This is a Task Assignment (TA) document issued by the State of Florida Department of Environmental Protection (FDEP) to Geosyntec Consultants for remediation activities at the Gentle Touch Dry Cleaners site located at 3611 W. Hillsborough Avenue in Tampa, Florida (ERIC 4712). The task assignment is entered pursuant to Contract Number HW683 and authorizes the contractor to conduct remediation design and planning services. Key personnel include Sarah Aduwa as the FDEP Project Manager and Nick Barnes as the Contractor's Project Manager.
The task assignment authorizes Geosyntec to conduct four subtasks with a total value of $16,473.14 on a fixed unit rate basis. Subtask 1 involves project management costs; Subtask 2 ($9,183.96, due May 21, 2026) covers preparation of an Interim Source Removal Work Plan to address vadose zone soil impacts using a soil vapor extraction system to treat soils from 0 to 4 feet below land surface; Subtask 3 covers bid package development including construction drawings and technical specifications; and Subtask 4 ($7,289.18, due July 20, 2026) encompasses bid walk coordination and contractor evaluation activities. The work plan includes communication with the site owner and tenant, development of bid documents for subcontractor solicitation, and evaluation of bids for contractor selection. The total task assignment value of $16,473.14 encompasses 93 labor hours with a completion date of September 25, 2026, and includes travel expenses of $240 for vehicle rental.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW683
DC037D Completion September 25, 2026
This Task Assignment authorizes Geosyntec to conduct remediation activities at Gentle Touch Dry Cleaners site in accordance with Geosyntec’s scope of work, cost estimate and schedule received on February 19, 2026.
Sarah Aduwa 850-245-8973 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Geosyntec
Geosyntec
Nick Barnes 813-557-1165
ERIC 4712
3611 W. Hillsborough Avenue (formerly 3613 W. Hillsborough Avenue) Tampa, FL 33614
Gentle Touch Dry Cleaners
✔ $ 16,473.14
$ 16,473.14
Scope of Work
Todd Kafka
Contract Manager
Todd K. Kafka, PG (FL) Digitally signed by Todd K. Kafka, PG (FL) Date: 2026.03.07 18:10:59 -05'00'
Mubeen Darji
Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.
Date: 2026.03.05 15:04:21 -05'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Subtask 2 - ISR Work Plan 05/21/2026
Subtasks 1,3,4 -Field deliverable for Bid Documents, Submittal to Subcontractors, Site Walk, and Bid Evaluation 07/20/2026
Subtask 2 - Submittal and FDEP approval of ISR Work Plan $ 9,183.96
Subtasks 1,3,4 - Submittal and FDEP approval of Field deliverable for Bid Documents, Submittal to Subcontractors, Site Walk, and Bid Evaluation $ 7,289.18
$ 16,473.14
HW683
DC037D
To:
From:
Date:
HW683 Contract Negotiation File Gentle Touch Dry Cleaners Tampa, Florida
ERIC_4712
Sarah Aduwa, Project Manager February 14, 2026
Subject: Negotiation Summary
HW683_DC037D
This Task Assignment authorizes Geosyntec to conduct remediation activities at Gentle Touch Dry Cleaners site in accordance with Geosyntec’s scope of work, cost estimate and schedule received on February 19, 2026.
Nick Barnes is the Project Manager.
Subtask 2, 3, and 4 This subtask includes costs associated with the preparation of an ISR Work Plan to address vadose zone soil impacts at the Site, bid documents, and conducting a bid walk.
Geosyntec anticipates that the ISRP will detail a soil vapor extraction (SVE) system to treat soils from 0 to 4 feet (ft) below land surface (BLS), as identified in the March 2024 Site Assessment Report.
Geosyntec will communicate with the Site owner to discuss the design plan and coordinate logistics for a Site visit with the owner. Geosyntec will develop and prepare Bid Documents necessary to obtain subcontractor costs to implement the ISR at the Site.
The Bid Documents will include the specifications necessary for potential subcontractors (i.e., bidders) to provide a cost to permit, mobilize, and prepare the Site for construction;
complete trenching, backfilling, and install the treatment system; and perform Site restoration activities.
Geosyntec will develop a list of at least three qualified SVE Contractors for invitation to the Site to participate in a bid walk. Prior to scheduling the Site visit, Geosyntec will send interested Contractors copies of the ISRP, Bid Documents, and Technical Specifications.
The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost is $16,473.14 with 93 labor hours.
FDEP COST ESTIMATEContractor: Geosyntec Consultants
Date: 2/16/2026
Task #: Pending SubTask 1 Project Management SubTask 6
Site: Gentle Touch SubTask 2 Interim Source Removal Work Plan SubTask 7
Activity/Phase: Design SubTask 3 Bid Package Development SubTask 8
Project Manager: N. Barnes SubTask 4 Bid Walk and Evaluation SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$63.75 Project Manager N. Barnes 10 9.8 $105.00 Principal T. Kafka 2 1 0 1 0 0 0 0 0 0
$58.93 Senior Professional M. Hensley 4 4 0 0 0 0 0 0 0 0 $63.75 Project Professional N. Barnes 49 34 4 11 0 0 0 0 0 0 $39.23 Senior Staff Professiona S. Santiago 18 0 12 6 0 0 0 0 0 0 $51.34 Designer C. Vickers 10 10 0 0 0 0 0 0 0 0
Total Hours 93 10 49 16 18 0 0 0 0 0 0
Direct Labor $5,411.58 $622.57 $3,021.62 $725.76 $1,041.63 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 172.70% $9,345.81 $1,075.18 $5,218.34 $1,253.39 $1,798.90 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $14,757.39 $1,697.75 $8,239.96 $1,979.15 $2,840.53 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cost Estimate Page 1 of 5 Cost Estimate
FDEP COST ESTIMATEContractor: Geosyntec Consultants
Date: 2/16/2026
Task #: Pending SubTask 1 Project Management SubTask 6
Site: Gentle Touch SubTask 2 Interim Source Removal Work Plan SubTask 7
Activity/Phase: Design SubTask 3 Bid Package Development SubTask 8
Project Manager: N. Barnes SubTask 4 Bid Walk and Evaluation SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Travel
Vehicle Rental $240.00 $120.00 $0.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $240.00 $120.00 $0.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) 0 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $14,997.39 $1,697.75 $8,359.96 $1,979.15 $2,960.53 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $1,475.75 $169.78 $824.00 $197.92 $284.05 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $16,473.14 $1,867.53 $9,183.96 $2,177.07 $3,244.58 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cost from Prior CEF: Manual Entry Cost from Delta CEF; Manual Entry
Cost (Prior + Delta): $0.00 Auto-Calculated Rounding Error: $16,473.14 Auto-Calculated
Final Total Cost: $16,473.14 Auto-Calculated
Cost Estimate Page 2 of 5 Cost Estimate
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Gentle Touch SUBTASK: Interim Source Removal Work Plan
DATE: 2/16/2026
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Principal T. Kafka 1
Senior Professional M. Hensley 4
Project Professional
N. Barnes 34
Designer C. Vickers 10
TOTAL LABOR 49
VEHICLE TYPE RATE UNIT USEAGE
Truck $480.00 Week 0 $0.00 Truck N. Barnes $120.00 Day 1 $120.00
Subtotal $120.00
TOTAL VEHICLE $120.00
Prepare construction drawings (process and instrumentation diagram, well details, electrical connection to system, and piping details)
Post-Site visit design discussion (1 hr).
Prepare figures and system/well/piping layouts
Mobe/demobe to the site (1 hr). Conduct site visit to evaluate ISR implementation (2 hr). Post-Site visit design discussions with property owner and tenants (1 hr). Prepare ISR, design drawings, calculation package, and develop monitoring plan, including technical design, well and piping layouts, and monitoring plan, PE sign/seal (30 hr).
2/24/2026 Page 3 of 5 Subtask 2
SUBTASK: Bid Package Development
DATE: 2/16/2026
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Professional N. Barnes 4
Senior Staff Professional S. Santiago 12
TOTAL LABOR 16
PE review and approval of bid specifications, contractor bid package
Prepare bid documents and technical specifications
2/24/2026 Page 4 of 5 Subtask 3
SUBTASK: Bid Walk and Evaluation
DATE: 2/16/2026
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Principal T. Kafka 1
Project Professional N. Barnes
Senior Staff S. Santiago 6
TOTAL LABOR 18
VEHICLE TYPE RATE UNIT USEAGE
Car $80.00 Day 0 $0.00 Truck Barnes $120.00 Day 1 $120.00 Van $120.00 Day 0 $0.00
Subtotal $120.00
TOTAL VEHICLE $120.00
Evaluate contractor selection summary
Mobilization to/from site (1 hr). Conduct site visit and bid walk with contractors (2 hr).
Correspond with tenants and property owner on design and implementation plans/schedule (2 hr). PE evaluation of bids and bid comparison, evaluate contractor selection and questions from bidders, requests for additional information (6 hr).
Develop contractor bid list (1 hr). Evaluate subcontractor bids and prepare bid comparison table (3 hr). Prepare selection summary for FDEP with recommended contractor (2 hr).
2/24/2026 Page 5 of 5 Subtask 4
Site Name:
Facility ID #:
Street Address:
City:
County:
Facility Type: Active Drycleaner
Dry Drop Off
Other Description:
YES NO
Is Vapor Treatment required?
Is there groundwater contamination associated with the site?
Is the groundwater contamination off site?
Is there a potentially sensitive receptor within 150 feet of the site?
What is the estimated cost for SVE Construction?
What is the estimated annual cost for O&M?
PM Comments:
Project Manager:
Waste Site Cleanup Section
Soil Vapor Extraction (SVE) Presumptive Remedy Approval
Facility Information:
date
Based on current site assessment data, the Department concurs with the selection of Soil Vapor Extraction as a presumptive remedy for soil contamination. Additional remediation of soil and/or groundwater may be implemented based upon subsequent assessment/monitoring data.
Will annual groundwater monitoring be performed to evaluate NAM/remediation?
date
Has Modified Active Gas Sampling (MAGS) shown SVE to be an effective soil remedial option for the site?
date
Technical Advisor:
Supervisor:
Gentle Touch Dry Cleaners
ERIC 4712
3611 W. Hillsborough Avenue
Tampa 33614
Hillsborough
Laundromat
X
$150,000
$50,000
No comments.
4-Sep-2025Sarah Aduwa Digitally signed by Sarah Aduwa Date: 2025.09.04 10:06:38 -04'00'
27-Jan-2026
27-Jan-2026
Mohammad Goudarzi Digitally signed by Mohammad Goudarzi Date: 2026.01.27 14:57:54 -05'00'
Mubeen Darji, P.E.
Digitally signed by Mubeen Darji, P.E.
Date: 2026.01.27 15:06:51 -05'00'
12802 Tampa Oaks Blvd, Suite 151 Tampa, FL 33637
PH 813.558.0990
www.geosyntec.com
Gentle Touch Dry Cleaners (ERIC_4712)_HW683 SOW_ISRWP_2026-02
February 19, 2026
Ms. Sarah Aduwa Florida Department of Environmental Protection Waste Cleanup Program 2600 Blair Stone Road Tallahassee, FL 32399-2400
Subject: Scope of Work and CEF/LOE – Interim Source Removal Work Plan &
Subcontractor Bidding Activities Gentle Touch Dry Cleaners 3611 W. Hillsborough Avenue (formerly 3613 W. Hillsborough Avenue) Tampa, FL 33614 FDEP Site ID ERIC_4712
Dear Ms. Aduwa:
Geosyntec Consultants, Inc. (Geosyntec) has prepared this proposed Scope of Work (SOW), Level of Effort (LOE), and Cost Estimating Form (CEF) for remediation activities at the Gentle Touch Dry Cleaners Site located in Tampa, Florida (ERIC_4712). This SOW includes (i) preparing an Interim Source Removal (ISR) Work Plan, (ii) preparing Bid Documents, and (iii) soliciting bids from qualified subcontractors and evaluating the subcontractor bids for selection. A description of task breakdown for field activities and report preparation is provided below. A CEF/LOE is provided as Attachment A.
Subtask 1 – Project Management
Costs associated with this subtask are directly computed.
Subtask 2 – ISR Work Plan
This subtask includes costs associated with the preparation of an ISR Work Plan (ISRP) pursuant to Chapter 62-780.525, Florida Administrative Code to address vadose zone soil impacts at the Site, bid documents, and conducting a bid walk. Geosyntec anticipates that the ISRP will detail a soil vapor extraction (SVE) system to treat soils from 0 to 4 feet (ft) below land surface (BLS), as identified in the March 2024 Site Assessment Report.
The ISRP will include the following elements:
• A recap of the soil assessment activities and results;
http://www.geosyntec.com/
• Proposed SVE well layout, piping layout, construction, operation, and maintenance details;
• A process and instrumentation diagram;
• SVE well details;
• Electrical connection to system;
• Piping details; and
• Engineering cost estimate for implementation and operation and maintenance (O&M).
Geosyntec will communicate with the Site owner to discuss the design plan and coordinate logistics for a Site visit with the owner (or local representative, if present) and existing tenant (in this case, a laundromat). The objectives of the Site visit are to (i) evaluate interior access for construction activities, such as trenching for subgrade piping runs or the use of above grade piping into overhead spaces (or both); (ii) document current Site conditions; discuss access and logistics with the Site owner and tenant; determine a location for the treatment equipment; and (iii) evaluate the presence of overhead and underground utilities. Nick Barnes (Project Manager, Engineer of Record [EoR]) will conduct the Site visit. Effort has been included for Geosyntec to communicate with the property owner and tenants before and after the Site walk to ensure the proposed design is appropriate.
Subtask 3 - Bid Package Development
Geosyntec will develop and prepare Bid Documents necessary to obtain subcontractor costs to implement the ISR at the Site. The Bid Documents will include the specifications necessary for potential subcontractors (i.e., bidders) to provide a cost to permit, mobilize, and prepare the Site for construction; complete trenching, backfilling, and install the treatment system; and perform Site restoration activities.
The Bid Documents will include:
• Instructions for Bidders;
• Request for Bids Scope of Work;
• Construction Drawings;
• Technical Specifications; and
• Bid Proposal Form.
The Bid Documents and Technical Specifications section will include, but not be limited to, the following elements:
• Summary of work;
• Description of site conditions, access constraints, known overhead and subsurface utilities, and historical soil data, etc.;
• Permitting (local, state, federal);
• Safety, health, and emergency response requirements;
• Site preparation and pre-mobilization activities (e.g., underground utility locating);
• Requirements for protection of existing structures, as applicable;
• Piping locations and specifications;
• Conveyance piping and connection specifications;
• Backfill specifications;
• Electrical connection requirements and electrical subcontractor costs;
• Telemetry system connection and operational requirements;
• Waste profiling, manifesting, transportation, and disposal requirements; and
• Site restoration and demobilization requirements.
Subtask 4: Bid Walk and Evaluation Geosyntec will develop a list of at least three qualified SVE Contractors for invitation to the Site to participate in a bid walk. Prior to scheduling the Site visit, Geosyntec will send interested Contractors copies of the ISRP, Bid Documents, and Technical Specifications. Geosyntec will coordinate the visit with the Site owner and current tenant to provide an overview of the ISRP and allow the owner and tenant to provide input on logistics, layout changes (if Site conditions differ from those at the time of the ISRP), and how to minimize disruptions to facility operations. This information will allow for the Site visit to run smoothly and provide the best opportunity for setting clear expectations for the contractors. Nick Barnes (PM/EoR) will attend the Bid Walk.
Geosyntec will respond to requests for additional information (RAIs) submitted by contractors following the Site visit. Geosyntec will review contractor bids and evaluate costs and approaches to identify the best value to FDEP. Geosyntec will submit the Contractor bids, bid evaluation, and our recommendation for Contactor selection to FDEP in a separate scope of work for implementation.
Invoice and Deliverable Schedule
Subtask Deliverable Due Date Invoice Amount 2 ISR Work Plan May 21, 2026 $9,183.96
1,3, 4 Bid Documents, Submittal to Subcontractors, Site Walk, and Bid Evaluation
July 20, 2026 $7,289.18
Total $16,473.14 Schedule assumes Task Assignment issued March 2026.
CLOSURE
We appreciate the opportunity to assist with this project. Please contact us if you have any questions or require additional information.
Sincerely, Nicholas S. Barnes, P.E. (FL) Todd K. Kafka, P.G. (FL) Project Engineer Senior Principal Hydrogeologist
Attachments: CEF-LOE
ATTACHMENT A
Cost Estimate Form and Level of Effort