CN-370000-HW683-DC018A.pdf

PDF 2 MB Posted

Attached to
Master Agreement FL|HW683|90e8124b5a65e607dedb86d39c72016e
Contract number
HW683
Issued by
Florida

About this file

This is a Task Assignment (TA) document issued by the State of Florida Department of Environmental Protection (FDEP) under Contract Number HW683. The task assignment, numbered DC018A, authorizes Geosyntec Consultants, Inc. to conduct semi-annual groundwater monitoring at the former First Class Dry Cleaner Site located at 591 East Semoran Boulevard, Casselberry, Seminole County, Florida (ERIC_5489). The assignment is effective through July 30, 2023, with primary contacts including Evan Miller as the FDEP Project Manager and Ann Sava as the Contractor's Project Manager.

The scope of work encompasses five subtasks: project management, semi-annual groundwater monitoring in August 2022, preparation of a semi-annual groundwater monitoring report, semi-annual groundwater monitoring in February 2023, and annual groundwater monitoring report preparation. The work includes collection of groundwater samples for analysis of volatile organic halocarbons (VOHs) using EPA Method 8260B, deployment of passive diffusion bags, depth-to-groundwater measurements from up to 37 monitoring wells, and investigation-derived waste disposal. The total task assignment value is $33,502.58, with invoicing scheduled in two phases: $15,274.72 upon FDEP receipt and approval of the first semi-annual report (due October 30, 2022) and $18,227.86 upon approval of the second semi-annual report with project management (due April 30, 2023). The contract operates on a fixed unit rate basis with 219 total labor hours, including costs for labor, travel, laboratory analysis, field equipment, and waste disposal services provided by Erwin Remediation at $110 per drum.

View the file

Other files

File Type Posted
CN-370000-CN802-T9.pdf PDF
CN-370000-HW683-BF01BCO1.pdf PDF
CN-370000-HW683-BF04C.pdf PDF
CN-370000-HW683-BF04CCO1.pdf PDF
CN-370000-HW683-BIL02A.pdf PDF
CN-370000-HW683-DC001E.pdf PDF
CN-370000-HW683-DC001F.pdf PDF
CN-370000-HW683-DC002D.pdf PDF
CN-370000-HW683-DC002E.pdf PDF
CN-370000-HW683-DC003B.pdf PDF
CN-370000-HW683-DC003C.pdf PDF
CN-370000-HW683-DC003E.pdf PDF
CN-370000-HW683-DC010D.pdf PDF
CN-370000-HW683-DC012A.pdf PDF
CN-370000-HW683-DC012C.pdf PDF
CN-370000-HW683-DC013B.pdf PDF
CN-370000-HW683-DC020A.pdf PDF
CN-370000-HW683-DC020C.pdf PDF
CN-370000-HW683-DC021A.pdf PDF
CN-370000-HW683-DC023A.pdf PDF
CN-370000-HW683-DC024B.pdf PDF
CN-370000-HW683-DC024C.pdf PDF
CN-370000-HW683-DC026A.pdf PDF
CN-370000-HW683-DC027A.pdf PDF
CN-370000-HW683-DC027B.pdf PDF
CN-370000-HW683-DC028A.pdf PDF
CN-370000-HW683-DC02DCO1.pdf PDF
CN-370000-HW683-DC02FCO1.pdf PDF
CN-370000-HW683-DC030C.pdf PDF
CN-370000-HW683-DC031B.pdf PDF
CN-370000-HW683-DC034C.pdf PDF
CN-370000-HW683-DC036A.pdf PDF
CN-370000-HW683-DC037D.pdf PDF
CN-370000-HW683-DC039C.pdf PDF
CN-370000-HW683-DC03CCO2.pdf PDF
CN-370000-HW683-DC03ECO1.pdf PDF
CN-370000-HW683-DC040C.pdf PDF
CN-370000-HW683-DC041D.pdf PDF
CN-370000-HW683-DC043C.pdf PDF
CN-370000-HW683-DC044A.pdf PDF
CN-370000-HW683-DC046A.pdf PDF
CN-370000-HW683-DC047A.pdf PDF
CN-370000-HW683-DC049A.pdf PDF
CN-370000-HW683-DC052A.pdf PDF
CN-370000-HW683-DC053B.pdf PDF
CN-370000-HW683-DC054A.pdf PDF
CN-370000-HW683-DC05BCO3.pdf PDF
CN-370000-HW683-DC06ACO1.pdf PDF
CN-370000-HW683-DC07BCo1.pdf PDF
CN-370000-HW683-DC08BCO2.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW683

DC018A Completion July 30, 2023

This Task Assignment authorizes Geosyntec to conduct semi-annual groundwater monitoring at the former First Class Dry Cleaner Site in accordance with the Geosyntec scope of work, cost estimate, and schedule received on 29 June 2022.

Evan Miller 850-245-8928 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

Geosyntec

Geosyntec

Ann Sava 727-330-9956

ERIC_5489

591 East Semoran Boulevard Casselberry, Seminole County, Florida

Former First Class Cleaners

✔ $ 33,502.58

$ 33,502.58

Scope of Work

Todd Kafka

Contract Manager

Todd Kafka, P.G. Digitally signed by Todd Kafka, P.G.

Date: 2022.07.08 11:20:19 -04'00'

William E. Burns, Jr.

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2022.07.08 11:09:33 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Subtask 2,3- Submittal of Semi-Annual Groundwater Monitoring report, field notes, laboratory report 10/30/2022

Subtask 1,4,5- Submittal of Semi-Annual Groundwater Monitoring report, field notes, laboratory report, Project Management 04/30/2023

Subtask 2,3- FDEP receipt and approval of Semi-Annual Groundwater Monitoring report, field notes, laboratory report $ 15,274.72

Subtask 1,4,5- FDEP receipt and approval of Semi-Annual Groundwater Monitoring report, field notes, laboratory report, Project Management $ 18,227.86

$ 33,502.58

HW683

DC018A

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Shawn Hamilton Secretary

To: HW683 Contract Negotiation File Former First Class Cleaners Casselberry, Seminole County

ERIC_5489

From: Evan Miller, Project Manager Date: June 29, 2022 Subject: Negotiation Summary

HW683 DC018A

This Task Assignment authorizes Geosyntec to conduct semi-annual groundwater monitoring at the former First Class Dry Cleaner Site. Geosyntec recommends increasing the frequency of groundwater monitoring from annual to semi-annual to better monitor a jump in concentrations seen in well MW034.

Subtask 1: Project Management An automatic calculation based upon total direct labor hours determines the labor hours within this subtask.

Subtask 2 – Semi-annual Groundwater Monitoring – August 2022 This subtask contains costs for performance of the first semi-annual groundwater monitoring event in August 2022. Geosyntec will mobilize to the Site to collect depth-to-groundwater measurements from each accessible monitoring well (up to 37 total wells) within a 24-hour period, collect 16 groundwater samples, and deploy passive diffusion bags (PDBs) for the February 2023 semi-annual groundwater monitoring. Geosyntec personnel will bail the manholes, measure and record groundwater levels, and resecure the manholes; extra time has been estimated because of the distances between wells, driving time and traffic to access off site wells, calls to the water department and waiting for arrival to access wells, and locating wells with a metal detector in overgrown right-of-way locations. We have assumed only the 3 PDB well locations will be sampled on Day 1.

Subtask 3 – Semi-Annual Groundwater Monitoring Report Geosyntec will prepare a report summarizing sampling activities and results, and provide conclusions and recommendations based on data evaluation. The report will contain tables summarizing field/laboratory data, figures showing groundwater flow direction(s) (one per depth interval, three total) and three VOH isoconcentration figures (three depth intervals), and the results of the groundwater monitoring event. The report will be signed/sealed by a Florida-licensed geologist/engineer.

Subtask 4 – Semi-annual Groundwater Monitoring – February 2023 This subtask contains costs for performance of the first semi-annual groundwater monitoring event in February 2023. Geosyntec will mobilize to the Site to collect depth-to-groundwater measurements from each accessible monitoring well (up to 37 total wells) within a 24-hour

Printed on recycled paper.

MEMORANDUM

First Class Cleaners June 29, 2022 Page Two period, collect 16 groundwater samples, and deploy passive diffusion bags (PDBs) for the August 2023 semi-annual groundwater monitoring. Geosyntec personnel will bail the manholes, measure and record groundwater levels, and resecure the manholes; extra time has been estimated because of the distances between wells, driving time and traffic to access off site wells, calls to the water department and waiting for arrival to access wells, and locating wells with a metal detector in overgrown right-of-way locations. We have assumed only the 4 PDB well locations will be sampled on Day 1.

Subtask 5 – Annual Groundwater Monitoring Report Preparation Geosyntec will prepare a report summarizing sampling activities and results, and provide conclusions and recommendations based on data evaluation. The report will contain tables summarizing field/laboratory data, figures showing groundwater flow direction(s) (one per depth interval, three total) and three VOH isoconcentration figures (three depth intervals), and the results of the groundwater monitoring event. The report will be signed/sealed by a Florida-licensed geologist/engineer.

No Site access agreement could be found on Oculus, therefore, prior to field work, Geosyntec will obtain an updated Access Agreement from the current real property owner of the former First Class Cleaners (ERIC_5489) site.

The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost for this Task Assignment is $33,502.58 with 219 labor hours.

Geosyntec may invoice following the schedule established in the Deliverables and Invoice Schedule Attachment, which accompanies the Task Assignment Notification Form.

FDEP COST ESTIMATEContractor: Geosyntec Consultants

Date: 6/29/2022

Task #: DC017N (pending) SubTask 1 Project Management SubTask 6

Site: Former First Class Clean SubTask 2 Semi-Annual Groundwater Sampling SubTask 7

Activity/Phase: SubTask 3 Semi-Annual NAM Report SubTask 8

Project Manager: Ann Sava SubTask 4 Semi-Annual Groundwater Sampling SubTask 9

SubTask 5 Annual NAM Report SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$38.94 Project Manager A. Sava 23 23.2 $76.92 Principal T.Kafka 4 0 2 0 2 0 0 0 0 0 $46.15 Senior Professional M. Hensley 8 0 4 0 4 0 0 0 0 0 $38.94 Professional A. Sava 66 11 21 9 25 0 0 0 0 0 $33.17 Senior Staff Professional L. Varner 62 31 0 31 0 0 0 0 0 0 $29.33 Staff Professional A. Lamore 54 25 2 25 2 0 0 0 0 0 $27.88 Administrative Assistant A. Acosta 2 0 1 0 1 0 0 0 0 0

Total Hours 219 23 67 30 65 34 0 0 0 0 0

Direct Labor $7,845.64 $902.60 $2,189.86 $1,242.72 $2,111.98 $1,398.48 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 172.70% $13,549.42 $1,558.79 $3,781.89 $2,146.18 $3,647.39 $2,415.17 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $21,395.06 $2,461.39 $5,971.75 $3,388.90 $5,759.37 $3,813.65 $0.00 $0.00 $0.00 $0.00 $0.00

Travel Vehicle Rental $720.00 $360.00 $0.00 $360.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $1,464.00 $732.00 $0.00 $732.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $2,184.00 $1,092.00 $0.00 $1,092.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $440.00 $220.00 $0.00 $220.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $440.00 $220.00 $0.00 $220.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $44.00 $22.00 $0.00 $22.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $484.00 $242.00 $0.00 $242.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $2,409.00 $1,241.00 $0.00 $1,168.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $300.00 $150.00 $0.00 $150.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $2,709.00 $1,391.00 $0.00 $1,318.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $240.00 $120.00 $0.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $3,480.00 $1,740.00 $0.00 $1,740.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $400.00 $200.00 $0.00 $200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $471.00 $193.00 $0.00 $278.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $4,591.00 $2,253.00 $0.00 $2,338.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $31,363.06 $2,461.39 $10,949.75 $3,388.90 $10,749.37 $3,813.65 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $2,139.52 $246.14 $597.18 $338.89 $575.94 $381.37 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $33,502.58 $2,707.53 $11,546.93 $3,727.79 $11,325.31 $4,195.02 $0.00 $0.00 $0.00 $0.00 $0.00

Cost Estimate Page 1 of 1 Cost Estimate

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Former First Class Cleaners SUBTASK: Semi-Annual Groundwater Sampling

DATE: 6/29/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Professional A. Sava

Staff Professional A. Lamore

TOTAL LABOR 67

VEHICLE TYPE RATE UNIT USEAGE

Van $120.00 Day 3 $360.00 Subtotal $360.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE

Per diem, 2 staff x 3 days $36.00 Day 6 $216.00 Luke Varner hotel (2 nights) $129.00 Day 2 $258.00 Alex Lamore Hotel (2 nights) $129.00 Day 2 $258.00

TOTAL PER DIEM $732.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

IDW

Erwin Remediation Pickup, transport, dispose IDW 2 drums $220.00 $220.00

Subtotal $220.00

TOTAL SUB $220.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOHs 16 GW samples, 1 IDW $73.00 17 0 $1,241.00 Subtotal $1,241.00

Shipping Large Cooler (25 to 50 lbs) $150.00 1 $150.00

Subtotal $150.00

TOTAL LAB $1,391.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Analytical Related

Shallow Groundwater Sampling Kit (2 ppl, 3 $290.00 Day 6 $1,740.00 Subtotal $1,740.00

IDW Related Drum $100.00 Drum 2 $200.00

Subtotal $200.00 Expendables

3 days $40.00 Day 3 $120.00 Subtotal $120.00

Other 5 Passive Diffusion Bag (PDB) Samplers $0.00 Large diameter (RW005) $40.00 each 1 $40.00 Small diameter (MW034, MW035, MW036) $36.00 each 3 $108.00 Diffusion sampler kit (RW005) $45.00 each 1 $45.00

Subtotal $193.00

TOTAL EQUIPMENT $2,253.00

Senior Staff Professional L. Varner

Field preparation (2 hrs); Mobilization (4 hrs rd trip); depth to water measurements 16 wells (4 hrs); equipment calibration (1 hr);

groundwater sampling 6 widely-spaced wells (1.75 each well = 11 hrs);

deploy 2 additional PDBs (1 hr); sample management (1 hr); IDW management (1 hr)

Obtain updated access agreement (2 hrs); Field event notifications to owners, tenant, and water department (2 hrs); field preparation (2 hrs);

daily field data evaluation (1 hr x 3 days); Characterization and waste profile for transportation and disposal of IDW Drums(s) (1 hr); IDW manifest and pickup arrangment (1 hr)

Field preparation (3 hrs); Mobilization (4 hrs rd trip); depth to water measurements 17 wells (4 hrs); equipment calibration (1 hr);

groundwater sampling and deploying 3 PDBs (2 hr); groundwater sampling 7 widely-spaced wells (1.75 each well = 13 hrs ); sample management/shipping (2 hrs); IDW sampling (1 hr); IDW management (1

6/29/2022 Page 1 of 4 Subtask 2

SUBTASK: Semi-Annual NAM Report

DATE: 6/29/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Principal T. Kafka 2

Project Professional M. Hensley 4

Professional

A. Sava 21

Staff Professional A. Lamore 2

Administrative Assistant A. Acosta 1

TOTAL LABOR 30

VEHICLE TYPE RATE UNIT USEAGE

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

TOTAL SUB $0.00

LABORATORY COSTS

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT $0.00

Compile and assemble final PDF.

Recommendation and path forward (1 hr)

GIS figures (Potmaps (3 intervals) and spider plots (3 intervals))

Report text (16 hrs), data evaluation and interpretation (2 hrs), preparation of preliminary figures for GIS and table formatiing (2 hrs), signature and submittal (1 hr)

Data table updates

6/29/2022 Page 2 of 4 Subtask 3

SUBTASK: Semi-Annual Groundwater Sampling

DATE: 6/29/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Professional A. Sava

Senior Staff Professional L. Varner

Staff Professional A. Lamore

TOTAL LABOR 65

VEHICLE TYPE RATE UNIT USEAGE

Van $120.00 Day 3 $360.00 Subtotal $360.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE

2 staff x 3 days $36.00 Day 6 $216.00 Luke Varner hotel (2 nights) $129.00 Day 2 $258.00 A. Lamore Hotel (2 nights) $129.00 Day 2 $258.00

TOTAL PER DIEM $732.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

IDW

Erwin Remediation Pickup, transport, dispose IDW 2 drums $220.00 $220.00

$0.00 $0.00 Subtotal $220.00

TOTAL SUB $220.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOHs $73.00 16 0 $1,168.00

Subtotal $1,168.00 Shipping

Large Cooler (25 to 50 lbs) $150.00 1 $150.00 Subtotal $150.00

TOTAL LAB $1,318.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Drilling Related Analytical Related

Groundwater Sampling Kit (2 ppl x 3 days $290.00 Day 6 $1,740.00 Subtotal $1,740.00

IDW Related Drum $100.00 Drum 2 $200.00

Subtotal $200.00 Expendables

3 days $40.00 Day 3 $120.00 Subtotal $120.00

Other 5 Passive Diffusion Bag (PDB) Samplers Large diameter (RW005) $40.00 each 1 $80.00 Small diameter (MW034, MW035, MW036) $36.00 each 3 $108.00

$90.00 Subtotal $278.00

TOTAL EQUIPMENT $2,338.00

Field preparation (3 hrs); Mobilization (4 hrs rd trip); depth to water measurements 17 wells (4 hrs);

equipment calibration (1 hr); groundwater sampling and deploying 3 PDBs (2 hr); groundwater sampling 7 widely-spaced wells (1.75 each well = 13 hrs ); sample management/shipping (2 hrs); IDW sampling (1 hr); IDW management (1 hr)

Field preparation (2 hrs); Mobilization (4 hrs rd trip); depth to water measurements 16 wells (4 hrs);

equipment calibration (1 hr); groundwater sampling 6 widely-spaced wells (1.75 each well = 11 hrs);

deploy 2 additional PDBs (1 hr); sample management (1 hr); IDW management (1 hr)

Field event notifications to owners, tenant, and water department (2 hrs); field preparation (2 hrs); daily field data evaluation (1 hr x 3 days); IDW profile confirmation (1 hr); Characterization and waste profile for transportation and disposal of IDW Drums(s) (1 hr)

6/29/2022 Page 3 of 4 Subtask 4

SUBTASK: Annual NAM Report

DATE: 6/29/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Principal T. Kafka 2

Project Professional M. Hensley 4

Professional A. Sava 25

Staff Professional A. Lamore 2

Administrative Assistant A. Acosta 1

TOTAL LABOR 34

VEHICLE TYPE RATE UNIT USEAGE

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

TOTAL SUB $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT $0.00

Compile and assemble final PDF.

Recommendation and path forward (1 hr); PG sign and seal (1 hr)

GIS figures (Potmaps (3 interals) and spider plots (3 intervals))

Annual report text (20 hrs), data evaluation and interpretation (2 hrs), preparation of preliminary figures for GIS and table formatiing (2 hrs), signature and submittal (1 hr)

Data table updates

6/29/2022 Page 4 of 4 Subtask 5

12802 Tampa Oaks, Suite 151 Tampa, Florida 33647

PH 813.558.0990

FAX 813.558.9726

www.geosyntec.com

FR0929#/First Class_2022_Semi-Annual GWM_SOW

June 29, 2022

Mr. Evan Miller Florida Department of Environmental Protection Waste Cleanup Program 2600 Blair Stone Road, MS 4520 Tallahassee, FL 32399-2400

Subject: Statement of Work – Semi-Annual Groundwater Monitoring Former First Class Cleaners 591 East Semoran Boulevard Casselberry, Seminole County, Florida

ERIC_5489

Dear Evan:

Geosyntec Consultants, Inc. (Geosyntec) has prepared this statement of work (SOW) and attached level of effort (LOE) cost estimate for the Florida Department of Environmental Protection (FDEP) to conduct semi-annual groundwater monitoring at the former First Class Dry Cleaner Site (FDEP Facility ID ERIC_5489). The Site is located at 591 East Semoran Boulevard, Casselberry, Seminole County, Florida. Proposed sampling activities are in accordance with the recommendations provided to FDEP from the Annual Groundwater Monitoring Report 2021.

Groundwater samples were last collected at the Site in December 2021 and a confirmation sample was collected from MW-034 in March 2022.

Based on direction from FDEP following concentration increases in well MW034, this SOW reflects an increase in sampling frequency from annual to semi-annual. Previous sampling events included sampling of six lower surficial wells and three intermediate wells. This SOW adds sampling of three additional upper surficial wells, two additional lower surficial wells, and two additional intermediate zone wells.

The purpose of the semi-annual groundwater monitoring is to collect groundwater samples for analysis of volatile organic halocarbons (VOHs) to evaluate groundwater quality at the Site. The attached LOE consists of five subtasks and is summarized below.

No site access agreement could be found on Oculus, therefore, prior to field work, Geosyntec will obtain an updated Access Agreement from the current real property owner of the former First Class Cleaners (ERIC_5489) site.

Subtask 1 – Project Management

Subtask 2 – Semi-annual Groundwater Monitoring – August 2022 This subtask contains costs for performance of the first semi-annual groundwater monitoring event in August 2022. Geosyntec will mobilize to the Site to collect depth-to-groundwater measurements from each accessible monitoring well (up to 37 total wells) within a 24-hour period, collect 16 groundwater samples, and deploy passive diffusion bags (PDBs) for the February 2023 semi-annual groundwater monitoring. Refer to the sampling plan provided in Attachment A.

Groundwater levels will be collected on the first day. All 37 monitoring wells are flush-mounted and in high traffic areas and prone to collecting stormwater inside the manhole. Geosyntec personnel will bail the manholes, measure and record groundwater levels, and resecure the manholes; extra time has been estimated because of the distances between wells, driving time and traffic to access off site wells, calls to the water department and waiting for arrival to access wells, and locating wells with a metal detector in overgrown right-of-way locations. We have assumed only the 3 PDB well locations will be sampled on Day 1.

Geosyntec will collect 16 groundwater samples from the monitoring well network using a combination of low flow sampling techniques and existing PDBs.

• PDBs deployed in December 2021 are located in MW034, MW035, and MW036 (each screened from 40-50 feet below land surface [ft bls]); new PDBs will be redeployed in these same wells for sampling in February 2023.

• Low flow sampling techniques will be used to collect groundwater samples from eleven 0.75-inch diameter monitoring wells that are too small for PDBs: three set in the upper surficial aquifer – (MW009 (10-15 ft bls), MW010 (20-30 ft bls), and MW012 (10-15 ft bls)); eight set in the lower surficial aquifer – (MW006 (47-52 ft bls), MW011 (50-55 ft bls), MW013 (50-55 ft bls), and MW028 (50-55 ft bls); and four installed in the intermediate zone – MW007 (66-71 ft bls), MW008 (85-90 ft bls), MW014 (70-75 ft bls) and MW029 (70-75 ft bls). Geosyntec has assumed that these wells can be sampled using a peristaltic pump, consistent with previous sampling events at the site. Additional time has been allotted to allow travel between widely spaced wells, right-of-way access, and heavy traffic. Two field personnel will work separately for maximum effectiveness.

• Additionally, low flow groundwater samples will be collected from RW002 (near base of screen near 96 ft bls) and RW005 should both recovery wells be accessible. A PDB will be deployed in RW005 for future sampling events. The presence of cords, tubing and a pump in RW002 prevents deployment of a PDB in that well.

• The groundwater samples will be submitted for laboratory analysis of VOHs by Environmental Protection Agency (EPA) Method 8260B.

Investigation derived waste (IDW) will be collected in two 55-gallon drums, which will be labelled, covered with plastic, and wrapped in orange construction fencing. Geosyntec obtained IDW transportation and disposal (T&D) estimates from Universal Environmental Solutions, LLC (UES), Erwin Remediation, LLC, and Clark Environmental (Attachment B). Each company is a licensed waste hauler in Florida. Erwin is recommended due to lowest per drum cost (total cost of $220.00). One composite IDW sample will be collected for VOH analysis for waste characterization.

Geosyntec will use a metal detector to locate several monitoring wells in vegetated areas that are typically overgrown. Two field personnel are slated in August 2022 due to uncertainties associated with access and removal of equipment from the two recovery wells to be sampled and health and safety concerns associated with the monitoring well locations along busy State Route 436 (Semoran Blvd). Three field days are assumed with round trip mobilization from Tampa.

Subtask 3 – Semi-Annual Groundwater Monitoring Report Geosyntec will prepare a report summarizing sampling activities and results, and provide conclusions and recommendations based on data evaluation. The report will contain tables summarizing field/laboratory data, figures showing groundwater flow direction(s) (one per depth interval, three total) and three VOH isoconcentration figures (three depth intervals), and the results of the groundwater monitoring event. The report will be signed/sealed by a Florida-licensed geologist/engineer.

Subtask 4 – Semi-annual Groundwater Monitoring – February 2023 This subtask contains costs for performance of the first semi-annual groundwater monitoring event in February 2023. Geosyntec will mobilize to the Site to collect depth-to-groundwater measurements from each accessible monitoring well (up to 37 total wells) within a 24-hour period, collect 16 groundwater samples, and deploy passive diffusion bags (PDBs) for the August 2023 semi-annual groundwater monitoring. Refer to the sampling plan provided in Attachment A.

Groundwater levels will be collected on the first day. All 37 monitoring wells are flush-mounted and in high traffic areas and prone to collecting stormwater inside the manhole. Geosyntec personnel will bail the manholes, measure and record groundwater levels, and resecure the manholes; extra time has been estimated because of the distances between wells, driving time and traffic to access off site wells, calls to the water department and waiting for arrival to access wells, and locating wells with a metal detector in overgrown right-of-way locations. We have assumed only the 4 PDB well locations will be sampled on Day 1.

Geosyntec will collect 16 groundwater samples from the monitoring well network using a combination of low flow sampling techniques and existing PDBs.

• PDBs deployed in August 2022 are located in MW034, MW035, MW036 (each screened from 40-50 feet below land surface [ft bls]); and RW005 (screened 5 to 50 ft bls). New PDBs will be redeployed in these same wells for sampling in February 2023.

• Low flow sampling techniques will be used to collect groundwater samples from eleven 0.75-inch diameter monitoring wells that are too small for PDBs: three set in the upper surficial aquifer – (MW009 (10-15 ft bls), MW010 (20-30 ft bls), and MW012(10-15 ft bls)); eight set in the lower surficial aquifer – (MW006 (47-52 ft bls), MW011 (50-55 ft bls), MW013 (50-55 ft bls), and MW028 (50-55 ft bls); and four installed in the intermediate zone – MW007 (66-71 ft bls), MW008 (85-90 ft bls), MW014 (70-75 ft bls) and MW029 (70-75 ft bls). RW002, installed in the intermediate zone (screened 66 to 96

ft) will also be sampled. Geosyntec has assumed that these wells can be sampled using a peristaltic pump, consistent with previous sampling events at the site. Additional time has been allotted to allow travel between widely spaced wells, right-of-way access, and heavy traffic. Two field personnel will work separately for maximum effectiveness.

• The groundwater samples will be submitted for laboratory analysis of VOHs by Environmental Protection Agency (EPA) Method 8260B.

Investigation derived waste (IDW) will be collected in two 55-gallon drums, which will be labelled, covered with plastic, and wrapped in orange construction fencing. Erwin Remediation will be contracted to pickup, transport, and dispose of ISW due to lowest per drum cost (total cost of $220.00).

Geosyntec will use a metal detector to locate several monitoring wells in vegetated areas that are typically overgrown. Two field personnel are slated in February 2023 due to uncertainties associated with access and health and safety concerns associated with the monitoring well locations along busy State Route 436 (Semoran Blvd). Two field days are assumed with round trip mobilization from Tampa.

Subtask 5 – Annual Groundwater Monitoring Report Preparation Geosyntec will prepare a report summarizing sampling activities and results, and provide conclusions and recommendations based on data evaluation. The report will contain tables summarizing field/laboratory data, figures showing groundwater flow direction(s) (one per depth interval, three total) and three VOH isoconcentration figures (three depth intervals), and the results of the groundwater monitoring event. The report will be signed/sealed by a Florida-licensed geologist/engineer.

Deliverable Schedule and Invoicing Note that this schedule reflects two weeks FDEP review of LOE. Geosyntec anticipates the following schedule of deliverables and invoices.

Subtask Deliverable Deliverable Date Invoice Amount

2 and 3 Submittal of Semi-Annual Groundwater Monitoring report, field notes, laboratory report

October 30, 2022 $15,274.72

1, 4, and 5 Submittal of Semi-Annual Groundwater Monitoring report, field notes, laboratory report April 30, 2023 $18,227.86

TOTAL COST $33,502.58

Closure

We appreciate this opportunity to work with FDEP on this project. Feel free to contact us if you have any questions or require any additional information.

Sincerely, Ann Sava, PG (#2740) Geologist

Todd K. Kafka, PG (#2338) Principal

Attachments: A – 2022-2023 Sampling Plan B – IDW cost estimates

ATTACHMENT A

Florida Department of Environmental Protection -- Bureau of Waste Cleanup -- Hazardous Waste Cleanup Section

TABLE 1: PROPOSED 2022 ANNUAL GROUNDWATER MONITORING PLAN

Depth to Groundwater Measurements

VOHs by US EPA Method

8260B MW001 Upper Surficial 20 to 25 X MW002 Lower Surficial 45 to 50 X MW003 Upper Surficial 20 to 30 X

MW004R Upper Surficial 3 to 13 X MW005R Upper Surficial 18 to 23 X MW006 Lower Surficial 47 to 52 X X Conduct low-flow sampling in 8-2022 MW007 Intermediate 66 to 71 X X Conduct low-flow sampling in 8-2022 MW008 Intermediate 85 to 90 X X Conduct low-flow sampling in 8-2022 MW009 Upper Surficial 10 to 15 X X Conduct low-flow sampling in 8-2022 MW010 Upper Surficial 20 to 30 X X Conduct low-flow sampling in 8-2022 MW011 Lower Surficial 50 to 55 X X Conduct low-flow sampling in 8-2022 MW012 Upper Surficial 10 to 15 X X Conduct low-flow sampling in 8-2022 MW013 Lower Surficial 50 to 55 X X Conduct low-flow sampling in 8-2022 MW014 Intermediate 70 to 75 X X Conduct low-flow sampling in 8-2022 MW015 Upper Surficial 20 to 30 X MW016 Intermediate 70 to 75 X MW017 Upper Surficial 10 to 15 X MW018 Upper Surficial 20 to 30 X MW019 Lower Surficial 50 to 55 X MW020 Upper Surficial 10 to 15 X Casselberry Water Works Division Property MW021 Upper Surficial 20 to 30 X Casselberry Water Works Division Property MW023 Upper Surficial 10 to 15 X MW024 Upper Surficial 20 to 30 X MW025 Lower Surficial 50 to 55 X MW026 Upper Surficial 20 to 30 X MW027 Upper Surficial 20 to 30 X MW028 Lower Surficial 50 to 55 X X Conduct low-flow sampling in 8-2022 MW029 Intermediate 70 to 75 X X Conduct low-flow sampling in 8-2022 MW030 Lower Surficial 50 to 55 X MW031 Upper Surficial 20 to 30 X MW034 Lower Surficial 40 to 50 X X Collect PDB sample in 8-2022 MW035 Lower Surficial 40 to 50 X X Collect PDB sample in 8-2022 MW036 Lower Surficial 40 to 50 X X Collect PDB sample in 8-2022 MW037 Upper Surficial 5 to 15 X RW001 Upper Surficial 7 to 52 X RW002 Intermediate 66 to 96 X X Deploy PDB in 8-2022 RW003 Lower Surficial 5 to 50 X Casselberry Water Works Division Property RW004 Lower Surficial 5 to 50 X RW005 Lower Surficial 5 to 50 X X Deploy PDB in 8-2022

39 depth to water 16 total samples in August 2022 Notes: 16 total samples in February 2023

1. VOH indicates volatile organic halogens.

2. EPA indicates Environmental Protection Agency.

3. PDB indicated passive diffusion bag.

4. ft BLS indicates feet below land surface.

5. ft BTOC indicates feet below top of casing

Facility Name: Former First Class Cleaners Facility ID No. ERIC_5489

Analysis Screen Interval

(ft BLS) Comment

6. Locations in bold text were sampled in December 2021.

Sampling Location Aquifer Zone

FR0929H/Sampling Table with header Page 1 of 1 Geosyntec Consultants, Inc.

ATTACHMENT B

408 Ditmar Street

Pensacola, FL 32503

ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562

(850) 292-6511

To: Mr. Todd Kafka - Geosyntec Consultants, Inc.

12802 Tampa Oaks Blvd, Ste 151

Tampa, FL 33637

June 14, 2022

Re: Non-Hazardous Drum Disposal Quote

Mr. Kafka:

The price for the transportation and disposal (T&D) of drums of non-hazardous soil, mud and water is listed below.

Non-Hazardous Chlorinated VOHs, Petroleum and Metals:

Description Rate Unit

T&D - Non-Haz Soil $ 110.00 Per Drum

T&D - Non-Haz Mud/Water $ 110.00 Per Drum

Non-Hazardous PFAS Impacted:

Description Rate Unit

Profile Fee $ 350.00 Per Site

T&D - Non-Haz PFOS/PFAS Impacted Soil $ 120.00 Per Drum

T&D - Non-Haz PFOS/PFAS Impacted Mud/Water $ 130.00 Per Drum

The prices listed are all inclusive without any additional fees or charges (fuel surcharge, low volume stop fee etc.) and are valid for all regions in the State of Florida except for the Florida Keys. Pricing for sites located in the Florida Keys will be bid on a case-by-case basis dependent on the volume of drums and the location.

This quote is valid for 90 days.

Respectfully, Jonathan Erwin

Erwin Remediation, Inc.

Email: ErwinRemediation@Gmail.com

Office: (850) 292-6511 mailto:Remediation@Gmail.com

1/7/22, 11:18 AM Clark Environmental Inc.: Quote Builder quote.clarkenvironmental.com/Quotes/ViewQuote?quoteId=19200 1/2

Quote Number: 19200

QUOTE

QUOTED TO: Todd Kafka

QUOTE DATE: 1/7/2022

COMPANY NAME: Geosyntec - 2022 QUOTED BY: Craig Burns

PHONE NUMBER:

Ext.

FAX NUMBER:

PROJECT REFERENCE: Drum Trans & Disposal for non-haz materials - Petro, Dry Cleaner & PFAS

CUSTOMER PO:

CONTACT EMAIL:

SITE ADDRESS: TBD

CLARK ENVIRONMENTAL, INC. IS PLEASED TO PROVIDE THE FOLLOWING

COST ESTIMATE FOR

THE SITE/ PROJECT LISTED ABOVE.

DESCRIPTION PRICE QTY. UNIT TOTAL

NON HAZ DRUM DISPOSAL**Soils, Solids, Sludges** $80.00 DRUM $0.00

NON HAZ DRUM DISPOSAL**Liquids, PPE, Pads/Rags** $60.00 DRUM $0.00

TRANSPORTATION: 0-100 miles from CLARK Mulberry FL <6 drums/site - surcharge of $50/site

$30.00 DRUM $0.00

TRANSPORTATION: 101-250 miles from CLARK Mulberry FL <6 drums/site - surcharge of $50/site

$40.00 DRUM $0.00

TRANSPORTATION: 251-400 miles from CLARK Mulberry FL <11 drums/site - surcharge of $200/site

$50.00 DRUM $0.00

Totes T&D is available. CLARK can also deliver new drums to each site if needed :$40 + tax

$0.00 . $0.00

HAZ Drums to be quoted case-by-case $0.00 . $0.00

TOTAL REQUIRED ITEMS $0.00

TOTAL OPTIONAL ITEMS $0.00

GRAND TOTAL $0.00

NOTES: Rates apply for FL. Labs and profiles must be approved prior to pick ups.

**Petro Sites required: TCLP 4 metals & TCLP Benzene**Dry Cleaner Sites require 8260 VOH's** Craig Burns

863.327.6289 - cburns@clarkenv.com

This quote will remain valid for 2022 and based on payment in net 30 days. Quote based on an accepted and approved profile. Please sign and return to accept this quotation and by signing agree to all terms and conditions.

Name (print) Title

1/7/22, 11:18 AM Clark Environmental Inc.: Quote Builder quote.clarkenvironmental.com/Quotes/ViewQuote?quoteId=19200 2/2

Signature Date

CLARK ENVIRONMENTAL, INC. * 755 Prairie Industrial Pkwy. * Mulberry, Florida 33860 Telephone: 863-425-4884 * Fax: 863-425-2854

WWW.ClarkEnvironmental.com

CEF.pdf
Cost Estimate
LOEs.pdf
Subtask 2
Subtask 3
Subtask 4
Subtask 5
First Class_2022_Semi-Annual GWM_SOW.pdf
Subtask 1 – Project Management
Subtask 2 – Semi-annual Groundwater Monitoring – August 2022
Subtask 3 – Semi-Annual Groundwater Monitoring Report
Subtask 4 – Semi-annual Groundwater Monitoring – February 2023
Subtask 5 – Annual Groundwater Monitoring Report Preparation
Deliverable Schedule and Invoicing
Closure
CEF.pdf
Cost Estimate
LOEs.pdf
Subtask 2
Subtask 3
Subtask 4
Subtask 5
First Class_2022_Semi-Annual GWM_SOW.pdf
Subtask 1 – Project Management
Subtask 2 – Semi-annual Groundwater Monitoring – August 2022
Subtask 3 – Semi-Annual Groundwater Monitoring Report
Subtask 4 – Semi-annual Groundwater Monitoring – February 2023
Subtask 5 – Annual Groundwater Monitoring Report Preparation
Deliverable Schedule and Invoicing
Closure

File details come from the government source that posted it. Updated .