This is a Task Assignment Change Order (TACO #2) issued by the State of Florida Department of Environmental Protection (FDEP) amending a contract with Geosyntec Consultants for site assessment activities at the Former Ruck's Park Brownfield Site (Site ID: ERIC_17896) in Miami-Dade County. The contract number is HW683, and the task assignment number is BF04C. The change order was executed on March 30, 2026, and settles Work Change Directive #2 issued on March 13, 2026.
The change order authorizes additional Geosyntec labor hours to address comments from the Miami-Dade County Division of Environmental Resources (DERM) on the Site Assessment Report Addendum (SARA), prepare responses to those comments, and revise the SARA report. The amended total task value increased from $58,452.35 to $65,953.08, representing a cost increase of $7,500.73. The specific increases include $862.93 for project management (Subtask 1) and $6,637.80 for SARA preparation and revision (Subtask 4). The task completion date was extended from March 31, 2026, to June 30, 2026, for a total of 91 additional days. Deliverables include responses to DERM comments, field notes and documentation, a revised Site Assessment Report Addendum, and investigation-derived waste disposal manifests, with Department approval required before invoicing for each deliverable component.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/17/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:
1. TA Number: TACO Number: Contract Number:
TACO Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department’s Project Manager: Department’s Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number) Project Name:
4. ☐ There are no changes to the TA compensation.
☐ The compensation of the TA is changed to the amounts indicated below:
Amended Price Price Prior to TACO ☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. ☐ There are no changes to the TA Expiration Date.
☐ The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).
6. ☐ There are no changes to the Attachments.
☐ Attachment ___ is replaced with Attachment -____.
7. ☐ No Additional Changes.
☐ Additional Changes:
8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.
IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
BF04C 2 HW683
This Task Assignment Change Order settles Work Change Directive (WCD) #2 issued on March 13, 2026. This WCD authorized additional Geosyntec labor hours to address DERM comments on the SARA, prepare responses to the comments, and revise the SARA Report.
Megan Johnson 850.245.8994 Contractor Contractor
Contractor Contractor
Contractor
Geosyntec Consultants Shekhar Melkote, P.G. 570.575.2631
ERIC_17896
Former Ruck's Park
✔ $ 65,953.08 $ 58,452.35
$ 65,953.08 $ 58,452.35 Completion
Completion✔ 03/31/2026 06/30/2026 91
✔ 1 1 1
Geosyntec Consultants
Joseph Applegate, P.G.
Sr. Principal Hydrogeologist
Joseph Applegate Digitally signed by Joseph Applegate Date: 2026.03.30 10:20:03 -04'00'
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2026.03.30 08:52:35 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 01_18
Contract Number:
Task Assignment #:
Change Order #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
HW683
BF04C
$ 65,953.08
Respond to comments (RTC) from the Miami-Dade County Division of Environmental Resources (DERM) review letter and prepare off-site contamination notifications.
Field notes, photographic log, chain of custody, and sampling logs
Revised Site Assessment Report Addendum; Project Management
Investigation derived waste (IDW) disposal manifests
Department approval of the RTC from the DERM review letter and preparation of the off-site contamination notifications (Subtask 2)
Department approval of Project Management and Revised Site Assessment Report Addendum (Subtasks 1 and 4)
Department approval of IDW Management documentation (Subtask 5)
Department approval of field notes, photographic log, chain of custody, and sampling logs (Subtask 3)
01/09/2026
01/09/2026
05/29/2026
04/30/2026
$ 31,636.84
$ 4,602.08
$ 28,093.46
$ 1,620.70
Memorandum
TO: Geosyntec Consultants, Inc. HW683 Contract File
FROM: Megan Johnson, Contract Manager
DATE: March 27, 2026
SUBJECT: Negotiation Summary – SRP28
Task Assignment (TA) Change Order #2 – TA BF04C C2 Former Ruck’s Park - Site ID #: ERIC_17896 Site Assessment Activities
This Task Assignment Change Order (TACO) settles Work Change Directive (WCD) #2 issued on March 13, 2026. This WCD authorized additional Geosyntec labor hours to address comments from Miami-Dade County DERM on the February 2026 Site Assessment Report Addendum (SARA). Specific changes are detailed below:
Subtask 1: Project Management Under this subtask there was an increase in project management hours due to an increase in labor hours needed for the activities under Subtask 4. This change resulted in a cost actual increase of $862.93.
Subtask 4: Site Assessment Report Addendum (SARA) Under this subtask there was an increase in Geosyntec staff hours to prepare responses to DERMs comments on the SARA, teleconference with DERM, revise the SARA, and update the tables and figures in the report. This change resulted in a cost actual increase of $6,637.80.
Summary The Department’s SRP Contract Manager and Geosyntec’s Contract Manager have both agreed to the above changes. All changes noted above represent a total overall cost increase of $7,500.73, as shown in the Final/Cost Actual LOE. The changes were noted in the TACO Request received from Geosyntec on March 25, 2026. The final cost associated with this TA increased from $58,452.35 to $65,953.08. Documentation of the changes is included in the attached TACO Request, the Delta LOE spreadsheet and the Cost Actual LOE spreadsheet, and the TACO form for BF04C C2 prepared by the Department.
FDEP COST ESTIMATEContractor: Geosyntec Consultants
Date: 3/25/2026
Task #: SubTask 1 Project Management SubTask 6
Site: SubTask 2 DERM Ltr RTC & Off-Site Notification SubTask 7
Activity/Phase: Offsite Notices, Fieldwork & Reporting SubTask 3 Fieldwork SubTask 8
Project Manager: S. Melkote SubTask 4 Site Assessment Report Addendum SubTask 9
SubTask 5 IDW Disposal SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$73.14 Project Manager S. Melkote 24 24.4 $74.29 Sr. Principal J. Applegate 35 6 7 22 0 0 0 0 0 0 $73.14 Senior Consultant S. Melkote 88 6 12 67 3 0 0 0 0 0 $39.92 Senior Staff Professiona E. Tesfamariam 8 8 0 0 0 0 0 0 0 0 $38.87 Senior Staff Professiona M. Guirard 37 0 37 0 0 0 0 0 0 0 $33.97 Senior Staff Professiona S. Abelson 45 0 45 0 0 0 0 0 0 0 $58.93 Project Professional M. Hensley 19 4 0 15 0 0 0 0 0 0 $23.63 Drafter J. Sea 11 4 0 7 0 0 0 0 0 0 $43.79 Admin Assist P. Gallahger 0 0 0 0 0 0 0 0 0 0
Total Hours 267 24 28 101 111 3 0 0 0 0 0
Direct Labor $15,483.57 $1,781.30 $1,534.18 $4,364.55 $7,584.12 $219.42 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 172.70% $26,740.14 $3,076.31 $2,649.53 $7,537.58 $13,097.78 $378.94 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $42,223.71 $4,857.61 $4,183.71 $11,902.13 $20,681.90 $598.36 $0.00 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $480.00 $0.00 $480.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $480.00 $0.00 $480.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $9,190.00 $0.00 $9,190.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utility Locate $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $2,825.00 $0.00 $2,825.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $875.00 $0.00 $0.00 $0.00 $875.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $750.00 $0.00 $750.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Subcontractor Subtotal $13,640.00 $0.00 $12,765.00 $0.00 $875.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $1,289.00 $0.00 $1,201.50 $0.00 $87.50 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $14,929.00 $0.00 $13,966.50 $0.00 $962.50 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $2,168.00 $0.00 $2,168.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $2,168.00 $0.00 $2,168.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $160.00 $0.00 $160.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $825.00 $0.00 $825.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $945.00 $0.00 $945.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $1,930.00 $0.00 $1,930.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $61,730.71 $4,857.61 $4,183.71 $30,446.63 $20,681.90 $1,560.86 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $4,222.37 $485.76 $418.37 $1,190.21 $2,068.19 $59.84 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $65,953.08 $5,343.37 $4,602.08 $31,636.84 $22,750.09 $1,620.70 $0.00 $0.00 $0.00 $0.00 $0.00
Site Assessment - TACO 2_Final
Former Rucks Park Brownfield Site
Cost Estimate Page 1 of 7 Cost Estimate
Final
Task #: SubTask 1 Project Management SubTask 6
Site: SubTask 2 DERM Ltr RTC & Off-Site Notification SubTask 7
Activity/Phase: Offsite Notices, Fieldwork & Reporting SubTask 3 Fieldwork SubTask 8
Project Manager: S. Melkote SubTask 4 Site Assessment Report Addendum SubTask 9
SubTask 5 IDW Disposal SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10
Site Assessment - TACO 2_Final
Former Rucks Park Brownfield Site
Cost from Prior CEF: Manual Entry Cost from Delta CEF; Manual Entry $6,964.07
Cost (Prior + Delta): $0.00 Auto-Calculated Rounding Error: $65,953.08 Auto-Calculated
Final Total Cost: $65,953.08 Auto-Calculated
Cost Estimate Page 2 of 7 Cost Estimate
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Former Rucks Park Brownfield Site SUBTASK 2: DERM Ltr RTC & Off-Site Notification
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Principal J. Applegate 6
Senior Consultant S.Melkote
Sr. Staff Professional E. Tesfamariam
8 24 original, minus 16 (Delta)
4 6 original, minus 2 (Delta)
Drafter J. Sea 4
TOTAL LABOR 28
3/25/2026
Assist with Property Notification with GIS Support/Figures (4 hr)
Meetings with DERM (2 hr). Prepare Responses to DERM comments (2 hr). Assist with offsite notifications (2 hr).
Meetings with DERM (2 hr). Prepare Responses (2 hr), Off-site notices (2 hrs).
Prepare Offsite Notifications for approximtaley 6 properties/entities (4 hrs each).
Off-site notices Editing/preparation (4 hr)
Project Professional M.Hensley
3/27/2026 Page 3 of 7 Subtask 2
SUBTASK 3: Fieldwork
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Principal J. Applegate 7
Senior Consultant S. Melkote 12
Sr. Staff Professional M. Guirard 37
Sr. Staff Professional S. Abelson 45
TOTAL LABOR 101
VEHICLE TYPE RATE UNIT USEAGE
Car $80.00 Day 0 $0.00 Truck $120.00 Day 4 $480.00 Van $120.00 Day 0 $0.00
Subtotal $480.00
TOTAL VEHICLE $480.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Drilling (Conventional) Earth Tech, Pompano Beach, FL Install 4 Shallow Monitoring Wells $9,190.00 $9,190.00
$0.00 $0.00 Subtotal $9,190.00
Surveying Engenuity Group, WPB, FL Survey soil, wells and verify property/fence corners $2,825.00 $2,825.00
Subtotal $2,825.00
Utilities Geotek Services, Melbourne, FL Utility locate for subsurface work $750.00 $750.00
$0.00 $0.00 Subtotal $750.00
TOTAL SUB $12,765.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
Metals -As Soil - 6020B $14.00 4 0 $56.00 Soil Percent Moisture Soil - D2216 $13.00 6 0 $78.00 Metals -As GW - 6020B $14.00 14 1 $210.00 PAHs GW - 8270 SIM $110.00 8 1 $990.00
OCP GW- 8018B $105.00 2 0 $210.00
Coliform, Total GW - SM9223B $52.00 5 1 $312.00 Coliform, Fecal GW - IDEXX $52.00 5 1 $312.00
Subtotal $2,168.00
TOTAL LAB $2,168.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Drilling Related
Monitoring Well Installation Kit $325.00 Day 2 $650.00 Soil Assessment Kit $175.00 Day 1 $175.00 Soil Sampling Kit (Through Concrete) $235.00 Day 0 $0.00
Subtotal $825.00 Analytical Related
Groundwater Sampling Kit $290.00 Day 3 $870.00 Peristaltic Pump $30.00 Day 0 $0.00 Tubing $0.30 Day 250 $75.00
Subtotal $945.00 IDW Related
Drum $100.00 Drum 0 $0.00 Subtotal $0.00
Expendables $40.00 Day 4 $160.00
Subtotal $160.00
Other $0.00 Day 0 $0.00
Subtotal $0.00
TOTAL EQUIPMENT $1,930.00
3/25/2026
Daily mob/demob (3 hr x4 days = 12 hr); Soil Sampling at about 4 locations (6 hrs); Oversee 4 new well installation (16 hr); Sample ~10 wells (16 hr);
Offsite Access (2 hr), and Fieldwork Oversight (5 hr)
Fieldwork data review (4 hr), field oversight and support (4 hr)
Daily mob/demob (3 hr x5 days = 15 hr); Soil Sampling at about 4 locations (6 hrs); Oversee 4 new well installation (16 hr); Sample ~10 wells (16 hr); Survey (5 hr)
3/27/2026 Page 5 of 7 Subtask 3
SUBTASK 4: Site Assessment Report Addendum
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Principal J. Applegate 22 Original 14, add 8 (Delta)
Senior Consultant S. Melkote 67 Original 46, add 21 (Delta)
Project Professional M. Hensley
15 Original 14, add 1 (Delta)
Drafter J. Sea 7 Original 6, add 1 (Delta)
TOTAL LABOR 111
3/25/2026
Senior Peer Review and signing and sealing final SARA
Update Tables, Text & Figures. Prepare draft and final Reports .
Prepare/update Draft and Final Report Figures
Assist with Technical Editing of Tables and Text
3/27/2026 Page 6 of 7 Subtask 4
SUBTASK: IDW Disposal
DATE: 3/25/2026
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Senior Consultant S. Melkote 3 2 original, add 1 (Delta)
TOTAL LABOR 3
SUBCONTRACTOR COSTS
NAME PURPOSE COST Use
IDW
Erwin Remediation IDW Drum Disposal $125.00 7 $875.00 6 drums original, add 1 (Delta)
$0.00 $0.00 Subtotal $875.00
TOTAL SUB $875.00
Coordinate IDW and Review Manifests
3/27/2026 Page 7 of 7 Subtask 5
Task #: SubTask 1 Project Management SubTask 6
Site: SubTask 2 DERM Ltr RTC & Off-Site Notification SubTask 7
Activity/Phase: Offsite Notices, Fieldwork & Reporting SubTask 3 Fieldwork SubTask 8
Project Manager: S. Melkote SubTask 4 Site Assessment Report Addendum SubTask 9
SubTask 5 IDW Disposal SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$73.14 Project Manager S. Melkote 4 3.9 $74.29 Sr. Principal J. Applegate 8 0 0 8 0 0 0 0 0 0 $73.14 Senior Consultant S. Melkote 21 0 0 21 0 0 0 0 0 0 $39.92 Senior Staff Professiona E. Tesfamariam 0 0 0 0 0 0 0 0 0 0 $38.87 Senior Staff Professiona M. Guirard 0 0 0 0 0 0 0 0 0 0 $33.97 Senior Staff Professiona S. Abelson 0 0 0 0 0 0 0 0 0 0 $58.93 Project Professional M. Hensley 1 0 0 1 0 0 0 0 0 0 $23.63 Drafter J. Sea 1 0 0 1 0 0 0 0 0 0 $43.79 Admin Assist P. Gallahger 0 0 0 0 0 0 0 0 0 0
Total Hours 35 4 0 0 31 0 0 0 0 0 0
Direct Labor $2,500.49 $287.67 $0.00 $0.00 $2,212.82 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 172.70% $4,318.35 $496.81 $0.00 $0.00 $3,821.54 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $6,818.84 $784.48 $0.00 $0.00 $6,034.36 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utility Locate $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $6,818.84 $784.48 $0.00 $0.00 $6,034.36 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $681.89 $78.45 $0.00 $0.00 $603.44 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $7,500.73 $862.93 $0.00 $0.00 $6,637.80 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Site Assessment - TACO 2_Delta
Former Rucks Park Brownfield Site
Cost Estimate Page 1 of 3 Cost Estimate
Delta
Task #: SubTask 1 Project Management SubTask 6
Site: SubTask 2 DERM Ltr RTC & Off-Site Notification SubTask 7
Activity/Phase: Offsite Notices, Fieldwork & Reporting SubTask 3 Fieldwork SubTask 8
Project Manager: S. Melkote SubTask 4 Site Assessment Report Addendum SubTask 9
SubTask 5 IDW Disposal SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10
Site Assessment - TACO 2_Delta
Former Rucks Park Brownfield Site
Cost from Prior CEF: Manual Entry Cost from Delta CEF; Manual Entry $862.93
Cost (Prior + Delta): $0.00 Auto-Calculated Rounding Error: $7,500.73 Auto-Calculated
Final Total Cost: $7,500.73 Auto-Calculated
Cost Estimate Page 2 of 3 Cost Estimate
SUBTASK 4: Site Assessment Report Addendum
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Principal J. Applegate 8
Senior Consultant S. Melkote 21
Project Professional M. Hensley
Drafter J. Sea 1
TOTAL LABOR 31
3/25/2026
Prepare RTC to DERM Comments (2), Meetging with DERM to discuss RTC (2), and SARA revisioin (4)
Prepare RTC to DERM Comments (3), Meetging with DERM to discuss RTC (2), and SARA revisioin (16)
Revise Report Figures
Revise Tables
3/27/2026 Page 3 of 3 Subtask 4
Task #: SubTask 1 Project Management SubTask 6
Site: SubTask 2 DERM Ltr RTC & Off-Site Notification SubTask 7
Activity/Phase: Offsite Notices, Fieldwork & Reporting SubTask 3 Fieldwork SubTask 8
Project Manager: S. Melkote SubTask 4 Site Assessment Report Addendum SubTask 9
SubTask 5 IDW Disposal SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$73.14 Project Manager S. Melkote 20 20.4 $74.29 Sr. Principal J. Applegate 27 6 7 14 0 0 0 0 0 0 $73.14 Senior Consultant S. Melkote 67 6 12 46 3 0 0 0 0 0 $39.92 Senior Staff Professiona E. Tesfamariam 8 8 0 0 0 0 0 0 0 0 $38.87 Senior Staff Professiona M. Guirard 37 0 37 0 0 0 0 0 0 0 $33.97 Senior Staff Professiona S. Abelson 45 0 45 0 0 0 0 0 0 0 $58.93 Project Professional M. Hensley 18 4 0 14 0 0 0 0 0 0 $23.63 Drafter J. Sea 10 4 0 6 0 0 0 0 0 0 $43.79 Admin Assist P. Gallahger 0 0 0 0 0 0 0 0 0 0
Total Hours 232 20 28 101 80 3 0 0 0 0 0
Direct Labor $12,983.08 $1,493.63 $1,534.18 $4,364.55 $5,371.30 $219.42 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 172.70% $22,421.79 $2,579.50 $2,649.53 $7,537.58 $9,276.24 $378.94 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $35,404.87 $4,073.13 $4,183.71 $11,902.13 $14,647.54 $598.36 $0.00 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $480.00 $0.00 $480.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $480.00 $0.00 $480.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $9,190.00 $0.00 $9,190.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utility Locate $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $2,825.00 $0.00 $2,825.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $875.00 $0.00 $0.00 $0.00 $875.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $750.00 $0.00 $750.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Subcontractor Subtotal $13,640.00 $0.00 $12,765.00 $0.00 $875.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $1,289.00 $0.00 $1,201.50 $0.00 $87.50 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $14,929.00 $0.00 $13,966.50 $0.00 $962.50 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $2,168.00 $0.00 $2,168.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $2,168.00 $0.00 $2,168.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $160.00 $0.00 $160.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $825.00 $0.00 $825.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $945.00 $0.00 $945.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $1,930.00 $0.00 $1,930.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $54,911.87 $4,073.13 $4,183.71 $30,446.63 $14,647.54 $1,560.86 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $3,540.48 $407.31 $418.37 $1,190.21 $1,464.75 $59.84 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $58,452.35 $4,480.44 $4,602.08 $31,636.84 $16,112.29 $1,620.70 $0.00 $0.00 $0.00 $0.00 $0.00
Site Assessment - TACO 1_Original
Former Rucks Park Brownfield Site
Cost Estimate Page 1 of 7 Cost Estimate
Original
Task #: SubTask 1 Project Management SubTask 6
Site: SubTask 2 DERM Ltr RTC & Off-Site Notification SubTask 7
Activity/Phase: Offsite Notices, Fieldwork & Reporting SubTask 3 Fieldwork SubTask 8
Project Manager: S. Melkote SubTask 4 Site Assessment Report Addendum SubTask 9
SubTask 5 IDW Disposal SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10
Site Assessment - TACO 1_Original
Former Rucks Park Brownfield Site
Cost from Prior CEF: Manual Entry Cost from Delta CEF; Manual Entry $6,101.14
Cost (Prior + Delta): $0.00 Auto-Calculated Rounding Error: $58,452.35 Auto-Calculated
Final Total Cost: $58,452.35 Auto-Calculated
Cost Estimate Page 2 of 7 Cost Estimate
SUBTASK 2: DERM Ltr RTC & Off-Site Notification
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Principal J. Applegate 6
Senior Consultant S.Melkote
Sr. Staff Professional E. Tesfamariam
8 24 original, minus 16 (Delta)
4 6 original, minus 2 (Delta)
Drafter J. Sea 4
TOTAL LABOR 28
3/25/2026
Assist with Property Notification with GIS Support/Figures (4 hr)
Meetings with DERM (2 hr). Prepare Responses to DERM comments (2 hr). Assist with offsite notifications (2 hr).
Meetings with DERM (2 hr). Prepare Responses (2 hr), Off-site notices (2 hrs).
Prepare Offsite Notifications for approximtaley 6 properties/entities (4 hrs each).
Off-site notices Editing/preparation (4 hr)
Project Professional M.Hensley
3/27/2026 Page 3 of 7 Subtask 2
SUBTASK 3: Fieldwork
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Principal J. Applegate 7
Senior Consultant S. Melkote 12
Sr. Staff Professional M. Guirard 37
Sr. Staff Professional S. Abelson 45
TOTAL LABOR 101
VEHICLE TYPE RATE UNIT USEAGE
Car $80.00 Day 0 $0.00 Truck $120.00 Day 4 $480.00 Van $120.00 Day 0 $0.00
Subtotal $480.00
TOTAL VEHICLE $480.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Drilling (Conventional) Earth Tech, Pompano Beach, FL Install 4 Shallow Monitoring Wells $9,190.00 $9,190.00
$0.00 $0.00 Subtotal $9,190.00
Surveying Engenuity Group, WPB, FL Survey soil, wells and verify property/fence corners $2,825.00 $2,825.00
Subtotal $2,825.00
Utilities Geotek Services, Melbourne, FL Utility locate for subsurface work $750.00 $750.00
$0.00 $0.00 Subtotal $750.00
TOTAL SUB $12,765.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
Metals -As Soil - 6020B $14.00 4 0 $56.00 Soil Percent Moisture Soil - D2216 $13.00 6 0 $78.00 Metals -As GW - 6020B $14.00 14 1 $210.00 PAHs GW - 8270 SIM $110.00 8 1 $990.00
OCP GW- 8018B $105.00 2 0 $210.00
Coliform, Total GW - SM9223B $52.00 5 1 $312.00 Coliform, Fecal GW - IDEXX $52.00 5 1 $312.00
Subtotal $2,168.00
TOTAL LAB $2,168.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Drilling Related
Monitoring Well Installation Kit $325.00 Day 2 $650.00 Soil Assessment Kit $175.00 Day 1 $175.00 Soil Sampling Kit (Through Concrete) $235.00 Day 0 $0.00
Subtotal $825.00 Analytical Related
Groundwater Sampling Kit $290.00 Day 3 $870.00 Peristaltic Pump $30.00 Day 0 $0.00 Tubing $0.30 Day 250 $75.00
Subtotal $945.00 IDW Related
Drum $100.00 Drum 0 $0.00 Subtotal $0.00
Expendables $40.00 Day 4 $160.00
Subtotal $160.00
Other $0.00 Day 0 $0.00
Subtotal $0.00
TOTAL EQUIPMENT $1,930.00
3/25/2026
Daily mob/demob (3 hr x4 days = 12 hr); Soil Sampling at about 4 locations (6 hrs); Oversee 4 new well installation (16 hr); Sample ~10 wells (16 hr);
Offsite Access (2 hr), and Fieldwork Oversight (5 hr)
Fieldwork data review (4 hr), field oversight and support (4 hr)
Daily mob/demob (3 hr x5 days = 15 hr); Soil Sampling at about 4 locations (6 hrs); Oversee 4 new well installation (16 hr); Sample ~10 wells (16 hr); Survey (5 hr)
3/27/2026 Page 5 of 7 Subtask 3
SUBTASK 4: Site Assessment Report Addendum
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Principal J. Applegate 14
Senior Consultant S. Melkote 46 Original 40, add 6 (Delta)
Project Professional M. Hensley
Drafter J. Sea 6
TOTAL LABOR 80
3/25/2026
Senior Peer Review and signing and sealing final SARA
Update Tables, Text & Figures. Prepare draft and final Reports .
Prepare/update Draft and Final Report Figures
Assist with Technical Editing of Tables and Text
3/27/2026 Page 6 of 7 Subtask 4
SUBTASK: IDW Disposal
DATE: 3/25/2026
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Senior Consultant S. Melkote 3 2 original, add 1 (Delta)
TOTAL LABOR 3
SUBCONTRACTOR COSTS
NAME PURPOSE COST Use
IDW
Erwin Remediation IDW Drum Disposal $125.00 7 $875.00 6 drums original, add 1 (Delta)
$0.00 $0.00 Subtotal $875.00
TOTAL SUB $875.00
Coordinate IDW and Review Manifests
3/27/2026 Page 7 of 7 Subtask 5
Site Name: Site ID #:
Contract #: Contractor:
• Reason for Work Change Directive :
• Description of Work Change Directive :
• Attachments (if applicable, list documents supporting change):
• Costs (if negotiated unit costs, provide information below):
WCP WCD 07-2018
Authorized Contractor Signature:
Authorized FDEP Signature:
WORK CHANGE DIRECTIVE FORM
FDEP Supervisor Approval:
(if applicable)
Additional work is not authorized without prior FDEP approval as indicated by an approved Work Change Directive Form or Task Assignment Change Order Form. It is the Contractor's responsibility to ensure that additional costs associated with this WCD are resolved by a Task Assignment Change Order (TACO) prior to the completion date of the original Task Assignment or subsequent TACOs completed prior to the execution date of this WCD. Failure to do so will result in a loss of reimbursement for work associated with this WCD.
Task Assignment #: Work Change Directive #:
Maximum Estimated Increase in Task Amount:
Former Rucks Park Site ERIC_17896
HW683 Geosyntec
BF04C 2
Address DERM comments on the February 2026 SARA. Prepare Responses to Comments, Discuss RTCs with DERM, and Revise SARA Report
Increased Geosyntec labor to prepare RTC to DERM comments, teleconference with DERM to discuss responses and revised SARA to address DERM comments.
Delta LOE for adjustments described above.
$ 7,500.00
Joseph Applegate Digitally signed by Joseph Applegate Date: 2026.03.13 14:18:29 -04'00'
Megan R. Johnson Digitally signed by Megan R.
Johnson Date: 2026.03.13 14:36:23 -04'00'
Scott L Sweeney
Digitally signed by Scott L Sweeney Date: 2026.03.13 14:48:53 -04'00'
From: Joseph L. Applegate To: Johnson, Megan R Cc: Shekhar Melkote Subject: Former Rucks Park - TACO 2 Date: Wednesday, March 25, 2026 1:20:33 PM Attachments: image001.png
Copy of HW683 Cost Estimate Form Rucks Park SARA_TACO 2_Original.xlsx Copy of HW683 Cost Estimate Form Rucks Park SARA_TACO 2_Delta.xlsx Copy of HW683 Cost Estimate Form Rucks Park SARA_TACO 2_Final.xlsx
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
Hi Megan
Please find attached the TACO 2 files for Rucks for the additional RTCs and SARA updates.
I took the final TACO 1 (now original), added the TACO 2 Delta (WCD amount), and the resultant TACO 2 Final. The numbers all add up to the penny . The final budget is $65,953.08.
We should probably extend the TA date to end of May or Maybe June 15, just to be safe.
We do have the IDW picked up . We have a call with Sandra next Tuesday to confirm the changes/additions that they want for the SARA. Hoping to get the revision in within the next couple of weeks.
Thank you!!
Joe mailto:JApplegate@Geosyntec.com mailto:Megan.R.Johnson@floridadep.gov mailto:SMelkote@Geosyntec.com
Cost Estimate
Contractor: Geosyntec Consultants
Date: 3/25/26
Task #: Site Assessment - TACO 1_Original SubTask 1 Project Management SubTask 6
Site: Former Rucks Park Brownfield Site SubTask 2 DERM Ltr RTC & Off-Site Notification SubTask 7
Activity/Phase: Offsite Notices, Fieldwork & Reporting SubTask 3 Fieldwork SubTask 8
Project Manager: S. Melkote SubTask 4 Site Assessment Report Addendum SubTask 9
SubTask 5 IDW Disposal SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10
Labor Rate Category
$73.14 Project Manager S. Melkote 20 20.4
$74.29 Sr. Principal J. Applegate 27 6 7 14 0 0 0 0 0 0
$0.00 Principal 0 0 0 0 0 0 0 0 0 0
$73.14 Senior Consultant S. Melkote 67 6 12 46 3 0 0 0 0 0
$0.00 Senior Consultant 0 0 0 0 0 0 0 0 0 0
$0.00 Senior Professional 0 0 0 0 0 0 0 0 0 0
$0.00 Senior Professional 0 0 0 0 0 0 0 0 0 0
$0.00 Senior Professional 0 0 0 0 0 0 0 0 0 0
$49.75 Project Professional P. Terselich 0 0 0 0 0 0 0 0 0 0
$0.00 Project Professional 0 0 0 0 0 0 0 0 0 0
$0.00 Professional 0 0 0 0 0 0 0 0 0 0
$0.00 Professional 0 0 0 0 0 0 0 0 0 0
$39.92 Senior Staff Professional E. Tesfamariam 8 8 0 0 0 0 0 0 0 0
$38.87 Senior Staff Professional M. Guirard 37 0 37 0 0 0 0 0 0 0
$33.97 Senior Staff Professional S. Abelson 45 0 45 0 0 0 0 0 0 0
$0.00 Senior Staff Professional 0 0 0 0 0 0 0 0 0 0
$0.00 Staff Professional 0 0 0 0 0 0 0 0 0 0
$0.00 Staff Professional 0 0 0 0 0 0 0 0 0 0
$0.00 Staff Professional 0 0 0 0 0 0 0 0 0 0
$0.00 Senior Engineering Technician 0 0 0 0 0 0 0 0 0 0
$0.00 Site Manager 0 0 0 0 0 0 0 0 0 0
$0.00 Designer 0 0 0 0 0 0 0 0 0 0
$58.93 Project Professional M. Hensley 18 4 0 14 0 0 0 0 0 0
$23.63 Drafter J. Sea 10 4 0 6 0 0 0 0 0 0
$43.79 Admin Assist P. Gallahger 0 0 0 0 0 0 0 0 0 0
$0.00 Intern 0 0 0 0 0 0 0 0 0 0
Total Hours 232 20 28 101 80 3 0 0 0 0 0
Direct Labor $12,983.08 $1,493.63 $1,534.18 $4,364.55 $5,371.30 $219.42 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 172.70% $22,421.79 $2,579.50 $2,649.53 $7,537.58 $9,276.24 $378.94 $0.00 $0.00 $0.00 $0.00 $0.00
Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Labor $35,404.87 $4,073.13 $4,183.71 $11,902.13 $14,647.54 $598.36 $0.00 $0.00 $0.00 $0.00 $0.00
Travel
Vehicle Rental $480.00 $0.00 $480.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Travel $480.00 $0.00 $480.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement)
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement)
Drilling (Conventional) $9,190.00 $0.00 $9,190.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utility Locate $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveying $2,825.00 $0.00 $2,825.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $875.00 $0.00 $0.00 $0.00 $875.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $750.00 $0.00 $750.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $13,640.00 $0.00 $12,765.00 $0.00 $875.00 $0.00 $0.00 $0.00 $0.00 $0.00
Handling Fee $1,289.00 $0.00 $1,201.50 $0.00 $87.50 $0.00 $0.00 $0.00 $0.00 $0.00
Total Subcontractor Cost $14,929.00 $0.00 $13,966.50 $0.00 $962.50 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory
Analytical Costs $2,168.00 $0.00 $2,168.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Laboratory $2,168.00 $0.00 $2,168.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses
Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Expendables $160.00 $0.00 $160.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Drilling related) $825.00 $0.00 $825.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Analytical related) $945.00 $0.00 $945.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Field Expenses $1,930.00 $0.00 $1,930.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $54,911.87 $4,073.13 $4,183.71 $30,446.63 $14,647.54 $1,560.86 $0.00 $0.00 $0.00 $0.00 $0.00
Completion Fee $3,540.48 $407.31 $418.37 $1,190.21 $1,464.75 $59.84 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $58,452.35 $4,480.44 $4,602.08 $31,636.84 $16,112.29 $1,620.70 $0.00 $0.00 $0.00 $0.00 $0.00
Cost from Prior CEF: Manual Entry
Cost from Delta CEF; Manual Entry $6,101.14
Cost (Prior + Delta): $0.00 Auto-Calculated
Rounding Error: $58,452.35 Auto-Calculated
Final Total Cost: $58,452.35 Auto-Calculated
$4,480.44 $4,602.08 $13,092.34 $16,112.29 $20,165.20
$0.00 $18,544.50 $0.00
&"CG Times,Bold"&16FDEP COST ESTIMATE
&"Courier New,Bold"&10&A &"Courier New,Bold"&10Page &P of &N &"Courier New,Bold"&10&A
Subtask 2
SITE : Former Rucks Park Brownfield Site
SUBTASK 2: DERM Ltr RTC & Off-Site Notification
DATE: 3/25/26
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Principal Meetings with DERM (2 hr). Prepare Responses to DERM comments (2 hr). Assist with offsite notifications (2 hr).
J. Applegate 6
Senior Professional
Project Professional
Professional
Senior Consultant S.Melkote Meetings with DERM (2 hr). Prepare Responses (2 hr), Off-site notices (2 hrs).
Sr. Staff Professional E. Tesfamariam Prepare Offsite Notifications for approximtaley 6 properties/entities (4 hrs each).
8 24 original, minus 16 (Delta)
Drafter/CADD Operator
Project Professional M.Hensley Assist with Property Notification with GIS Support/Figures (4 hr)
4 6 original, minus 2 (Delta)
Drafter Off-site notices Editing/preparation (4 hr)
J. Sea 4
TOTAL LABOR 28
VEHICLE TYPE RATE UNIT USEAGE
Car $80.00 Day 0 $0.00
Truck $480.00 Week $0.00
Truck $120.00 Day 0 $0.00
Subtotal $0.00
Mileage $0.59 Mile 0 $0.00
Subtotal $0.00
Air Fare $0.00 Round Trip 0 $0.00
Subtotal $0.00
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
Per Diem $36.00 Day 0 $0.00
Hotel $140.00 Day 0 $0.00
Per Diem $36.00 Day 0 $0.00
Hotel $140.00 Day 0 $0.00
Per Diem $36.00 Day 0 $0.00
Hotel $140.00 Day 0 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Equipment Procurement
$0.00
$0.00 $0.00
Subtotal $0.00
Drilling (Conventional)
$0.00 $0.00
$0.00 $0.00
Subtotal $0.00
Drilling (Non-Conventional)
$0.00 $0.00
$0.00 $0.00
Subtotal $0.00
Mobile Laboratory
$0.00 $0.00
Subtotal $0.00
Surveying
$0.00 $0.00
Subtotal $0.00
IDW
$0.00 $0.00
$0.00 $0.00
Subtotal $0.00
Utilities
$0.00 $0.00
$0.00 $0.00
Subtotal $0.00
Other
$0.00
$0.00 $0.00
Subtotal $0.00
TOTAL SUB $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOCs $70.00 0 0 $0.00
VOHs $73.00 0 0 $0.00
VOAs $60.00 0 0 $0.00
RCRA-8 $14.00 0 0 $0.00
TOC $30.00 0 0 $0.00
TDS $16.00 0 0 $0.00
TRPH $88.00 0 0 $0.00
PFAS $315.00 0 0 $0.00
Subtotal $0.00
Fast Turnaround Charges Percent
24 Hours 110% $0.00 0 $0.00
3 Days 65% $0.00 0 $0.00
1 Week 20% $0.00 0 $0.00
Subtotal $0.00
Shipping
Large Cooler (25 to 50 lbs) $150.00 0 $0.00
Small Cooler (0 to 25 lbs) $110.00 0 $0.00
Subtotal $0.00
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Drilling Related
Monitoring Well Installation Kit $325.00 Day 0 $0.00
Soil Assessment Kit $175.00 Day 0 $0.00
Soil Sampling Kit (Through Concrete) $235.00 Day 0 $0.00
Subtotal $0.00
Analytical Related
Deep Groundwater Sampling Kit $1,660.00 Week 0 $0.00
Deep Groundwater Sampling Kit $415.00 Day 0 $0.00
YSI 556 MPS $105.00 Day 0 $0.00
Subtotal $0.00
IDW Related
Drum $100.00 Drum 0 $0.00
Subtotal $0.00
Expendables
$40.00 Day 0 $0.00
Subtotal $0.00
Other
$0.00 Day 0 $0.00
Subtotal $0.00
TOTAL EQUIPMENT $0.00
&"Times New Roman,Bold"LEVEL OF EFFORT/EXPENSE WORKSHEET
&D Page &P of &N &A
Subtask 3
SITE : Former Rucks Park Brownfield Site
SUBTASK 3: Fieldwork
DATE: 3/25/26
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Principal Offsite Access (2 hr), and Fieldwork Oversight (5 hr)
J. Applegate 7
Senior Professional
Project Professional
Senior Consultant Fieldwork data review (4 hr), field oversight and support (4 hr)
S. Melkote 12
Sr. Staff Professional Daily mob/demob (3 hr x4 days = 12 hr); Soil Sampling at about 4 locations (6 hrs); Oversee 4 new well installation (16 hr); Sample ~10 wells (16 hr);
M. Guirard 37
Sr. Staff Professional Daily mob/demob (3 hr x5 days = 15 hr); Soil Sampling at about 4 locations (6 hrs); Oversee 4 new well installation (16 hr); Sample ~10 wells (16 hr); Survey (5 hr)
S. Abelson 45
Project Professional GIS Assistance with Site Access and Permit Applciation (2 hr)
M. Hensley 0
Administrative Assistant
TOTAL LABOR 101
VEHICLE TYPE RATE UNIT USEAGE
Car $80.00 Day 0 $0.00
Truck $120.00 Day 4 $480.00
Van $120.00 Day 0 $0.00
Subtotal $480.00
Mileage $0.59 Mile 0 $0.00
Subtotal $0.00
Air Fare $0.00 Round Trip 0 $0.00
Subtotal $0.00
TOTAL VEHICLE $480.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00 Day 0 $0.00
$0.00 Day 0 $0.00
$0.00 Day 0 $0.00
$0.00 Day 0 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Equipment Procurement
$0.00 $0.00
$0.00 $0.00
Subtotal $0.00
Drilling (Conventional)
Earth Tech, Pompano Beach, FL Install 4 Shallow Monitoring Wells $9,190.00 $9,190.00
$0.00 $0.00
Subtotal $9,190.00
Drilling (Non-Conventional)
$0.00 $0.00
$0.00 $0.00
Subtotal $0.00
Mobile Laboratory
$0.00 $0.00
Subtotal $0.00
Surveying
Engenuity Group, WPB, FL Survey soil, wells and verify property/fence corners $2,825.00 $2,825.00
Subtotal $2,825.00
IDW
$0.00 $0.00
$0.00 $0.00
Subtotal $0.00
Utilities
Geotek Services, Melbourne, FL Utility locate for subsurface work $750.00 $750.00
$0.00 $0.00
Subtotal $750.00
Other
$0.00 $0.00
$0.00 $0.00
Subtotal $0.00
TOTAL SUB $12,765.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
Metals -As Soil - 6020B $14.00 4 0 $56.00
Soil Percent Moisture Soil - D2216 $13.00 6 0 $78.00
Metals -As GW - 6020B $14.00 14 1 $210.00
Metals -Pb GW $14.00 0 0 $0.00
PAHs GW - 8270 SIM $110.00 8 1 $990.00
OCP GW- 8018B $105.00 2 0 $210.00
Coliform, Total GW - SM9223B $52.00 5 1 $312.00
Coliform, Fecal GW - IDEXX $52.00 5 1 $312.00
Subtotal $2,168.00
Fast Turnaround Charges Percent
24 Hours 110% $0.00 0 $0.00
3 Days 65% $0.00 0 $0.00
1 Week 20% $0.00 0 $0.00
Subtotal $0.00
Shipping
Large Cooler (25 to 50 lbs) $150.00 0 $0.00
Small Cooler (0 to 25 lbs) $110.00 0 $0.00
Subtotal $0.00
TOTAL LAB $2,168.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Drilling Related
Monitoring Well Installation Kit $325.00 Day 2 $650.00
Soil Assessment Kit $175.00 Day 1 $175.00
Soil Sampling Kit (Through Concrete) $235.00 Day 0 $0.00
Subtotal $825.00
Analytical Related
Groundwater Sampling Kit $290.00 Day 3 $870.00
Peristaltic Pump $30.00 Day 0 $0.00
Tubing $0.30 Day 250 $75.00
Subtotal $945.00
IDW Related
Drum $100.00 Drum 0 $0.00
Subtotal $0.00
Expendables
$40.00 Day 4 $160.00
Subtotal $160.00
Other
$0.00 Day 0 $0.00
Subtotal $0.00
TOTAL EQUIPMENT $1,930.00
&"Times New Roman,Bold"LEVEL OF EFFORT/EXPENSE WORKSHEET
&D Page &P of &N &A
Subtask 4
SITE : Former Rucks Park Brownfield Site
SUBTASK 4: Site Assessment Report Addendum
DATE: 3/25/26
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Principal Senior Peer Review and signing and sealing final SARA
J. Applegate 14
Senior Consultant Update Tables, Text & Figures. Prepare draft and final Reports .
S. Melkote 46 Original 40, add 6 (Delta)
Project Professional Prepare/update Draft and Final Report Figures
M. Hensley
Drafter Assist with Technical Editing of Tables and Text
J. Sea 6
Administrative Assistant
TOTAL LABOR 80
VEHICLE TYPE RATE UNIT USEAGE
Car $80.00 Day 0 $0.00
Truck $120.00 Day 0 $0.00
Van $120.00 Day 0 $0.00
Subtotal $0.00
Mileage $0.59 Mile 0 $0.00
Subtotal $0.00
Air Fare $0.00 Round Trip 0 $0.00
Subtotal $0.00
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00 Day 0 $0.00
$0.00 Day 0 $0.00
$0.00 Day 0 $0.00
$0.00 Day 0 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Equipment Procurement
XRF Soil Screening for Arsenic (2 days @ $580/day) $0.00 $0.00
$0.00 $0.00
Subtotal $0.00
Drilling (Conventional)
Earth Tech Drilling, Inc. Soil Borings, Well Install and Development $0.00 $0.00
$0.00 $0.00
Subtotal $0.00
Drilling (Non-Conventional)
GeoTek Services, Inc. Mark underground utilities $0.00 $0.00
Titusville, FL $0.00 $0.00
Subtotal $0.00
Mobile Laboratory
$0.00 $0.00
Subtotal $0.00
Surveying
Engenuity Group Survey Soil Borings, Monitoring Wells & Confirm Property Boundary $0.00
Subtotal $0.00
IDW
Erwin Remediation 1 drum @ $125/drum $0.00 $0.00
$0.00 $0.00
Subtotal $0.00
Utilities
$0.00 $0.00
$0.00 $0.00
Subtotal $0.00
Other
$0.00 $0.00
$0.00 $0.00
Subtotal $0.00
TOTAL SUB $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
Metals -As Soil $12.00 0 0 $0.00
PAHs Soil $110.00 0 0 $0.00
Metals -As GW $12.00 0 0 $0.00
Metals -Pb GW $12.00 0 0 $0.00
PAHs GW $110.00 0 0 $0.00
OCP GW $105.00 0 0 $0.00
Coliform, Total GW $49.00 0 0 $0.00
Coliform, Fecal GW $49.00 0 0 $0.00
SPLP - PAH Soil $155.00 0 0 $0.00
$0.00 0 0 $0.00
Subtotal $0.00
Fast Turnaround Charges Percent
24 Hours 110% $110.00 0 $0.00
3 Days 65% $0.00 0 $0.00
1 Week 20% $0.00 0 $0.00
Subtotal $0.00
Shipping
Large Cooler (25 to 50 lbs) $150.00 0 $0.00
Small Cooler (0 to 25 lbs) $110.00 0 $0.00
Subtotal $0.00
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Drilling Related
Monitoring Well Installation Kit $325.00 Day 0 $0.00
Soil Assessment Kit $175.00 Day 0 $0.00
Soil Sampling Kit (Through Concrete) $235.00 Day 0 $0.00
Subtotal $0.00
Analytical Related
Groundwater Sampling Kit $290.00 Day 0 $0.00
Peristaltic Pump $30.00 Day 0 $0.00
Tubing $0.30 Day 0 $0.00
Subtotal $0.00
IDW Related
Drum $100.00 Drum 0 $0.00
Subtotal $0.00
Expendables
$40.00 Day 0 $0.00
Subtotal $0.00
Other
$0.00 Day 0 $0.00
Subtotal $0.00
TOTAL EQUIPMENT $0.00
&"Times New Roman,Bold"LEVEL OF EFFORT/EXPENSE WORKSHEET
&D Page &P of &N &A
Subtask 5
SITE : Former Rucks Park Brownfield Site
SUBTASK: IDW Disposal
DATE: 3/25/26
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Principal
J. Applegate
Senior Consultant Coordinate IDW and Review Manifests
S. Melkote 3 2 original, add 1 (Delta)
Project Professional Prepare draft (20 hr) and final GIS (10 hr) figures
M. Hensley
Drafter Assist tables and database
J. Sea
Senior Staff Professional
Staff Professional
Drafter/CADD Operator
Administrative Assistant
TOTAL LABOR 3
VEHICLE TYPE RATE UNIT USEAGE
Car $80.00 Day 0 $0.00
Truck $120.00 Day 0 $0.00
Van $120.00 Day 0 $0.00
Subtotal $0.00
Mileage $0.59 Mile 0 $0.00
Subtotal $0.00
Air Fare $0.00 Round Trip 0 $0.00
Subtotal $0.00
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00 Day 0 $0.00
$0.00 Day 0 $0.00
$0.00 Day 0 $0.00
$0.00 Day 0 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST Use
Equipment Procurement
$0.00 $0.00
$0.00 $0.00
Subtotal $0.00
Drilling (Conventional)
$0.00 $0.00
$0.00 $0.00
Subtotal $0.00
Drilling (Non-Conventional)
$0.00 $0.00
$0.00 $0.00
Subtotal $0.00
Mobile Laboratory
$0.00 $0.00
Subtotal $0.00
Surveying
$0.00 $0.00
Subtotal $0.00
IDW
Erwin Remediation IDW Drum Disposal $125.00 7 $875.00 6 drums original, add 1 (Delta)
$0.00 $0.00
Subtotal $875.00
Utilities
$0.00 $0.00
$0.00 $0.00
Subtotal $0.00
Other
$0.00 $0.00
$0.00 $0.00
Subtotal $0.00
TOTAL SUB $875.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOCs $70.00 0 0 $0.00
VOHs $73.00 0 0 $0.00
VOAs $60.00 0 0 $0.00
RCRA-8 $14.00 0 0 $0.00
TOC $30.00 0 0 $0.00
TDS $16.00 0 0 $0.00
TRPH $88.00 0 0 $0.00
PFAS $315.00 0 0 $0.00
Subtotal $0.00
Fast Turnaround Charges Percent
24 Hours 110% $0.00 0 $0.00
3 Days 65% $0.00 0 $0.00
1 Week 20% $0.00 0 $0.00
Subtotal $0.00
Shipping
Large Cooler (25 to 50 lbs) $150.00 0 $0.00
Small Cooler (0 to 25 lbs) $110.00 0 $0.00
Subtotal $0.00
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Drilling Related
Monitoring Well Installation Kit $325.00 Day 0 $0.00
Soil Assessment Kit $175.00 Day 0 $0.00
Soil Sampling Kit (Through Concrete) $235.00 Day 0 $0.00
Subtotal $0.00
Analytical Related
Groundwater Sampling Kit $290.00 Day 0 $0.00
Water Level Meter $25.00 Day 0 $0.00
YSI 556 MPS $105.00 Day 0 $0.00
Subtotal $0.00
IDW Related
Drum $100.00 Drum 0 $0.00
Subtotal $0.00
Expendables
$40.00 Day 0 $0.00
Subtotal $0.00
Other
$0.00 Day 0 $0.00
Subtotal $0.00
TOTAL EQUIPMENT $0.00
&"Times New Roman,Bold"LEVEL OF EFFORT/EXPENSE WORKSHEET
&D Page &P of &N &A
Subtask 6
SITE : Former Rucks Park Brownfield Site
SUBTASK:
DATE: 3/25/26
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Principal
Senior Consultant Review waste manifests and coordinate IDW disposal.
S.Melkote 0
Project Professional
Professional
Senior Staff Professional Meet waste contractor on-site during IDW drum pickup
M. Guirard
TOTAL LABOR 0
VEHICLE TYPE RATE UNIT USEAGE
Car $80.00 Day 0 $0.00
Truck $120.00 Day 0 $0.00
Van $120.00 Day 0 $0.00
Subtotal $0.00
Mileage $0.59 Mile 0 $0.00
Subtotal $0.00
Air Fare $0.00 Round Trip 0 $0.00
Subtotal $0.00
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00 Day 0 $0.00
$0.00 Day 0 $0.00
$0.00 Day 0 $0.00
$0.00 Day 0 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Equipment Procurement
$0.00 $0.00
$0.00 $0.00
Subtotal $0.00
Drilling (Conventional)
$0.00 $0.00
$0.00 $0.00
Subtotal $0.00
Drilling (Non-Conventional)
$0.00 $0.00
$0.00 $0.00
Subtotal $0.00
Mobile Laboratory
$0.00 $0.00
Subtotal $0.00
Surveying
$0.00 $0.00
Subtotal $0.00
IDW
Erwin Remediation IDW Disposal 15 drums @ $125/drum $0.00 $0.00
$0.00 $0.00
Subtotal $0.00
Utilities
$0.00 $0.00
$0.00 $0.00
Subtotal $0.00
Other
$0.00 $0.00
$0.00 $0.00
Subtotal $0.00
TOTAL SUB $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOCs $70.00 0 0 $0.00
VOHs $73.00 0 0 $0.00
VOAs $60.00 0 0 $0.00
RCRA-8 $14.00 0 0 $0.00
TOC $30.00 0 0 $0.00
TDS $16.00 0 0 $0.00
TRPH $88.00 0 0 $0.00
P…