This is a Task Assignment (TA) document executed between the State of Florida Department of Environmental Protection (FDEP) and Geosyntec Consultants, Inc., for annual groundwater monitoring services at the Former Contemporary Cleaners site in Orlando, Florida (FDEP Facility ID ERIC_4970). The Task Assignment Number is DC012A, issued under Contract Number HW683, with a completion date of October 7, 2022. The FDEP Project Manager is Evan Miller (850-245-8928), and Geosyntec's Project Manager is Olivia Cain (727-330-9961).
Geosyntec will conduct annual groundwater monitoring work through three subtasks: Project Management, Groundwater Sampling, and Groundwater Monitoring Report preparation. The work includes collecting groundwater levels from 35 monitoring wells across three aquifer intervals, sampling 21 designated monitoring wells for volatile organic halogens analysis, and preparing a comprehensive report with updated groundwater elevation contour maps and treatment interval comparisons. The total contract value is $15,115.22 on a fixed unit rate basis, comprising 104 labor hours and associated field expenses, laboratory analytical costs, equipment rental, and non-hazardous waste disposal. A single deliverable—the Annual Groundwater Monitoring Report, ADaPT/GIS uploads, and IDW manifests—is due August 5, 2022, with full payment invoiced upon FDEP receipt and approval. Erwin Remediation was selected as the lowest-cost subcontractor for non-hazardous liquid waste transportation and disposal at $100.00 per drum.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW683
DC012A Completion October 7, 2022
This Task Assignment authorizes Geosyntec to conduct annual groundwater monitoring in accordance with the Geosyntec scope of work, cost estimate, and schedule received on 15 April 2022.
Evan Miller 850-245-8928 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Geosyntec
Geosyntec
Olivia Cain 727-330-9961
ERIC_4970
4882 South Kirkman Road Orlando, Florida 32811
Former Contemporary Cleaners
✔ $ 15,115.22
$ 15,115.22
Scope of Work
Todd Kafka
Contract Manager
Todd Kafka, P.G. Digitally signed by Todd Kafka, P.G.
Date: 2022.04.25 08:43:59 -04'00'
William E. Burns, Jr.
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2022.04.15 13:21:44 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Subtask 1,2,3- Submittal of Annual Groundwater Monitoring Report, ADaPT/GIS upload, IDW Manifests; Project Management 08/05/2022
Subtask 1,2,3- FDEP receipt and approval of Annual Groundwater Monitoring Report, ADaPT/GIS upload, IDW Manifests; Project Management $ 15,115.22
$ 15,115.22
HW683
DC012A
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
To: HW683 Contract Negotiation File Former Contemporary Cleaners Orlando, Orange County
ERIC_4970
From: Evan Miller, Project Manager Date: April 15, 2022 Subject: Negotiation Summary
HW683 DC012A
This Task Assignment authorizes Geosyntec to conduct annual groundwater monitoring.
Subtask 1: Project Management An automatic calculation based upon total direct labor hours determines the labor hours within this subtask.
Subtask 2 – Groundwater Sampling Groundwater levels will be collected from the site-wide monitoring well network consisting of 35 monitoring wells. Measurements will be collected over a 24-hour period to generate groundwater elevation contour maps to evaluate groundwater flow directions in the upper surficial (screened less than 30 ft BLS), lower surficial (screened between 47 to 55 ft BLS), and intermediate aquifers (screened between 63 to 75 ft BLS). While MW018 was not located in May 2021 due to overgrown vegetation, Geosyntec personnel will attempt to locate the monitoring well for inspection. Purge water generated during sampling activities will be containerized in one 55-gallon drum. A composite sample will be collected from the drum to characterize the groundwater IDW for VOHs by EPA Method 8260B to confirm non-hazardous disposal of the purge water.
Subtask 3 – Groundwater Monitoring Report Geosyntec will prepare a Groundwater Monitoring Report documenting the results of the depth to groundwater measurements and annual groundwater monitoring event. The report will contain tables summarizing field/laboratory groundwater data, figures showing groundwater flow direction(s), and a summary of the groundwater monitoring event. Geosyntec will also compare the treatment intervals proposed in the January 2022 RAP Modification – Revision 2 to the groundwater results to confirm the bioremediation design.
The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost for this Task Assignment is $15,115.22 with 104 labor hours.
Geosyntec may invoice following the schedule established in the Deliverables and Invoice Schedule Attachment, which accompanies the Task Assignment Notification Form.
Printed on recycled paper.
FDEP COST ESTIMATEContractor: Geosyntec Consultants
Date: 4/15/2022
Task #: SubTask 1 Project Management SubTask 6
Site: SubTask 2 Groundwater Sampling SubTask 7
Activity/Phase: Monitoring SubTask 3 Groundwater Monitoring Report SubTask 8
Project Manager: O. Cain SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$39.90 Project Manager O. Cain 11 10.6 $68.75 Principal T. Kafka 0 0 0 0 0 0 0 0 0 0 $72.60 Principal K. Warner 4 0 4 0 0 0 0 0 0 0 $46.15 Project Professional M. Hensley 7 0 7 0 0 0 0 0 0 0 $39.90 Professional O. Cain 21 2 19 0 0 0 0 0 0 0 $32.21 Senior Staff Professional A. Langteau 9 0 9 0 0 0 0 0 0 0 $29.33 Staff Professional A. Lamore 27 27 0 0 0 0 0 0 0 0 $29.25 Senior Engineering Technician R. Mathias 25 25 0 0 0 0 0 0 0 0
Total Hours 104 11 54 39 0 0 0 0 0 0 0
Direct Labor $3,688.77 $424.37 $1,602.96 $1,661.44 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 172.70% $6,370.51 $732.89 $2,768.31 $2,869.31 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $10,059.28 $1,157.26 $4,371.27 $4,530.75 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $480.00 $480.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $404.00 $404.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $884.00 $884.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $10.00 $10.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $1,606.00 $1,606.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $1,716.00 $1,716.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $80.00 $80.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $1,160.00 $1,160.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $1,340.00 $1,340.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $14,109.28 $1,157.26 $8,421.27 $4,530.75 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $1,005.94 $115.73 $437.13 $453.08 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $15,115.22 $1,272.99 $8,858.40 $4,983.83 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Former Contemporary Cleaners
Cost Estimate Page 1 of 1 Cost Estimate
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Former Contemporary Cleaners SUBTASK: Groundwater Sampling
DATE: 4/15/2022
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Professional O. Cain 2
Staff Professional A. Lamore 27
Senior Engineering Technician R. Mathias 25
TOTAL LABOR 54
VEHICLE TYPE RATE UNIT USEAGE
Car $80.00 Day 0 $0.00 Truck Mathias $120.00 Day 2 $240.00 Van Lamore $120.00 Day 2 $240.00
Subtotal $480.00
TOTAL VEHICLE $480.00
PER DIEM STAFF RATE UNIT USEAGE
Mathias M&I $36.00 Day 2 $72.00 Lamore M&I $36.00 Day 2 $72.00 Mathias Hotel in Orlando $130.00 Day 1 $130.00 Lamore Hotel in Orlando $130.00 Day 1 $130.00
TOTAL PER DIEM $404.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
IDW
Erwin Remediaiton Non-hazardous liquid IDW (1 drum x $100/drum) $100.00 $100.00
Subtotal $100.00
TOTAL SUB $100.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOCs $70.00 0 0 $0.00 VOHs $73.00 22 0 $1,606.00 VOAs $60.00 0 0 $0.00
Subtotal $1,606.00 Shipping
Large Cooler (25 to 50 lbs) $150.00 0 $0.00 Small Cooler (0 to 25 lbs) $110.00 1 $110.00
Subtotal $110.00
TOTAL LAB $1,716.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Analytical Related
Groundwater Sampling Kit $290.00 Day 4 $1,160.00 Water Level Meter $25.00 Day 0 $0.00 YSI 556 MPS $105.00 Day 0 $0.00
Subtotal $1,160.00 IDW Related
Drum $100.00 Drum 1 $100.00 Subtotal $100.00
Expendables $40.00 Day 2 $80.00
Subtotal $80.00
TOTAL EQUIPMENT $1,340.00
Field preparation (1 hr). Round trip mob/demob from Tampa (4 hr). Collect depth to water measurements (2 hr). Calibrate sampling equipment (0.5 hr/day x 2 days = 1 hr).
Groundwater sampling (1.5 hr/well x 11 wells = 17 hr).
Field scope planning with team and EHS docs
Field preparation (1 hr). Round trip mob/demob from Tampa (4 hr). Collect depth to water measurements (2 hr). Calibrate equipment (0.5 hr/day x 2 days = 1 hr). Groundwater sampling (1.5 hr/well x 10 wells = 15 hr). Sampling management (2 hr). IDW management (1 hr). Compile and organize field notes (1 hr).
4/15/2022 Page 1 of 2 Subtask 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Former Contemporary Cleaners SUBTASK: Groundwater Monitoring Report
DATE: 4/15/2022
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Principal K. Warner 4
Project Professional M. Hensley 7
Professional O. Cain 19
Senior Staff Professional A. Langteau 9
TOTAL LABOR 39
Evaluation of remedial design and path forward, evaluate design parameters with FDEP, and PE sign/seal.
Groundwater contour figures (3 intervals), groundwater results figures (3 intervals), cross section with plumes (1 section)
Preparation of summary report, including drafting tables and figures and evaluating remedial design (18 hr). Evaluate design parameters with FDEP (1 hr).
ADaPT/GIS update (29 water levels + 21 samples + 3 duplicates = 53 data points x 8 min/point = 7 hr). GIS checker and submittal (2 hr).
4/15/2022 Page 2 of 2 Subtask 3
12802 Tampa Oaks Blvd., Suite 151 Tampa, Florida 33637
PH 813.558.0990
FAX 813.558.9726
www.geosyntec.com
Contemporary Cleaners (ERIC_4970)_HW683 SOW_Annual GW Monitoring_2022-04_Rev1
15 April 2022
Mr. Evan Miller Florida Department of Environmental Protection 2600 Blair Stone Road, MS 4520 Tallahassee, FL 32399-2400
Subject: Scope of Work and CEF/LOE – Annual Groundwater Monitoring Former Contemporary Cleaners 4882 South Kirkman Road Orlando, Florida 32811 FDEP Facility ID No. ERIC_4970
Dear Mr. Miller:
Geosyntec has prepared the following scope of work (SOW), Cost Estimating Form (CEF), and Level of Effort (LOE) for annual groundwater monitoring at the Former Contemporary Cleaners (Site) located in Orlando, Florida. This scope will include groundwater assessment activities to satisfy the 270-day groundwater data requirement (as outlined in Chapter 62-780, Florida Administrative Code) for the Florida Department of Environmental Projection’s (FDEP’s) approval of the Remedial Action Plan Modification – Revision 2 submitted on 28 January 2022.
A copy of the CEF and LOE is provided as Attachment A.
Subtask 1 – Project Management
Subtask 2 – Groundwater Sampling
This subtask includes costs associated with monitoring well sampling activities. Groundwater levels will be collected from the site-wide monitoring well network consisting of 35 monitoring wells. Measurements will be collected over a 24-hour period to generate groundwater elevation contour maps to evaluate groundwater flow directions in the upper surficial (screened less than 30 ft BLS), lower surficial (screened between 47 to 55 ft BLS), and intermediate aquifers (screened between 63 to 75 ft BLS). A depth to groundwater measurement was unable to be collected from MW024 by Geosyntec staff in February 2020 or May 2021 (date of the previous two monitoring events), so this well has been removed from the proposed depth-to-water measurement list. While MW018 was not located in May 2021 due to overgrown vegetation, Geosyntec personnel will attempt to locate the monitoring well for inspection.
Groundwater levels will be collected from the monitoring wells listed on the next page.
Mr. Evan Miller 15 April 2022
Contemporary Cleaners (ERIC_4970)_HW683 SOW_Annual GW Monitoring_2022-04_Rev1
Upper Surficial Aquifer (18) Lower Surficial Aquifer (13) Intermediate Aquifer (4)
MW001
MW002
MW003
MW004*
MW005
MW006*
MW019*
MW021
MW027
MW031*
MW032
MW033R*
MW034
MW035R
MW036R*
MW038*
MW039*
MW041*
MW008
MW009*
MW014*
MW017*
MW018
MW023
MW025*
MW026
MW028*
MW29R*
MW040*
MW042*
MW043*
MW010*
MW015*
MW016*
MW037
* Indicates the monitoring well is also proposed for sampling.
The 21 monitoring wells sampled in February 2020 and May 2021 are proposed for sampling, since the most recent groundwater data is more than 270 days old (e.g., May 2021). The monitoring wells recommended for sampling in 2022 include the following:
Upper Surficial Aquifer (9) Lower Surficial Aquifer (9) Intermediate Aquifer (3) MW004 - cross gradient background monitoring location MW006 – mid-plume MW019 – drain line source area MW031 – mid-plume MW033R – downgradient of VOH plume MW036R – former dry cleaner source area MW038 – former dry cleaner source area MW039 – drain line source area MW041 – former dry cleaner source area
MW009 – former dry cleaner source area MW014 – downgradient of VOH plume MW017 – downgradient along property line MW025 – drain line source area MW028 – downgradient MW29R – offsite MW040 – former dry cleaner source area MW042– former dry cleaner source area MW043 – drain line source area
MW010 – adjacent to former dry cleaner source area MW015 - downgradient MW016 - downgradient
Contemporary Cleaners (ERIC_4970)_HW683 SOW_Annual GW Monitoring_2022-04_Rev1
Historically, a combination of passive diffusion bag (PDBs) sampling and conventional low-flow sampling has been performed during the NAM events since the well diameters range between 0.5 and 2 inches. PDBs were not re-deployed in 2020 and low-flow sampling (peristaltic pump assumed based on previous events) will be continued at each of the monitoring wells.
Groundwater samples will be submitted to a fixed base laboratory for analysis for volatile organic halogens (VOHs) by Environmental Protection Agency (EPA) Method 8260B.
Purge water generated during sampling activities will be containerized in one 55-gallon drum. A composite sample will be collected from the drum to characterize the groundwater IDW for VOHs by EPA Method 8260B to confirm non-hazardous disposal of the purge water. Erwin Remediation provides the lowest unit rate cost among the three subcontractors evaluated for transportation and disposal of non-hazardous liquid waste (Attachment B).
Subtask 3 – Groundwater Monitoring Report
Geosyntec will prepare a Groundwater Monitoring Report documenting the results of the depth to groundwater measurements and annual groundwater monitoring event. The report will contain tables summarizing field/laboratory groundwater data, figures showing groundwater flow direction(s), and a summary of the groundwater monitoring event. Geosyntec will also compare the treatment intervals proposed in the January 2022 RAP Modification – Revision 2 to the groundwater results to confirm the bioremediation design. The report will be signed and sealed by a Florida-licensed professional engineer. Effort included in this subtask also includes time to evaluate the remedial approach with FDEP based on the sampling results and the expected effort needed to provide FDEP with updated ADaPT and GIS data tables consisting of groundwater elevation measurements and groundwater sampling laboratory results. A final signed waste manifest for IDW transport and disposal will also be included in the Groundwater Monitoring Report.
Contemporary Cleaners (ERIC_4970)_HW683 SOW_Annual GW Monitoring_2022-04_Rev1
Invoice and Deliverable Schedule:
Subtask Deliverable Deliverable Due Date Invoice Amount
1, 2, 3
Annual Groundwater Monitoring Report, ADaPT/GIS upload, IDW Manifests
5 August 2022 $15,115.22
Period of Performance 7 October 2022
Total: $15,115.22
The above schedule is based on the assumption that Geosyntec will be tasked for this scope of work by 29 April 2022 and Subtask 2 sampling activities conducted in May 2022.
CLOSURE
Please review and contact us if you have any questions or require any additional information. As always, it is a pleasure to work with the FDEP.
Sincerely, Olivia Cain, P.E. (FL) Todd K. Kafka, P.G. (FL) Engineer Senior Principal Hydrogeologist
Attachments
Copies to
Attachment A – CEF-LOE Attachment B – IDW Transportation & Disposal Cost Estimates
Kevin Warner, Geosyntec
ATTACHMENT B
IDW Transportation & Disposal Cost Estimates
1/7/22, 11:18 AM Clark Environmental Inc.: Quote Builder quote.clarkenvironmental.com/Quotes/ViewQuote?quoteId=19200 1/2
Quote Number: 19200
QUOTE
QUOTED TO: Todd Kafka
QUOTE DATE: 1/7/2022
COMPANY NAME: Geosyntec - 2022 QUOTED BY: Craig Burns
PHONE NUMBER:
Ext.
FAX NUMBER:
PROJECT REFERENCE: Drum Trans & Disposal for non-haz materials - Petro, Dry Cleaner & PFAS
CUSTOMER PO:
CONTACT EMAIL:
SITE ADDRESS: TBD
CLARK ENVIRONMENTAL, INC. IS PLEASED TO PROVIDE THE FOLLOWING
COST ESTIMATE FOR
THE SITE/ PROJECT LISTED ABOVE.
DESCRIPTION PRICE QTY. UNIT TOTAL
NON HAZ DRUM DISPOSAL**Soils, Solids, Sludges** $80.00 DRUM $0.00
NON HAZ DRUM DISPOSAL**Liquids, PPE, Pads/Rags** $60.00 DRUM $0.00
TRANSPORTATION: 0-100 miles from CLARK Mulberry FL <6 drums/site - surcharge of $50/site
$30.00 DRUM $0.00
TRANSPORTATION: 101-250 miles from CLARK Mulberry FL <6 drums/site - surcharge of $50/site
$40.00 DRUM $0.00
TRANSPORTATION: 251-400 miles from CLARK Mulberry FL <11 drums/site - surcharge of $200/site
$50.00 DRUM $0.00
Totes T&D is available. CLARK can also deliver new drums to each site if needed :$40 + tax
$0.00 . $0.00
HAZ Drums to be quoted case-by-case $0.00 . $0.00
TOTAL REQUIRED ITEMS $0.00
TOTAL OPTIONAL ITEMS $0.00
GRAND TOTAL $0.00
NOTES: Rates apply for FL. Labs and profiles must be approved prior to pick ups.
**Petro Sites required: TCLP 4 metals & TCLP Benzene**Dry Cleaner Sites require 8260 VOH's** Craig Burns
863.327.6289 - cburns@clarkenv.com
This quote will remain valid for 2022 and based on payment in net 30 days. Quote based on an accepted and approved profile. Please sign and return to accept this quotation and by signing agree to all terms and conditions.
Name (print) Title
OCain Rectangle
OCain Text Box $80.00
OCain Text Box $60.00
OCain Text Box $140.00
1/7/22, 11:18 AM Clark Environmental Inc.: Quote Builder quote.clarkenvironmental.com/Quotes/ViewQuote?quoteId=19200 2/2
Signature Date
CLARK ENVIRONMENTAL, INC. * 755 Prairie Industrial Pkwy. * Mulberry, Florida 33860 Telephone: 863-425-4884 * Fax: 863-425-2854
WWW.ClarkEnvironmental.com
408 Ditmar Street
Pensacola, FL 32503
ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511
To: Mr. Todd Kafka
Geosyntec Consultants, Inc.
12802 Tampa Oaks Blvd, Ste 151
Tampa, FL 33637
December 23, 2021
Re: Non-Hazardous Drum Disposal
Mr. Kafka:
The price for the transportation and disposal (T&D) of drums of non-hazardous soil, mud and water is listed below.
Non-Hazardous Chlorinated VOHs, Petroleum and Metals:
Description Rate Unit
T&D - Non-Haz Soil $ 100.00 Per Drum
T&D - Non-Haz Mud/Water $ 100.00 Per Drum
Non-Hazardous PFAS Impacted:
Description Rate Unit
Profile Fee $ 350.00 Per Site
T&D - Non-Haz PFAS Impacted Soil $ 110.00 Per Drum
T&D - Non-Haz PFAS Impacted Mud/Water $ 120.00 Per Drum
The prices listed are all inclusive without any additional fees or charges (fuel surcharge, low volume stop fee etc.) and are valid for all regions in the State of Florida except for the Florida Keys. Pricing for sites located in the Florida Keys will be bid on a case-by-case basis dependent on the volume of drums and the location.
Respectfully, Jonathan Erwin
Erwin Remediation, Inc.
Email: ErwinRemediation@Gmail.com
Office: (850) 292-6511 mailto:Remediation@Gmail.com OCain Rectangle
OCain Rectangle
| CEF.pdf |
| Cost Estimate |
| LOEs.pdf |
| Subtask 2 |
| Subtask 3 |
| CEF.pdf |
| Cost Estimate |
| LOEs.pdf |
| Subtask 2 |
| Subtask 3 |
File details come from the government source that posted it. Updated .