Summary of Task Assignment HW683 DC017B
This Task Assignment is executed between the State of Florida Department of Environmental Protection (FDEP) and Geosyntec Consultants, Inc. for remediation activities at the Maitland Plaza property located at 110 North Orlando Avenue, Maitland, Florida 32751 (ERIC_5057, Orange County). The contract is authorized under Contract Number HW683 with a completion date of March 29, 2024. The Task Assignment is supported by a Scope of Work, Cost Estimate, and Schedule dated May 26, 2023, and comprises four subtasks focused on preparation of an Interim Source Removal (ISR) Work Plan, development of bid documents, and evaluation of subcontractor bids for soil vapor extraction system implementation.
The total contract value is $30,592.22 on a fixed unit rate basis, representing 202 labor hours. Compensation is structured across four deliverables with invoice payments tied to FDEP approval milestones: $15,908.60 upon approval of the ISR Work Plan (due September 13, 2024); $5,786.61 upon approval of the Technical Specification Package (due October 31, 2024); and $8,897.01 upon approval of the Submittal to Subcontractors, Site Walk, and Bid Evaluation (due January 31, 2025). Subtask 1 encompasses project management costs calculated at 13 percent of direct labor. The work includes site visitations, utility evaluations, design development, specification preparation, contractor bidding coordination, and bid evaluation services. Rachel Klinger serves as the Engineer of Record, with Olivia Cain designated as the primary project engineer. The FDEP Project Manager is Brittany Plyler (850-245-8851), and Geosyntec's Project Manager is Olivia Cain (727-330-9961).
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW683
DC017B Completion March 29, 2024
This Task Assignment authorizes Geosyntec to conduct remediation activities in accordance with the Geosyntec scope of work, cost estimate, and schedule received on May 26, 2023.
Brittany Plyler 850-245-8851 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Geosyntec
Geosyntec
Olivia Cain 727-330-9961
ERIC_5057
110 North Orlando Avenue Maitland, FL 32751
Maitland Plaza
✔ $ 30,592.22
$ 30,592.22
Scope of Work
Todd Kafka
Contract Manager
Todd Kafka, P.G. Digitally signed by Todd Kafka, P.G.
Date: 2023.06.20 08:41:57 -04'00'
Kelly Crain
Kelly Crain Digitally signed by Kelly Crain Date: 2023.06.07 14:50:00 -04'00'
N/A
Murphy_SL Highlight
Murphy_SL Highlight
Murphy_SL Highlight
Murphy_SL Highlight
Murphy_SL Highlight
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Subtask 2: ISR Work Plan 09/13/2024
Subtask 3: Technical Specification Package 10/31/2024
Subtask 1, 4: Submittal to Subcontractors, Site Walk, and Bid Evaluation; PM 01/31/2025
Subtask 2:FDEP submittal and approval of the ISR Work Plan $ 15,908.60
Subtask 3: FDEP submittal and approval of the Technical Specification Package $ 5,786.61
Subtask 1, 4: FDEP submittal and approval of Submittal to Subcontractors, Site Walk, and Bid Evaluation; PM $ 8,897.01
$ 30,592.22
HW683
DC017B
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
To: HW683 Contract Negotiation File Maitland Plaza Orange County, Florida
ERIC_5057
From: Brittany Plyler, Project Manager Date: June 5, 2023 Subject: Negotiation Summary
HW683_DC017B
This Task Assignment authorizes Geosyntec to conduct remediation activities at Maitland Plaza in accordance with the Geosyntec scope of work, cost estimate, and schedule received on May 26, 2023.
Geosyntec confirmed on May 26, 2023, that Subtask 1 consists of the calculated project management labor, based upon 13% of the direct labor costs in this proposal, and includes fringe, overhead, other direct costs (ODCs) and completion fees.
Subtask 2: This subtask includes costs associated with the preparation of an ISR Work Plan.
The ISR Work Plan will recap the results of the soil assessment activities completed at the Site and propose the SVE well layout, as well also include an engineering cost estimate for implementation and operation and maintenance.
Subtask 3: Geosyntec will develop and prepare Bid Documents necessary to obtain subcontractor costs to implement the ISR at the Site. The Bid Documents will include the specifications necessary for potential subcontractors to provide cost for site restoration activities.
Subtask 4: Geosyntec will develop a list of up to three qualified SVE Contractors for invitation to the Site to participate in a bid walk. Geosyntec will send interested Contractors copies of the ISR Work Plan, Bid Documents, and Technical Specifications.
The FDEP project manager confirmed site access on June 5, 2023.
The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost is $30,592.22 with 202 labor hours.
Printed on recycled paper.
FDEP COST ESTIMATE
Contractor: Geosyntec Consultants
Date: 5/26/2023
Task #: Pending SubTask 1 Project Management SubTask 6
Site: SubTask 2 Interim Source Removal Work Plan SubTask 7
Activity/Phase: ISR Work Plan SubTask 3 Bid Package Development SubTask 8
Project Manager: O. Cain SubTask 4 Bid Walk and Evaluation SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$43.51 Project Manager O. Cain 27 26.5 $78.51 Principal R. Klinger 36 20 8 8 0 0 0 0 0 0
$48.56 Project Professional M. Hensley 10 10 0 0 0 0 0 0 0 0
$43.51 Professional O. Cain 103 61 24 18 0 0 0 0 0 0
$39.98 Professional M. Lemes 8 0 0 8 0 0 0 0 0 0
$42.79 Designer B. Lardizbal 18 12 6 0 0 0 0 0 0 0
Total Hours 202 27 103 38 34 0 0 0 0 0 0
Direct Labor $10,038.41 $1,154.86 $5,223.39 $1,929.06 $1,731.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 172.70% $17,336.33 $1,994.44 $9,020.79 $3,331.49 $2,989.61 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Labor $27,374.74 $3,149.30 $14,244.18 $5,260.55 $4,720.71 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $480.00 $240.00 $0.00 $240.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Travel $480.00 $240.00 $0.00 $240.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement)
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Maitland Plaza
Cost Estimate Page 1 of 5 Cost Estimate
FDEP COST ESTIMATEContractor: Geosyntec Consultants
Date: 5/26/2023
Task #: Pending SubTask 1 Project Management SubTask 6
Site: SubTask 2 Interim Source Removal Work Plan SubTask 7
Activity/Phase: ISR Work Plan SubTask 3 Bid Package Development SubTask 8
Project Manager: O. Cain SubTask 4 Bid Walk and Evaluation SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10
Maitland Plaza
Subcontractor (Services Procurement)
Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory
Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses
Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Expendables $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $27,854.74 $3,149.30 $14,484.18 $5,260.55 $4,960.71 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Completion Fee $2,737.48 $314.93 $1,424.42 $526.06 $472.07 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $30,592.22 $3,464.23 $15,908.60 $5,786.61 $5,432.78 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Invoice 1 $15,908.60 Invoice 2 $5,786.61 Invoice 3 (Final) $8,897.01 Total (check) $30,592.22
Cost Estimate Page 2 of 5 Cost Estimate
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Maitland Plaza SUBTASK: Interim Source Removal Work Plan
DATE: 5/26/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Principal
R. Klinger 20
Project Professional
M. Hensley 10
Professional O. Cain 61
Designer
B. Lardizbal 12
TOTAL LABOR 103
VEHICLE TYPE RATE UNIT USEAGE
Car $80.00 Day 0 $0.00
Truck R. Klinger $120.00 Day 1 $120.00
Van O. Cain $120.00 Day 1 $120.00
Subtotal $240.00
TOTAL VEHICLE $240.00
Prepare design drawings (process and instrumentation diagram, well details for multiple depth intervals, electircal connection to system, and trench cross sections)
Mob/demob to the site from Jacksonville (5 hr). Site visit to evaluate ISR implementation (4 hr). Pre- and post-Site visit design discussions with property owner and tenants (2 hr).
Establish design criteria with FDEP (1 hr). Technical design support, calculation packages, well and piping layouts, and monitoring plan. PE sign/seal (8 hr).
Prepare figures and system/well/piping layouts
Mob/demob to the site from Clearwater (5 hr). Site visit to evaluate ISR implementation (4 hr). Summary of meeting notes and photo log to FDEP (2 hr). Prepare for and conduct pre-and post-Site visit design discussions with property owner and tenants (2 hr/meeting x 2 meetings = 4 hr). Establish design criteria with FDEP (1 hr). Prepare ISR, design drawings, calculation package, and develop monitoring plan (45 hr).
6/1/2023 Page 3 of 5 Subtask 2
SUBTASK: Bid Package Development
DATE: 5/26/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Principal
R. Klinger 8
Professional
O. Cain 24
Designer
B. Lardizbal 6
TOTAL LABOR 38
Prepare bid spec drawings
PE development and certification of bid specifications, contractor bid package
Prepare bid documents and technical specifications
6/1/2023 Page 4 of 5 Subtask 3
SUBTASK: Bid Walk and Evaluation
DATE: 5/26/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Principal
R. Klinger 8
Professional
O. Cain 18
Professional
M. Lemes 8
TOTAL LABOR 34
VEHICLE TYPE RATE UNIT USEAGE
Car $80.00 Day 0 $0.00
Truck M. Lemes $120.00 Day 1 $120.00
Van O. Cain $120.00 Day 1 $120.00
Subtotal $240.00
TOTAL VEHICLE $240.00
Teleconference with tenants and property owner on design and implementation plans/schedule (2 hr). PE evaluation of bids and bid comparison, evaluate contractor selection and questions from bidders, requests for additional information (6 hr).
Teleconference with tenants and property owner on design and implementation plans/schedule (2 hr). Develop contractor bid list (2 hr). Mobilization to/from the site from Clearwater (5 hr). Conduct site visit and bid walk with contractors and technical discussions with PE during bid walk (4 hr). Evaluate subcontractor bids and prepare bid comparison table (3 hr). Prepare selection summary for FDEP with recommended
Mobilization to/from the site from Tampa (4 hr). Conduct site visit and bid walk with contractors and technical discussions with PE during bid walk (4 hr).
6/1/2023 Page 5 of 5 Subtask 4
19321 U.S. Highway 19 North Building C, Suite 200 Clearwater, FL 33764
PH 813-792-4820
www.geosyntec.com
Maitland Plaza (ERIC_5057)_HW683 SOW_ISRWP_2023-05
May 26, 2023
Ms. Brittany Plyer Florida Department of Environmental Protection 2600 Blair Stone Road Tallahassee, FL 32399-2400
Subject: Scope of Work and CEF/LOE – Interim Source Removal Work Plan
Maitland Plaza 110 North Orlando Avenue Maitland, FL 32751 FDEP Site ID No. ERIC_5057
Dear Ms. Plyer:
Geosyntec Consultants, Inc. (Geosyntec) has prepared this proposed Scope of Work (SOW), Level of Effort (LOE), and Cost Estimating Form (CEF) for remediation activities at the Maitland Plaza/Utopia Cleaners Site located in Maitland, Florida (ERIC_5057). This SOW includes (i) preparing an Interim Source Removal (ISR) Work Plan, (ii) preparing Bid Documents, and (iii) soliciting bids from qualified subcontractors and evaluating the subcontractor bids for selection.
A description of task breakdown for field activities and report preparation is provided below. A CEF/LOE is provided as Attachment A.
Subtask 1 – Project Management
Costs associated with this subtask are directly computed.
Subtask 2 – ISR Work Plan
This subtask includes costs associated with the preparation of an ISR Work Plan pursuant to Chapter 62-780.525, Florida Administrative Code to address vadose zone soil impacts at the Site.
Specifically, Geosyntec anticipates that the ISR Work Plan will detail a soil vapor extraction (SVE) system to treat soils from 0 to 19 feet (ft) below land surface (BLS), as identified in the January 2023 Supplemental Site Assessment Report.
The ISR Work Plan will recap the results of the soil assessment activities completed at the Site and propose the SVE well layout (including use of existing modified active gas sampling [MAGS] wells), piping layout, construction, operation, and maintenance details (including a process and instrumentation diagram, well details, electrical connection to system, and trenching cross section details). The ISRWP will also include an engineering cost estimate for implementation and operation and maintenance (O&M).
To support the preparation of the ISR Work Plan, Geosyntec will communicate with the Site owner to discuss the design plan and coordinate logistics for a Site visit with the owner (or local representative, if present) and existing tenants. The objectives of the Site visit are to evaluate interior access for construction activities, such as trenching for subgrade piping runs or the use of above grade piping along building columns into overhead crawlspaces (or both); document current Site conditions; discuss access and logistics with the Site owner and building tenants; determine a location for the treatment trailer; and evaluate the presence of overhead and underground utilities.
Due to the complexity of the Site footprint and potential challenges with implementation of the system, Olivia Cain (Engineer) and Rachel Klinger (Engineer of Record) will conduct the Site visit. Effort has been included for Geosyntec to converse with the property owner and tenants before and after the Site walk to ensure the proposed design is appropriate (assumed two, 1-hour teleconferences with Olivia Cain and Rachel Klinger).
Prior to submittal of the ISR Work Plan, Geosyntec will provide FDEP with a photo log documenting existing Site conditions and a copy of notes and/or meeting minutes from discussions with the Site owner and building tenants that culminates in an acceptable conceptual design. The conceptual design will be discussed with FDEP during a 1-hour teleconference to facilitate the SVE design and minimize FDEP comments.
Subtask 3 – Bid Package Development
After FDEP’s approval of the ISRWP, Geosyntec will develop and prepare Bid Documents necessary to obtain subcontractor costs to implement the ISR at the Site. The Bid Documents will include the specifications necessary for potential subcontractors (i.e., bidders) to provide a cost to permit, mobilize, and prepare the Site for construction; complete trenching, backfilling, and install the treatment system; and perform Site restoration activities. Geosyntec will submit the Bid Documents or Technical Specifications to complete this Subtask and recognizes the FDEP Engineer will not review them.
The Bid Documents will include:
Instructions for Bidders;
Request for Bids Scope of Work;
Construction Drawings;
Technical Specifications; and Bid Proposal Form.
The Bid Documents and Technical Specifications section will include, but not be limited to, the following elements:
Summary of work;
Description of site conditions, access constraints, overhead and subsurface utilities, and historical soil data, etc.;
Permitting (local, state, federal);
Safety, health, and emergency response requirements;
Site preparation and pre-mobilization activities (e.g., underground utility locating);
Requirements for protection of existing structures, as applicable;
Trenching locations and specifications;
Conveyance piping and connection specifications;
Backfill specifications;
Electrical connection requirements and electrical subcontractor costs;
Telemetry system connection and operational requirements;
Waste profiling, manifesting, transportation, and disposal requirements; and Site restoration and demobilization requirements.
Subtask 4 – Bid Walk and Evaluation
Following FDEP’s review and approval of the Bid Documents and Technical Specifications, Geosyntec will develop a list of up to three qualified SVE Contractors for invitation to the Site to participate in a bid walk. Prior to scheduling the Site visit, Geosyntec will send interested Contractors copies of the ISR Work Plan, Bid Documents, and Technical Specifications approved by FDEP. Geosyntec will coordinate the visit with the Site owner and current tenants and will conduct a 1-hour pre-call with both to provide an overview of the ISR Work Plan and allow the owner and tenant to provide input on logistics, layout changes (if Site conditions differ from those at the time of the ISR Work Plan), and how to minimize disruptions to facility operations. This information will allow for the Site visit to run smoothly and provide the best opportunity for setting clear expectations for the contractors. No additional labor has been included to address requests or changes from the discussions with the owners and tenants during the ISR Work Plan preparation.
Olivia Cain (Engineer) and Maria Lemes (Professional) will attend the bid walk, with support from Rachel Klinger, as needed (Engineer of Record).
Geosyntec will respond to requests for additional information (RAIs) submitted by contractors following the Site visit. Geosyntec will review contractor bids and evaluate costs and approaches to identify the best value to FDEP. Geosyntec will submit the Contractor bids, RAIs, bid evaluation, and our recommendation for Contactor selection to FDEP to serve as the deliverable for this Subtask. We anticipate implementation of the ISR will be performed under a separate Task Assignment.
Invoice and Deliverable Schedule
Subtask Deliverable Due Date Invoice Amount
2 ISR Work Plan August 29, 2023 $15,908.60
3 Technical Specification Package October 31, 2023 $5,786.61
1, 4 Submittal to Subcontractors, Site Walk, and Bid Evaluation
January 30, 2024 $8,897.01
Total $30,592.22
The above schedule is based on the assumptions that Geosyntec is tasked for this scope of work by June 29, 2023.
Assumes Geosyntec submits the ISR Work Plan by August 29, 2023 and the FDEP approves the ISR Work Plan by September 29, 2023. Assumes Geosyntec submits the draft Bid Documents by October 31, 2023, that the FDEP approves the Bid Documents by November 30, 2023, and Geosyntec submits the Bid Documents to bidders by December 15, 2023. Assumes the bid walk is conducted and the bids are received by Geosyntec no later than January 16, 2024, and Geosyntec submits the Bid Evaluation Letter by January 30, 2023.
CLOSURE
Please review and contact us if you have any questions or require additional information. As always, it is a pleasure to work with the FDEP.
Sincerely, Olivia Cain, P.E. (FL) Todd K. Kafka, P.G. (FL) Engineer Senior Principal Hydrogeologist
Copies to Rachel Klinger, Geosyntec
Attachments: Attachment A – CEF-LOE
File details come from the government source that posted it. Updated .