This Task Assignment (TA) Document DC044C is issued under Contract HW683 between the State of Florida Department of Environmental Protection (FDEP) and Geosyntec Consultants. The assignment authorizes Geosyntec to conduct quarterly groundwater monitoring at the former Rips Quality Cleaners site (ERIC_5065) located at 304 Michigan Street, Orlando, Orange County, Florida. The Department Project Manager is Sarah Aduwa, and the Contractor's Project Manager is Melissa Shook. The assignment is effective through September 18, 2026.
The scope of work consists of seven subtasks: (1) Project Management calculated at 13% of direct labor; (2) First Quarter Groundwater Monitoring collecting depth-to-groundwater measurements from six monitoring wells and groundwater sampling from MW044; (3) Second Quarter Groundwater Monitoring with preparation of a field deliverable containing updated tables, analytical reports, and field forms; (4) Third Quarter Groundwater Monitoring; (5) Fourth Quarter Groundwater Monitoring; (6) Site Closure Communication meetings if 1,1-DCE concentrations at MW044 are below the GCTL for two consecutive events; and (7) Site Rehabilitation Completion Report (SRCR) preparation. The total task assignment value is $16,814.09 on a fixed unit rate basis, with invoicing scheduled in two milestones: $5,201.78 due December 15, 2025, and $11,612.31 due June 19, 2026. The work includes laboratory analysis of volatile organic hydrocarbons (VOHs) using EPA Method 8260B, investigative derived waste (IDW) transportation and disposal services provided by subcontractor Erwin Remediation at $125.00 per drum, and project completion by May 31, 2026.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O.
Object Code
Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department
Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature)
Date:
Additional signatures attached on separate page.
HW683
DC044C September 18, 2026
This Task Assignment authorizes Geosyntec to conduct quarterly groundwater monitoring at Rips Quality Cleaners.
Sarah Aduwa 850-245-8973 Geosyntec
Melissa Shook 321-747-1909
ERIC_5065
304 Michigan Street, Orlando, Orange County, Florida
Rips Quality Cleaners
$ 16,814.09
$ 16,814.09
Scope of Work
Geosyntec
Todd Kafka
COntract Manager
Todd Kafka, P.G. Digitally signed by Todd Kafka, P.G.
Date: 2025.08.29 10:52:06 -04'00'
Mubeen Darji
Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.
Date: 2025.08.29 08:58:27 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WC TAFORM
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
To: HW683 Contract Negotiation File Rips Quality Cleaners Orlando, Orange County, Florida
ERIC_5065
From: Sarah Aduwa, Project Manager Date: August 29, 2025 Subject: Negotiation Summary
HW683_DC044C
This Task Assignment authorizes Geosyntec to conduct quarterly groundwater monitoring at Rips Quality Cleaners in Orange County, Florida (FL). Erwin Remediation (Erwin) was selected as the lowest responsive and responsible bidder. Specific subtasks are detailed below:
Subtask 1: Project Management Project Management is calculated at 13% of the direct labor.
Subtask 2: Quarterly Groundwater Monitoring - First Quarter Geosyntec will collect depth-to-groundwater measurements from MW041.
MW034, MW033, MW040, MW044, and MW045. Groundwater sampling will be conducted at MW044.
Subtask 3: Quarterly Groundwater Monitoring - Second Quarter Geosyntec will replicate the Groundwater Sampling and IDW sections of Subtask 2 approximately 3 months after completion of Subtask 2.
Due to the time lag between quarterly events, Geosyntec will prepare a field deliverable containing updated tables, laboratory analytical report, and field forms as a payment milestone for Quarters 1 and 2. In the event that the results from Subtasks 2 and 3 are below GCTLs, Geosyntec will submit a change order to remove the field deliverable and Subtasks 4 and 5 from the Task Assignment. Subtask 7 will be completed in the place of the field deliverable.
Subtask 4: Quarterly Groundwater Monitoring Geosyntec will replicate the Groundwater Sampling and IDW sections of Subtask 2 approximately 3 months after completion of Subtask 3.
Subtask 5: Quarterly Groundwater Monitoring Geosyntec will replicate the Groundwater Sampling and IDW sections of Subtask 2 approximately 3 months after completion of Subtask 4.
Subtask 6: Site Closure Communication If the 1,1-DCE concentration (assuming no other VOHs appear) at MW044 is below the GCTL for two consecutive events, unconditional site closure will be recommended. Geosyntec will conduct (1) a meeting between the RPO, the RPO representatives, or both as appropriate, regarding the site closure recommendation and (2) a meeting between Geosyntec and the FDEP to discuss next steps regarding site closure. If the 1,1-DCE concentration at MW044 is above the GCTL, a Task Assignment Change Order (TACO) will be submitted to remove Subtask 6 from the Task Assignment.
Subtask 7: Groundwater Monitoring Report/Site Rehabilitation Completion Report It is anticipated that the results of quarterly monitoring will support the preparation of a Site Rehabilitation Completion Report (SRCR) due to attaining GCTLs in two consecutive events.
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Former Rips Quality Cleaners SUBTASK: Q1 GW Sampling
DATE: 6/24/2025
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Professional M. Shook 2
Senior Staff Professional
L. Haverlin 10
TOTAL LABOR 12
VEHICLE TYPE RATE UNIT USEAGE
Truck $120.00 Day 1 $120.00 Subtotal $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL SUB $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOHs $73.00 1 0 $73.00 Subtotal $73.00
Shipping Small Cooler (0 to 25 lbs) $110.00 1 $110.00
Subtotal $110.00
TOTAL LAB $183.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Analytical Related Groundwater Sampling Kit $290.00 Day 1 $290.00
Subtotal $290.00 IDW Related
Drum $100.00 Drum 1 $100.00 Subtotal $100.00
Expendables Expendables $40.00 Day 1 $40.00
Subtotal $40.00
TOTAL EQUIPMENT $430.00
Field kickoff (1 hr), Property Owner and Tenant Notification (1 hr)
Field work preparation (1 hours), Field Kickoff and H&S (1.5 hr) Mobe/demobe (4 hours).
Water level measurements of 6 wells (1 hours), sample 1 monitoring well (1.5 hr/well = 1.5 hours); finalize/compile field forms (1 hr)
6/24/2025 Page 3 of 8 Subtask 2
SUBTASK: Q2 GW Sampling/ Field Report
DATE: 6/24/2025
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Principal T. Kafka 1
Professional
M. Shook 6
Senior Staff Professional
L. Haverlin 10
TOTAL LABOR 17
VEHICLE TYPE RATE UNIT USEAGE
Truck $120.00 Day 1 $120.00 Subtotal $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
IDW
Erwin Remediation Transporation and Disposal of IDW. $125.00 $125.00
Subtotal $125.00
TOTAL SUB $125.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOHs $73.00 1 0 $73.00 Subtotal $73.00
Shipping Small Cooler (0 to 25 lbs) $110.00 1 $110.00
Subtotal $110.00
TOTAL LAB $183.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Analytical Related Groundwater Sampling Kit $290.00 Day 1 $290.00
Subtotal $290.00 IDW Related
Drum $100.00 Drum 0 $0.00 Subtotal $0.00
Expendables Expendables $40.00 Day 1 $40.00
Subtotal $40.00
TOTAL EQUIPMENT $330.00
PG certification and develop recommendations for path forward
Property Owner and Tenant Notification (1 hr) IDW management & manifest preparation (2 hrs) Field Deliverable: Evaluating and interpreting data (1 hr). Prepare field deliverable (lab report, field note, updated data tables - 2 hr).
Field work preparation (1 hours), Field Kickoff and H&S (1.5 hr) Mobe/demobe (4 hours).
Water level measurements of 6 wells (1 hours), sample 1 monitoring well (1.5 hr/well = 1.5
6/24/2025 Page 4 of 8 Subtask 3
SUBTASK: Q3 GW Sampling
DATE: 6/24/2025
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Professional M. Shook 2
Senior Staff Professional
L. Haverlin 10
TOTAL LABOR 12
VEHICLE TYPE RATE UNIT USEAGE
Truck $120.00 Day 1 $120.00 Subtotal $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL SUB $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOHs $73.00 1 0 $73.00 Subtotal $73.00
Fast Turnaround Charges Percent Subtotal $0.00
Shipping Small Cooler (0 to 25 lbs) $110.00 1 $110.00
Subtotal $110.00
TOTAL LAB $183.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Drilling Related Subtotal $0.00
Analytical Related Groundwater Sampling Kit $290.00 Day 1 $290.00
Subtotal $290.00 IDW Related
Drum $100.00 Drum 1 $100.00 Subtotal $100.00
Expendables Expendables $40.00 Day 1 $40.00
Subtotal $40.00
TOTAL EQUIPMENT $430.00
Field kickoff (1 hr), Property Owner and Tenant Notification (1 hr)
Field work preparation (1 hours), Field Kickoff and H&S (1.5 hr) Mobe/demobe (4 hours).
Water level measurements of 6 wells (1 hours), sample 1 monitoring well (1.5 hr/well = 1.5
6/24/2025 Page 5 of 8 Subtask 4
SUBTASK: Q4 GW Sampling
DATE: 6/24/2025
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Principal T. Kafka 1
Professional
M. Shook 6
Senior Staff Professional
L. Haverlin 10
TOTAL LABOR 17
VEHICLE TYPE RATE UNIT USEAGE
Truck $120.00 Day 1 $120.00 Subtotal $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
IDW
Erwin Remediation Transporation and Disposal of IDW. $125.00 $125.00
Subtotal $125.00
TOTAL SUB $125.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOHs $73.00 1 0 $73.00 Subtotal $0.00
Shipping Small Cooler (0 to 25 lbs) $110.00 1 $110.00
Subtotal $110.00
TOTAL LAB $183.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Subtotal $0.00 Analytical Related
Groundwater Sampling Kit $290.00 Day 1 $290.00 Water Level Meter $25.00 Day 0 $0.00 YSI 556 MPS $105.00 Day 0 $0.00
Subtotal $290.00 Expendables
Expendables $40.00 Day 1 $40.00 Subtotal $40.00
TOTAL EQUIPMENT $330.00
PG certification and develop recommendations for path forward
Property Owner and Tenant Notification (1 hr) IDW management & manifest preparation (2 hrs) Field Deliverable: Evaluating and interpreting data (1 hr). Prepare field deliverable (lab report, field note, updated data tables - 2 hr).
Field work preparation (1 hours), Field Kickoff and H&S (1.5 hr) Mobe/demobe (4 hours).
Water level measurements of 6 wells (1 hours), sample 1 monitoring well (1.5 hr/well = 1.5
6/24/2025 Page 6 of 8 Subtask 5
SUBTASK: Site Closure Communication
DATE: 6/24/2025
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Principal T. Kafka 2
Professional M. Shook 5
TOTAL LABOR 7
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
TOTAL SUB $0.00
LABORATORY COSTS
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT $0.00
Attend RPO Meeting (1 hr) Provide site closure guidance (1 hr)
Prepare for (3 hr) and lead (1 hr) up to two meetings concerning site closure (3+1 x 2 meetings = 5 hr)
6/24/2025 Page 7 of 8 Subtask 6
SUBTASK: SRCR
DATE: 6/24/2025
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Principal T. Kafka 2
Project Professional C. Saville 4
Professional
M. Shook 17
Admistirative Assistant PDF Assesmbly (1 hr) P. Gallagher
TOTAL LABOR 24
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
TOTAL SUB $0.00
LABORATORY COSTS
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT $0.00
Data evaluation/interpretation, PG sign seal NAM Report (2 hr)
Preparing groundwater flow direction maps (surficial, intermediate), and laboratory analysis figures (both zones) (4 hrs)
Draft Report Tables (2 hr) and Groundwater Flow Maps (2 hr) Prepare Monitoring Report (12 hrs) .
Prepare summary to RPO regarding recommendations (1 hr)
6/24/2025 Page 8 of 8 Subtask 7
6770 South Washington Ave Suite 3
Titusville, FL 32780
PH 321-269-5880
www.geosyntec.com
Former Rips Cleaners_Quarterly GW Sampling_SOW_MS.docx
27 May 2025 Ms. Sarah Aduwa Florida Department of Environmental Protection Waste Cleanup Program 2600 Blair Stone Road, MS 4520 Tallahassee, FL 32399-2400
Subject: Proposal for 2025 Quarterly Groundwater Monitoring Former Rips Quality Cleaners (ERIC_5065) 304 East Michigan Street, Orlando, Orange County, Florida
Dear Ms. Aduwa:
Geosyntec has prepared the attached Scope of Work (SOW) and Cost Estimate Form and proposed Level of Effort (CEF/LOE) for quarterly groundwater monitoring at the former RIPS Quality Cleaners (Site) located in Orlando, Florida. The scope of work was proposed in Geosyntec’s February 2025 Groundwater Monitoring Report and discussed during our site review meeting with the Department on April 29, 2025. The goal is to move the Site towards unrestricted closure as only one monitoring well, MW044, has occasional exceedances of 1,1-DCE above its GCTL (e.g., May 2024 = < 0.7 µg/L and January 2025 = 0.8 µg/L and above the GCTL). Geosyntec recommended (and the Department agreed) collecting a quarterly sample from MW044 in an effort to obtain a two consecutive 1,1-DCE concentrations from MW044 below its GCTL.
Geosyntec has a site access agreement for 300 E Michigan St Orlando, FL 32806 from Stanbery Southside LLC, who purchased the property in 2021, and there has not been a change of ownership since then.
A detailed explanation of the proposed scope of work and report preparation is provided below.
Subtask 1 – Project Management
This subtask covers the general management of the project as specified in Contract No. HW683 by Melissa Shook.
Subtask 2 – Quarterly Groundwater Monitoring – First Quarter
Geosyntec will mobilize to the Site in April 2025 to collect depth-to-groundwater measurements from select Site-wide monitoring wells screened in the surficial aquifer (MW041, MW034, MW033) and intermediate aquifer (MW040, MW044, and MW045) (6 monitoring wells) and collect a groundwater sample from MW044. The Groundwater sample will be submitted for
ERIC_5065
27 May 2025
Former Rips Cleaners_Quarterly GW Sampling_SOW_MS.docx laboratory analysis of VOHs by Environmental Protection Agency (EPA) Method 8260B. Field activities will be performed using FDEP SOPs.
Groundwater sampling purge water will be containerized in a 55-gallon drum, which will be labeled and covered with construction fencing for intended continued use.
Subtask 3 – Quarterly Groundwater Monitoring – Second Quarter
Geosyntec will replicate the Groundwater Sampling and IDW sections of Subtask 2 approximately three months after completion of Subtask 2.
Due to the time lag between quarterly events, Geosyntec will prepare a field deliverable containing updated tables, laboratory analytical report, and field forms as a payment milestone for Quarters 1 and 2. In the event that the results from Subtasks 2 and 3 are below GCTLs, Geosyntec will submit a change order to remove the field deliverable and Subtasks 4 and 5 from the Task Assignment.
Subtask 7 will be completed in the place of the field deliverable.
For purposes of cost reduction, the cost for transportation and disposal (T&D) of one 55-gallon drum of investigative derived waste (IDW) is included for Subtask 3 and 5 only. The monitoring well data will be utilized for waste profiling; therefore, additional IDW samples are not required.
Erwin Remediation is the selected subcontractor for IDW transport and disposal. Subcontractor bids are included in Attachment A.
Subcontractor Cost Per T&D Event Selected
Hull’s Environmental Services
$300.00
Erwin Remediation $125.00 X
WRI $215.00
Subtask 4 –Quarterly Groundwater Monitoring – Third Quarter
Geosyntec will replicate the Groundwater Sampling and IDW sections of Subtask 2 approximately three months after completion of Subtask 3.
Subtask 5 –Quarterly Groundwater Monitoring – Fourth Quarter
Geosyntec will replicate the Groundwater Sampling and IDW sections of Subtask 2 approximately three months after completion of Subtask 4.
Former Rips Cleaners_Quarterly GW Sampling_SOW_MS.docx
Subtask 6 – Site Closure Communication
If the 1,1-DCE concentration (assuming no other VOHs appear) at MW044 is below the GCTL for two consecutive events, unconditional site closure will be recommended. Geosyntec will conduct (1) a meeting between the RPO, the RPO representatives, or both as appropriate, regarding the site closure recommendation and (2) a meeting between Geosyntec and the FDEP to discuss next steps regarding site closure. At a minimum, the Geosyntec Project Manager and Project Director will be in attendance.
If the 1,1-DCE concentration at MW044 is above the GCTL, a Task Assignment Change Order (TACO) will be submitted to remove Subtask 6 from the Task Assignment.
Subtask 7 – Groundwater Monitoring Report/Site Rehabilitation Completion Report
It is anticipated that the results of quarterly monitoring will support the preparation of a Site Rehabilitation Completion Report (SRCR) due to attaining GCTLs in two consecutive events. The SRCR will document the field activities and results from the monitoring events performed. Geosyntec will update existing figures and tables based on the results of the sampling events as appropriate. The SRCR will include a section detailing site rehabilitation completion and historical assessment/remediation conducted at the Site. The report will be signed/sealed by a licensed professional geologist/engineer in the State of Florida.
Invoice and Deliverable Schedule:
We have provided the milestone deliverable date below based on an assumed FDEP-approval date of April 15, 2025
Subtask Deliverable Deliverable Due Date Invoice Amount
2, 3 Submittal of Field Deliverable, and
IDW Manifest 31 August 2025
$5,201.78
1,4,5,6,&7 Submittal of SRCR and IDW
Manifest 30 April 2026 $11,612.31
Period of Performance 31 May 2026
Total: $16,814.09
Former Rips Cleaners_Quarterly GW Sampling_SOW_MS.docx
We appreciate the opportunity to work with FDEP on this project. Please call me if you have questions or require additional information.
Sincerely, Geosyntec Consultants
Melissa Shook, E.I.
Project Manager
Todd Kafka, P.G.
Senior Principal
Attachment A – IDW quotes
ATTACHMENT A
IDW Contractor Quotes
D ru m
$1
D ru m
$2
Dr um $1
Tr an sp or ta tio $5
St op
F ee
$5
En er gy $1
ID
W
D
IS
PO
SA
L Er w in
R em ed ia tio n
H ul ls En vi ro se rv e
$1
.0
$2
.0
$1
.0
755 Prairie Industrial Parkway, Mulberry, Florida 33860 Telephone (863) 425-4884
Disposal Pricing Effective January 1, 2024
GEOSYNTEC CONSULTANTS
DRUMS WASTE PROCESSING
Size (gal) Trans Liquid
Light Debris
Sludge or Oil Dry Solids Gels
Lab Packs
Empty Trans
Empty Disp
1 $2 $5 $5 $8 $8 $8 $25 $3 $5 5 $5 $10 $10 $12 $12 $15 $75 $5 $5
10 $10 $20 $20 $20 $20 $30 $75 $5 $5 15-25 $15 $40 $40 $55 $55 $65 $100 $10 $8
55 Below $ 0 $ $80 $80 $105 $175 $10 $15 85 Below $80 $80 $125 $125 $155 $15 $20 yd³ Below $180 $210 $250 $250 $350 $80 251-400 miles - $50/drum ($60/85-gal) Totes- $200 <11 drums/site – Surcharge of $200/site 101-250 miles - $40/drum ($50/85-gal) Totes- $160 < 6 drums/site – Surcharge of $50/site 0-100 miles - $30/drum ($40/85-gal) Totes- $120 < 6 drums/site – Surcharge of $50/site New Empties- $40 + Tax
BULK - Based on Centrifuge Testing (v/v) per SOP WASTE PROCESSING
Liquids <10% Solid
Sludge 10-25% Solid Solids
Sludge >25%
Light Debris
$0.040/lb $0.045/lb $0.040/lb $0.070/lb $0.080/lb
BULK SOILS BR CODE (Recycling)
Tons Standard
< 14 tons $500 minimum 14 - 140 $35.00
141 – 700 $33.00 701 – 1400 $30.00
1401 – 2100 Negotiable > 2100 Negotiable
Clean Fill $3.25/yd3 + tax Excess Debris Surcharge N/A
Hazadous Waste E-Manifest Fee - $40/manifest 10% FSC to all Invoices
$ 0Below
- $50/drum ($60/85-
- $40/drum ($50/85-
10% FSC to all Invoices
File details come from the government source that posted it. Updated .