This is a Task Assignment (TA) document entered into between the State of Florida Department of Environmental Protection (FDEP) and Geosyntec Consultants for operation and maintenance services at the Colonial/Touch of Class facility located at 4552 Lake Worth Road, Greenacres, Palm Beach County, Florida (ERIC_5222). The task assignment is issued under Contract Number HW683 with task assignment number DC002A. The Department Project Manager is Evan Miller (850-245-8928) and the Contractor's Project Manager is Todd Kafka (813-379-4396). The assignment is effective January 26, 2022, with a completion date of January 31, 2023.

The task assignment authorizes Geosyntec to conduct six months of operation and maintenance for a soil vapor extraction system, consisting of five subtasks: project management, Quarter 1 O&M (February-March 2022), Quarter 2 O&M (April-June 2022), Quarter 3 O&M (July 2022), and utilities costs. The total task assignment value is $24,619.44, consisting of $20,643.60 in fixed unit rate charges and $3,975.84 in cost reimbursement for utilities. The payment structure includes Fixed Unit Rate compensation of $20,643.60 for labor and direct costs across 130 total labor hours, with utility payments as Cost Plus Fixed Fee not to exceed $3,975.84. Invoicing is scheduled in four installments: $4,999.14 (Quarter 1 deliverables due 04/29/2022), $11,233.71 (Quarter 2 deliverables due 07/29/2022), $4,270.75 (Quarter 3 and project management due 08/31/2022), and $4,115.84 (utilities due 01/31/2023). The scope includes monthly O&M visits, groundwater and air sampling, semi-annual reporting, and utility costs including electrical service and telemetry fees.

View the file

Other files

File Type Posted
CN-370000-HW683-BF01A.pdf PDF
CN-370000-HW683-BF01B.pdf PDF
CN-370000-HW683-BF02A.pdf PDF
CN-370000-HW683-BF02ACO2.pdf PDF
CN-370000-HW683-BF04A.pdf PDF
CN-370000-HW683-BF04BCO1.pdf PDF
CN-370000-HW683-BF2BCO1.pdf PDF
CN-370000-HW683-BIL01A.pdf PDF
CN-370000-HW683-CSS02.pdf PDF
CN-370000-HW683-CSS02A.pdf PDF
CN-370000-HW683-DC002F.pdf PDF
CN-370000-HW683-DC004B.pdf PDF
CN-370000-HW683-DC004E.pdf PDF
CN-370000-HW683-DC005D.pdf PDF
CN-370000-HW683-DC005E.pdf PDF
CN-370000-HW683-DC007A.pdf PDF
CN-370000-HW683-DC007B.pdf PDF
CN-370000-HW683-DC008A.pdf PDF
CN-370000-HW683-DC008B.pdf PDF
CN-370000-HW683-DC008D.pdf PDF
CN-370000-HW683-DC009A.pdf PDF
CN-370000-HW683-DC009B.pdf PDF
CN-370000-HW683-DC009G.pdf PDF
CN-370000-HW683-DC010C.pdf PDF
CN-370000-HW683-DC011B.pdf PDF
CN-370000-HW683-DC011C.pdf PDF
CN-370000-HW683-DC011D.pdf PDF
CN-370000-HW683-DC012B.pdf PDF
CN-370000-HW683-DC016B.pdf PDF
CN-370000-HW683-DC017A.pdf PDF
CN-370000-HW683-DC018B.pdf PDF
CN-370000-HW683-DC019A.pdf PDF
CN-370000-HW683-DC019B.pdf PDF
CN-370000-HW683-DC019C.pdf PDF
CN-370000-HW683-DC019D.pdf PDF
CN-370000-HW683-DC01ACO1.pdf PDF
CN-370000-HW683-DC025B.pdf PDF
CN-370000-HW683-DC026B.pdf PDF
CN-370000-HW683-DC029A.pdf PDF
CN-370000-HW683-DC029E.pdf PDF
CN-370000-HW683-DC02ACO1.pdf PDF
CN-370000-HW683-DC02E.pdf PDF
CN-370000-HW683-DC031C.pdf PDF
CN-370000-HW683-DC032A.pdf PDF
CN-370000-HW683-DC032C.pdf PDF
CN-370000-HW683-DC035A.pdf PDF
CN-370000-HW683-DC036B.pdf PDF
CN-370000-HW683-DC037B.pdf PDF
CN-370000-HW683-DC038A.pdf PDF
CN-370000-HW683-DC039A.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW683

DC002A Completion January 31, 2023

This Task Assignment authorizes GEO to conduct operation and maintenance for six months in accordance with the GEO scope of work, cost estimate, bid documentation, and schedule received on January 25, 2022

The payment of utilities is the only part of this Task Assignment that is Cost Plus Fixed Fee.

Evan Miller 850-245-8928 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

Geosyntec

Geosyntec

Todd Kafka 813-379-4396

ERIC_5222

4552 Lake Worth Road Greenacres, Palm Beach County, Florida 33463

Colonial/Touch of Class

✔ $ 20,643.60 ✔ $ 3,975.84

$ 24,619.44

Scope of Work

Todd Kafka

Contract Manager

1-26-22

Todd Kafka, P.G. Digitally signed by Todd Kafka, P.G.

Date: 2022.01.26 15:32:22 -05'00'

William E. Burns, Jr.

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2022.01.26 14:52:25 -05'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Quarter 1: February to March 2022 O&M summary emails and air sampling field notes- Subtask 2 04/29/2022

Quarter 2: April 2022 to June 2022 O&M summary emails, air sampling field notes, Semi-Annual O&M report, ADaPT and GIS Tables - Subtask 3

07/29/2022

July 2022 O&M summary; Project Management - Subtask 1, 4 08/31/2022

Quarter 1: February to March 2022 O&M summary emails and air sampling field notes- Subtask 2 $ 4,999.14

Quarter 2: April 2022 to June 2022 O&M summary emails, air sampling, Semi-Annual O&M report, ADaPT and GIS Tables - Subtask 3

$ 11,233.71

July 2022 O&M summary; Project Management - Subtask 1, 4 $ 4,270.75

FDEP receipt of utility invoices for 6 months (February to July 2022); Utilities (Cost Plus Fixed Fee) = not to exceed $3,975.84; Utilities Handling Fee = $140 - Subtask 5 $ 4,115.84

$ 24,619.44

HW683

DC002A

Printed on recycled paper.

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Shawn Hamilton Secretary

To: HW550 Contract Negotiation File Colonial/Touch of Class Greenacres, Palm Beach County

ERIC_5222

From: Evan Miller, Project Manager Date: January 26, 2022 Subject: Negotiation Summary

HW683 DC002A

This Task Assignment authorizes Geosyntec six months of O&M consisting of the following:

Subtask 1: Project Management An automatic calculation based upon total direct labor hours determines the labor hours within this subtask.

Subtask 2: Quarter 1: February 2022 (Month 14) to March 2022 (Month 15) O&M and Reporting Two months of O&M with monthly email summaries to FDEP and air sampling in Month 15.

Includes separate mobilization for Quarter 1 to drain moisture separator.

Subtask 3: Quarter 2: April 2022 (Month 16) to June 2022 (Month 18) O&M and Reporting Three months of O&M with monthly email summaries to FDEP, air sampling and semi-annual groundwater sampling in Month 18 and Semi-Annual O&M Report

Subtask 4: Quarter 3: July 2022 (Month 19) O&M and Reporting One month of O&M with a monthly email summary to FDEP.

Subtask 5: Year 2 Utilities - February 2022 (Month 14) to July 2022 (Month 19) Six months of O&M utility costs.

The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost for this Task Assignment is $24,619.44 with 130 labor hours.

Geosyntec may invoice following the schedule established in the Deliverables and Invoice Schedule Attachment, which accompanies the Task Assignment Notification Form.

FDEP COST ESTIMATEContractor: Geosyntec Consultants

Date: 1/25/2022

Task #: HW550-DC038F SubTask 1 Project Management SubTask 6

Site: Colonial/Touch of Class SubTask 2 Quarter 1: Feb 2022 - March 2022 O&M and Reporting SubTask 7

Activity/Phase: 6 Months O&M - Year 2 SubTask 3 Quarter 2: April 2022 - June 2022 O&M and Reporting SubTask 8

Project Manager: A. Galvin SubTask 4 Quarter 3: July 2022 O&M and Reporting SubTask 9

SubTask 5 Year 2 Utilities: Feb 2022 - July 2022 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$37.50 Project Manager A. Galvin 15 15.4 $72.60 Principal K. Warner 6 2 3 1 0 0 0 0 0 0 $53.41 Senior Professional A. Smith 10 2 7 1 0 0 0 0 0 0 $46.15 Project Professional M. Hensley 2 0 2 0 0 0 0 0 0 0 $37.50 Professional A. Galvin 28 4 22 2 0 0 0 0 0 0 $33.89 Senior Staff Professional J. Udvardy 65 20 33 12 0 0 0 0 0 0 $32.21 Senior Staff Professional A. Langteau 2 0 2 0 0 0 0 0 0 0 $32.21 Administrative Assistant S. Darling 2 0 2 0 0 0 0 0 0 0

Total Hours 130 15 28 71 16 0 0 0 0 0 0

Direct Labor $5,021.37 $577.68 $1,079.82 $2,756.18 $607.69 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 172.70% $8,671.90 $997.65 $1,864.85 $4,759.92 $1,049.48 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $13,693.27 $1,575.33 $2,944.67 $7,516.10 $1,657.17 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Travel Vehicle Rental $1,080.00 $360.00 $480.00 $240.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF ARCADIS Page 1

FDEP COST ESTIMATEContractor: Geosyntec Consultants

Date: 1/25/2022

Task #: HW550-DC038F SubTask 1 Project Management SubTask 6

Site: Colonial/Touch of Class SubTask 2 Quarter 1: Feb 2022 - March 2022 O&M and Reporting SubTask 7

Activity/Phase: 6 Months O&M - Year 2 SubTask 3 Quarter 2: April 2022 - June 2022 O&M and Reporting SubTask 8

Project Manager: A. Galvin SubTask 4 Quarter 3: July 2022 O&M and Reporting SubTask 9

SubTask 5 Year 2 Utilities: Feb 2022 - July 2022 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $1,080.00 $360.00 $480.00 $240.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $3,000.00 $0.00 $0.00 $0.00 $3,000.00 $0.00 $0.00 $0.00 $0.00 $0.00 telemetry fee $975.84 $0.00 $0.00 $0.00 $975.84 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $3,975.84 $0.00 $0.00 $0.00 $3,975.84 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $140.00 $0.00 $0.00 $0.00 $140.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $4,115.84 $0.00 $0.00 $0.00 $4,115.84 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $546.00 $200.00 $346.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $410.00 $150.00 $260.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $956.00 $350.00 $606.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $280.00 $80.00 $160.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $315.00 $0.00 $315.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $200.00 $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $2,610.00 $870.00 $1,305.00 $435.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $3,405.00 $1,050.00 $1,880.00 $475.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $23,250.11 $1,575.33 $4,704.67 $10,482.10 $2,372.17 $4,115.84 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $1,369.33 $157.53 $294.47 $751.61 $165.72 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $24,619.44 $1,732.86 $4,999.14 $11,233.71 $2,537.89 $4,115.84 $0.00 $0.00 $0.00 $0.00 $0.00 subtasks (list) cost (by subtasks) Invoice 1 2 $4,999.14 invoice 2 3 $11,233.71 Invoice 3 1,4 $4,270.75 Invoice 4 5 $4,115.84

REV: 02/03 CEF ARCADIS Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Colonial/Touch of Class SUBTASK: Quarter 1: Feb 2022 - March 2022 O&M and Reporting

DATE: 1/25/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Principal K. Warner 2

Senior Professional A. Smith 2

Professional A. Galvin 4

Senior Staff Professional J. Udvardy 20

TOTAL LABOR 28

VEHICLE TYPE RATE UNIT USEAGE

Car $80.00 Day 0 $0.00

Truck 2 days O&M, 1 mobe for IDW $120.00 Day 3 $360.00

Van $120.00 Day 0 $0.00 Subtotal $360.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

TOTAL SUB $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TO-15 - Vapor VOCs combined influent $200.00 1 0 $200.00

Subtotal $200.00 Fast Turnaround Charges Percent

24 Hours 110% $0.00 0 $0.00 3 Days 65% $0.00 0 $0.00 1 Week 20% $0.00 0 $0.00

Subtotal $0.00 Shipping summa can Large Cooler (25 to 50 lbs) $150.00 1 $150.00

Small Cooler (0 to 25 lbs) $110.00 0 $0.00 Subtotal $150.00

TOTAL LAB $350.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

IDW Related

Drum $100.00 each 1 $100.00 Subtotal $100.00

Expendables 2 days O&M $40.00 Day 2 $80.00

Subtotal $80.00 Other

O&M supplies $75.00 Day 2 $150.00 O&M Kit $360.00 Day 2 $720.00

Subtotal $870.00

TOTAL EQUIPMENT $1,050.00

Quarterly O&M data and optimization evaluation (2 hrs)

Quarterly data interpretation (2 hr)

Monthly data evaluation and summary email (2 hrs/event - total 4 hrs)

2 O&M visits (8 hrs each incl rd trip, prep, breakdown - total 16 hrs); 1 rd trip mobe to drain moisture separator and manage onsite IDW (4 hrs)

FINAL --7/24/96

SUBTASK: Quarter 2: April 2022 - June 2022 O&M and Reporting

DATE: 1/25/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Principal K. Warner 3

Senior Professional A. Smith 7

Project Professional M. Hensley 2

Professional A. Galvin 22

Senior Staff Professional

J. Udvardy 33

Senior Staff Professional A. Langteau 2

Administrative Assistant S. Darling 2

TOTAL LABOR 71

VEHICLE TYPE RATE UNIT USEAGE

Car $80.00 Day 0 $0.00

Truck 3 days O&M, 1 mobe for IDW $120.00 Day 4 $480.00

Van $120.00 Day 0 $0.00 Subtotal $480.00

TOTAL VEHICLE $480.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

TOTAL SUB $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOHs - GW 2 MWs $73.00 2 0 $146.00 TO-15 - Vapor VOCs $200.00 1 0 $200.00

Subtotal $346.00 Fast Turnaround Charges Percent

24 Hours 110% $0.00 0 $0.00 3 Days 65% $0.00 0 $0.00 1 Week 20% $0.00 0 $0.00

Subtotal $0.00 Shipping summa can Large Cooler (25 to 50 lbs) $150.00 1 $150.00

Small Cooler (0 to 25 lbs) $110.00 1 $110.00 Subtotal $260.00

TOTAL LAB $606.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Analytical Related

Groundwater Sampling Kit $290.00 Day 1 $290.00 Water Level Meter $25.00 Day 1 $25.00 YSI 556 MPS $105.00 Day 0 $0.00

Subtotal $315.00 IDW Related

Drum $100.00 each 1 $100.00 Subtotal $100.00

Expendables 3 days O&M, 1 day GW sampling $40.00 Day 4 $160.00

Subtotal $160.00 Other

O&M supplies $75.00 Day 3 $225.00 O&M Kit $360.00 Day 3 $1,080.00

Subtotal $1,305.00

TOTAL EQUIPMENT $1,880.00

report formatting, PDF assembly and compilation

Quarterly O&M data review and optimization evaluation (3 hrs), Groundwater data evaluation (2 hrs); Semi-annual report data evaluation and interpretation (2 hrs); PE certification of Semi-Annual Report (3 hrs)

Preparation of figures for O&M Report (2 hrs)

Monthly data evaluation and summary email (2 hrs/event - 6 hrs); Semi-Annual SVE O&M Report (16 hrs)

3 O&M visits (8 hrs each incl rd trip, prep, breakdown - total 24 hrs); Semi-annual GW sampling event: GW equip calibration (pre, post) (1 hr); collect water levels at 7 wells (1 hr) and sample 2 wells @ 1.5 hrs/well (3 hrs); 1 rd trip mobe to drain moisture separator and manage onsite IDW (4 hrs)

11 data pts (2 air sample, 2 GW samples, 7 water levels =@ 8 min ea = 2 hr)

SUBTASK: Quarter 3: July 2022 O&M and Reporting

DATE: 1/25/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Principal K. Warner 1

Senior Professional A. Smith 1

Professional A. Galvin 2

Senior Staff Professional J. Udvardy 12

TOTAL LABOR 16

VEHICLE TYPE RATE UNIT USEAGE

Car $80.00 Day 0 $0.00 Truck 1 day O&M, 1 mobe IDW $120.00 Day 2 $240.00 Van $120.00 Day 0 $0.00

Subtotal $240.00

TOTAL VEHICLE $240.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

TOTAL SUB $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TO-15 - Vapor VOCs $200.00 0 0 $0.00

Subtotal $0.00 Fast Turnaround Charges Percent

24 Hours 110% $0.00 0 $0.00 3 Days 65% $0.00 0 $0.00 1 Week 20% $0.00 0 $0.00

Subtotal $0.00 Shipping summa can Large Cooler (25 to 50 lbs) $150.00 0 $0.00

Small Cooler (0 to 25 lbs) $110.00 0 $0.00 Subtotal $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables

1 day O&M $40.00 Day 1 $40.00 Subtotal $40.00

Other O&M supplies $75.00 Day 1 $75.00 O&M Kit $360.00 Day 1 $360.00

Subtotal $435.00

TOTAL EQUIPMENT $475.00

Quarterly O&M data and optimization evaluation (3 hrs)

Quarterly data interpretation (3 hr)

Monthly data evaluation and summary email (2 hrs/event - 2 hrs)

1 O&M visits (8 hrs each incl rd trip, prep, breakdown - total 8 hrs); 1 rd trip mobe to drain moisture separator and manage onsite IDW (4 hrs)

SUBTASK: Year 2 Utilities: Feb 2022 - July 2022

DATE: 1/25/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

TOTAL LABOR 0

VEHICLE TYPE RATE UNIT USEAGE

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Utilities FPL estimate (usage) electrical $500.00 6 $3,000.00 PRM Telemetry Fee Annual $975.84 1 $975.84 Processing Fee (electric) 6 months x $20/month $20.00 6 $120.00 Processing Fee (telemetry) 1 time (annual fee) $20.00 1 $20.00

Subtotal $4,115.84

TOTAL SUB $4,115.84

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT $0.00

12801 Tampa Oaks Blvd., Suite 151 Tampa, Florida 33637

PH 813.558.0990

FAX 813.558.9726

www.geosyntec.com

FR3169A/Colonial TOC_LOE_Year 2 OM_DC038F_revised

25 January 2022

Mr. Evan Miller Florida Department of Environmental Protection Waste Cleanup Program 2600 Blair Stone Road, MS 4520 Tallahassee, FL 32399-2400

Subject: 6 Months O&M – Year 2 - Soil Vapor Extraction System Colonial/Touch of Class 4552 Lake Worth Road Greenacres, Palm Beach County, Florida 33463 FDEP Facility ID NO. ERIC_5222 FDEP Task Assignment No. DC038F

Dear Evan:

Geosyntec Consultants, Inc. (Geosyntec) has prepared this Statement of Work (SOW) and Level of Effort (LOE) for six months of operations and maintenance (O&M) in the second operation year of the soil vapor extraction (SVE) system at Colonial/Touch of Class (Site) (Facility ID - ERIC 5222) located in Greenacres, Florida. The SVE system startup occurred 30 November 2020 through 2 December 2020. Monthly O&M has been conducted at the Site since startup, and air and groundwater sampling has been performed in general accordance with Table 6 of the FDEP-approved May 2020 Interim Source Removal (ISR) Work Plan. Note that some additional air and groundwater samples have been approved by FDEP and collected during Year 1.

This LOE is subdivided into subtasks by quarter. For ease of reference, the major scope elements are outlined below as they will pertain to multiple subtasks in some cases. Each subtask will be outlined separately thereafter.

SCOPE OF WORK ELEMENTS

Monthly SVE System O&M Tasks

Geosyntec personnel will conduct 6 monthly O&M visits to the Site beginning in February 2021 (Months 14 to 19 of system operation). Note that the January 2022 O&M (Month 13) is included

Colonial/Touch of Class – Year 2 O&M LOE

FR3169/Colonial TOC_LOE_Year 2 OM_DC038F_revised under TA DC038E, which has been approved by FDEP and is in progress. During each O&M visit, Geosyntec personnel will perform the following tasks:

• record vacuum, pressure, and temperature readings at the SVE blower;

• record air flow rates at the blower and five vapor extraction wells (VEWs);

• record vacuum readings at the five VEWs (VEW-1 through VEW-5), MW001 and

VMP01 through VMP05;

• drain fluids accumulated in the moisture separator and disposing of fluids in a 55-gallon drum as investigation derived waste (IDW; water from the moisture separator at the Site has been sampled, analyzed for volatile organic halocarbons [VOHs] and characterized as non-hazardous);

• collect groundwater level measurements from monitoring wells MW001 through

MW007;

• perform required air sampling;

• inspect and clean the equipment compound; and

• perform periodic equipment maintenance activities recommended by equipment manufacturers.

The results of the monthly system O&M activities will be documented in a site-specific O&M log, which will be submitted to the FDEP with the monthly O&M summary emails.

Groundwater sampling

In accordance with Table 6 of the approved May 2020 ISR Work Plan, MW001 and MW002 will be sampled semi-annually (June 2022). During Year 1, MW003 was added to the semi-annual sampling event due to an increase in VOH concentrations observed in November 2020; however, no GCTL exceedances were reported in MW003 during 2021 semi-annual or annual sampling event. Therefore, for Year 2, groundwater sampling in accordance with Table 6 of the May 2020 ISR Work Plan is proposed.

Prior to collecting groundwater samples, depth to water measurements will be collected from monitoring wells MW001 through MW007. The groundwater samples will be analyzed by a FDOH NELAC certified laboratory for VOHs using EPA Method 8260. Results of the groundwater sampling events will be documented in the O&M report for the same reporting period.

IDW Generation and Management

Investigative Derived Waste (IDW) is not assumed to be generated during the M14 – M19 O&M activities, therefore costs for IDW are not included in this LOE. If IDW is generated during this period, Geosyntec will submit a work change directive (WCD).

Air sampling

In accordance with Table 6 of the approved May 2020 ISR Work Plan, air emissions will be monitored by sampling combined influent air from the VEWs on a quarterly basis at the Site (one air sample per quarter). Combined effluent will not be sampled as the granular activated carbon (GAC) was removed from the SVE system on 11 May 2021 following the 7 April 2021 sampling event that continued to show that VOHs were below the Hazardous Air Pollutant (HAP) criteria requiring GAC treatment. Air samples will be collected with a summa canister and analyzed at a fixed-base laboratory for VOHs by EPA Method TO-15.

Reporting

A Year 2 Semi-Annual O&M Report (following Month 18 [June 2022]) will be prepared to document the results of O&M activities. The O&M reports will include, at a minimum, the following:

• results of laboratory analyses of air samples (tabular and graphical form);

• O&M activities performed during the reporting period;

• the calculated mass of PCE (and daughter products, if detected) removed by the SVE system during the reporting period, and cumulative total removed since startup;

• the SVE system hours of operation during the reporting period;

• information regarding the depth to groundwater;

• information regarding any repairs and/or modifications made to the SVE system;

• vacuum ROI data (tabular and illustrated); and

• recommendations and conclusions pertaining to the continued operation and/or optimization of the SVE system.

Utilities

Monthly electrical utility bills have been estimated at $300 based on the previous year’s average monthly invoices from Florida Power & Light. An invoice from Product Recovery Management, Inc. (PRM) for annual telemetry services from 1 January to 31 December 2022 was received.

Telemetry is currently provided by PRM and is available through 31 December 2021. The cost of telemetry is $76.00 per month with taxes for a total of $975.84 and is levied as an annual fee (Attachment A). The utilities also include a $20 monthly processing fee for electrical service and we have also applied $20 processing fee for one-time payment of the PRM telemetry invoice.

LOE SUBTASKS

Subtask 1: Project Management

Subtask 2: Quarter 1: February 2022 (Month 14) to March 2022 (Month 15) O&M and Reporting

Two months of O&M with monthly email summaries to FDEP and air sampling in Month 15.

Includes separate mobilization for Quarter 1 to drain moisture separator. Note that January 2022 O&M is included under TA DC037E, which has been approved by FDEP and is in progress.

Subtask 3: Quarter 2: April 2022 (Month 16) to June 2022 (Month 18) O&M and Reporting

Three months of O&M with monthly email summaries to FDEP, air sampling and semi-annual groundwater sampling in Month 18 and Semi-Annual O&M Report.

Subtask 4: Quarter 3: July 2022 (Month 19) O&M and Reporting

One month of O&M with a monthly email summary to FDEP.

Subtask 5: Year 2 Utilities - February 2022 (Month 14) to July 2022 (Month 19)

Six months of O&M utility costs.

Invoice and Deliverable Schedule:

Subtask Deliverable Deliverable Due

Date Invoice Amount

Quarter 1: February to March 2022 O&M summary emails and air sampling field notes 4/29/22 $4,999.14

Quarter 2: April 2022 to June 2022 O&M summary emails, air sampling, Semi-Annual O&M report, ADaPT and GIS Tables 7/29/22 $11,233.71

1,4 Quarter 3: July 2022 O&M summary email 8/31/22 $4,270.75 6 Utilities 1/31/23 $4,115.84

Total $24,619.44

As always, we appreciate the opportunity to continue working on this project for the FDEP. Please contact me at 561.922.1033 if you have any questions.

Andrew Galvin, P.E. Todd Kafka, P.G.

Engineer Senior Principal Geologist

Attachments

Cost Estimate Form Attachment A – Annual Telemetry Invoice

PRODUCT RECOVERY MGMT., INC.

200 20th STREET

BUTNER, NC 27509-2443 INVOICE NUMBER: 90917

INVOICE DATE: 11/03/21

DUE DATE: 12/02/21

919-957-8890 CUSTOMER NO: GEOSYF

919-957-7230 FAX SALESMAN: JUSTK

TERMS: NET 30 DAYS

P.O. NUMBER: TELEMETRY 2022 JOB: 006207 WS: 021 (1-1)

Stephanie Sanchez GEOSYNTEC CONSULTANTS Colonial Dry Cleaners stripp@geosyntec.com Palm Beach, FL

9000 BROKEN SOUND PKWY,STE.200

BOCA RATON, FL 33487

2022 Annual Telemetry Renewal.

RETURNS: No returns will be accepted without prior authorization.

Returns are subject to a 25% restocking fee which will be advised when RI # is issued.

Service will be valid from 1/1/2022 - 12/31/2022 12.00 76.00 912.00 and will automatically renew the following year unless cancelled in writing to PRM.

Subtotal: 912.00

(02051-PALM BEACH COUNTY, FL) Tax: 63.84 Invoice Total: 975.84

Service charge of 1.5% per month will be charged on all overdue invoices. If legal action is required to collect debts, client agrees to pay PRODUCT RECOVERY MGMT., INC. reasonable attorney fees. This agreement shall be governed by and construed in accordance with the laws of the State of North Carolina and venue shall be proper and personal jurisdiction had in Granville County, NC. Materials are warranteed by the manufacturer. This warranty does not cover labor charges. Warranty on workmenship is one year from date of installation.

Colonial TOC_CEF.pdf
Cost Estimate
Colonial TOC_LOEs.pdf
Subtask 2
Subtask 3
Subtask 4
Subtask 5
Colonial TOC_LOE_Year 2 OM_DC038F_(6 months).pdf
SCOPE OF WORK ELEMENTS
Monthly SVE System O&M Tasks
Groundwater sampling
IDW Generation and Management
Air sampling
Reporting
Utilities
LOE subtasks
Subtask 1: Project Management
Subtask 2: Quarter 1: February 2022 (Month 14) to March 2022 (Month 15) O&M and Reporting
Subtask 3: Quarter 2: April 2022 (Month 16) to June 2022 (Month 18) O&M and Reporting
Subtask 4: Quarter 3: July 2022 (Month 19) O&M and Reporting
Subtask 5: Year 2 Utilities - February 2022 (Month 14) to July 2022 (Month 19)