This document is a Task Assignment (TA) issued by the State of Florida Department of Environmental Protection (FDEP) to Geosyntec Consultants for site assessment activities at the Former Peacock Dry Cleaner facility located at 5021 Gulfport Boulevard in Gulfport, Florida (FDEP Site ID: ERIC_5330). The task assignment was executed on June 7, 2023, with a completion date of December 29, 2023, under Contract Number HW683. The work is being conducted as part of FDEP's Drycleaning Solvent Cleanup Program.

Geosyntec will perform site assessment services including soil sampling, modified active gas sampling (MAGS), direct push technology (DPT) groundwater sampling, monitoring well installation, and surveying for a total contract value of $76,752.97 on a fixed unit rate basis. The scope comprises seven subtasks: project management, soil sampling and MAGS activities, DPT groundwater investigation and monitoring well installation, monitoring well sampling and surveying, preliminary data review, investigation-derived waste (IDW) management, and site assessment report preparation. Work is scheduled across multiple invoicing phases with deliverables due from July through November 2023. Subcontractors selected for specialized services include Action Environmental for concrete coring and DPT drilling (based on earliest availability and competitive pricing), GeoTek Services for utility locating, SurvTech Solutions for monitoring well surveying, and Erwin Remediation for IDW transportation and disposal. The 342 total labor hours span professional and technical staff across multiple disciplines.

View the file

Other files

File Type Posted
CN-370000-HW683-BF02A.pdf.crdownload CRDOWNLOAD file
CN-370000-HW683-BF02ACO1.pdf PDF
CN-370000-HW683-BF02B.pdf PDF
CN-370000-HW683-BF04CCO2.pdf PDF
CN-370000-HW683-BIL01B.pdf PDF
CN-370000-HW683-BIL01C.pdf PDF
CN-370000-HW683-BIL03A.pdf PDF
CN-370000-HW683-CSS01.pdf PDF
CN-370000-HW683-CSS02B.pdf PDF
CN-370000-HW683-DC002B.pdf PDF
CN-370000-HW683-DC002C.pdf PDF
CN-370000-HW683-DC003D.pdf PDF
CN-370000-HW683-DC003F.pdf PDF
CN-370000-HW683-DC005A.pdf PDF
CN-370000-HW683-DC005B.pdf PDF
CN-370000-HW683-DC005C.pdf PDF
CN-370000-HW683-DC008C.pdf PDF
CN-370000-HW683-DC009D.pdf PDF
CN-370000-HW683-DC010B.pdf PDF
CN-370000-HW683-DC014B.pdf PDF
CN-370000-HW683-DC015A.pdf PDF
CN-370000-HW683-DC017B.pdf PDF
CN-370000-HW683-DC017D.pdf PDF
CN-370000-HW683-DC018A.pdf PDF
CN-370000-HW683-DC019E.pdf PDF
CN-370000-HW683-DC01ACO2.pdf PDF
CN-370000-HW683-DC01B.pdf PDF
CN-370000-HW683-DC020D.pdf PDF
CN-370000-HW683-DC025A.pdf PDF
CN-370000-HW683-DC025C.pdf PDF
CN-370000-HW683-DC028C.pdf PDF
CN-370000-HW683-DC029C.pdf PDF
CN-370000-HW683-DC029F.pdf PDF
CN-370000-HW683-DC029G.pdf PDF
CN-370000-HW683-DC02ECO2.pdf PDF
CN-370000-HW683-DC030A.pdf PDF
CN-370000-HW683-DC030B.pdf PDF
CN-370000-HW683-DC031A.pdf PDF
CN-370000-HW683-DC032B.pdf PDF
CN-370000-HW683-DC034A.pdf PDF
CN-370000-HW683-DC036C.pdf PDF
CN-370000-HW683-DC037A.pdf PDF
CN-370000-HW683-DC042B.pdf PDF
CN-370000-HW683-DC043B.pdf PDF
CN-370000-HW683-DC044C.pdf PDF
CN-370000-HW683-DC048A.pdf PDF
CN-370000-HW683-DC04A.pdf PDF
CN-370000-HW683-DC04ACO1.pdf PDF
CN-370000-HW683-DC05BCO1.pdf PDF
CN-370000-HW683-DC05BCO2.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW683

DC028B Completion December 29, 2023

This Task Assignment authorizes Geosyntec to conduct site assessment activities in accordance with the Geosyntec scope of work, cost estimate, and schedule received on May 26, 2023.

Brittany Plyler 850-245-8851 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

Geosyntec

Geosyntec

Olivia Cain 727-330-9961

ERIC_5330

5021 Gulfport Boulevard Gulfport, Florida 33707

Former Peacock Dry Cleaner

✔ $ 76,725.97

$ 76,725.97

Scope of Work

Todd Kafka

Contract Manager

Todd Kafka, P.G. Digitally signed by Todd Kafka, P.G.

Date: 2023.06.07 18:08:57 -04'00'

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2023.06.07 14:23:09 -04'00'

N/A

Murphy_SL Highlight

Murphy_SL Highlight

Murphy_SL Highlight

Murphy_SL Highlight

Murphy_SL Highlight

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Subtask 2: Soil Sampling and MAGS Field Deliverable 07/31/2023

Subtask 3: DPT Groundwater Sampling and Monitoring Well Installation Field Deliverable 08/18/2023

Subtask 4: Monitoring Well Sampling and Surveying Field Deliverable 08/31/2023

Subtask 5: Preliminary Data Review Meeting Minutes 09/29/2023

Subtask 1, 6, 7: Site Assessment Report with Final IDW Manifests 11/30/2023

Subtask 2: FDEP receipt and approval of the Soil Sampling and MAGS Field Deliverable $ 27,030.30

Subtask 3: FDEP receipt and approval of DPT Groundwater Sampling and Monitoring Well Installation Field Deliverable $ 27,826.41

Subtask 4: FDEP receipt and approval of Monitoring Well Sampling and Surveying Field Deliverable $ 7,367.62

Subtask 5: FDEP receipt and approval of Preliminary Data Review Meeting Minutes $ 1,041.26

Subtask 1, 6, 7: FDEP receipt and approval of Site Assessment Report with Final IDW Manifests $ 13,487.38

$ 76,752.97

HW683

DC028B

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Shawn Hamilton Secretary

To: HW683 Contract Negotiation File Former Peacock Cleaners Pinellas County, Florida

ERIC_5330

From: Brittany Plyler, Project Manager Date: May 30, 2023 Subject: Negotiation Summary

HW683_DC028B

This Task Assignment authorizes Geosyntec to conduct site assessment activities in accordance with the Geosyntec scope of work, cost estimate, and schedule received on May 26, 2023.

Geosyntec confirmed on May 26, 2023, that Subtask 1 consists of the calculated project management labor, based upon 13% of the direct labor costs in this proposal, and includes fringe, overhead, other direct costs (ODCs) and completion fees.

Subtask 2: This subtask includes costs to conduct a private utility locate, hand auger soil sampling, and modified active gas sampling (MAGS). Soil samples will be collected at up to seven (7) locations (MAGS001 through MAGS005, VMP001, and VMP002). Five, 2-inch diameter Schedule 40 polyvinyl chloride (PVC) MAGS wells (MAGS001 through MAGS005) will be installed.

Geosyntec has included costs to generate one figure and table that summarize VOC laboratory analytical results from soil samples and one figure and table that summarize VOC laboratory analytical results from MAGS samples.

Subtask 3: This subtask includes costs to conduct direct push technology (DPT) groundwater sampling, DPT soil sampling, and monitoring well installation during a single mobilization.

Geosyntec will mobilize to the Site to oversee the advancement of one lithologic soil boring (LSB001) using a DPT drill rig. Geosyntec will also collect groundwater samples using DPT at up to seven (7) locations (DPT001 through DPT007). Five monitoring wells (MW001 through MW005) will be installed at the approximate locations.

Action Environmental, the second lowest bidder was chosen instead of Ambient due to earliest avalibility.

Subtask 4: Subtask 4 includes costs for Geosyntec personnel to mobilize to the Site to conduct ground water sampling activities of Site monitoring wells. Cost also include a Florida professional land surveyor to survey the five (5) newly installed monitoring wells.

Subtask 5: This subtask includes time to prepare for and conduct a teleconference with FDEP to discuss the Subtask 2 and Subtask 3 results.

Printed on recycled paper.

MEMORANDUM

Former Peacock Dry Cleaners May 30, 2023 Page Two

Subtask 6: This subtask includes costs associated with the transportation and disposal of IDW generated as part of Site assessment activities. The soil and liquid IDW will be containerized in new 55-gallon drums and staged on-Site at a location designated by Geosyntec.

Subtask 7: Following completion of field activities, Geosyntec will proceed with the preparation and submittal of a Site Assessment Report (SAR) documenting assessment activities and summarizing analytical results.

The FDEP Project manager confirmed site access on May 30, 2023.

The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost is $76,752.97 with 342 labor hours.

FDEP COST ESTIMATE

Contractor: Geosyntec Consultants

Date: 5/26/2023

Task #: Pending SubTask 1 Project Management SubTask 6 Investigation Derrved Waste Management

Site: SubTask 2 Soil Sampling and Modified Active Gas Sampling SubTask 7 Site Assessment Report

Activity/Phase: Site Assessment SubTask 3 DPT GW Investigation and MW Install SubTask 8

Project Manager: O. Cain SubTask 4 Monitoring Well Sampling and Surveying SubTask 9

SubTask 5 Preliminary Data Review Teleconference SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10

Labor Rate Category

$43.51 Project Manager O. Cain 36 36.0 $86.54 Principal T. Kafka 9 2 2 1 2 0 2 0 0 0

$48.56 Project Professional M. Hensley 17 6 3 2 0 0 6 0 0 0

$43.51 Professional O. Cain 82 16 12 7 4 3 40 0 0 0

$39.98 Professional M. Lemes 53 53 0 0 0 0 0 0 0 0

$36.06 Senior Staff Professional K. Pierce 61 0 61 0 0 0 0 0 0 0

$30.29 Staff Professional M. Mohr 84 61 0 21 0 2 0 0 0 0

Total Hours 342 36 138 78 31 6 5 48 0 0 0

Direct Labor $13,599.73 $1,564.57 $5,127.23 $3,040.54 $1,124.32 $347.12 $191.11 $2,204.84 $0.00 $0.00 $0.00

Overhead 172.70% $23,486.74 $2,702.01 $8,854.73 $5,251.01 $1,941.70 $599.48 $330.05 $3,807.76 $0.00 $0.00 $0.00

Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Labor $37,086.47 $4,266.58 $13,981.96 $8,291.55 $3,066.02 $946.60 $521.16 $6,012.60 $0.00 $0.00 $0.00

Travel

Vehicle Rental $1,740.00 $1,080.00 $480.00 $120.00 $0.00 $60.00 $0.00 $0.00 $0.00 $0.00

Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Travel $1,740.00 $1,080.00 $480.00 $120.00 $0.00 $60.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement)

Atlantic Drilling $469.46 $469.46 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Home Depot $45.66 $45.66 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $515.12 $515.12 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Procurement Fee $51.52 $51.52 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Subcontractor Cost $566.64 $566.64 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Former Peacock Dry Cleaner

Cost Estimate Page 1 of 8 Cost Estimate

FDEP COST ESTIMATEContractor: Geosyntec Consultants

Date: 5/26/2023

Task #: Pending SubTask 1 Project Management SubTask 6 Investigation Derrved Waste Management

Site: SubTask 2 Soil Sampling and Modified Active Gas Sampling SubTask 7 Site Assessment Report

Activity/Phase: Site Assessment SubTask 3 DPT GW Investigation and MW Install SubTask 8

Project Manager: O. Cain SubTask 4 Monitoring Well Sampling and Surveying SubTask 9

SubTask 5 Preliminary Data Review Teleconference SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10

Former Peacock Dry Cleaner

Subcontractor (Services Procurement)

Drilling (Conventional) $13,347.00 $0.00 $13,347.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Surveying $2,800.00 $0.00 $0.00 $2,800.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $770.00 $0.00 $0.00 $0.00 $0.00 $770.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Concrete Coring $995.00 $995.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Private Utility Locate $750.00 $750.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $18,662.00 $1,745.00 $13,347.00 $2,800.00 $0.00 $770.00 $0.00 $0.00 $0.00 $0.00

Handling Fee $1,866.20 $174.50 $1,334.70 $280.00 $0.00 $77.00 $0.00 $0.00 $0.00 $0.00

Total Subcontractor Cost $20,528.20 $1,919.50 $14,681.70 $3,080.00 $0.00 $847.00 $0.00 $0.00 $0.00 $0.00

Laboratory

Analytical Costs $7,021.00 $3,932.00 $2,044.00 $365.00 $0.00 $680.00 $0.00 $0.00 $0.00 $0.00

Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Laboratory $7,021.00 $3,932.00 $2,044.00 $365.00 $0.00 $680.00 $0.00 $0.00 $0.00 $0.00

Field Expenses

Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Expendables $500.00 $240.00 $200.00 $40.00 $0.00 $20.00 $0.00 $0.00 $0.00 $0.00

Equipment (Drilling related) $3,160.00 $1,860.00 $1,300.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Analytical related) $792.00 $502.00 $0.00 $290.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (IDW related) $300.00 $200.00 $0.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Other) $1,350.00 $1,350.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Field Expenses $6,102.00 $4,152.00 $1,500.00 $430.00 $0.00 $20.00 $0.00 $0.00 $0.00 $0.00

Subtotal $73,044.31 $4,266.58 $25,632.10 $26,997.25 $7,061.02 $946.60 $2,128.16 $6,012.60 $0.00 $0.00 $0.00

Completion Fee $3,708.66 $426.66 $1,398.20 $829.16 $306.60 $94.66 $52.12 $601.26 $0.00 $0.00 $0.00

Total Estimated Cost $76,752.97 $4,693.24 $27,030.30 $27,826.41 $7,367.62 $1,041.26 $2,180.28 $6,613.86 $0.00 $0.00 $0.00

Invoice 1 (ST 2) $27,030.30 Invoice 2 (ST 3) $27,826.41 Invoice 3 (ST 4) $7,367.62 Invoice 5 (ST 5) $1,041.26

Invoice 6 (ST 1,6,7) $13,487.38 Check $76,752.97

Cost Estimate Page 2 of 8 Cost Estimate

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Former Peacock Dry Cleaner SUBTASK: Soil Sampling and Modified Active Gas Sampling

DATE: 5/26/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Principal T. Kafka 2

Project Professional M. Hensley 6

Professional O. Cain 16

Professional M. Lemes 53

Staff Professional M. Mohr 61

TOTAL LABOR 138

VEHICLE TYPE RATE UNIT USEAGE

Truck Mohr $120.00 Day 1 $120.00 Truck Mohr $480.00 Week 1 $480.00 Van Lemmes $480.00 Week 1 $480.00

Subtotal $1,080.00

Mileage $0.59 Mile 0 $0.00 Subtotal $0.00

Air Fare $0.00 Round Trip 0 $0.00 Subtotal $0.00

TOTAL VEHICLE $1,080.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 Day 0 $0.00 $0.00 Day 0 $0.00 $0.00 Day 0 $0.00 $0.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Equipment Procurement Atlantic Drilling Supply MAGS materials $469.46 $469.46 Home Depot MAGS materials $45.66 $45.66

Subtotal $515.12

Other Action Environmental Interior concrete coring $995.00 $995.00 GeoTek, LLC Utility locate $750.00 $750.00

Subtotal $1,745.00

TOTAL SUB $2,260.12

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOHs - Soil 7 borings x 3 samples/boring $73.00 21 0 $1,533.00 VOHs - Soil or Water Unknown manholes $73.00 3 0 $219.00 VOHs - Water SPLP $73.00 10 0 $730.00 SPLP Extraction $45.00 10 0 $450.00 TO-15 - Soil Gas 5 MAGs $200.00 5 0 $1,000.00

Subtotal $3,932.00

TOTAL LAB $3,932.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Drilling Related Soil Vapor Sampling Kit $1,160.00 Week 1 $1,160.00 Soil Assessment Kit $700.00 Week 1 $700.00

Subtotal $1,860.00 Analytical Related

Water Level Meter $100.00 Week 1 $100.00 Encore Sampler $16.00 Each 21 $336.00 Air Sampling Summa Canister $33.00 Day 2 $66.00

Subtotal $502.00 IDW Related

Drum $100.00 Drum 2 $200.00 Subtotal $200.00

Expendables $40.00 Day 6 $240.00

Subtotal $240.00

Other GPS $175.00 Day 2 $350.00 Vacuum Gauges $19.00 Day 2 $38.00 Differential Pressure Gauge $18.00 Day 2 $36.00 Regenerative Blower $180.00 Day 2 $360.00 Air Flow Meter $33.00 Day 2 $66.00 Portable Generator $250.00 Day 2 $500.00

Subtotal $1,350.00

TOTAL EQUIPMENT $4,152.00

Evaluating and interpreting field data

Preparation of soil and MAGS results figures

Property owner and tenant notificaitons (1 hr). Evaluating and interpreting field data (1 hr/day x 5 days = 5 hr). MAGS and soil results tables (3 hr). MAGS and soil figure generation (2 hr). MAGS data evaluation (2 hr). Prepare field deliverable package (3 hr).

Field preparation (1 hr). Mob/demob from Tampa (1 hr/day x 5 day = 5 hr). Calibration of instruments (0.5 hr/day x 5 day = 3 hr). Soil sampling (1.5 hr/location x 10 locations = 15 hr);

MAGS well installation (2 hr/well x 5 wells = 10 hr). VMP well installation (2 hr/well x 2 wells = 4 hr). MAGS equipment setup (0.5 hr/well x 5 wells = 3 hrs). MAGS testing with step test (2 hr/well x 5 wells = 10 hr). Interior as-built sketch (2 hr).

Field preparation, including purchasing MAGS supplies and picking up blower (4 hr). Mark borings, oversee utility locate, and suvey utilities including mob (8 hr).

Mob/demob from Clearwater (0.5 hr/day x 5 days = 3 hr). Soil coring and sampling (1.5 hr/location x 10 locations = 15 hr). MAGS well installation (2 hr/well x 5 wells = 10 hr). VMP well installation (2 hr/well x 2 wells = 4 hr). MAGS equipment setup (0.5 hr/well x 5 wells = 3 hrs). MAGS testing with step test (2 hr/well x 5 wells = 10 hr). Interior as-built generation (2 hr). IDW management (1 hr). Sample management (1 hr).

5/26/2023 Page 3 of 8 Subtask 2

SUBTASK: DPT GW Investigation and MW Install

DATE: 5/26/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Principal

T. Kafka 2

Project Professional

M. Hensley 3

Professional

O. Cain 12

Senior Staff Professional

K. Pierce 61

TOTAL LABOR 78

VEHICLE TYPE RATE UNIT USEAGE

Truck Pierce $480.00 Week 1 $480.00

Subtotal $480.00

TOTAL VEHICLE $480.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Drilling (Conventional)

Action Environmental DPT drilling $13,347.00 $13,347.00

Subtotal $13,347.00

TOTAL SUB $13,347.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOHs - Water 7 borings x 4 samples/boring $73.00 28 0 $2,044.00

Subtotal $2,044.00

TOTAL LAB $2,044.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Drilling Related

Monitoring Well Installation Kit $1,300.00 Week 1 $1,300.00

Subtotal $1,300.00

Expendables

$40.00 Day 5 $200.00

Subtotal $200.00

TOTAL EQUIPMENT $1,500.00

Evaluating and interpreting field data

Prepare DPT groundwater results figure

Property owner and tenant notificaitons (1 hr). Evaluating and interpreting field data (1 hr/day x 5 days = 5 hr). Prepare field deliverable package (3 hr). DPT groundwater results table (2 hr). DPT groundwater figure generation (1 hr).

Field preparation (1 hr). Mob/demob from Tampa (1 hr/day x 5 days = 5 hr). Oversight of DPT lithology, DPT groundwater sampling, and monitoring well installation (10 hr/day x 5 days = 50 hr). Interior as-built generation (2 hr). IDW management (1 hr). Sample management (1 hr).

5/26/2023 Page 4 of 8 Subtask 3

SUBTASK: Monitoring Well Sampling and Surveying

DATE: 5/26/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Principal

T. Kafka 1

Project Professional

M. Hensley 2

Professional

O. Cain 7

Staff Professional

M. Mohr 21

TOTAL LABOR 31

VEHICLE TYPE RATE UNIT USEAGE

Van Mohr $120.00 Day 1 $120.00

Subtotal $120.00

TOTAL VEHICLE $120.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Surveying

SurvTech Solutions MW survey $2,800.00 $2,800.00

Subtotal $2,800.00

TOTAL SUB $2,800.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOHs $73.00 5 0 $365.00

Subtotal $365.00

TOTAL LAB $365.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Analytical Related

Groundwater Sampling Kit $290.00 Day 1 $290.00

Subtotal $290.00

IDW Related

Drum $100.00 Drum 1 $100.00

Subtotal $100.00

Expendables

$40.00 Day 1 $40.00

Subtotal $40.00

TOTAL EQUIPMENT $430.00

Evaluating and interpreting field data

Prepare monitoring well results figure

Property owner and tenant notifications (1 hr). Evaluating and interpreting field data (1 hr).

Prepare field package (2 hr). Monitoring well results tables (2 hr). Monitoring well results

Field preparation (1 hr). Mob/demob from Clearwater (1 hr). Instrument calibration (1 hr).

Sample monitoring wells (1.5 hr/well x 5 wells = 8 hr). IDW management (1 hr). Sample management (1 hr). Compile field notes (1 hr).

Mob/demob from Clearwater (1 hr). Oversee monitoring well survey (4 hr).

5/26/2023 Page 5 of 8 Subtask 4

SUBTASK: Preliminary Data Review Teleconference

DATE: 5/26/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Principal

T. Kafka 2

Professional

O. Cain 4

TOTAL LABOR 6

Prepare for and conduct teleconference with FDEP to discuss soil, MAGS, and groundwater results

Prepare for and conduct teleconference with FDEP to discuss soil, MAGS, and groundwater results (3 hr). Prepare email summary of meeting minutes (1 hr).

5/26/2023 Page 6 of 8 Subtask 5

SUBTASK: Investigation Derrved Waste Management

DATE: 5/26/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Professional

O. Cain 3

Staff Professional

M. Mohr 2

TOTAL LABOR 5

VEHICLE TYPE RATE UNIT USEAGE

Van $120.00 Day 0.5 $60.00

Subtotal $60.00

TOTAL VEHICLE $60.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

IDW

Erwin Remediation 7 drums x $110/drum $770.00 $770.00

$0.00 $0.00

Subtotal $770.00

TOTAL SUB $770.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TCLP VOCs (Soil) $210.00 1 0 $210.00

TCLP Metals (Soil) $135.00 1 0 $135.00

TCLP VOCs (Aqueous) $205.00 1 0 $205.00

TCLP Metals (Aqueous) $130.00 1 0 $130.00

Subtotal $680.00

TOTAL LAB $680.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables

$40.00 Day 0.5 $20.00

Subtotal $20.00

TOTAL EQUIPMENT $20.00

Characterization and waste profile for transport and disposal of drums (2 hr). Prepare and sign IDW manifest (1 hr).

IDW sampling with mobilization

5/26/2023 Page 7 of 8 Subtask 6

SUBTASK: Site Assessment Report

DATE: 5/26/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Principal

T. Kafka 2

Project Professional

M. Hensley 6

Professional

O. Cain 40

TOTAL LABOR 48

Develop recommendations and path forward

SAR figure preparation, including a well survey, cross section, and groundwater elevation map

SAR preparation

5/26/2023 Page 8 of 8 Subtask 7

19321 U.S. Highway 19 North Building C, Suite 200

Clearwater, Florida 33764

PH 813-792-4820

www.geosyntec.com

Former Peacock Dry Cleaner (ERIC_5330)_HW683 SOW_SAR_2023-05

May 26, 2023

Ms. Brittany Plyer Florida Department of Environmental Protection 2600 Blair Stone Road Tallahassee, FL 32399-2400

Subject: Scope of Work and CEF/LOE – Site Assessment

Former Peacock Dry Cleaner 5021 Gulfport Boulevard Gulfport, Florida 33707 FDEP Site ID No. ERIC_5330

Dear Ms. Plyer:

Geosyntec Consultants, Inc. (Geosyntec) has prepared this Scope of Work (SOW) and Level of Effort (LOE) for site assessment activities at the Former Peacock Dry Cleaner (“Site”) located in Gulfport, Florida (ERIC_5330). Geosyntec prepared this LOE based on Geosyntec’s March 15, 2023 Site Assessment Work Plan (SAWP), approved by FDEP. A description of task breakdown for Site assessment field activities and report preparation is provided below. A cost estimating form (CEF) and LOE is provided as Attachment A.

Geosyntec obtained three bids from licensed and qualified contractors for utility locating, concrete coring, drilling, and investigation derived waste (IDW) transportation and disposal. A cost comparison is provided in Attachment B. Geosyntec recommends the following subcontractors based on lowest cost and/or earliest availability among the qualified bidders:

Underground utility locating – GeoTek Services, LLC Concrete coring – Action Environmental DPT groundwater sampling and monitoring well installation – Action Environmental

(earliest availability and second lowest cost) IDW transportation and disposal – Erwin Remediation, Inc.

SurvTech Solutions, Inc. is recommended for surveying of the five (5) monitoring wells. Copies of the bids from each subcontractor are included in Attachment B.

The figures and Table 1 from the SAWP have been revised to reflect FDEP’s comments and are included in Attachment C.

Subtask 1 – Project Management

Costs associated with this subtask are directly computed.

Subtask 2 – Soil Sampling and Modified Active Gas Sampling

This subtask includes costs to conduct a private utility locate, hand auger soil sampling, and modified active gas sampling (MAGS). These activities are summarized below and are anticipated to be performed during a single mobilization.

Private Utility Locate

Geosyntec personnel will mobilize to the Site to oversee a private underground utility survey.

Identified utilities inside and around the Site building will be mapped by Geosyntec staff using a Global Position System (GPS) unit following the private underground utility survey. As a cost savings, Geosyntec assumes that the locator will also scan each location proposed under Subtask 3 for underground utilities while on-Site.

Concrete Coring

Geosyntec personnel will oversee coring activities within the Site building by a concrete coring contractor. Based on observations during the SAWP Site visit, it is anticipated that the foundation inside the Site building may be up to 12 inches thick. The contractor will core the concrete at locations MAGS001 through MAGS005, VMP001, and VMP002 (Subtask 2), and MW001 and MW002 (Subtask 3).

Unknown Manhole Assessment

Geosyntec will attempt to sample soil and/or groundwater encountered in the three unknown manholes in the Storage Area of the Family Dollar. Either a grab soil sample or grab groundwater sample will be collected from each location depending on conditions observed and if Geosyntec is able to chip/break open the grouted locations. The samples will be analyzed using United States Environmental Protection Agency (EPA) Method 8260 (full list) for volatile organic compounds (VOCs) by a state of Florida certified, National Environmental Laboratory Accreditation Program (NELAP) accredited fixed-based laboratory.

Soil Sampling

Soil samples will be collected at up to seven (7) locations (MAGS001 through MAGS005, VMP001, and VMP002) to identify the location of potential source area(s). A hand auger will be used to collect samples from the following intervals: 0 to 0.5, 0.5 to 2, and 2 to 4 (or the water table if encountered shallower than 4 ft BLS). The depth of each soil boring may be adjusted based on the observed depth to water encountered during soil boring completion.

Soil samples will be screened with a photo-ionization detector (PID) organic vapor analyzer.

Should observations suggest that a separate discrete depth should also be sampled, the sample will be collected and held for subsequent analysis, pending discussions with FDEP.

The soil samples will be analyzed using EPA Method 8260 (full list) for VOCs by a state of Florida certified, NELAP-accredited fixed-based laboratory. At each soil sample location, a 25-gram, Encore sample will be collected to evaluate soil leachability. The samples will be placed on hold with the analytical laboratory. If leachability criteria for constituents are exceeded in soil sample(s), and concentrations are below the Residential Soil Cleanup Target Level (SCTL), Geosyntec will inform FDEP and request approval to instruct the analytical laboratory to analyze the corresponding Encore sample using the Synthetic Precipitation Leaching Procedure (SPLP).

For budgetary purposes, it is assumed that approximately half of the proposed soil samples (10) will be analyzed by SPLP for VOHs.

Exterior soil samples will be surveyed with a GPS. Interior sampling locations will be transcribed using as-builts based on Site features.

MAGS

Five, 2-inch diameter Schedule 40 polyvinyl chloride (PVC) MAGS wells (MAGS001 through MAGS005) will be installed at the approximate locations shown on Figure 1 included in Attachment C by hand auger to a depth of approximately 3 ft BLS (i.e., 1-ft above the anticipated depth to groundwater). Each MAGS well will be installed with 1-ft of riser and 2-ft of 0.01-inch slotted well screen extending from approximately 1 to 3 ft BLS. A 20/30 grade environmental sand filter pack will be placed from the bottom of the boring to the top of the well screen. The remaining annular space will be grouted to just below the top of casing. A temporary grout patch will be placed on top of a PVC cap that will be placed on each well to match existing grade and protect the well fo9llowing installation and testing. Exterior MAGS locations will be surveyed with a GPS. Interior sampling locations will be transcribed using as-builts based on Site features.

Three, 1-inch diameter Schedule 40 PVC vapor monitoring points (VMPs; VMP001 through VMP003) will be installed at the approximate locations shown on Figure 1 included in Attachment C using a hand auger to a depth of approximately 3 ft BLS (or 1-ft above the anticipated depth to groundwater). Each VMP will be installed with approximately 1-ft of 1-inch diameter Schedule 40 PVC riser and 2-ft of 1-inch diameter Schedule 40 PVC screen slotted at 0.010-inches extending from approximately 1 to 3 ft BLS. A 20/30 grade environmental sand filter pack will be placed from the bottom of the boring to the top of the VMP screen. The remaining annular space will be grouted to just below the top of casing. A temporary grout patch will be placed on top of a PVC cap that will be placed on each well to match existing grade and protect the VMP following installation and testing. VMP locations will be transcribed using as-builts based on Site features.

Quotes for MAGS supplies are included in Attachment D.

Each MAGS well will be tested for a period calculated to remove one, 10 to 15-ft radius of soil vapor volume using a blower. The test duration is expected to be up to 1 hour. The vacuum and flow rates used at each MAGS well will be based on the results of a step test at one interior location.

The step test will include a minimum of three steps at increasing vacuums to evaluate to evaluate optimum air flow rates. Vacuum will be monitored at adjacent MAGS wells, VMPs, and monitoring wells (see Subtask 3) at approximate 15-minute intervals, as practical, during MAGS testing.

During testing, soil vapor will be monitored with an organic vapor analyzer equipped with a photoionization detector (PID) utilizing a 10.6 electronic volt lamp. Soil vapor samples (5 total) will be collected at the end of each MAGS test using a batch-certified “clean” Summa canister provided by the analytical laboratory. The soil vapor samples will be sent to a fixed-based laboratory for analysis of VOCs by the TO-15 method.

Field Deliverable and Draft Summary Figures

Geosyntec has included costs to generate one figure and table that summarize VOC laboratory analytical results from soil samples and one figure and table that summarize VOC laboratory analytical results from MAGS samples. These data will be provided to FDEP for evaluation. Data gaps will be addressed during Subtask 5, if warranted.

Subtask 3 – DPT Investigation and Monitoring Well Installation

This subtask includes costs to conduct direct push technology (DPT) groundwater sampling, DPT soil sampling, and monitoring well installation during a single mobilization. These activities are summarized below.

Lithologic Soil Boring and DPT Groundwater Sampling

Geosyntec will mobilize to the Site to oversee the advancement of one lithologic soil boring (LSB001) using a DPT drill rig to a depth of approximately 50 ft BLS (or refusal, whichever comes first) to characterize the Site-specific lithology. Geosyntec proposes to install the LSB001 south of the Site building between the locations of the former temporary monitoring wells (Figure 2 of the SAWP included in Attachment C). This data will be used to assist in the evaluation of DPT groundwater sampling intervals and better understand the lithology at the Site.

Geosyntec will also collect groundwater samples using DPT at up to seven (7) locations (DPT001 through DPT007) as shown on Figure 2 of the SAWP included in Attachment C. Groundwater samples will be collected at 4-ft intervals approximately every 10 feet (i.e., 6 to 10 ft BLS, 16 to 20 ft BLS, 26 to 30 ft BLS, and 36 to 40 ft BLS) to an estimated 40 ft BLS or refusal, whichever comes first. Sampling depths may be adjusted based on the results from LSB001. Groundwater samples submitted to a NELAP-approved fixed-based laboratory will be analyzed for the presence of VOCs by EPA Method 8260 (full list).

Geosyntec has included costs to generate one figure and table that summarize VOC laboratory analytical results from the DPT groundwater samples. If fixed-based laboratory analytical results of DPT groundwater samples indicate that additional groundwater sampling will be required for delineation of groundwater impacts, Geosyntec will propose additional sampling locations and corresponding depths and/or monitoring wells, if warranted.

Monitoring Well Installation

Five monitoring wells (MW001 through MW005) will be installed at the approximate locations shown on Figure 2 of the SAWP included in Attachment C. Monitoring wells MW001 and MW002 will be installed using a hand auger and constructed of 2-ft of 1-inch diameter Schedule 40 PVC riser and either 5-ft or 10-ft of 1-inch diameter Schedule 40 PVC pre-packed well screen.

If the borehole does not collapse, the monitoring wells will be screened from approximately 2 to 12 ft BLS. If the borehole collapses, then the monitoring wells will be screened from 2 to 7 ft BLS.

Monitoring wells MW003 through MW005 will be installed using DPT and constructed of 2-ft of 1-inch diameter Schedule 40 polyvinyl chloride (PVC) riser and 10-ft of 1-inch diameter Schedule 40 PVC pre-packed well screen extending from approximately 2 to 12 ft BLS.

If the formation does not collapse around the PVC during installation, a filter pack consisting of 20/30 silica sand will be placed around the well screen to approximately 0.5-ft above the top of the screen followed by at least a 0.5-ft thick, fine sand (30/65 silica sand) seal. The remaining annular space will be grouted to land surface with Portland Cement Type I/II and monitoring wells will be completed at the surface with a flush-mount 6- or 8-inch diameter manhole and a locking monitoring well cap. The monitoring wells will be developed until the discharge is relatively sediment-free. The top-of-casing elevation and horizontal coordinates of each monitoring well will be measured by a Florida-licensed professional surveyor as part of Subtask 4.

Field Deliverable and Draft Summary Figure

Geosyntec has included costs to generate one figure and table that summarize VOC laboratory analytical results from DPT groundwater samples. These data will be provided to FDEP for evaluation. Data gaps will be addressed during Subtask 5, if warranted.

Subtask 4 – Monitoring Well Sampling and Surveying

This subtask includes costs to collect groundwater samples from the newly installed monitoring wells and oversee a professional survey. These activities are summarized below.

Monitoring Well Sampling

Subtask 4 includes costs for Geosyntec personnel to mobilize to the Site to conduct groundwater sampling activities of Site monitoring wells. Prior to sampling, depth to water measurements will be collected from Site monitoring wells to evaluate groundwater flow direction. The monitoring wells will be sampled using a peristaltic pump in general accordance with FDEP Standard Operating Procedures (SOPs). The samples will be stored on ice and shipped to a NELAP approved, fixed-based analytical laboratory under chain of custody for analysis under standard turnaround times. The groundwater samples will be analyzed for VOCs by EPA Method 8260.

Screening for per- and polyfluoroalkyl substances (PFAS) has been authorized by FDEP for the two monitoring wells under task assignment HW028A.

Monitoring Well Survey

This subtask includes costs for a Florida professional land surveyor to survey the five (5) newly installed monitoring wells. Cost has been included for Geosyntec to oversee the survey.

Field Deliverable and Draft Summary Figure

Geosyntec has included costs to generate one figure and table that summarize VOC laboratory analytical results from groundwater monitoring well samples. These data will be provided to FDEP for evaluation. Data gaps will be addressed during Subtask 5, if warranted.

Subtask 5 – Preliminary Data Review Teleconference

This subtask includes time to prepare for and conduct a teleconference with FDEP to discuss the Subtask 2 and Subtask 3 results. If warranted and agreed upon during the teleconference, additional assessment activities may be proposed to complete Site assessment under Chapter 62-780, FAC.

Presumptive remedies, if warranted, will also be discussed during this teleconference.

Subtask 6 – IDW Management

This subtask includes costs associated with the transportation and disposal of IDW generated as part of Site assessment activities. The soil and liquid IDW will be containerized in new 55-gallon drums and staged on-Site at a location designated by Geosyntec. It is estimated that the following number of drums will be generated as part of each subtask.

Soil Drums Liquid Drums

Subtask 2 – Soil Sampling and MAGS 1 1

Subtask 3 – DPT Soil and Groundwater Sampling, and Monitoring Well Installation

1 2

Subtask 4 – Monitoring Well Sampling 0 1

Total Drums for All Subtasks 3 4

The IDW will be sampled prior to profiling. One composite liquid and one composite soil sample will be collected ana analyzed for VOCs and metals using the Toxic Characteristic Leaching Procedure. Geosyntec will review the generation of a waste characterization profile as well as the preparation of IDW manifests. Geosyntec will coordinate disposal arrangements for up to 7 drums of non-hazardous IDW. Analytical costs are included to establish the soil and groundwater profiles required by the selected waste hauler. We have assumed field oversight of the drum pickup is not necessary.

Subtask 7 – Site Assessment Report

Following completion of field activities, Geosyntec will proceed with the preparation and submittal of a Site Assessment Report (SAR) documenting assessment activities and summarizing analytical results. This subtask includes costs to generate a SAR that summarizes the analytical results of the assessment activities outlined above and complies with the requirements of Chapter 62-780.600, FAC. The costing included in the CEF/LOE includes the following figures:

USGS Site Topographic Map

Potable Well Survey

Site Layout

Site Utility Map

Lithologic Cross Section (1 transect)

Summary of Soil Analytical Results from 0-0.5, 0.5-2, and 2-4 ft BLS (3 figures)

Summary of DPT Groundwater Sampling Analytical Results

Summary of Groundwater Elevations

Summary of Monitoring Well Analytical Results

Invoice and Deliverable Schedule

Subtask Deliverable Due Date Invoice Amount

Soil Sampling and MAGS Field Deliverable

July 20, 2023 $27,030.30

DPT Groundwater Sampling and Monitoring Well Installation Field Deliverable

July 27, 2023 $27,826.41

Monitoring Well Sampling and Surveying Field Deliverable

August 17, 2023 $7,367.62

Preliminary Data Review Meeting Minutes

September 14, 2023 $1,041.26

1,6,7 Site Assessment Report with Final IDW Manifests

November 16, 2023 $13,487.38

Total $76,752.97

The above schedule is based on the assumptions that Geosyntec is tasked for this scope of work by May 31, 2023.

Assumes Subtask 2 and Subtask 3 activities are conducted in June 2023.

CLOSURE

Please review and contact us if you have any questions or require additional information. As always, it is a pleasure to work with the FDEP.

Sincerely, Olivia Cain, P.E. (FL) Todd K. Kafka, P.G. (FL) Engineer Senior Principal Hydrogeologist

Attachments: Attachment A – CEF-LOE Attachment B – Bid Evaluations

Attachment C – SAWP Attachment D – MAGS Materials Quotes

ATTACHMENT B

Bid Evaluations

Utility Locate Bids

Underground Utility Locate

Company GeoTek, LLC GeoView, Inc Site Lines, LLC

Total Quote $750.00 $1,300.00 $800.00

Peacock Dry Cleaner (Formerly), Gulfport, Florida

Subcontractor Cost Evaluation

Job Details - Scan up to 20 locations inside and outside the Site building.

FDEP Site ID No. ERIC_5330

GeoTek Services, LLC

09 May 2023

To: Olivia Cain

Geosyntec Consultants 19321 US Highway 19 N

Clearwater, Florida 33764

From: GeoTek Services, LLC 4060 Sparrow Hawk Road

Melbourne, Florida 32934

RE: Utility Locating Services – Peacock Dry Cleaners, Gulfport, Florida

Ms. Cain, GeoTek Services is pleased to respond to your request for Utility Locating services at the Peacock Dry Cleaner site located in Gulfport, Florida. We will scan a 10’ x 10’ area around 20 proposed bore locations with the goal of locating underground utilities.

We can only scan the easily accessible open areas for utilities. Note that we cannot scan beneath fixed objects such as landscaping, fencing, buildings, or vehicles. We will scan as close as reasonably possible to fixed objects such as brush, curbing, etc. Our deliverable will be marking paint and/or flags indicating the location of potential underground utilities. It is the client’s responsibility to protect and preserve all marks.

We will use both Electromagnetic Induction instruments as well as Ground Penetrating Radar (GPR) to detect objects below the surface. Due to the nature of sub-surface detection and the physical laws governing radio wave propagation, some buried objects may not be detectable due to depth, obscuration, or a weak radar signature. GeoTek Services will use industry standard best practices to locate sub-surface objects, however some objects may not be detectable. Geotek Services does not guarantee that all underground objects can be found. GeoTek Services assumes no liability for any damages.

We request access to any as-built site plans of the scan areas prior to rendering services. Our quote for this effort is $750.00. No out-of-pocket expenses are expected for this project. This quote is valid for sixty days.

Best Regards, Martin (Bud) Connor GeoTek Services, LLC

4060 Sparrow Hawk Road ● Melbourne, FL 32934-8525 ● info@GeoTekServices.com ● 321.473.7498

Olivia Cain

From: Mike Wightman <mwightman@geoviewinc.com> Sent: Wednesday, May 10, 2023 5:56 PM To: Olivia Cain Subject: RE: Request for Quote (GeoView) - Utility Locate in Gulfport - Peacock Dry Cleaner

CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe. If you have any suspicion, please confirm with the sender verbally that this email is authentic. If you suspect fraud, click "Phish Alert Report."

No, I can estimate it. Our bid would be $1300. Do you need a formal proposal?

Mike Wightman, P.G President, GeoView O: 727‐209‐2334 C: 813‐690‐6667 mwightman@geoviewinc.com

From: Olivia Cain <OCain@Geosyntec.com> Sent: Wednesday, May 10, 2023 5:34 PM To: Mike Wightman <mwightman@geoviewinc.com> Subject: RE: Request for Quote (GeoView) ‐ Utility Locate in Gulfport ‐ Peacock Dry Cleaner

That is correct – do you need a count?

Olivia B. Cain, P.E. (FL) Engineer Geosyntec Consultants, Inc.

Clearwater, FL Pronouns: she/her

From: Mike Wightman <mwightman@geoviewinc.com> Sent: Wednesday, May 10, 2023 9:58 AM To: Olivia Cain <OCain@Geosyntec.com> Subject: RE: Request for Quote (GeoView) ‐ Utility Locate in Gulfport ‐ Peacock Dry Cleaner

CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe. If you have any suspicion, please confirm with the sender verbally that this email is authentic. If

Thanks, and there are locations inside of the building, correct?

President, GeoView

Sent: Wednesday, May 10, 2023 8:41 AM

To: Mike Wightman <mwightman@geoviewinc.com> Subject: Re: Request for Quote (GeoView) ‐ Utility Locate in Gulfport ‐ Peacock Dry Cleaner

Yes, the locations will be marked before you all arrive.

Olivia Cain, P.E.

Engineer Geosyntec Consultants, Inc.

Get Outlook for iOS

From: Mike Wightman <mwightman@geoviewinc.com> Sent: Tuesday, May 9, 2023 10:47:53 PM To: Olivia Cain <OCain@Geosyntec.com> Subject: RE: Request for Quote (GeoView) ‐ Utility Locate in Gulfport ‐ Peacock Dry Cleaner

CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe. If you have any suspicion, please confirm with the sender verbally that this email is authentic. If

Thanks Olivia, just to confirm it appears that many of the planned locations are inside of the building?

Also, will all the locations be marked at the time of the study so we can move without delay from location to location?

Regards, MJW

President, GeoView

Sent: Tuesday, May 9, 2023 6:22 PM To: Mike Wightman <mwightman@geoviewinc.com> Subject: Request for Quote (GeoView) ‐ Utility Locate in Gulfport ‐ Peacock Dry Cleaner

Hi Mike, Reaching out to get a quote for a utility locate at 20 locations in Gulfport. This is for the Former Peacock Dry Cleaner site located at 5021 Gulfport Boulevard. I’ve attached maps showing the proposed locations for reference. This site is part of the Florida Department of Environmental Protection Waste Site Cleanup Section and the work is being competitively bid.

The bidder providing the lowest cost meeting project requirements will be selected for the work.

Let me know if you have any questions or need any additional information! We are requesting that bids be submitted no later than 12 May 2023 at 6:00 PM EST.

Hope you have a nice evening, Olivia B. Cain, P.E. (FL) Engineer Geosyntec Consultants, Inc.

19321 U.S. Highway 19 North Building C, Suite 200 Clearwater, Florida 33764 Phone: 727.330.9961 Mobile: 727.262.8268 Pronouns: she/her

GEOSYNTEC | SIREM | SAVRON

Follow Us – LinkedIn | Twitter | Facebook | YouTube

SITE LINES LLC

Utility Locating 1143 59th Avenue North (727) 432-9482 St. Petersburg, FL 33703 bhardy@sitelinesllc.com

Olivia B. Cain, P.E.

19321 U.S. Highway 19 North Building C, Suite 200 Clearwater, FL 33764

May 11, 2023

SITE: Peacock Dry Cleaner Site – Gulfport, Florida PROPOSAL: 01277p

Dear Ms. Cain:

Thank you for contacting Site Lines LLC regarding the private utility locate at your project site. Attached is our proposal in response to your inquiry.

Please review the proposal to ensure I have accurately captured the project details.

If you agree to the proposal, including the terms and conditions, and the statement of work, please sign, initial and date where indicated. Upon signing, the proposal will serve as the Agreement of the parties as to the above-referenced Project.

If you have any questions, please feel free to contact me. I look forward to working with you.

Sincerely, Site Lines LLC

William L. Hardy II Geophysicist President

Enclosure

SITE LINES LLC PROPOSAL

SITE LOCATION

Peacock Dry Cleaner Site – 5021 Gulfport Boulevard, Gulfport, FL

PROPOSED SCOPE OF WORK

Site Lines (“Company”) will use Ground Penetrating Radar (GPR) and conventional electromagnetic (EM) pipe and cable locators to determine the location of underground utilities at the site identified by Geosyntec (“Client”). Of specific concern is the utilities within a 10-foot radius of approximately 20 proposed sample locations.

RESULTS OF THE INVESTIGATION

The estimated depth and location of utilities identified during the investigation will be marked on the ground surface using spray paint or other method to be agreed upon by the parties. The American Public Works Association Uniform Color Codes for the marking of underground utilities will be used.

PROJECT FEE

The fee to complete the project as described within this proposal is: Eight Hundred Dollars [$800.00].

Client shall pay Company in full within thirty (30) days of the invoice date, unless the parties have agreed to another payment arrangement in writing. If during the investigation, Company determines that the goals of the project cannot be achieved with the resources available to Company, Company will notify Client as soon as reasonably possible. Under such circumstances, Company will charge Client only for time expended and materials used to date.

CLIENT REQUIREMENTS

Client is responsible for all site access, maintenance of traffic (MOT), site clearing and/or any other logistical considerations necessary to conduct the utility locate.

Client will also provide all pertinent maps of the project site, including those that show the boundaries of the utility locate, pertinent landmarks, and known utilities (if available). Company is not a substitute for Chapter 556, Florida Statutes.

Accordingly, Client is responsible for calling Sunshine State One Call of Florida

(811) before undertaking any invasive activities, whether through Company, any other entity, or on its own.

DESCRIPTION OF COMPANY INVESTIGATION AND LIMITATIONS

A GSSI SIR-4000 GPR system will be used with a 900, 400, or 270 megahertz antenna configuration depending on site conditions and desired targets. The GPR will assist in locating nonmetallic and metallic utilities. Physical surface conditions, subsurface conditions and technical limitations effect the ability of GPR to resolve targeted utilities and/or subsurface structures. Depth and/or diameter of the utility, soil type, moisture/ionic content of the soil, and electrical properties of the soil compared to that of the utility can prevent the GPR from identifying utilities at the site. The diameter of a utility cannot be determined by GPR data. Estimated depths of utilities are directly affected by soil conditions and the material of the utility. A margin of error of +/- 20-25% in depth should be expected when performing invasive activities.

An RD 8000 will be used for the EM survey. Electromagnetic induction which transmits a signal directly into the desired target and passive power detection which locates naturally occurring magnetic fields in energized lines will be identified by detecting and following the signals with a receiver. The EM survey will assist in finding only metallic utilities. The magnetic field and/or induced signal should emanate from the target in a circular geometry. When this occurs, the receiver will receive its peak signal directly above the target. However, when metallic utilities are running near each other, or there is environmental interference from fences, cars or overhead power lines, the signal can become distorted and the peak no longer can be directly over the utility. Care must be taken when doing any invasive work around the utilities. A margin of error of +/- 20-25% in depth should be expected when performing invasive activities. Company’s personnel are highly experienced and certified operators of GPR and EM pipe and cable locators.

Due to the limitations described above, when Client is working around indicated utilities, a minimum of two (2)-feet clearance from either side of the marked utility will be maintained. For absolute confirmation, Client is responsible for exposing any indicated underground utility.

Company will conduct utility investigations in accordance with the level of care and generally accepted professional practices as ordinarily exercised by members of the same profession practicing in the same locality under similar conditions.

REPRESENTATIONS AND WARRANTIES

Neither Company nor its employees or agents are licensed surveyors under Florida law, nor do they represent themselves as such. Accordingly, the work Company is to perform is not a substitute for work typically completed by a licensed surveyor.

Company specifically and expressly disclaims any liability for any type of property damage or personal injury, including but not limited to death, arising from client’s failure to determine that the services of a licensed surveyor are necessary or to retain a…