Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW683
DC032A Completion April 30, 2024
This Task Assignment authorizes Geosyntec to conduct for soil gas and groundwater monitoring activities at the Former Coles Cleaners Site in accordance with the Geosyntec scope of work, cost estimate, and schedule received on March 14, 2023.
Brittany Plyler 850-245-8851 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Geosyntec
Geosyntec
Blaine Dawson 904-450-4271
ERIC_4608
791 3rd Street N Jacksonville Beach, Duval County, Florida
Former Coles Cleaners
✔ $ 39,985.52
$ 39,985.52
Scope of Work
Todd Kafka
Contract Manager
Todd Kafka, P.G. Digitally signed by Todd Kafka, P.G.
Date: 2023.03.24 09:02:34 -04'00'
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2023.03.23 11:46:30 -04'00'
N/A
Murphy_SL Highlight
Murphy_SL Highlight
Murphy_SL Highlight
Murphy_SL Highlight
Murphy_SL Highlight
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Subtask 2: Field Deliverable for Q1 Groundwater Sampling and IDW Manifest 05/30/2023
Subtask 3: Field Deliverable for Q2 Groundwater Sampling and IDW Manifest 08/31/2023
Subtask 4: Field Deliverable for Q3 Groundwater Sampling and IDW Manifest 11/30/2023
Subtask 5: Field Deliverable for Q4 Groundwater Sampling and IDW Manifest 02/28/2024
Subtask 1 & 6: Groundwater Monitoring Report; Project Management 03/31/2024
Subtask 2: Submittal and FDEP approval of the Field Deliverable for Q1 Groundwater Sampling and IDW Manifest $ 3,913.17
Subtask 3: Submittal and FDEP approval of the Field Deliverable for Q2 Groundwater Sampling and IDW Manifest $ 8,919.62
Subtask 4:Submittal and FDEP approval of the Field Deliverable for Q3 Groundwater Sampling and IDW Manifest $ 3,606.70
Subtask 5: Submittal and FDEP approval of the Field Deliverable for Q4 Groundwater Sampling and IDW Manifest $ 15,188.12
Subtask 1 & 6: Submittal and FDEP approval of the Groundwater Monitoring Report;
Project Management $ 8,357.91
$ 39,985.52
HW683
DC032A
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
To: HW683 Contract Negotiation File Former Coles Cleaners Duval County, Florida
ERIC_4608
From: Brittany Plyler, Project Manager Date: March 22, 2023 Subject: Negotiation Summary
HW683_DC032A
This Task Assignment authorizes Geosyntec to conduct for soil gas and groundwater monitoring activities at the Former Coles Cleaners Site in accordance with the Geosyntec scope of work, cost estimate, and schedule received on March 14, 2023.
Geosyntec confirmed on March 14, 2023, that Subtask 1 consists of the calculated project management labor, based upon 13% of the direct labor costs in this proposal, and includes fringe, overhead, other direct costs (ODCs) and completion fees.
Subtask 2: Cost include obtaining a new site access agreement and Quarter 1 groundwater monitoring which is scheduled for March 2023. The samples will be stored on ice and shipped to the analytical laboratory.
Subtask 3: Quarter 2 groundwater and soil gas monitoring is scheduled for June 2023. Soil gas monitoring will also be conducted to assess potential methane and hydrogen sulfide generation beneath the former dry-cleaning building. Air samples will be collected from SGP01, SGP02, and the soil vent fan (SV1) and screened for methane, oxygen, and hydrogen sulfide using a multi-RAE. The samples will be stored on ice and shipped to the analytical laboratory.
Subtask 4: Quarter 3 groundwater monitoring is tentatively scheduled for September 2023. The samples will be stored on ice and shipped to the analytical laboratory.
Subtask 5: Quarter 4 groundwater monitoring is tentatively scheduled for December 2023. The samples will be stored on ice and shipped to the analytical laboratory.
Subtask 6: Geosyntec will prepare an Annual Groundwater Monitoring Report documenting the results of the depth to groundwater measurements and groundwater analytical results during the groundwater monitoring events (Q1 through Q4).
The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost for this Task Assignment is $39,985.52 with 219 labor hours.
Printed on recycled paper.
FDEP COST ESTI MATEContractor: Geosyntec Consultants
Date: 3/13/2023
Task #: SubTask 1 Project Management SubTask 6 Groundwater Monitoring Report
Site: Former Coles Cleaners SubTask 2 Q1 Quarterly Monitoring SubTask 7
Activity/Phase: Monitoring SubTask 3 Q2 Semi-Annual Monitoring SubTask 8
Project Manager: B. Dawson SubTask 4 Q3 Quarterly Monitoring SubTask 9
SubTask 5 Q4 Annual Monitoring SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$49.76 Project Manager B. Dawson 18 18.1 $76.92 Principal T. Kafka 2 0 0 0 0 2 0 0 0 0 $49.76 Project Professional B. Dawson 24 4 5 4 5 6 0 0 0 0 $48.56 Project Professional M. Hensley 10 0 0 0 0 10 0 0 0 0 $36.30 Senior Staff Professiona G. Summers 17 17 0 0 0 0 0 0 0 0 $30.29 Staff Professional D. McGill 147 0 41 17 59 30 0 0 0 0 $37.26 Administrative Assistant P. Gallagher 1 0 0 0 0 1 0 0 0 0
Total Hours 219 18 21 46 21 64 49 0 0 0 0
Direct Labor $7,842.96 $902.29 $816.14 $1,490.69 $713.97 $2,035.91 $1,883.96 $0.00 $0.00 $0.00 $0.00
Overhead 172.70% $13,544.79 $1,558.25 $1,409.47 $2,574.42 $1,233.03 $3,516.02 $3,253.60 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $21,387.75 $2,460.54 $2,225.61 $4,065.11 $1,947.00 $5,551.93 $5,137.56 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $1,080.00 $120.00 $360.00 $120.00 $480.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $1,080.00 $120.00 $360.00 $120.00 $480.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cost Estimate Page 1 of 7 Cost Estimate
FDEP COST ESTI MATEContractor: Geosyntec Consultants
Date: 3/13/2023
Task #: SubTask 1 Project Management SubTask 6 Groundwater Monitoring Report
Site: Former Coles Cleaners SubTask 2 Q1 Quarterly Monitoring SubTask 7
Activity/Phase: Monitoring SubTask 3 Q2 Semi-Annual Monitoring SubTask 8
Project Manager: B. Dawson SubTask 4 Q3 Quarterly Monitoring SubTask 9
SubTask 5 Q4 Annual Monitoring SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Subcontractor (Services Procurement)
Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $800.00 $200.00 $200.00 $200.00 $200.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $800.00 $200.00 $200.00 $200.00 $200.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $80.00 $20.00 $20.00 $20.00 $20.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $880.00 $220.00 $220.00 $220.00 $220.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $9,009.00 $545.00 $2,038.00 $545.00 $5,881.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $1,500.00 $150.00 $450.00 $150.00 $750.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $10,509.00 $695.00 $2,488.00 $695.00 $6,631.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $400.00 $40.00 $120.00 $40.00 $200.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $3,190.00 $290.00 $1,160.00 $290.00 $1,450.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $400.00 $100.00 $100.00 $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $3,990.00 $430.00 $1,380.00 $430.00 $1,750.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $37,846.75 $2,460.54 $3,690.61 $8,513.11 $3,412.00 $14,632.93 $5,137.56 $0.00 $0.00 $0.00 $0.00 Completion Fee $2,138.77 $246.05 $222.56 $406.51 $194.70 $555.19 $513.76 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $39,985.52 $2,706.59 $3,913.17 $8,919.62 $3,606.70 $15,188.12 $5,651.32 $0.00 $0.00 $0.00 $0.00
Labor Expenses Subtask 2 $3,913.17 $2,448.17 $1,465.00 Subtask 3 $8,919.62 $4,471.62 $4,448.00 Subtask 4 $3,606.70 $2,141.70 $1,465.00 Subtask 5 $15,188.12 $6,107.12 $9,081.00 Subtask 1, 6 $8,357.91 $8,357.91 $0.00
$39,985.52 $23,526.52 $16,459.00 $39,985.52
Cost Estimate Page 2 of 7 Cost Estimate
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Former Coles Cleaners SUBTASK: Q1 Quarterly Monitoring
DATE: 3/13/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Professional B. Dawson 4
Senior Staff Professional G. Summers
TOTAL LABOR 21
VEHICLE TYPE RATE UNIT USEAGE
Truck $120.00 Day 1 $120.00 Subtotal $120.00
TOTAL VEHICLE $120.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
IDW
Hulls $200.00 $200.00
Subtotal $200.00
TOTAL SUB $200.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOHs IDW $73.00 1 0 $73.00 Sodium $14.00 4 0 $56.00
TDS $16.00 4 0 $64.00
TRPH $88.00 4 0 $352.00
Subtotal $545.00 Shipping
Large Cooler (25 to 50 lbs) $150.00 1 $150.00 Subtotal $150.00
TOTAL LAB $695.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Analytical Related
Groundwater Sampling Kit $290.00 Day 1 $290.00 Subtotal $290.00
IDW Related Drum $100.00 Drum 1 $100.00
Subtotal $100.00 Expendables
$40.00 Day 1 $40.00 Subtotal $40.00
TOTAL EQUIPMENT $430.00
RPO and tenant notifications (1); evaluate field data (1); prepare field package and UIC sampling letter (1); prepare and sign IDW manifest (1)
Field prep (1); Mob/demob (4 hr rount trip to Jax + 2 hr/day x 1 day = 6 hr); calibrate sampling equipment (1 days @ 0.5 hr/day - 1); groundwater sampling (4 wells @ 1.5 hr/well - 6); sample management (1); IDW management (1); Update data tables (2);
Prepare field package and UIC sampling letter (2);
3/21/2023 Page 3 of 7 Subtask 2
SUBTASK: Q2 Semi-Annual Monitoring
DATE: 3/13/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Professional B. Dawson 5
Staff Professional D. McGill
TOTAL LABOR 46
VEHICLE TYPE RATE UNIT USEAGE
Truck $120.00 Day 3 $360.00 Subtotal $360.00
TOTAL VEHICLE $360.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
IDW
Hulls $200.00 $200.00
Subtotal $200.00
TOTAL SUB $200.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOHs 11 wells + 1 IDW $73.00 12 0 $876.00 Sodium $14.00 4 0 $56.00
TOC $30.00 11 0 $330.00
TDS $16.00 4 0 $64.00
TRPH $88.00 4 0 $352.00
MEE $180.00 2 0 $360.00
Subtotal $2,038.00 Shipping
Large Cooler (25 to 50 lbs) $150.00 3 $450.00 Subtotal $450.00
TOTAL LAB $2,488.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Analytical Related
Groundwater Sampling Kit $290.00 Day 3 $870.00 Soil Vapor Sampling Kit $290.00 Day 1 $290.00
Subtotal $1,160.00 IDW Related
Drum $100.00 Drum 1 $100.00 Subtotal $100.00
Expendables $40.00 Day 3 $120.00
Subtotal $120.00
TOTAL EQUIPMENT $1,380.00
RPO and tenant notifications (1); evaluate field data (2); prepare field package and UIC sampling letter (1); prepare and sign IDW manifest (1)
Field prep (1); Mob/demob (2 hr/day x 3 day = 6 hr); calibrate sampling equipment (3 days @ 0.5 hr/day - 2); collect water level measurements from MWs not sampled on first day (3); groundwater sampling (13 wells @ 1.5 hr/well - 20); perform soil gas screening @ 1 hr/probe (3); sample management (1); IDW management (1); Update data tables (2);
3/21/2023 Page 4 of 7 Subtask 3
SUBTASK: Q3 Quarterly Monitoring
DATE: 3/13/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Professional B. Dawson 4
Staff Professional
D. McGill 17
TOTAL LABOR 21
VEHICLE TYPE RATE UNIT USEAGE
Truck $120.00 Day 1 $120.00 Subtotal $120.00
TOTAL VEHICLE $120.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
IDW
Hulls $200.00 $200.00
Subtotal $200.00
TOTAL SUB $200.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOHs IDW $73.00 1 0 $73.00 Sodium $14.00 4 0 $56.00
TDS $16.00 4 0 $64.00
TRPH $88.00 4 0 $352.00
Subtotal $545.00 Shipping
Large Cooler (25 to 50 lbs) $150.00 1 $150.00 Subtotal $150.00
TOTAL LAB $695.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Analytical Related
Groundwater Sampling Kit $290.00 Day 1 $290.00 Subtotal $290.00
IDW Related Drum $100.00 Drum 1 $100.00
Subtotal $100.00 Expendables
$40.00 Day 1 $40.00 Subtotal $40.00
TOTAL EQUIPMENT $430.00
RPO and tenant notifications (1); evaluate field data (1); prepare field package and UIC sampling letter (1); prepare and sign IDW manifest (1)
Field prep (1); Mob/demob (4 hr rount trip to Jax + 2 hr/day x 1 day = 6 hr); calibrate sampling equipment (1 days @ 0.5 hr/day - 1); groundwater sampling (4 wells @ 1.5 hr/well - 6); sample management (1); IDW management (1); Update data tables (2);
3/21/2023 Page 5 of 7 Subtask 4
SUBTASK: Q4 Annual Monitoring
DATE: 3/13/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Professional B. Dawson 5
Staff Professional D. McGill
TOTAL LABOR 64
VEHICLE TYPE RATE UNIT USEAGE
Truck $480.00 Week 1 $480.00 Subtotal $480.00
TOTAL VEHICLE $480.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
IDW
Hulls $200.00 $200.00
Subtotal $200.00
TOTAL SUB $200.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOHs 22 wells + 1 IDW $73.00 23 0 $1,679.00 Sodium $14.00 4 0 $56.00
TOC $30.00 11 0 $330.00
TDS $16.00 4 0 $64.00
TRPH $88.00 4 0 $352.00
MEE $180.00 11 0 $1,980.00
Sirem Dhc $270.00 4 0 $1,080.00 Sirem vcra $85.00 4 0 $340.00
Subtotal $5,881.00 Shipping
Large Cooler (25 to 50 lbs) $150.00 5 $750.00 Subtotal $750.00
TOTAL LAB $6,631.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Analytical Related
Groundwater Sampling Kit $1,160.00 Week 1 $1,160.00 Soil Vapor Sampling Kit $290.00 Day 1 $290.00
Subtotal $1,450.00 IDW Related
Drum $100.00 Drum 1 $100.00 Subtotal $100.00
Expendables $40.00 Day 5 $200.00
Subtotal $200.00
TOTAL EQUIPMENT $1,750.00
RPO and tenant notifications (1); evaluate field data (2); prepare field package and UIC sampling letter (1); prepare and sign IDW manifest (1)
Field prep (1); Mob/demob (2 hr/day x 5 day = 10 hr); calibrate sampling equipment (5 days @ 0.5 hr/day - 3); collect water level measurements from MWs not sampled on first day (3); groundwater sampling (22 wells @ 1.5 hr/well - 33); perform soil gas screening @ 1 hr/probe (3); sample management (1); IDW management (1); Update data tables (2);
3/21/2023 Page 6 of 7 Subtask 5
SUBTASK: Groundwater Monitoring Report
DATE: 3/13/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Principal T. Kafka 2
Project Professional M. Hensley 10
Project Professional B. Dawson 6
Staff Professional D. McGill 30
Administrative Assistant P. Gallagher 1
TOTAL LABOR 49
Report formatting and PDF compilation
Develop recommendations and path forward
Updating of GMR figures (inclusive of each quarter, semi-annual, and annual sampling event)
GMR preparation and PG seal
GMR Preparation (inclusive of each quarter, semi-annual, and annual sampling event)
3/21/2023 Page 7 of 7 Subtask 6
Coles Cleaners_HW683 SOW_2023 Monitoring 1
1200 Riverplace Boulevard, Suite 710 Jacksonville, Florida 32207
PH 904.858.1818
FAX 904.396.1143
www.geosyntec.com
14 March 2023
Ms. Brittany Plyler Florida Department of Environmental Protection 2600 Blair Stone Road Tallahassee, FL 32399-2400
Subject: Scope of Work and CEF/LOE – Groundwater Monitoring Former Coles Cleaners 791 3rd Street N Jacksonville Beach, Duval County, Florida FDEP Facility ID ERIC_4608
Dear Ms. Plyler, Geosyntec Consultants, Inc. (Geosyntec) has prepared this statement of work (SOW), Cost Estimate Form (CEF), and Level of Effort (LOE) for soil gas and groundwater monitoring activities at the Former Coles Cleaners Site (Site) located in Jacksonville Beach, Florida. This below described assessment activities are in accordance with the recommendations presented in the January 2023 Annual Groundwater Monitoring Report (GMR).
On 7 October 2022, Geosyntec identified that a Site Access Agreement was executed with the real property owner (David W. Cole) on 29 November 2004, for the Former Coles Cleaners Site (ERIC_4608). On 5 November 2005, Mr. Cole and his wife, Emma I. Cole, sold the property for $1.00 to No. 3 Commercial, LLC; however, there is no access agreement with this entity, although Geosyntec has been interfacing with Mr. Cole regarding access and notifications since our first involvement in 2015. Subtask 2 includes effort to coordinate and obtain a current, signed access agreement for the subject Site.
Subtask 1 – Project Management
Subtask 2 – Q1 Quarterly Monitoring: Quarter 1 groundwater (UIC and performance) monitoring is tentatively scheduled for March 2023 and will be completed in accordance with Table 1.
The samples will be stored on ice and shipped to the analytical laboratory under chain of custody for analysis under standard turnaround times. Groundwater sampling logs, updated groundwater analytical data tables, and a one-page UIC sampling letter will be submitted to FDEP to document the field work for invoicing.
Coles Cleaners_HW683 SOW_2023 Monitoring
Purge water generated during sampling activities will be placed in a 55-gallon drum and manifested for off-site disposal. IDW will be staged in the rear of the facility. To confirm compliance with the existing non-hazardous IDW groundwater profile with the selected IDW waste hauler (Hull’s Environmental Services), an IDW groundwater sample will be collected for VOHs via EPA Method 8260 from the purge water drum.
Subtask 3 – Q2 Semi-Annual Monitoring: Quarter 2 groundwater (UIC and performance) and soil gas monitoring is scheduled for June 2023 and will be completed in accordance with Table 1.
Consistent with previous sampling events, groundwater level measurements will be collected within a 24-hour period from 22 monitoring wells on the first day of field activities.
The samples will be stored on ice and shipped to the analytical laboratory under chain of custody for analysis under standard turnaround times. Groundwater sampling logs, updated groundwater analytical data tables, and a one-page UIC sampling letter will be submitted to FDEP to document the field work for invoicing.
Soil gas monitoring will also be conducted to assess potential methane and hydrogen sulfide generation beneath the former dry-cleaning building. Air samples will be collected from SGP01, SGP02, and the soil vent fan (SV1) and screened for methane, oxygen, and hydrogen sulfide using a multi-RAE.
Purge water generated during sampling activities will be placed in a 55-gallon drum and manifested for off-site disposal. IDW will be staged in the rear of the facility. To confirm compliance with the existing non-hazardous IDW groundwater profile with the selected IDW waste hauler (Hull’s Environmental Services), an IDW groundwater sample will be collected for VOHs via EPA Method 8260 from the purge water drum.
Subtask 4 – Q3 Quarterly Monitoring: Quarter 1 groundwater (UIC and performance) monitoring is tentatively scheduled for September 2023 and will be completed in accordance with Table 1.
The samples will be stored on ice and shipped to the analytical laboratory under chain of custody for analysis under standard turnaround times. Groundwater sampling logs, updated groundwater analytical data tables, and a one-page UIC sampling letter will be submitted to FDEP to document the field work for invoicing.
Purge water generated during sampling activities will be placed in a 55-gallon drum and manifested for off-site disposal. IDW will be staged in the rear of the facility. To confirm compliance with the existing non-hazardous IDW groundwater profile with the selected IDW
Coles Cleaners_HW683 SOW_2023 Monitoring waste hauler (Hull’s Environmental Services), an IDW groundwater sample will be collected for VOHs via EPA Method 8260 from the purge water drum.
Subtask 5 – Quarter 4 Annual Monitoring: Quarter 4 groundwater (UIC and performance) monitoring is tentatively scheduled for December 2023 and will be completed in accordance with Table 1. Note that the annual monitoring event includes microbial analyses performed by a specialty analytical laboratory, SiREM; their quote is attached.
The samples will be stored on ice and shipped to the analytical laboratory under chain of custody for analysis under standard turnaround times. Groundwater sampling logs, updated groundwater analytical data tables, and a one-page UIC sampling letter will be submitted to FDEP to document the field work for invoicing.
Soil gas monitoring will also be conducted to assess potential methane and hydrogen sulfide generation beneath the former dry-cleaning building. Air samples will be collected from SGP-1, SGP-2, and SV-1 (soil vent fan) and screened for methane, oxygen, and hydrogen sulfide using a multi-RAE.
Purge water generated during sampling activities will be placed in a 55-gallon drum and manifested for off-site disposal. IDW will be staged in the rear of the facility. To confirm compliance with the existing non-hazardous IDW groundwater profile with the selected IDW waste hauler (Hull’s Environmental Services), an IDW groundwater sample will be collected for VOHs via EPA Method 8260 from the purge water drum.
Subtask 6 – Groundwater Monitoring Report: Geosyntec will prepare an Annual Groundwater Monitoring Report documenting the results of the depth to groundwater measurements and groundwater analytical results. The report will contain tables summarizing field/laboratory groundwater data, figures showing groundwater flow direction(s), and a summary of the groundwater monitoring events (Q1 through Q4).
Coles Cleaners_HW683 SOW_2023 Monitoring
Invoice and Deliverable Schedule:
Subtask Deliverable Deliverable Date Invoice Amount
Field Deliverable for Q1 Groundwater Sampling and IDW Manifest
5 May 2023 $3,913.17
Field Deliverable for Q2 Groundwater Sampling and IDW Manifest
4 August 2023 $8,919.62
Field Deliverable for Q3 Groundwater Sampling and IDW Manifest
3 November 2023 $3,606.70
Field Deliverable for Q4 Groundwater Sampling and IDW Manifest
2 February 2024 $15,188.12
1, 6 Groundwater Monitoring Report 15 March 2024 $8,357.91
Total $39,985.52
As always, it is a pleasure to work with the FDEP. If you require any additional information or have any questions, please contact Blaine Dawson at 904.450.4271.
Sincerely, Blaine Dawson, P.G.
Project Geologist
Todd K. Kafka, P.G.
Senior Principal Hydrogeologist
Copies to: Rachel Klinger, Geosyntec
Attachments: Attachment A – CEF/LOE
Attachment B – IDW Quotes
Florida Department of Environmental Protection -- Waste Site Cleanup Section
TABLE 7: PROPOSED MONITORING WELL SAMPLING PLAN
Facility Name: Former Coles Cleaners
ERIC_4608
VOCs by EPA method
8260B
TOC by EPA method
415.1
TRPH by FL-
PRO
TDS by EPA method 160.1
Sodium by EPA method
200.7
Dissolved Gases by
RSK-175
Soil Gas Screening
Microbial Dhc/vcrA
MW021 (downgradient UIC) X X X
MW022 (downgradient UIC) X X X
MW026 (source UIC) X X X
MW028 (source UIC) X X X
MW001, MW002, MW021 through
MW029
X X
MW014 & MW015 X
SGP01, SGP02, SV1 X
MW001, MW002, MW008-MW010,
MW017, MW021-MW034, MW036,
MW037
X
MW022, MW024, MW028, MW029 X X
MW021, MW023, MW025, MW026,
MW027
X
Notes:
1. VOC = volatile organic compound.
2. Dissolved gases = methane, ethene, and ethane.
3. TOC = total organic carbon.
4. TRPH = total recoverable petroleum hydrocarbons.
5. TDS = total dissolved solids.
7. UIC monitoring will continue on a quarterly basis until all pertinent parameters are below the applicable standards or the baseline values.
8. Dhc = Dehalococcoides.
9. vcrA = vinyl chloride reductase.
Post-Injection Quarterly (Year 4)
6. Underground injection control (UIC) monitoring includes TRPH, sodium, and TDS.
Post-Injection Semi-Annual
(Year 4)
Sampling Event
Analysis
Annual NAM
ATTACHMENT A
130 Stone Road West Guelph, ON N1G 3Z2
8 Mar 2023 SiREM Ref: Si-06509-030823
Blaine Dawson Geosyntec Consultants, Inc.
1200 Riverplace Boulevard Suite 710 Jacksonville, FLORIDA 32207
Via email: bcdawson@geosyntec.com
Reference: Quotation for Gene-Trac® Testing – Former Coles Cleaners
Dear Blaine:
Thank you for your interest in SiREM’s Gene-Trac® quantitative polymerase chain reaction (qPCR) testing services for the Former Coles Cleaners site. This quotation provides project specific pricing as requested as well as a brief overview of our Gene-Trac® testing service and the targets provided by SiREM (Attachment A).
Gene-Trac® Testing
SiREM’s Gene-Trac® testing provides value, quality and service including:
• Clear and easy to understand reports that detail our comprehensive testing and quality control parameters;
• Electronic data deliverables (EDDs) in various formats;
• USA or Canada sample reception;
• Field filter protocols that reduce shipping costs; and
• Unparalleled technical support for data interpretation and planning.
The turn-around time for Gene-Trac® analyses is 10 business days; SiREM reports results for all Gene-Trac® tests in gene copies per liter of groundwater or per gram of solid, the detection limit is 1,000 gene copies per liter.
Should you require further documentation or have any questions regarding this proposal, I can be reached at +1 519-515-0838 or by email XDruar@Siremlab.com. Thank you for your interest in SiREM’s molecular genetic testing services, we look forward to working with you on this project.
Ximena Druar, B.Sc.
Molecular Services Manager
Blaine Dawson 8 Mar 2023
SiREM Quotation: # Si-06509-030823
Project Name/Location: Former Coles Cleaners
Summary of Testing Services and Prices:
Test Description Quantity Unit Price Extended Price
Gene-Trac Dhc Dehalococcoides 4 $270 $1,080 Gene-Trac FGA vcrA, bvcA, tceA 4 $85 $340
Total (USD) $1,420
Key Contact Persons:
Invoice To: Report To:
Address:
Address:
Email: Email:
Telephone:
Telephone:
The attached terms and conditions will govern this quotation which will be filled upon execution and completion of the information below. This quotation is valid for one year from date of issue.
Please return this completed document to Ximena Druar by email at XDruar@Siremlab.com.
SiREM is a division of Geosyntec Consultants, Inc.
Agreed and Accepted By:
Proposal: Si-06509-030823 Amount: USD $1,420
Authorized Signature Printed Name Fax & Email Address Purchase Order PO # No PO will be issued Prime Contract Applies, Copy Attached No Prime Contract Applies
Attachment A: Gene-Trac® Test Targets Attachment B: Terms and Conditions for Testing Services
Attachment A: Gene-Trac® Test Targets
Contaminant Class Gene-Trac®
Test Name
Target
Relevance
Reductive Dechlorination Dhc Dehalococcoides Dechlorinates PCE, TCE, all DCE isomers, VC Dhb Dehalobacter Dechlorination of PCE &TCE to cDCE Dsm Desulfuromonas Dechlorination of PCE & TCE to cDCE Dsb Desulfitobacterium Partial dechlorination of PCE and TCE to cDCE Geo Geobacter Dechlorinates PCE to cDCE/biogeochemical degradation
Dhgm Dehalogenimonas Dechlorination of tDCE to VC and VC to ethene SSP Sulfurospirillum Sulfurospirillum multivorans degrades PCE to cDCE
Dehalobium Dehalobium chlorocoercia Hexachlorobenzene, PCBs
Chloroethene
FGA
Vinyl Chloride Reductase (vcrA) Dechlorination of cDCE & VC to ethene BAV1 Reductase (bvcA) Dechlorination of cDCE and VC to ethene
Trichloroethene Reductase (tceA) Dechlorination of PCE and TCE to cDCE and VC cerA cerA Dehalogenimonas VC-Reductase Dechlorinates VC to ethene cfrA/dcrA Dichloroethane dehalogenase (dcrA) Dechlorinates 1,1,1-TCA & 1,1-DCA
Aerobic chlorinated compounds degradation
Polaromonas Polaromonas JS666 Aerobic dechlorination of cDCE etn etnE Aerobic degradation of VC dhIA Haloalkane dehalogenase Aerobic dechlorination of 1,2-DCA by Xanthobacter pMMO
Particulate Methane monooxygenase (pMMO)
Co-oxidation of 1,4-dioxane and TCE in presence of methane sMMO Soluble Methane Monooxygenase Co-metabolism of 1,1,1-TCA & 1,1-DCA by methanotrophs PMO Propane Monooxygenase Co-metabolism of chlorinated ethanes by propanotrophs dhlA Haloalkane Dehalogenase (dhlA) Aerobic dechlorination of 1,2-DCA
Anaerobic BTEX ORM-2 Deltaproteobacterium ORM-2 Anaerobic benzene degrader (SO4/CH4 reducing conditions)
Pepto-ben Benzene degrading Peptococcaceae Anaerobic benzene degrader under NO3- reducing conditions abcA Benzene Carboxylase (abcA) Involved in benzene ring cleavage under anaerobic conditions bssA Benzyl Succinate Synthase (bssA) Functional gene for anaerobic toluene biodegradat
Aerobic hydrocarbon degradation TMO Toluene Monooxygenase Aerobic oxidation of toluene
TDO
Toluene Dioxygenase
Degrades toluene and benzene by incorporating incorporated two oxygen molecules into the aromatic ring
PhMO
Phenol Monooxygenase
Hydroxylates phenol to catechol which is subject to further degradation under aerobic and anaerobic conditions
XMO Xylene Monooxygenase Degrades xylene and toluene by oxidizing methyl groups
NDO
Naphthalene Dioxygenase (nahAc)
Catalyzes the first step in the aerobic degradation of naphthalene reported activity for other polcyclic compounds with less than 3 rings
MTBE/TBA
Methylibium petroleiphilum PM1 MTBE/TBE degrading microorganism tert-butyl alcohol hydroxylase (mdpJ) Active on 2-HIBA in aerobic MTBE degradation pathway HIBA mutase (hcmA) Active on 2-HIBA in aerobic MTBE degradation pathway
1,4 -Dioxane
1,4 -Dioxane Dioxane monooxygenase (dxmb) Energy yielding 1,4-dioxane degradation
Aldehyde Dehydrogenase Energy yielding 1,4-dioxane degradation
Nitrogen Metabolism
Denitrification Three denitrification functional gene, nitrous oxide reductase (nosZ) and nitrite reductases (nirS and nirK)
Functional genes in anaerobic pathway that converts nitrate to dinitrogen gas
Nitrification
Three target test ammonia monooxygenase genes (amoA) from Bacteria and Archaea and 16S rRNA gene for Nitrobacter
Functional genes in aerobic pathway that converts ammonium to nitrate
Anammox Major anammox genera ia 16S rRNA Anaerobic co-removal of ammonium and nitrite
Perchlorate
Perchlorate Perchlorate Reductases of (pcrA)
Dechloromonas agitata and Dechloromonas aromatica
Reduces perchlorate to chlorate and chlorite -diagnostic for perchlorate degrading bacteria
Metals
Selenium Identifies selenium-reducing bacteria via selenate reductase (serA) of Thauera selenatis
The presence of selenate reductases signals increased likelihood of selenium precipitation in aqueous systems
Selenium
Identifies selenium-reducing bacteria via selenate reductase (srdA) of Bacillus selenatarsenatis
Mercury
Two target test for mercuric ion reductase (merA) and organomercurial lyase (merB) merA converts Hg2+ to Hg0 reducing its toxicity merB converts methylmercury with high bioavailability to less toxic elemental mercury -these genes are important in bacterial mercury resistance
Microbial Groups Universal Bacteria Quantifies Bacteria-measure of total biomass
Arch Archaea Quantifies Archaea biomass SRB Sulfate Reducing bacteria (dsrA) Partners to ORM-2 in anaerobic benzene degradation
Methanogens quantifies methyl coenzyme reductase (mcrA) mcrA catalyzes the final step in methanogenesis and is highly conserved among methanogens
SOX-B
Sulfur-oxidizing bacteria (SOB) via Sox enzyme system (soxB) of non-filamentous chemolithotrophic SOB
Sulfur oxidizing bacteria produce sulfuric acid and are important in acid mine drainage and in microbially induced corrosion (MIC) of concrete and metal
Gene-Trac NGS Next generation sequencing of 16S rRNA gene of Bacteria and Archaea Characterize entire microbial communities to determine metabolic functions and responses to changing conditions etc
ATTACHMENT B: Terms and Conditions for SiREM Products and Services
SiREM Terms and Conditions - 6-3-19
The following terms and conditions are an integral part of the contractual relationship between the Client (“Client”) identif ied in the Confirming Order or Quotation (“Order”) and SiREM, a division of Geosyntec Consultants International, Inc., (“SiREM”), and they apply to the purchase, sale, and shipment of products, equipment, materials or supplies (collectively “Products”), and any related testing, research or evaluative services (collectively “Services”) rendered by SiREM. Client and SiREM shall be referred to individually as “Party” and collectively as “Parties”:
1. Acceptance of Terms. These terms and conditions are incorporated into the Order which shall describe the Products being sold and any related Services to be rendered. The Order and these terms and conditions are deemed accepted and become effective upon Client’s acknowledgement of the Order or SiREM’s initial performance in accordance with the Order. All prior or contemporaneous terms, representations or agreement, and any proposal or offer of additional or different terms and conditions is expressly rejected. This Order shall constitute the full agreement between the Client and SiREM and all prior or contemporaneous communications, representations or agreements are superseded unless expressly incorporated into this Order by written amendment signed by both Parties.
2. Delivery. SiREM shall provide Products or Services as specified in Order. Products shall be packaged and supported in a manner to ensure safety and protection against damage during shipment. Ownership of the Products shall transfer from SiREM to Client upon shipment.
3. Payment. All fees and charges, including shipping for Products shall be reflected in the Order. Payment for Products and Services shall be as indicated in the Order. SiREM shall invoice Client and payment is due within 30 days of invoice date. Client shall pay an additional charge of one percent (1%) of the amount of the invoice per month or the maximum percentage allowed by law, whichever is the lesser, for any payment received by SiREM beyond the payment terms set forth herein.
4. Intellectual Property Rights/Obligations. Intellectual Property shall mean ideas, results, technical information, patents, patent applications, know-how, copyrights, inventions, developments, trade-secrets, models, drawings, specifications, prototypes, deliverables and discoveries, whether registered or not, relating to the Products and the Services. All rights, including but not limited to ownership rights, to the Intellectual Property in the Products and Services are owned by SiREM and others, but not Client. SiREM is an authorized seller of the Products which are provided to Client in accordance with the limitations imposed upon SiREM. Upon payment in full of the amount reflected in the Order SiREM transfers to the Client a non-exclusive, non-commercial, non-transferable right to use the Products and the associated Intellectual Property for the limited application of the Products as set forth in the Order, and only at the project site described in the Order, and at no other site and for no other project or purpose. The Client does not have, nor will it acquire, any ownership interest or rights in the Product and/or the associated Intellectual Property and Client shall not sell, resell or transfer any of the Products to any third-party under any circumstances. In addition, Client agrees that it will not “reverse engineer” or undertake any activity which would enable Client, or any other person or entity, to duplicate, imitate, reproduce, copy, grow or culture the Products.
5. Confidential Information. In connection with the Order, Products and/or Services, Client will have access to confidential, proprietary and other non-public or sensitive information, including but not limited to Intellectual Property, belonging or licensed to SiREM (collectively “Confidential Information”). Except as, and to the extent necessary, to comply with the Order, Client shall not directly or indirectly disclose any Confidential Information. Furthermore, Client agrees (i) the Confidential Information shall be used solely for the purpose intended in this Order; (ii) it will not use any Confidential Information disclosed hereunder to compete with or negatively impact Discloser, either directly or indirectly; (iii) it will not distribute, disclose or disseminate any Confidential Information to anyone except its employees and agents with a need to know and who, in each case, have been informed of the confidential nature of the Confidential Information and have agreed to be bound by the terms of this Order; and (iv) it will keep all Confidential Information separate from all of its other documentation and records. In the event that the Client is requested or required to disclose any part of the Confidential Information, the Client will provide immediate written notice to SiREM for prior approval of release
6. Force Majeure. Neither Party shall be liable for delays or defaults due to an act of god, and act of government, public enemy, strike, natural disaster or other unforeseeable causes beyond the reasonable control of the Parties.
7. Termination or Suspension. Client may by written notice terminate or suspend this Order, in whole or in part, for any reason at any time. Upon receipt of a notice of termination SiREM shall immediately stop all performance under this Order. Client shall reimburse SiREM for any costs incurred in connection with the Order up until receipt of the notice of termination.
8. Assignment. Neither Party shall assign its obligations under this Order without the prior written approval of the other Party. There shall be no third-party beneficiary to this Order.
9. Standard of Care. The Services rendered by SiREM will render its Services in a manner consistent with the level of care and skill ordinarily exercised by other firms rendering the same services under similar circumstances at the same time the Services are performed.
10. LIMITED WARRANTY. SIREM WARRANTS THAT THE PRODUCTS SUPPLIED PURSUANT TO THIS ORDER WILL NOT INFRINGE THE INTELLECTUAL PROPERTY RIGHTS OF ANYONE NOT A PARTY TO THIS ORDER. SIREM WARRANTS THAT IT IS DULY LICENSED, QUALIFIED AND CAPABLE OF FULFILLING ITS OBLIGATIONS UNDER THE ORDER. ALL OTHER WARRANTIES AND GUARANTEES OF ANY KIND, WHETHER EXPRESS OR IMPLIED, INCLUDING BUT NOT LIMITED TO ANY IMPLIED WARRANTIES
OF MERCHANTABILITY OR FITNESS FOR PURPOSE ARE DISCLAIMED.
11. Collecting Procedures. If the Order includes Services for testing, Client will collect and obtain samples to be shipped to and tested by SiREM at Client’s sole expense. At Client’s request, SiREM will provide sample containers at no cost. If recollection or resampling becomes necessary, for any reason other than SiREM’s gross negligence or wilful misconduct, Client shall be responsible for re-collecting and re-shipping the samples. The results of the testing will be delivered to Client in SiREM’s standard report format.
12. Liability. To the maximum extent permitted by Law, Client agrees to limit SiREM’s liability for the Client’s damages to the greater of SiREM’s fee or $50,000. In no event will SiREM be liable to Client for any incidental or consequential damages arising in connection with this Order, the use of the Product or the Services rendered by SiREM.
13. Disputes. The Parties agree to promptly resolve their differences through good faith negotiations as a condition precedent to filing a formal claim. In the event disputes remain following such negotiations, any remaining dispute shall be submitted to senior representatives of the Parties who shall have the authority to enter into an agreement to resolve the dispute (“Representative”). The Representatives shall not have been directly involved in the performance of the Subcontracted Services. If the Representatives are unable to resolve the dispute within three weeks or within such longer time period as the Representatives may agree, the dispute shall be mediated by an independent third-party agreed to by both parties. Any disputes or portions thereof remaining following mediation shall be determined by remedies at law or equity, as they may be available, subject to the limitations in this Agreement. Any applicable statute of limitations on any claim in any way related to Agreement shall commence to run and alleged cause of action shall be deemed to have accrued no later than the date of either SiREM’s final invoice or termination of this Agreement by either Party. Both Parties agree that the applicable statute of limitations for any claims in any way related to this Agreement shall be shortened to a period not longer than two years, unless a shorter statute of limitations would otherwise apply.
ATTACHMENT B
IDW QUOTES
4 Drum $200 4 Drum $105 4 Drum $192
4 Stoppage $425 4 Stopage $146
4 Recovery Fee $51
Note: The selected subcontractor is highlighted in yellow.
Subcontractor Evaluation: Former Coles Cleaners, Jacksonville Beach, Florida
Hepaco, LLC
$800.00 $2,120.00 $1,553.28
IDW DISPOSAL
Hulls Moran/WRI
4390 28th St N, St. Petersburg, FL 33714
Office: 727-610-2080
03/13/2023
GEOSYNTEC CONSULTANTS
1200 Riverplace Blvd Suite 710 Jacksonville, Florida 32207
Dear Blaine, Hull's Environmental Services, Inc. (Hull's) is pleased to submit the enclosed Quote for the Scope of Work described, along with our Standard Terms & Conditions. We appreciate the opportunity to quote this work and are prepared to perform the work upon your approval.
Please do not hesitate to call me if you have any questions. To accept the quote, please sign and date the final page of the quote.
Sincerely, Jamie Michael Vice President Business Development Hull’s Environmental Services
QUOTE
Customer GEOSYNTEC CONSULTANTS
Project Street Address Various Locations
Project State FL
Project City Various Cities
Project Zip Various Zips
Quote Number Q212641TPA
Quote Date Mar 13, 2023 04:43:47 PM
Hull's Rep Jamie Michael
SCOPE OF WORK
Waste T&D for non-hazardous IDW drum pickup and disposal in various Florida regions as designated by Geosyntec.
Conditions:
Drums must be readily available and accessible by drum dolly and/or lift gate truck Lab analysis provided for profile acceptance
Item description Quantity Unit Rate Amount
Northwest, <50 Miles From Portal 1.00 Drum $ 225.00 $ 225.00
Northeast, <50 Miles From Portal 1.00 Drum $ 200.00 $ 200.00
Central, <50 Miles From Portal 1.00 Drum $ 185.00 $ 185.00
Southwest, <50 Miles From Portal 1.00 Drum $ 200.00 $ 200.00
Southeast, ***NO BID*** 1.00 Drum $ 0.00 $ 0.00
Demurrage < 1 Hour 1.00 Each $ 0.00 $ 0.00
Demurrage > 1 Hour 1.00 Hour $ 85.00 $ 85.00
Stop Fee, >50 Miles From Portal 1.00 Each $ 75.00 $ 75.00
TOTAL $ 970.00
Unit Pricing Disclaimer
Unit price quotations are designed to provide an estimated cost when complexity, duration and resource needs for a particular scope of work are difficult to determine due to factors like training requirements, location, weather conditions, materials, supplies, market fluctuations, unforeseen circumstances, and other characteristics. As such, Hull’s Environmental Services and client acknowledge that this is a unit price contract , that such unit prices vary from project to project and can ultimately alter the final cost of a project.
UNIT PRICING
BCDawson Rectangle
STANDARD TERMS AND CONDITIONS
Acceptance and Formation of Contract: All written proposals shall be valid for a period of thirty (30) days. The cancellation or expiration of any contract hereunder shall not affect either Party’s obligations under any orders issued and accepted prior to such expiration or cancellation.
By issuance of a notice to proceed with the work, whether oral or written, Customer agrees to the terms and conditions stated herein. Any terms proposed in Customer's acceptance of this proposal which add to, vary from, or conflict with the proposal or these terms and conditions, are hereby rejected. Any such proposed terms shall be void and the terms in the proposal and these terms and conditions shall constitute the complete and exclusive statement of the terms and conditions of the contract between Hull’s Environmental Services, Inc. (“Hull’s”) and Customer.
Project Documents: Hull’s proposal includes and incorporates Hull’s Rate Schedule which is in effect at the time of performance of the work, all documents provided to Hull’s by or on behalf of Customer and all documents provided to Customer or its representative by or on behalf of Hull’s. The term “Customer” refers to the party with whom Hull’s is contracting. This document is incorporated by reference to the Contract as specified therein and is an integral part of the Contract.
Scope of Work and Price: All work performed hereunder shall be performed and invoiced in accordance with Hull’s written proposal, Hull’s Rate Schedule which is in effect at the time of performance of the work, the other Project Documents, and the terms and conditions stated herein as each may be applicable to the type of work performed. In the event that the scope of work, schedule, or material changes, Customer agrees to pay Hull’s on a time and material basis in accordance with Hull’s then current Rate Schedule or other unit rates, whichever is applicable, unless a revised proposal is prepared by Hull’s and accepted by Customer. Emergency response services shall be performed and invoiced in accordance with Hull’s current Rate Schedule. Unless expressly set forth, Hull’s proposal does not include state or local sales tax. If any such taxes are applicable and the client does not provide a Direct Pay or Tax Exemption Certificate for this work, such taxes will be added to the invoiced amount as a separate line item.
General Conditions of Work: Customer is responsible for furnishing to Hull’s all pertinent data and information concerning the work to be performed hereunder, the nature of the work site and the nature of the conditions to be remediated, including special hazards or risks involved with such work, premises, site or conditions. Unless otherwise stated in Hull’s proposal, all pricing is based upon the following general conditions:
(a) Hull’s will not incur any waiting or standby time for reason beyond Hull’s control; (b) access to, from and at the work site will not be restricted or limited; (c) there will be no overhead, underground, aboveground or other obstructions, rocks, pipelines, or utilities that would impede Hull’s work;
(d) the work site and all access ways shall be suitable for the size and weight of all vehicles and equipment utilized to perform the work; (e) all wastes shall conform to the representations of Customer and the Project Documents; (f) all non-emergency response related work will be performed Monday through Friday during daytime business hours between 8:00 a.m. and 4:00 p.m. (work performed outside of this time frame will be charged at 1.5 times the standard rates or as otherwise provided in Hull’s then current Rate Schedule; work performed on Sundays and holidays will be charged at two times the standard rates); (g) Customer is responsible for all damage to equipment and its components not caused by the direct fault of Hull’s; and (h) Customer is responsible for all costs associated with overloading of containers or trucks including citations, damages to equipment or property, loss of revenue, etc., unless loaded by Hull’s. Any variance in these conditions is considered a change in the scope of work unless expressly otherwise stated in Hull’s proposal.