This is a Task Assignment (TA) and associated scope of work documentation executed between the State of Florida Department of Environmental Protection (FDEP) and Geosyntec Consultants for site assessment activities at the Aurora Foundation Building in Bradenton, Florida. The task assignment was authorized under Contract Number HW683, with TA Number DC027B, and includes cost estimates, subcontractor quotes, and supporting documentation for environmental site investigation services.
The scope of work comprises five subtasks: (1) project management at 13 percent of direct labor costs; (2) multi-media soil sampling, direct push technology groundwater sampling, and monitoring well installation; (3) groundwater sampling and professional land surveying; (4) investigation-derived waste management; and (5) preparation of a site assessment report. The total contract value is $104,382.81, with 443 labor hours estimated for completion. Invoice payments are structured in three installments corresponding to deliverable milestones: $80,607.76 upon submittal and FDEP approval of field deliverables for soil sampling and well installation (due November 30, 2023); $9,473.24 upon submittal and approval of groundwater sampling deliverables and surveyor report (due December 29, 2023); and $14,301.81 upon submittal of the site assessment report and investigation-derived waste manifests (due March 29, 2024). The work includes subcontracted services from Action Environmental for drilling ($14,328.00), Speedy Concrete Cutting for concrete coring ($4,350.00), SurvTech Solutions for well surveying ($2,360.00), Erwin Remediation for waste disposal ($550.00), and various laboratory and analytical services totaling approximately $19,834.00, with the FDEP project manager confirming site access and approving the final scope and costs on June 21, 2023.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW683
DC027B Completion May 31, 2024
This Task Assignment authorizes Geosyntec to conduct Site Assessment activities at Aurora Foundation Building in accordance with the Geosyntec scope of work, cost estimate, and schedule received on June 21, 2023.
Brittany Plyler 850-245-8851 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Geosyntec
Geosyntec
Fabio Fortes 703-606-8538
ERIC_4904
1115 6th Avenue West Bradenton, Florida 34205
Aurora Foundation Building
✔ $ 104,382.81
$ 104,382.81
Scope of Work
Todd Kafka
Contract Manager
Todd Kafka, P.G. Digitally signed by Todd Kafka, P.G.
Date: 2023.06.22 18:03:34 -04'00'
Jennifer Farrell
Teresa Booeshaghi Digitally signed by Teresa Booeshaghi Date: 2023.06.22 11:11:38 -04'00'
6/22/23
N/A
Murphy_SL Highlight
Murphy_SL Highlight
Murphy_SL Highlight
Murphy_SL Highlight
Murphy_SL Highlight
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Subtask 2: Field deliverable for Soil Sampling, DPT Groundwater Profiling, and Monitoring Well Installation 11/30/2023
Subtask 3: Field deliverable for groundwater sampling, and final surveyor report 12/29/2023
Subtask 1,4,5: Submittal of Site Assessment Report and IDW Manifests; PM 03/29/2024
Subtask 2: Submittal and FDEP Approval of the Field deliverable for Soil Sampling, DPT Groundwater Profiling, and Monitoring Well Installation $ 80,607.76
Subtask 3: Submittal and FDEP approval of the Field deliverable for groundwater sampling, and final surveyor report $ 9,473.24
Subtask 1,4,5: Submittal of Site Assessment Report and IDW Manifests; PM $ 14,301.81
$ 104,382.81
HW683
DC027B
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
To: HW683 Contract Negotiation File Aurora Foundation Building Manatee County, Florida
ERIC_4904
From: Brittany Plyler, Project Manager Date: June 21, 2023 Subject: Negotiation Summary
HW683_DC027B
This Task Assignment authorizes Geosyntec to conduct Site Assessment activities at Aurora Foundation Building in accordance with the Geosyntec scope of work, cost estimate, and schedule received on June 21, 2023.
Geosyntec confirmed on June 21, 2023, that Subtask 1 consists of the calculated project management labor, based upon 13% of the direct labor costs in this proposal, and includes fringe, overhead, other direct costs (ODCs) and completion fees.
Subtask 2: This subtask includes cost site assessment activities, which include a private underground utility survey by Geotek, concrete coring up to 7 locations (SB004 through SB008, DPT005, and DPT006), one lithology boring (SB001), MAGS installation (MAGS001 – MAGS005) at locations (SB004 – SB008) as well testing will occur.
Geosyntec will also do soil sampling at up to 8 locations (SB001 – SB008) and samples will be analyzed for VOCS by synthetic precipitation leaching procedure (SPLP). Direct push technology (DPT) groundwater sampling will occur at up to 6 locations (DPT001 – DPT006).
Monitoring wells will be installed with up to 4 exterior wells with one vertical well.
Although PDS and Geoview were the lowest bidders, Action and GeoTek, the second lowest bidders, had the earliest availability.
Subtask 3: This subtask includes cost for a Florida professional land surveyor to survey the newly installed monitoring wells. Cost also include groundwater sampling from newly installed wells. The groundwater samples will be analyzed for VOCs by USEPA Method 8260 (full list), PAHs (partial list with acenaphthene, acenaphthylene, and naphthalene’s) by USEPA Method 8270-SIM, and TRPH by the FL-PRO method
Subtask 4: This subtask includes cost for IDW management. One composite liquid and one composite soil sample will be collected and analyzed for VOCs and metals using the Toxic Characteristic Leaching Procedure. Geosyntec will coordinate disposal arrangements for up to 5 drums of non-hazardous IDW. Erwin Remediation was chosen as the lowest bidder.
Printed on recycled paper.
MEMORANDUM
Aurora Foundation Building June 21, 2023 Page Two
Subtask 5: This subtask includes cost for the preparation and submittal of a Site Assessment Report (SAR) documenting assessment activities and summarizing analytical results of the assessment activities outlined above and complies with the requirements of Chapter 62-780.600, FAC.
The FDEP Project Manager confirmed site access on June 21, 2023.
The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost is $104,382.81 with 443 labor hours.
FDEP COST ESTI MATEContractor: Geosyntec Consultants
Date: 6/21/2023
Task #: Pending SubTask 1 Project Management SubTask 6
Site: SubTask 2 Multi-Media Sampling and MW Installation SubTask 7
Activity/Phase: Site Assessment SubTask 3 GW Sampling and Surveying SubTask 8
Project Manager: Fabio Fortes SubTask 4 IDW Management SubTask 9
SubTask 5 Site Assessment Report SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$40.38 Project Manager F. Fortes 49 48.8 $86.54 Principal T. Kafka 11 8 1 0 2 0 0 0 0 0 $64.90 Senior Professional S. Wang 13 8 5 0 0 0 0 0 0 0 $48.56 Project Professional M. Hensley 16 6 4 0 6 0 0 0 0 0 $40.38 Professional F. Fortes 89 38 8 3 40 0 0 0 0 0 $39.98 Professional M. Lemes 122 102 20 0 0 0 0 0 0 0 $28.85 Staff Professional O. Hollingsworth 141 139 0 2 0 0 0 0 0 0 $27.88 Administrative Assistant A. Acosta 2 0 0 0 2 0 0 0 0 0
Total Hours 443 49 301 38 5 50 0 0 0 0 0
Direct Labor $17,139.38 $1,971.79 $11,125.43 $1,727.92 $178.84 $2,135.40 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 172.70% $29,599.72 $3,405.28 $19,213.62 $2,984.12 $308.86 $3,687.84 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $46,739.10 $5,377.07 $30,339.05 $4,712.04 $487.70 $5,823.24 $0.00 $0.00 $0.00 $0.00 $0.00
Aurora Foundation Building
Cost Estimate Page 1 of 7 Cost Estimate
Task #: Pending SubTask 1 Project Management SubTask 6
Site: SubTask 2 Multi-Media Sampling and MW Installation SubTask 7
Activity/Phase: Site Assessment SubTask 3 GW Sampling and Surveying SubTask 8
Project Manager: Fabio Fortes SubTask 4 IDW Management SubTask 9
SubTask 5 Site Assessment Report SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10
Aurora Foundation Building
Travel Vehicle Rental $2,280.00 $1,920.00 $240.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $2,280.00 $1,920.00 $240.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $14,328.00 $14,328.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $2,360.00 $0.00 $2,360.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $550.00 $0.00 $0.00 $550.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Private Utility Locate $750.00 $750.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$4,350.00 $4,350.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $22,338.00 $19,428.00 $2,360.00 $550.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $2,233.80 $1,942.80 $236.00 $55.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $24,571.80 $21,370.80 $2,596.00 $605.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $18,934.00 $17,170.00 $1,084.00 $680.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $900.00 $900.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $19,834.00 $18,070.00 $1,084.00 $680.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $560.00 $440.00 $80.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $3,450.00 $3,160.00 $290.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $549.00 $549.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $1,625.00 $1,625.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $6,284.00 $5,874.00 $370.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $99,708.90 $5,377.07 $77,573.85 $9,002.04 $1,932.70 $5,823.24 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $4,673.91 $537.71 $3,033.91 $471.20 $48.77 $582.32 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $104,382.81 $5,914.78 $80,607.76 $9,473.24 $1,981.47 $6,405.56 $0.00 $0.00 $0.00 $0.00 $0.00
Cost Estimate Page 2 of 7 Cost Estimate
Task #: Pending SubTask 1 Project Management SubTask 6
Site: SubTask 2 Multi-Media Sampling and MW Installation SubTask 7
Activity/Phase: Site Assessment SubTask 3 GW Sampling and Surveying SubTask 8
Project Manager: Fabio Fortes SubTask 4 IDW Management SubTask 9
SubTask 5 Site Assessment Report SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10
Aurora Foundation Building
Cost from Prior CEF: Manual Entry Cost from Delta CEF; Manual Entry
Cost (Prior + Delta): $0.00 Auto-Calculated Rounding Error: $104,382.81 Auto-Calculated
Final Total Cost: $104,382.81 Auto-Calculated
Labor $5,914.78 $33,372.96 $5,183.24 $536.47 $6,405.56 $0.00 $51,413.01 Expenses $0.00 $47,234.80 $4,290.00 $1,445.00 $0.00 $0.00 $52,969.80 Total $5,914.78 $80,607.76 $9,473.24 $1,981.47 $6,405.56 $0.00 Check $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cost Estimate Page 3 of 7 Cost Estimate
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Aurora Foundation Building SUBTASK: Multi-Media Sampling and MW Installation
DATE: 6/21/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Principal T. Kafka
Senior Professional S. Wang 8
Project Professional M. Hensley 6
Professional F. Fortes
Professional M. Lemes
Staff Professional O. Hollingsworth
TOTAL LABOR 301
VEHICLE TYPE RATE UNIT USAGE
Truck Hollingsworth/Fortes $120.00 Day 6 $720.00 Truck (drilling oversight Hollingsworth/Lemes $480.00 Week 2 $960.00 Truck (MAGS event) Hollingsworth/Lemes $120.00 Day 2 $240.00
Subtotal $1,920.00
TOTAL VEHICLE $1,920.00
PER DIEM STAFF RATE UNIT USAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Drilling (Conventional) Action ######### $14,328.00
Subtotal $14,328.00 Other GeoTek, LLC $750.00 $750.00 Speedy Concrete Coring 3 days of coring assumed $4,350.00 $4,350.00
Subtotal $5,100.00
TOTAL SUB $19,428.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOHs - Soil 8 borings x 3 samples/boring $73.00 24 0 $1,752.00 VOHs - DPT Water 6 borings x 3 samples/boring $73.00 18 0 $1,314.00 VOHs - Water SPLP $73.00 12 0 $876.00 VOH SPLP Extraction $45.00 12 0 $540.00 TRPH/PAH Extraction $45.00 12 0 $540.00 PAH - Soil 8 borings x 3 samples/boring $110.00 24 0 $2,640.00 PAH - DPT Water 6 borings x 3 samples/boring $110.00 12 0 $1,320.00 PAH - Water SPLP $110.00 12 0 $1,320.00 TRPH - Soil 8 borings x 3 samples/boring $88.00 24 0 $2,112.00 TRPH - DPT Water 6 borings x 3 samples/boring $88.00 12 0 $1,056.00 TRPH - Speciation (Eurofins quote in Attachment A) $225.00 12 0 $2,700.00 TO-15 - Soil Gas 5 MAGS $200.00 5 0 $1,000.00
Subtotal $17,170.00 Shipping
Large Cooler (25 to 50 lbs) $150.00 6 $900.00 Subtotal $900.00
TOTAL LAB $18,070.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Drilling Related
Soil Vapor Sampling Kit $1,160.00 Week 1 $1,160.00 Soil Assessment Kit $700.00 Week 1 $700.00 MW installation kit MWs and DPT GW $1,300.00 Week 1 $1,300.00
Subtotal $3,160.00 Analytical Related
Encore Sampler $16.00 Each 24 $384.00 Air Sampling Summa Canister $33.00 Each 5 $165.00
Subtotal $549.00 IDW Related
$100.00 Drum 1 $100.00 Subtotal $100.00
Expendables $40.00 Day 11 $440.00
Subtotal $440.00
Other Water Level Meter $100.00 week 1 $100.00 Vacuum Gauges $19.00 Day 2 $38.00 Differential Pressure Gauge $18.00 Day 2 $36.00 Regenerative Blower $180.00 Day 2 $360.00 Air Flow Meter $33.00 Day 2 $66.00 Portable Generator $250.00 Day 2 $500.00 GPS $175.00 Day 3 $525.00
Subtotal $1,625.00
TOTAL EQUIPMENT $5,874.00
Evaluating and interpreting field data (2 hr). Prepare for and conduct teleconferences with FDEP, construction contractor, and property owner to discuss the scope of work (4 hr). Prepare for and conduct teleconference with FDEP to discuss soil and groundwater results (2 hr)
Analytical data import and data management (4 hr); prepare DPT GW, and soil data tables (4 hr)
Preparation of soil and DPT groundwater results figures
Property owner and tenant notification (1 hr). Prepare for and conduct teleconferences with FDEP, construction contractor, and Property owner to discuss the scope of work (4 hr). Mob/demob from Tampa (2 days x 2 hrs = 4). Day 1 concrete coring (4 hrs). Day 1 field kickoff/oversight (8 hrs). Healthy & Safety Plan preparation (2 hr). Evaluating and interpreting field data (1 hr/day x 5 days = 5 hr). Prepare draft DPT groundwater and soil figures (3 hr). Prepare field deliverable package (3 hr). Prepare for and conduct teleconference with FDEP to discuss soil, MAGS, and DPT groundwater results (3 hr). Prepare email summary of meeting minutes (1 hr)
Site Assessment: Field preparation (1 hr). Mob/demob from Tampa (2 hr/day x 5 day = 10 hr).
Calibration of instruments (0.5 hr/day x 5 days = 3 hr). Fieldwork oversight: soil and DPT GW sampling, and MW installation (10 hr x 5 days = 50 hrs). Interior as-built sketch (2 hr). Field GPS of exterior sample locations (4 hr). Prepare field forms documentation (4 hr). MAGS event: Field preparation (1 hr).
Mob/demob from Tampa (2 hr/day x 2 day = 4 hr). MAGS well installation (2 hr/well x 5 wells = 10 hr).
MAGS equipment setup (0.5 hr/well x 5 wells = 3 hrs). MAGS testing with step test (2 hr/well x 5 wells = 10 hr).
Utility Locating: Mark borings, oversee utility locate, and survey utilities including mob (8 hr). Site Assessment: Mob/demob from Tampa (2 hr/day x 8 days = 16 hr). Fieldwork oversight: concrete coring (10hrs x 3 days = 30 hrs), soil and DPT GW sampling, and MW installation (10 hr x 5 days = 50 hrs).
IDW management (1 hr). Sample management (1 hr). Compile field notes (1 hr). MAGS event:
Mob/demob from Tampa (2 hr/day x 2 day = 4 hr). MAGS supplies and picking up blower (4 hr). MAGS well installation (2 hr/well x 5 wells = 10 hr). MAGS equipment setup (0.5 hr/well x 5 wells = 3 hrs). MAGS testing with step test (2 hr/well x 5 wells = 10 hr). Sample management (1 hr).
6/21/2023 Page 4 of 7 Subtask 2
SUBTASK: GW Sampling and Surveying
DATE: 6/21/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Principal T. Kafka 1
Senior Professional S. Wang 5
Project Professional M. Hensley 4
Professional F. Fortes 8
Professional M. Lemes
TOTAL LABOR 38
VEHICLE TYPE RATE UNIT USEAGE
Truck Lemes $120.00 Day 2 $240.00 Subtotal $240.00
TOTAL VEHICLE $240.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Surveying SurvTech Solutions $2,360.00 $2,360.00
Subtotal $2,360.00
TOTAL SUB $2,360.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOHs - Water 4 MW $73.00 4 0 $292.00 TRPH - Water 4 MW $88.00 4 0 $352.00 PAH - Water 4 MW $110.00 4 0 $440.00
Subtotal $1,084.00
TOTAL LAB $1,084.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Drilling Related
Groundwater Sampling Kit $290.00 Day 1 $290.00 Subtotal $290.00
Expendables $40.00 Day 2 $80.00
Subtotal $80.00
TOTAL EQUIPMENT $370.00
Evaluating and interpreting field data
Analytical data import and data management (3 hr); prepare MW results/parameter tables (2 hr
Prepare monitoring well results figure (2 hr) and GW elevation contour map (2)
Property owner and tenant notification (1 hr). Evaluating and interpreting field data (3 hr).
Prepare field deliverable package (3 hr). Monitoring well results draft figure generation (1 hr).
GW Sampling: Mob/demob (2 hr/day x 1 day = 2 hr). instrument calibration (0.5 hr/day x 1 day = 0.5 hr). Sampling 4 monitoring wells @ 1.5hrs each (6 hr). IDW sampling and management (2.5 hr). Sample management/shipping (2 hr). Compile field notes (1 hr). MW Survey: Mob/demob from Tampa (2 hr/day x 1 day = 2 hr). Oversee monitoring well survey (4 hr).
6/21/2023 Page 5 of 7 Subtask 3
SUBTASK: IDW Management
DATE: 6/21/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Professional F. Fortes 3
Staff Professional O. Hollingsworth 2
TOTAL LABOR 5
VEHICLE TYPE RATE UNIT USEAGE
Van Hollingsworth $120.00 Day 1 $120.00 Subtotal $120.00
TOTAL VEHICLE $120.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
IDW
Erwin Remediation 5 drums x $110/drum (non-PFAS) $550.00 $550.00
Subtotal $550.00
TOTAL SUB $550.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TCLP VOCs (Soil) $210.00 1 0 $210.00 TCLP Metals (Soil) $135.00 1 0 $135.00 TCLP VOCs (Aqueous) $205.00 1 0 $205.00 TCLP Metals (Aqueous) $130.00 1 0 $130.00
Subtotal $680.00
TOTAL LAB $680.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
$40.00 Day 1 $40.00 Subtotal $40.00
TOTAL EQUIPMENT $40.00
Characterization and waste profile for transport and disposal of drums (2 hr). Prepare and sign IDW manifest (1 hr).
IDW sampling with mobilization
6/21/2023 Page 6 of 7 Subtask 4
SUBTASK: Site Assessment Report
DATE: 6/21/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Principal T. Kafka 2
Project Professional M. Hensley 6
Professional F. Fortes 40
Administrative Assistant A. Acosta 2
TOTAL LABOR 50
Report formatting and PDF compilation
Develop recommendations and path forward
SAR figure preparation, including a well survey, and cross section
SAR preparation
6/21/2023 Page 7 of 7 Subtask 5
12802 Tampa Oaks Blvd, Suite 151 Tampa, Florida 33637
PH 813.558.0990
www.geosyntec.com
21 June 2023
Ms. Brittany Plyer Florida Department of Environmental Protection 2600 Blair Stone Road, MS 4520 Tallahassee, Florida 32399-2400
Subject: Scope of Work and Level of Effort – Site Assessment Aurora Foundation Building 1115 6th Avenue West Bradenton, Florida 34205 FDEP Site ID No. ERIC_4904
Dear Ms. Plyer, Geosyntec Consultants, Inc. (Geosyntec) has prepared this Scope of Work and Level of Effort (LOE) for site assessment activities at the Aurora Foundation Building (Site) located in Bradenton, Florida (ERIC_4904). Geosyntec prepared this LOE based on Geosyntec’s 13 March 2023 Site Assessment Work Plan (SAWP), approved by FDEP. A description of task breakdown for Site assessment field activities and report preparation is provided below.
SUBCONTRACTOR EVALUATION
Geosyntec obtained three bids from licensed and qualified utility locating, concrete coring, drilling, and IDW transportation and disposal firms; a cost comparison is provided in Attachment A. Geosyntec recommends the following subcontractors based on lowest cost bid (or earliest availability) among the qualified bidders:
• Underground utility locating – GeoTek Services, LLC
• Concrete Coring - Speedy Concrete Cutting, Inc (Speedy).
• Soil sampling, DPT groundwater sampling, and MW installation – Action Environmental (Action) (5 total field days)
• IDW transportation and disposal – Erwin Remediation
• SurvTech Solutions, Inc. is recommended for surveying the four (4) monitoring wells.
Copies of the bids from each subcontractor are included in Attachment A.
Ms. Brittany Plyer 21 June 2023
For ease of reference, Table 1 and Figures from the SAWP are attached as a summary of the field activities and samples to be collected.
Subtask 1 – Project Management
Fabio Fortes (Tampa Bay) will be the Geosyntec Project Manager. His labor hours are directly computed.
Subtask 2 – Multi-Media Sampling (Soil, DPT groundwater, soil vapor) and Monitoring Well Installation
Subtask 2 includes labor for field preparation, kick off meeting with FDEP, property owner, and construction contractor (because the building is under active construction), and preparation of a Site Health and Safety Plan. Geosyntec personnel will mobilize to the Site to observe the site assessment activities, which include a private underground utility survey, concrete coring, lithology boring, soil sampling, direct push technology (DPT) groundwater sampling, and monitoring well installation.
Utility locating: Geosyntec will observe utility locating at the Site performed by GeoTek.
Identified utilities will be mapped by Geosyntec staff using a Global Position System (GPS) unit following the private underground utility survey.
Concrete Coring: Geosyntec personnel will oversee coring activities within the Site building by a concrete coring contractor. Based on observations during the SAWP site visit, it is anticipated that the foundation inside the Site building may be up to 12 to 36 inches thick. The contractor should core the concrete up to 7 locations (SB004 through SB008, DPT005, and DPT006). Speedy will complete the boring holes with concrete at the end of the sampling.
Modified Active Gas Sampling (MAGS) installations and testing: Five, 2-inch (in.) diameter Schedule 40 polyvinyl chloride (PVC) MAGS wells (MAGS001 through MAGS005) will be installed (at location SB004 through SB008) by hand auger to a depth of approximately 4 ft BLS (or 1-ft above the static water level if the depth to groundwater is different than historically observed). Each MAGS well will be installed with 1-ft of riser and 10-ft of 0.01-in. slotted well screen extending from approximately 1 to 4 ft BLS. A 20/30 grade environmental sand filter pack will be placed from the bottom of the boring to the top of the well screen. The remaining annular space will be grouted to just below the top of casing.
Each MAGS well will be tested for a period calculated to remove one, 10 to 15-ft radius of soil vapor volume using a blower. The test duration is expected to be approximately 1 hour. The vacuum and flow rates used at each MAGS well will be based on the results of a step test at one interior location. The step test will include a minimum of three steps at increasing vacuums to evaluate optimum airflow rates. Vacuum will be monitored at adjacent MAGS wells at approximate 15-minute intervals, as practical, during MAGS testing. After the completion of the study, the MAGS wells will be left in place, capped, and covered with a flush-mount manhole so that they may be converted into soil vapor extraction wells and resampled as necessary in the future.
During testing, soil vapor will be monitored with an organic vapor analyzer equipped with a photoionization detector (PID) utilizing a 10.6 electronic volt lamp. Soil vapor samples will be collected at the end of each MAGS test using a batch-certified “clean” Summa canister provided by the analytical laboratory. The soil vapor samples will be sent to a fixed-based laboratory for analysis of VOCs by the TO-15 method.
It is possible that the vadose zone available for testing may be too thin due to the concrete thickness and water table depth. Geosyntec will evaluate in the field the ability to convert soil borings advanced (SB004 through SB008) in and around the suspected former suite into MAGS wells.
Geosyntec will notify FDEP for any change in the scope of work and prepare a WCD or TACO, if necessary.
Lithology boring: One soil boring (at SB001 location) will be advanced using a DPT drill rig to a depth of approximately 50-feet below land surface (ft BLS) or refusal (limestone is expected around 30 ft BLS), whichever is encountered first, to characterize the Site-specific lithology. This data will be used to assist in the selection of soil samples and DPT groundwater sampling intervals.
Soil Sampling: Soil sampling will be performed at up to 8 locations (SB001 through SB008) as presented on Figure 3 in the FDEP-approved SAWP. Based on an assumed depth-to-water (DTW) of 5 ft BLS, a minimum of three soil samples 0-0.5 ft BLS, 0.5-2 ft BLS, and 2-4 feet below land surface [ft BLS] or water table) will be collected from each of the 8 proposed soil sample locations.
Soil samples will be collected by hand auger. A concrete core drill will be used to access soil under the building slab (concrete) and driveway/parking lot (asphalt).
The soil samples will be analyzed for VOCs by USEPA Method 8260 (full list), PAHs (partial list with acenaphthene, acenaphthalene, and naphthalenes) by USEPA Method 8270-SIM, and TRPH by the FL-PRO method by a state of Florida certified, National Environmental Laboratory Accreditation Program (NELAP) accredited fixed-based laboratory. Soil samples will be screened with a photoionization detector (PID) organic vapor analyzer. Supplemental soil samples will be collected from each location and depth interval (via Encore samplers) for analysis of VOCs by the synthetic precipitation leaching procedure (SPLP) should VOC concentrations exceed the leachability-based soil cleanup target levels (SCTLs). PAH analysis by SPLP and TRPH speciation are also proposed for the soil analyses exceeding the applicable SCTLs. For budgetary purposes, it is assumed that approximately half of the proposed soil samples will be analyzed by
SPLP for VOCs and PAHs, and TRPH speciation (Eurofins quote for TRPH speciation is presented in Attachment A). Exterior soil samples will be surveyed with a GPS and interior sampling locations will be transcribed using as-builts based on Site features.
DPT groundwater sampling: Geosyntec personnel will observe the collection of DPT groundwater samples at up to 6 locations (DPT001 through DPT006) as shown on Figure 3 of the SAWP.
Groundwater samples will be collected at 4-ft intervals approximately every 10 feet (i.e., 5 to 9 ft BLS, 15 to 19 ft BLS, and 25 to 29 ft BLS assuming refusal at limestone is encountered at 30 ft BLS), resulting in 3 samples x 6 locations (18 samples). Sampling intervals may be adjusted based on observed depth to water and Site lithology. Groundwater samples submitted to a NELAP-approved fixed-based laboratory will be analyzed for the presence of VOCs by USEPA Method 8260 (full list), PAHs (partial list with acenaphthene, acenaphthalene, and naphthalenes) by USEPA Method 8270-SIM, and TRPH by the FL-PRO method. No field duplicates will be collected.
Monitoring well installations: In the same mobilization, Geosyntec personnel will observe the installation of up to 4 exterior monitoring wells to evaluate groundwater quality; the proposed locations are presented on Figure 3 of the SAWP. We have assumed the existing utility survey will be sufficient for siting the proposed monitoring well locations; however, should the spray paint be worn away or if there is any uncertainty in utility locations relative to drilling locations, Geosyntec will submit a WCD or TACO to FDEP for a focused utility locating at the drilling locations.
Water-table monitoring wells MW001 through MW003 will be installed via DPT drilling. The wells will be constructed of 1-in. diameter Schedule 40 PVC pipe with 10 ft of 0.010-in. slotted well screen, filter pack consisting of 20/30 silica sand, and at least a 0.5-ft thick, fine sand (30/65 silica sand) seal. The remaining annular space will be grouted to land surface with Portland Cement Type I/II and monitoring wells will be completed at the surface with a flush-mount 8-in. manhole with a locking monitoring well cap.
Geosyntec will install one vertical extent monitoring well (MW004) to a depth of 30 feet, if DPT groundwater sampling results warrant vertical delineation. The well will also be constructed with a 5-ft screen depending upon the lithologic information from SB001.
The monitoring wells will be developed until the discharge is relatively sediment-free and sampled no sooner than 24 hours after development.
Field GPS and Interior Mapping: Exterior sampling locations (DPT groundwater and soil boring) will be surveyed throughout the week with a field GPS by Geosyntec personnel. Interior sampling locations will be transcribed using as-builts based on Site features.
Subtask 2 activities will be performed by Geosyntec staff members assuming 1 day for utility locating and marking the boring locations (1 Geosyntec staff), 3 days for concrete coring (1 Geosyntec staff), 2 days for MAGS well installation and testing (2 Geosyntec staffs), and 5 days for drilling oversight and close out tasks at the Site (2 Geosyntec staffs). We have assumed 10-hours per day.
Subtask 3 – Groundwater Sampling and Surveying
Monitoring Well Survey: This subtask includes costs for a Florida professional land surveyor to survey the four (4) newly installed monitoring wells. Cost has been included for Geosyntec to oversee the survey.
Groundwater sampling: Geosyntec personnel will collect groundwater samples from the four (4) Site monitoring wells. Depth to water measurements (DTW) will be collected from the monitoring wells to evaluate groundwater flow direction. The monitoring wells will be sampled using a peristaltic pump in general accordance with FDEP Standard Operating Procedures (SOPs), assuming the DTW and drawdown do not exceed the suction limit of the peristaltic pump. The samples will be stored on ice and shipped to a NELAP approved, fixed-based analytical laboratory under chain of custody for analysis under standard turnaround times. The groundwater samples will be analyzed for VOCs by USEPA Method 8260 (full list), PAHs (partial list with acenaphthene, acenaphthalene, and naphthalenes) by USEPA Method 8270-SIM, and TRPH by the FL-PRO method.
Field Deliverable and Draft Summary Figure: Geosyntec has included costs to generate the following to facilitate the discussion with FDEP:
• One figure and table to summarize laboratory analytical results from the DPT groundwater samples;
• One figure and table to summarize laboratory analytical results from soil samples; and
• One figure and table to summarize laboratory analytical results from the groundwater monitoring well samples.
These data will be provided to FDEP for evaluation. The deliverable will include the final surveyor report, field forms for soil and groundwater assessment, and groundwater sampling forms. If fixed-based laboratory analytical results of soil and groundwater samples indicate that additional sampling will be required to complete delineation, Geosyntec will propose additional sampling locations and corresponding depths.
Subtask 3 activities will be performed by 1 Geosyntec staff member assuming 1 day for monitoring well survey oversight, and 1 day for monitoring well sampling, IDW sampling, and close out tasks at the Site. We have assumed 10-hour per day.
Subtask 4 – IDW Management
IDW Sampling: The IDW will be sampled prior to profiling. One composite liquid and one composite soil sample will be collected and analyzed for VOCs and metals using the Toxic Characteristic Leaching Procedure. Geosyntec will review the generation of a waste characterization profile as well as the preparation of IDW manifests. Geosyntec will coordinate disposal arrangements for up to 5 drums of non-hazardous IDW. Analytical costs are included to establish the soil and groundwater profiles required by the selected waste hauler. We have assumed field oversight of the drum pickup is not necessary.
For this cost estimation, we assumed the IDW will not be impacted by (screening to be performed under HW028A) and Geosyntec will submit a WCD or TACO to FDEP for any change of scope.
Subtask 5 – Site Assessment Report
Following completion of field activities, Geosyntec will proceed with the preparation and submittal of a Site Assessment Report (SAR) documenting assessment activities and summarizing analytical results. This subtask includes costs to generate a SAR that summarizes the analytical results of the assessment activities outlined above and complies with the requirements of Chapter 62-780.600, FAC. The costing included in the CEF/LOE includes the following figures:
• USGS Site Topographic Map
• Potable Well Survey
• Site Layout
• Site Utility Map
• Lithologic Cross Section (1 transect)
• Summary of Soil Analytical Results from 0-0.5, 0.5-2, and 2-4 ft BLS (3 figures)
• Summary of DPT Groundwater Sampling Analytical Results
• Summary of Groundwater Elevations
• Summary of Monitoring Well Analytical Results
Deliverable and Invoicing Schedule:
Subtask Deliverable Deliverable Due Date*
Invoice Amount
Field deliverable for Soil Sampling, DPT Groundwater Profiling, and Monitoring
Well Installation 11/10/23 $80,607.76
3 Field deliverable for groundwater sampling, and final surveyor report 12/15/23 $9,473.24
1, 4, 5 Submittal of Site Assessment Report and IDW Manifests 3/15/24 $14,301.81
Total $104,382.81 *Assumes TA is approved by 14 July 2023.
Geosyntec appreciates the opportunity to provide this proposal and cost estimate to you and the FDEP. Please contact us if you have any questions or require additional information.
Sincerely, Fabio Fortes, P.E.
Professional Engineer
Todd K. Kafka, P.G.
Sr. Principal Hydrogeologist
Figures and Table 1 Attachment A – Subcontractor Cost Evaluation and Quotes
FIGURES AND TABLE 1
6th Ave. W.
th S t.
W th S t.
W
Former Drycleaning
Facility
Former Laundry Facility
Unknown Historical Use
TMW-2
SB4
SB1
SB3
SB2
SB6
SB5
SB008 (tentative)
SB007 (tentative)
SB006 (tentative)
DPT006
(tentative)
DPT005
(tentative)
MW003
MW002
MW001
MW004
SB003
SB002
SB004 (tentative)
SB005 (tentative)
DPT004DPT003
DPT002
DPT001
SB001 (Lithology Boring)
Path: prj1(\\Tampa-01) J:\_GIS\A\Aurora Foundation Bldg\MXDs\Proposed_Site_Investigation.mxd 13 March 2023. Last Edited by: Fabio.Fortes
Aurora Foundation Building 1115 6th Avenue West
Bradenton, Florida
Proposed Site Investgation
0 20
Feet
³ Figure
Tampa, FL March 2023
Notes:
1. Approximate parcel boundary was obtained from Manatee
County Property Appaiser https://www.manateepao.gov/.
2. Aerial Photo Source: Nearmap website, November 11, 2022
3. Historical Building Layout Source: Sanborn Fire Insurance Map,1929.
4. Historical Temporary Well Location from Site Screening Report Form, March 1996.
5. Soil Boring Locations SB1 to SB6 were advanced by
Environmental Safety Consultants, Inc. (ESC) in June 2022.
Soil analytical results are presented in Appendix D.
6. Tentative soil sampling and DPT boring inside the building contingent upon the thickness of concrete from footers and slabs
Legend
!. Proposed Direct Push Technology (DPT) Groundwater Location
&< Proposed Shallow Monitoring Well Location
&< Proposed Deep Monitoring Well Location
!( Proposed Soil Boring Location
"/ Approximated Soil Boring Location from ESC - June 2022
&< Historical Temporary Monitoring Well Location
Property Boundary
Alley
Current Oil Water Separator Tank / Grease Trap
Historical Building Layout (See note 3)
Manatee County Parcels
Sewer Line
Underground Power Line
TABLE 1: SAMPLING LOCATIONS, MATRICES, ANALYTES, RATIONALE, AND CRITERIA
Aurora Foundation Building (ERIC_4904)
Location ID Sample ID Matrix Approximate Depth (ft BLS)*
Sampling Method Rationale Criteria Status
SB001 (0.5') 0.5
SB001 (2') 2
SB001 (4') 4
SB002 (0.5') 0.5
SB002 (2') 2
SB002 (4') 4
SB003 (0.5') 0.5
SB003 (2') 2
SB003 (4') 4
SB004 (0.5') 0.5
SB004 (2') 2
SB004 (4') 4
SB005 (0.5') 0.5
SB005 (2') 2
SB005 (4') 4
SB006 (0.5') 0.5
SB006 (2') 2
SB006 (4') 4
SB007 (0.5') 0.5
SB007 (2') 2
SB007 (4') 4
SB008 (0.5') 0.5
SB008 (2') 2
SB008 (4') 4
DPT001 (5-9) 5-9
DPT001 (15-19) 15-19
DPT001 (25-29) 25-26
DPT002 (5-9) 5-9
DPT002 (15-19) 15-19
DPT002 (25-29) 25-26
DPT003 (5-9) 5-9
DPT003 (15-19) 15-19
DPT001 (25-29) 25-26
DPT001 (5-9) 5-9
DPT001 (15-19) 15-19
DPT001 (25-29) 25-26
DPT001 (5-9) 5-9
DPT001 (15-19) 15-19
DPT001 (25-29) 25-26
DPT001 (5-9) 5-9
DPT001 (15-19) 15-19
DPT001 (25-29) 25-26
MW001 MW001 5-15 Southwest of the former drycleaning facility
MW002 MW002 5-15 Southwest/South of the former drycleaning facility
MW003 MW003 5-15 Southeast of the former drycleaning facility
MW004 MW004 25-30 Southwest of the former drycleaning facility
Drum Number Sample ID Matrix IDW Source Rationale Criteria
Composite IDW-1 Soil Waste Characterization NA Composite IDW-2 Water Waste Characterization NA
Notes:
1. ft BLS indicates feet below land surface. 7. GCTL indicates groundwater cleanup target levels.
2. SB indicates soil boring 8. MW indicates monitoring well.
3. HA indicates hand auger. 9. IDW indicates investigation derived waste.
4. VOCs indicates volatile organic carbons. 10. NA indicates not applicable.
5. L-SCTLs indicates leachability-based soil cleanup ta 11. ND indicates not determined.
6. DPT indicates direct-push technology.
DPT004 South of the building at the parking lot
DPT006 Northeast of the building a near the former drycleaning facility (tentative)
VOC SCTLs USEPA Method 8260 (full list) / PAHs USEPA Method 8270 / TRPH FL-PRO
(Hold SPLP)
VOC SCTLs USEPA Method 8260 (full list) / PAHs USEPA Method 8270 / TRPH FL-PRO
(Hold SPLP)
VOC GCTLs USEPA Method 8260 (full list) / PAHs USEPA Method 8270 / TRPH FL-
PRO
VOC GCTLs USEPA Method 8260 (full list) / PAHs USEPA Method 8270 / TRPH FL-
PRO
DPT / Grab
VOC SCTLs USEPA Method 8260 (full list) / PAHs USEPA Method 8270 / TRPH FL-PRO
(Hold SPLP)
VOC SCTLs USEPA Method 8260 (full list) / PAHs USEPA Method 8270 / TRPH FL-PRO
(Hold SPLP)
Drilling, decon, purge water
IDW Source
Soil Cuttings
SB006 Northeast of the building a near the former drycleaning facility (tentative)
SB008 Northeast of the building a near the former Laundry facility (tentative)
DPT003 South of the building at the parking lot
Soil HA
SB007 Northeast of the building a near the former drycleaning facility (tentative)
Soil Sampling (8 Locations, 24 Samples)
Monitoring Wells (4 samples)
Investigation Derived Waste Sample
SB002
SB001
SB003
SB004
SB005
VOC GCTLs USEPA Method 8260 (full list) / PAHs USEPA Method 8270 / TRPH FL-
PRO/ PFAS Provisional GCTLs
South of the building at the parking lot / Lithology Soil Boring
South of the building at the parking lot
South of the building at the parking lot
East of the building at Alley area - near the former drycleaning facility
(tentative)
Northeast of the building a near the former drycleaning facility (tentative)
DPT005 Northeast of the building a near the former drycleaning facility (tentative)
VOC SCTLs USEPA Method 8260 (full list) / PAHs USEPA Method 8270 / TRPH FL-PRO
(Hold SPLP)
VOC SCTLs USEPA Method 8260 (full list) / PAHs USEPA Method 8270 / TRPH FL-PRO
(Hold SPLP)
VOC SCTLs USEPA Method 8260 (full list) / PAHs USEPA Method 8270 / TRPH FL-PRO
(Hold SPLP)
VOC GCTLs USEPA Method 8260 (full list) / PAHs USEPA Method 8270 / TRPH FL-
PRO
Groundwater Peristaltic Pump
DPT Sampling (6 Locations, 18 Samples)
DPT001 Southwest of the building at the parking lot
VOC GCTLs USEPA Method 8260 (full list) / PAHs USEPA Method 8270 / TRPH FL-
PRO
DPT002 Southwest of the building at the parking lot
VOC GCTLs USEPA Method 8260 (full list) / PAHs USEPA Method 8270 / TRPH FL-
PRO
VOC SCTLs USEPA Method 8260 (full list) / PAHs USEPA Method 8270 / TRPH FL-PRO
(Hold SPLP)
VOC GCTLs USEPA Method 8260 (full list) / PAHs USEPA Method 8270 / TRPH FL-
PRO
Groundwater
ATTACHMENT A
SUBCONTRACTOR COST
EVALUATION AND QUOTES
Quantity Unit Rate Quantity Unit Rate Quantity Unit Rate Daily Rate 4 Days 2100 5 Days 1800 mobilization 1 Lump Sum 675 1 Lump Sum 2650 materials/footage 1 Lump Sum 1130 1 Lump Sum 2110
Permits 1 Each 170 Each Miscellaneous 1 Lump Sum 1250 1 Lump Sum 300
Drum 9 Drums 125 4 Drums 67
Quantity Unit Rate Quantity Unit Rate Quantity Unit Rate 1 Mobilization 1000 3 Mobilization/day 1450
16 up to 12" deep (per hour) 250 14 deeper than 12" (per extra foot) 150
Quantity Unit Rate Quantity Unit Rate Quantity Unit Rate 1 Lump Sum 1300 1 Lump Sum 750 1 Lump Sum 2050
3 Liquid IDW Cost 110 3 Liquid IDW Cost 860 3 Liquid IDW Cost 141.75 6 Solid IDW Cost 110 6 Solid IDW Cost 660 6 Solid IDW Cost 210
1 Lump Sum 2360
Note: The selected subcontractor is highlighted in Blue.
No submmited
$2,360.00
SURVEYING (Professional Service)
UNDERGROUND UTILITY LOCATE
GPRSGeoView GeoTek
$990.00 $6,540.00 $1,685.25
$1,300.00 $750.00 $2,050.00
IDW DISPOSAL (Only Chlorinated Solvents) Erwin
$7,100.00
$12,750.00 $14,328.00 N/A
ActionSpeedyReliable CONCRETE CORING (2 days of service)
Not Submited
Subcontractor Evaluation: Aurora Foundation Building, Bradenton, Florida
DRILLING COMPANIES TOTAL
PDS Action (best schedule) GW Protection
$4,350.00
Hulls Hepaco
N/A
From: Jesse Hornsby To: Fabio Fortes Subject: RE: Question Date: Thursday, June 15, 2023 12:39:10 PM Attachments: image002.png
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe. If you have any suspicion, please confirm with the sender verbally that this email is authentic. If you suspect fraud, click "Phish Alert Report."
OK.
VOCs -- $66 PAHs -- $99
TRPH -- $79
SPLP prep for non-volatiles - $40 SPLP prep for volatiles -- $50
You’ll need a quote form for the EnCore samplers ($10) and TRPH Speciation ($225); they aren’t on the contract.
Jess Hornsby Client Services Manager Eurofins Environment Testing Southeast
Direct: 321-280-2054
E-mail: jess.hornsby@et.eurofinsus.com www.EurofinsUS.com
From: Fabio Fortes <Fabio.Fortes@Geosyntec.com> Sent: Thursday, June 15, 2023 12:34 PM To: Jesse Hornsby <Jess.Hornsby@et.eurofinsus.com> Subject: RE: Question
EXTERNAL EMAIL*
Drycleaning
Fabio Fortes, P.E. (FL) mailto:Jess.Hornsby@et.eurofinsus.com mailto:Fabio.Fortes@Geosyntec.com https://nam02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.eurofinsus.com%2Fenvironment-testing%2Fresources%2Fholiday-hours%2F&data=05%7C01%7CFabio.Fortes%40Geosyntec.com%7C5996dcf7cd0f4330c5d508db6dbf0768%7C7125495671b047f48977c4c17bc205cb%7C0%7C0%7C638224439493480696%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=3jtaiOptJnHGB1sik8%2B6ijxqrvZ4g9S5uH%2FwkYJjbBU%3D&reserved=0 mailto:jess.hornsby@et.eurofinsus.com https://nam02.safelinks.protection.outlook.com/?url=http%3A%2F%2Fwww.eurofinsus.com%2F&data=05%7C01%7CFabio.Fortes%40Geosyntec.com%7C5996dcf7cd0f4330c5d508db6dbf0768%7C7125495671b047f48977c4c17bc205cb%7C0%7C0%7C638224439493480696%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=W%2FJqSEbC5SeTSwu%2B6LXfMywcTZCa33JUq0dBDXMfKuc%3D&reserved=0
Fabio.Fortes Oval
Concrete Coring Quotes
Fabio Fortes
From: Matt Ferguson <matt.ferguson@speedycon.com>
Sent: Wednesday, June 21, 2023 10:32 AM
To: Fabio Fortes
Subject: Re: Request for Quote (Speedy) - Concrete Coring in Bradenton,, FL
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe. If you have any suspicion, please confirm with the sender verbally that this email is authentic. If you suspect fraud, click "Phish Alert Report."
Fabio, I already quoted 2 days @ 1450.00 add one more day.
Total 4350.00
Joe Kenney
District Manager, Speedy Concrete Cutting
Cell: 813.453.8637 joe.kenney@speedycon.com www.speedycon.com
Date: Wednesday, June 21, 2023 at 8:28 AM
To: Matt Ferguson <matt.ferguson@speedycon.com>
Subject: RE: Request for Quote (Speedy) - Concrete Coring in Bradenton,, FL
Hi Matt, we only need the service inside the building (up to 7 locations) and let’s think in the worst scenario (3 ft of concrete). Can you send me the cost to fill the concrete back after the concrete coring work?
Thank you, Professional Engineer
Tampa, FL 33637 Mobile: 703-606-8538 Direct: 813-379-4421
This electronic mail message contains information that (a) is or may be LEGALLY PRIVILEGED, CONFIDENTIAL, PROPRIETARY IN NATURE, OR
OTHERWISE PROTECTED BY LAW FROM DISCLOSURE, and (b) is intended only for the use of the Addressee(s) named herein. If you are not the intended recipient, an addressee, or the person responsible for delivering this to an addressee, you are hereby notified that reading, using, copying, or distributing any part of this message is strictly prohibited. If you have received this electronic mail message in error, please contact us immediately and take the steps necessary to delete the message completely from your computer system.
From: Matt Ferguson <matt.ferguson@speedycon.com>
Sent: Wednesday, June 21, 2023 8:08 AM
To: Fabio Fortes <Fabio.Fortes@Geosyntec.com>
Subject: Re: Request for Quote (Speedy) - Concrete Coring in Bradenton,, FL
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe. If you have any suspicion, please confirm with the sender verbally that this email is authentic. If
I will need to know how deep you are going total and what type of material can go back in each hole. Do you want me to only fill in the holes drilled through the concrete?
I believe you had asphalt also.
Cell: 813.453.8637
Date: Tuesday, June 20, 2023 at 4:09 PM
Hi Matt, can you send me the cost to fill the concrete holes (up to 7 locations)?
Tampa, FL 33637 Mobile: 703-606-8538 Direct: 813-379-4421
This electronic mail message contains information that (a) is or may be LEGALLY PRIVILEGED, CONFIDENTIAL, PROPRIETARY IN NATURE, OR
OTHERWISE PROTECTED BY LAW FROM DISCLOSURE, and (b) is intended only for the use of the Addressee(s) named herein. If you are not the intended recipient, an addressee, or the person responsible for delivering this to an addressee, you are hereby notified that reading, using, copying, or distributing any part of this message is strictly prohibited. If you have received this electronic mail message in error, please contact us immediately and
Sent: Wednesday, June 14, 2023 10:56 AM
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe. If you have any suspicion, please confirm with the sender verbally that this email is authentic. If
The cost for each mob is 1450.00. I believe we can complete the coring in 2 days. 2 mobs
Cell: 813.453.8637
Date: Tuesday, June 13, 2023 at 5:36 PM
Hi Matt, $1,450.00 is the cost for 2 days of concrete coring? Or only the cost for mobilization?
Mobile: 703-606-8538 Direct: 813-379-4421
This electronic mail message contains information that (a) is or may be LEGALLY PRIVILEGED, CONFIDENTIAL, PROPRIETARY IN NATURE, OR OTHERWISE PROTECTED BY LAW FROM DISCLOSURE, and (b) is intended only for the use of the Addressee(s) named herein. If you are not the intended recipient, an addressee, or the person responsible for delivering this to an addressee, you are hereby notified that reading, using, copying, or distributing any part of this message is strictly prohibited. If you have received this electronic mail message in error, please contact us immediately and
Sent: Tuesday, June 13, 2023 5:33 PM
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe. If you have any suspicion, please confirm with the sender verbally that this email is authentic. If
Our minimum mob Bradenton is 1450.00. I don’t think it would take more than 2 days total.
Cell: 813.453.8637
Date: Tuesday, June 13, 2023 at 12:53 PM
To: "matt.ferguson@speedycon.com" <matt.ferguson@speedycon.com>
Subject: FW: Request for Quote (Speedy) - Concrete Coring in Bradenton,, FL
Hi Matt, Let me know if you can send the quote for this service described below.
Mobile: 703-606-8538 Direct: 813-379-4421
This electronic mail message contains information that (a) is or may be LEGALLY PRIVILEGED, CONFIDENTIAL, PROPRIETARY IN NATURE, OR
OTHERWISE PROTECTED BY LAW FROM DISCLOSURE, and (b) is intended only for the use of the Addressee(s) named herein.