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee ($12.50) $0.00 $0.00 ($12.50) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost ($137.50) $0.00 $0.00 ($137.50) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal ($137.50) $0.00 $0.00 $0.00 ($137.50) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Cost Estimate Page 1 of 3 Cost Estimate

Delta

Task #: BF02B_TACO 1 DELTA SubTask 1 Project Management SubTask 6

Site: Jackson Square SubTask 2 Groundwater Sampling and Analysis SubTask 7

Activity/Phase: Additional GW sampling and SAR Add. SubTask 3 SAR Addendum Letter Report SubTask 8

Project Manager: K. Warner SubTask 4 IDW Disposal SubTask 9

SubTask 5 SubTask 10

TTotals 1 2 3 4 5 6 7 8 9 10 TTotal Estimated Cost ($137.50) $0.00 $0.00 $0.00 ($137.50) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Cost from Prior CEF: Manual Entry Cost from Delta CEF; Manual Entry

Cost (Prior + Delta): $0.00 Auto-Calculated Rounding Error: ($137.50) Auto-Calculated

FFinal Total Cost: ($137.50) Auto-Calculated

Cost Estimate Page 2 of 3 Cost Estimate

SUBTASK 4: IDW Disposal

DATE: 6/3/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Staff Professional T. Barnett 0

TOTAL LABOR 0

VEHICLE TYPE RATE UNIT USEAGE

Car $80.00 Day 0 $0.00 Truck $120.00 Day 0 $0.00 Van $120.00 Day 0 $0.00

Subtotal $0.00

Mileage $0.59 Mile 0 $0.00 Subtotal $0.00

Air Fare $0.00 Round Trip 0 $0.00 Subtotal $0.00

TOTAL VEHICLE $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

IDW

Erwin Remediation 1 drum @ $125/drum $0.00 ($125.00) $0.00 $0.00

Subtotal ($125.00)

TOTAL SUB ($125.00)

6/10/2025 Page 3 of 3 Subtask 4

Date: 2/6/2025

Task #: BF02B_TACO 1 Origina SubTask 1 Project Management SubTask 6

Site: Jackson Square SubTask 2 Groundwater Sampling and Analysis SubTask 7

Activity/Phase: Additional GW sampling and SAR Add. SubTask 3 SAR Addendum Letter Report SubTask 8

Project Manager: K. Warner SubTask 4 IDW Disposal SubTask 9

SubTask 5 SubTask 10

TTotals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$80.14 PProject Manager Warner 4 4.1 $80.14 Principal Warner 10 2 8 0 0 0 0 0 0 0 $36.54 Senior Staff Professiona T. Barnett 29 11 15 3 0 0 0 0 0 0 $44.20 Project Professional M. Hensley 6 0 6 0 0 0 0 0 0 0 $42.32 Senior Engineering Tech K. Starling 8 8 0 0 0 0 0 0 0 0 $36.84 Admin Assist T. Hampton 1 0 1 0 0 0 0 0 0 0

Total Hours 64 4 21 36 3 0 0 0 0 0 0

Direct Labor $2,826.88 $325.22 $900.78 $1,491.26 $109.62 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 172.70% $4,882.02 $561.65 $1,555.65 $2,575.41 $189.31 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $7,708.90 $886.87 $2,456.43 $4,066.67 $298.93 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Travel Vehicle Rental $240.00 $120.00 $0.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $240.00 $120.00 $0.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) 0 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $125.00 $0.00 $0.00 $125.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $125.00 $0.00 $0.00 $125.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $12.50 $0.00 $0.00 $12.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $137.50 $0.00 $0.00 $137.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $210.00 $210.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $320.00 $320.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $415.00 $415.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $555.00 $555.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $8,961.40 $886.87 $3,451.43 $4,066.67 $556.43 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $770.89 $88.69 $245.64 $406.67 $29.89 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Cost Estimate Page 1 of 5 Cost Estimate

Original

Date: 2/6/2025

Task #: BF02B_TACO 1 Origina SubTask 1 Project Management SubTask 6

Site: Jackson Square SubTask 2 Groundwater Sampling and Analysis SubTask 7

Activity/Phase: Additional GW sampling and SAR Add. SubTask 3 SAR Addendum Letter Report SubTask 8

Project Manager: K. Warner SubTask 4 IDW Disposal SubTask 9

SubTask 5 SubTask 10

TTotals 1 2 3 4 5 6 7 8 9 10 TTotal Estimated Cost $9,732.29 $975.56 $3,697.07 $4,473.34 $586.32 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Cost from Prior CEF: Manual Entry Cost from Delta CEF; Manual Entry

Cost (Prior + Delta): $0.00 Auto-Calculated Rounding Error: $9,732.29 Auto-Calculated

FFinal Total Cost: $9,732.29 Auto-Calculated

Cost Estimate Page 2 of 5 Cost Estimate

SUBTASK 2: Groundwater Sampling and Analysis

DATE: 2/6/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Principal K. Warner 2

Senior Staff Professional T. Barnett 11

Senior Engineering Technician K. Starling 8

TOTAL LABOR 21

VEHICLE TYPE RATE UNIT USEAGE

Truck $480.00 Week $0.00 Truck $120.00 Day 1 $120.00

Subtotal $120.00

TOTAL VEHICLE $120.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOCs $70.00 2 1 $210.00 VOHs $73.00 0 0 $0.00 VOAs $60.00 0 0 $0.00

RCRA-8 $14.00 0 0 $0.00

TOC $30.00 0 0 $0.00

TDS $16.00 0 0 $0.00

TRPH $88.00 0 0 $0.00

PFAS $315.00 0 0 $0.00

Subtotal $210.00 Fast Turnaround Charges Percent

24 Hours 110% $0.00 0 $0.00 3 Days 65% $0.00 0 $0.00 1 Week 20% $0.00 0 $0.00

Subtotal $0.00 Shipping

Large Cooler (25 to 50 lbs) $150.00 0 $0.00 Small Cooler (0 to 25 lbs) $110.00 1 $110.00

Subtotal $110.00

TOTAL LAB $320.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Drilling Related

Monitoring Well Installation Kit $325.00 Day 0 $0.00 Soil Assessment Kit $175.00 Day 0 $0.00 Soil Sampling Kit (Through Concrete) $235.00 Day 0 $0.00

Subtotal $0.00 Analytical Related

$1,660.00 Week 0 $0.00

$415.00 Day 1 $415.00 YSI 556 MPS $105.00 Day 0 $0.00

Subtotal $415.00 IDW Related

Drum $100.00 Drum 1 $100.00 Subtotal $100.00

Expendables $40.00 Day 1 $40.00

Subtotal $40.00

Other $0.00 Day 0 $0.00

Subtotal $0.00

TOTAL EQUIPMENT $555.00

Deep Groundwater Sampling Kit

Deep Groundwater Sampling Kit

Complete pre-field work and field preparation activities (1 hr). Round trip mobilization from Tallahassee to Marianna (2hr). Collect depth-to-water measurements, 2 monitoring well samples, and manage IDW 5 hr.

Field Staff Prepation and Data review

Complete pre-field work and field preparation activities (2 hr). Round trip mobilization from Tallahassee to Marianna (2hr). Collect depth-to-water measurements, 2 monitoring well samples, and manage IDW 5 hr. Finalize and organize field notes (2 hr).

6/10/2025 Page 3 of 5 Subtask 2

SUBTASK 3: SAR Addendum Letter Report

DATE: 2/6/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Principal K. Warner 8

Professional M. Hensley 6

Senior Staff Professional T. Barnett 15

Project Professional M. Hensley 6

Administrative Assistant T. Hampton 1

TOTAL LABOR 36

Preparing and Revising Figures

Senior level revew and P.G. approval

Preparing and revising Figures

Data tabulation, Figures development, and Letter Report Prepartion

6/10/2025 Page 4 of 5 Subtask 3

SUBTASK 4: IDW Disposal

DATE: 2/6/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Staff Professional T. Barnett 3

TOTAL LABOR 3

VEHICLE TYPE RATE UNIT USEAGE

Car $80.00 Day 0 $0.00 Truck $120.00 Day 1 $120.00 Van $120.00 Day 0 $0.00

Subtotal $120.00

Mileage $0.59 Mile 0 $0.00 Subtotal $0.00

Air Fare $0.00 Round Trip 0 $0.00 Subtotal $0.00

TOTAL VEHICLE $120.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

IDW

Erwin Remediation 1 drum @ $125/drum $125.00 $125.00 $0.00 $0.00

Subtotal $125.00

TOTAL SUB $125.00

6/10/2025 Page 5 of 5 Subtask 4

From: Joseph L. Applegate To: Johnson, Megan R Cc: Kevin M. Warner Subject: TACO 1 - Jackson Square Date: Tuesday, June 3, 2025 9:25:59 AM Attachments: HW683 Cost Estimate Form Jackson Square_TACO 1_Original.xlsx

HW683 Cost Estimate Form Jackson Square_TACO 1_DELTA.xlsx HW683 Cost Estimate Form Jackson Square_TACO 1_Final_6_3_2025.xlsx

EXTERNAL MESSAGE

This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.

Hi Megan, Please find attached 3 files; the original LOE, the DELTA, and the Final TACO 1 excel files. We checked the lab invoice and other items and the only thing that changes was for the disposal of one IDW drum which went missing (minus $125 plus markup which came out to be minus $137.50).

Let us know if this is good and depending on timing of report approval (hopefully ) we can at least invoice Subtask 2 and 4.

Thank you, Joe and Kevin

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

Additional signatures attached on separate page.

HW683

BF02B Completion June 27, 2025

Geosyntec Consultants, Inc. will perform groundwater sampling at the below project site and prepare a SAR Addendum Letter Report in accordance with the Cost Proposal and Level of Effort (LOE) submitted on February 10, 2025.

Megan Johnson 850.245.8994 Contractor Geosyntec Consultants, Inc. Contractor

Contractor Kevin Warner Contractor 850.528.2269

ERIC_18453

4154 Lafayette Street, Marianna, Jackson County, Florida

Jackson Square

Contractor Contractor

✔ $ 9,732.29

$ 9,732.29

Scope of Work

Geosyntec Consultants, Inc.

Contractor Joseph Applegate, P.G.

Senior Principal Hydrogeologist

Joseph Applegate Digitally signed by Joseph Applegate Date: 2025.02.17 11:47:01 -05'00'

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2025.02.17 10:11:28 -05'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WC TAFORM

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Field forms and lab reports 04/15/2025

IDW Disposal Confirmation 06/01/2025

SAR Addendum Letter Report; Project Management 05/15/2025

Department approval of field forms and lab reports (Subtask 2) $ 3,697.07

Department approval of IDW Disposal Confirmation (Subtask 4) $ 586.32

Department approval of Project Management and SAR Addendum Letter Report (Subtasks 1 and 3) $ 5,448.90

$ 9,732.29