Task Assignment DC003B Summary
This Task Assignment (TA) is a contract between the State of Florida Department of Environmental Protection (FDEP) and Geosyntec Consultants for environmental remediation services at the Super Drycleaner site (ERIC_5142) located in Greenacres, Palm Beach County, Florida. The contract is governed by the underlying Contract Number HW683 and was executed on June 30, 2022, with a completion date of June 30, 2023.
The task authorizes Geosyntec to conduct six months of operations and maintenance (O&M) services from August 2022 through January 2023 for a soil vapor extraction (SVE) system at the contaminated site. The scope of work encompasses monthly O&M visits including system monitoring, groundwater and air sampling, equipment maintenance, reporting, and utility costs. The contract is structured with four subtasks: Project Management (Subtask 1), Year 2 Quarter 4 O&M and Reporting covering August-October 2022 (Subtask 2), Year 3 Quarter 1 O&M covering November 2022-January 2023 (Subtask 3), and Utilities for the full six-month period (Subtask 4). The total contract value is $27,185.49, comprised of fixed unit rates of $25,085.49 and cost reimbursement of $2,100.00 for utilities. Invoicing is tied to deliverable milestones: $14,549.64 due upon completion of Quarter 2 O&M and Annual Report by November 30, 2022; $10,415.85 for Quarter 3 O&M completion by February 28, 2023; and $2,220.00 for utility invoices by March 31, 2023. The work requires 138 total labor hours and includes third-party costs for laboratory analysis, equipment rental, and investigation-derived waste disposal through Erwin Remediation at $110 per drum.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW683
DC003B Completion June 30, 2023
This Task Assignment authorizes Geosyntec to conduct six months of operations and maintenance (O&M), from August 2022 through January 2023, of the soil vapor extraction (SVE) system in accordance with the Geosyntec scope of work, cost estimate, and schedule received on 29 June 2022.
Evan Miller 850-245-8928 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Geosyntec
Geosyntec
Andrew Galvin 561-922-1033
ERIC_5142
5702 Lake Worth Road #6 Greenacres, Palm Beach County, Florida 33463
Super Drycleaner
✔ $ 25,085.49 ✔ $ 2,100.00
$ 27,185.49
Scope of Work
Todd Kafka
Contract Manager
Todd Kafka, P.G. Digitally signed by Todd Kafka, P.G.
Date: 2022.06.30 13:27:49 -04'00'
William E. Burns, Jr
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2022.06.30 11:23:23 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Subtask 2- Submittal of Quarter 2: August 2022 to October 2022 O&M summary emails and Annual O&M report 11/30/2022
Subtask 1,3- Submittal of Quarter 3: November 2022 to January 2023 O&M summary emails; Project Management 02/28/2023
Subtask 2- FDEP receipt and approval of Quarter 2: August 2022 to October 2022 O&M summary emails and Annual O&M report $ 14,549.64
Subtask 1,3- FDEP receipt and approval of Quarter 3: November 2022 to January 2023 O&M summary emails; Project Management $ 10,415.85
Subtask 4- FDEP receipt of utility invoices for 6 months; Utilities (Cost Plus Fixed Fee) = not to exceed 2,100.00 Utilities Handling Fee = $120 $ 2,220.00
$ 27,185.49
HW683
DC003B
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
To: HW683 Contract Negotiation File Super Drycleaner Greenacres, Palm Beach County
ERIC_5142
From: Evan Miller, Project Manager Date: June 30, 2022 Subject: Negotiation Summary
HW683 DC003B
This Task Assignment authorizes Geosyntec to conduct six months of operations and maintenance (O&M), from August 2022 through January 2023, of the soil vapor extraction (SVE) system.
Subtask 1: Project Management An automatic calculation based upon total direct labor hours determines the labor hours within this subtask.
Subtask 2 –Year 2 Quarter 4: August 2022 (Month 22) to October 2022 (Month 24) O&M and Reporting Three months of O&M with monthly email summaries to FDEP, air sampling in Month 24, annual groundwater sampling in Month 24, and Annual Report.
Subtask 3 – Year 3 Quarter 1: November 2022 (Month 25) to January 2023 (Month 27) O&M Three months of O&M with monthly email summaries to FDEP, bump test related air sampling in Month 25, and air sampling in Month 27.
Subtask 4 – Utilities: August 2022 (Month 22) to January 2023 (Month 27) Six months of O&M utility costs.
Geosyntec and the FDEP confirmed on 30 June 2022, that an Access Agreement with the current real property owner of the Super Drycleaner (ERIC_5142) Site has been executed.
The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost for this Task Assignment is $27,185.49 with 138 labor hours.
Geosyntec may invoice following the schedule established in the Deliverables and Invoice Schedule Attachment, which accompanies the Task Assignment Notification Form.
Printed on recycled paper.
FDEP COST ESTIMATEContractor: Geosyntec Consultants (HW550)
Date: 6/29/2022
Task #: HW550-DC003B SubTask 1 Project Management SubTask 6
Site: Super Drycleaner SubTask 2 Year 2 Quarter 4: Aug 2022 - Oct 2022 O&M and Reporting SubTask 7
Activity/Phase: O&M - Year 2 Q4 and Year 3 Q1 SubTask 3 Year 3 Quarter 1: Nov 2022 - Jan 2023 O&M and Reporting SubTask 8
Project Manager: Andrew Galvin SubTask 4 Utilities : Aug 2022 - January 2023 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$38.46 Project Manager A. Galvin 17 16.8 $75.00 Principal K. Warner 6 3 3 0 0 0 0 0 0 0 $56.30 Senior Professional A. Smith 12 7 5 0 0 0 0 0 0 0 $46.15 Project Professional M. Hensley 3 3 0 0 0 0 0 0 0 0 $38.46 Senior Staff Professional A. Galvin 38 30 8 0 0 0 0 0 0 0 $36.54 Senior Staff Professional T. Hood 60 36 24 0 0 0 0 0 0 0 $32.21 Administrative Assistant S. Darling 2 2 0 0 0 0 0 0 0 0
Total Hours 138 17 81 40 0 0 0 0 0 0 0
Direct Labor $5,630.06 $647.71 $3,291.21 $1,691.14 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 172.70% $9,723.12 $1,118.60 $5,683.92 $2,920.60 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $15,353.18 $1,766.31 $8,975.13 $4,611.74 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $960.00 $600.00 $360.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $960.00 $600.00 $360.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $2,100.00 $0.00 $0.00 $2,100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $2,210.00 $110.00 $0.00 $2,100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $131.00 $11.00 $0.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $2,341.00 $121.00 $0.00 $2,220.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $2,384.00 $1,384.00 $1,000.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $1,010.00 $560.00 $450.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $3,394.00 $1,944.00 $1,450.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $280.00 $160.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $315.00 $315.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $2,907.00 $1,437.00 $1,470.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $3,602.00 $2,012.00 $1,590.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $25,650.18 $1,766.31 $13,652.13 $8,011.74 $2,220.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $1,535.31 $176.63 $897.51 $461.17 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $27,185.49 $1,942.94 $14,549.64 $8,472.91 $2,220.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 subtasks (list) cost (by subtasks) Invoice 1 2 $14,549.64 invoice 2 1,3 $10,415.85 Invoice 3 4 $2,220.00 Invoice 4 5 $0.00
REV: 02/03 CEF ARCADIS Page 1
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Super Drycleaner SUBTASK: Year 2 Quarter 4: Aug 2022 - Oct 2022 O&M and Reporting
DATE: 6/29/2022
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Principal K. Warner 3
Senior Professional A. Smith 7
Project Professional M. Hensley 3
Senior Staff Professional A. Galvin 30
Senior Staff Professional
T. Hood 36
Administrative Assistant S. Darling 2
TOTAL LABOR 81
VEHICLE TYPE RATE UNIT USEAGE
Car $80.00 Day 0 $0.00 Truck 3 days O&M, 1 day GW sampling, 1 mob for IDW $120.00 Day 5 $600.00 Van $120.00 Day 0 $0.00
Subtotal $600.00
TOTAL VEHICLE $600.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
IDW
Erwin remediation - Non-Haz Disposal & Transportaion 1 drum $110.00 $110.00
$0.00 $0.00 Subtotal $110.00
TOTAL SUB $110.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOHs - GW 7 MWs + 1 IDW $73.00 8 0 $584.00 TO-15 - Vapor VOCs Influent and VEWs $200.00 4 0 $800.00
Subtotal $1,384.00 Fast Turnaround Charges Percent
24 Hours 110% $0.00 0 $0.00 3 Days 65% $0.00 0 $0.00 1 Week 20% $0.00 0 $0.00
Subtotal $0.00 Shipping summa cans and GW samples Large Cooler (25 to 50 lbs) $150.00 3 $450.00 IDW sample Small Cooler (0 to 25 lbs) $110.00 1 $110.00
Subtotal $560.00
TOTAL LAB $1,944.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Analytical Related
Groundwater Sampling Kit $290.00 Day 1 $290.00 Water Level Meter $25.00 Day 1 $25.00 YSI 556 MPS $105.00 Day 0 $0.00
Subtotal $315.00 IDW Related
Drum $100.00 each 1 $100.00 Subtotal $100.00
Expendables 3 days O&M, 1 day GW sampling $40.00 Day 4 $160.00
Subtotal $160.00 Other
O&M supplies $75.00 Day 3 $225.00 O&M Kit $360.00 Day 3 $1,080.00 Air Sampling Canister (Summa) $33.00 Day 4 $132.00
Subtotal $1,437.00
TOTAL EQUIPMENT $2,012.00
report formatting, PDF assembly and compilation
Quarterly O&M data and optimization evaluation (3 hrs), Groundwater data evaluation (2 hrs); Annual report data evaluation and interpretation (2 hrs); PE certification of Annual Report (3 hrs)
Generate groundwater elevation contour map, update historical groundwater quality figure, genrate ROI figure (3 hrs)
Monthly data evaluation and summary email (2 hrs/event - 6 hrs); update GW and air result tables (2 hrs); draft groundwater contour and spider plot figures (2 hrs), Annual SVE O&M Report (20 hrs)
3 O&M visits (8 hrs each incl rd trip, prep, breakdown - total 24 hrs); Annual GW sampling event: 1 rd trip mob (2 hrs), GW equip calibration (pre, post) (1 hr), collect water levels at 7 wells (1 hr), and sample 3 wells @ 1.5 hrs/well (5 hrs); 1 rd trip mobe to manage onsite IDW (3 hrs)
FINAL --7/24/96
SUBTASK: Year 3 Quarter 1: Nov 2022 - Jan 2023 O&M and Reporting
DATE: 6/29/2022
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Principal K. Warner 3
Senior Professional A. Smith 5
Senior Staff Professional
A. Galvin 8
Senior Staff Professional T. Hood 24
TOTAL LABOR 40
VEHICLE TYPE RATE UNIT USEAGE
Car $80.00 Day 0 $0.00 Truck 3 days O&M $120.00 Day 3 $360.00 Van $120.00 Day 0 $0.00
Subtotal $360.00
TOTAL VEHICLE $360.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
TOTAL SUB $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TO-15 - Vapor VOCs Nov bump test and Jan Influent $200.00 5 0 $1,000.00
Subtotal $1,000.00 Fast Turnaround Charges Percent
24 Hours 110% $0.00 0 $0.00 3 Days 65% $0.00 0 $0.00 1 Week 20% $0.00 0 $0.00
Subtotal $0.00 Shipping summa cans and GW samples Large Cooler (25 to 50 lbs) $150.00 3 $450.00 IDW samples Small Cooler (0 to 25 lbs) $110.00 0 $0.00
Subtotal $450.00
TOTAL LAB $1,450.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Analytical Related
Groundwater Sampling Kit $290.00 Day 0 $0.00 Water Level Meter $25.00 Day 0 $0.00 YSI 556 MPS $105.00 Day 0 $0.00
Subtotal $0.00 IDW Related
Drum $100.00 each 0 $0.00 Subtotal $0.00
Expendables 3 days O&M $40.00 Day 3 $120.00
Subtotal $120.00 Other
O&M supplies $75.00 Day 3 $225.00 O&M Kit $360.00 Day 3 $1,080.00 Air Sampling Canister (Summa) $33.00 Day 5 $165.00
Subtotal $1,470.00
TOTAL EQUIPMENT $1,590.00
Quarterly O&M data and optimization evaluation (3 hrs), Quarterly data interpretation (3 hrs), Bump test evaluation (2 hrs)
Monthly data evaluation and summary email (2 hrs/event - 6 hrs); update air result tables (2 hrs);
3 O&M visits (8 hrs each incl rd trip, prep, breakdown - total 24 hrs)
SUBTASK: Utilities : Aug 2022 - January 2023
DATE: 6/29/2022
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
TOTAL LABOR 0
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Utilities FPL estimate (usage) electrical 6 months $350.00 6 $2,100.00 Processing Fee (electric) 6 months x $20/month $20.00 6 $120.00
Subtotal $2,220.00
TOTAL SUB $2,220.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT $0.00
12801 Tampa Oaks Blvd., Suite 151 Tampa, Florida 33637
PH 813.558.0990
FAX 813.558.9726
www.geosyntec.com
FR3170B/Super DC SOW Year 2_3 OM_DC003B
30 June 2022
Mr. Evan Miller Florida Department of Environmental Protection Waste Cleanup Program 2600 Blair Stone Road, MS 4520 Tallahassee, FL 32399-2400
Subject: 6 Months O&M/Year 3 - Soil Vapor Extraction System Super Drycleaner 5702 Lake Worth Road #6 Greenacres, Palm Beach County, Florida 33463 FDEP Facility ID NO. ERIC_5142 FDEP Task Assignment No. DC003B (pending)
Dear Evan:
Geosyntec Consultants, Inc. (Geosyntec) has prepared this Statement of Work (SOW) and Level of Effort (LOE) for six months of operations and maintenance (O&M), from August 2022 through January 2023, of the soil vapor extraction (SVE) system at Super Drycleaner (Site) (Facility ID- ERIC 5142) located in Greenacres, Florida. The SVE system startup occurred 26 through 28 October 2020. Bump tests were performed in November 2021 and in May 2022 to evaluate if a rebound of volatile organic halocarbon (VOHs) would in the SVE influent or the individual VEWs.
Geosyntec and the FDEP confirmed on 30 June 2022, that an Access Agreement with the current real property owner of the Super Drycleaner (ERIC_5142) Site has been executed.
This LOE is subdivided into subtasks for quarter 4 for Year 2 and quarter 1 for Year 3 since quarter 3 of Year 2 was performed under DC003A. The major scope elements are outlined below as they will pertain to multiple subtasks in some cases. Each subtask will be outlined separately thereafter.
SCOPE OF WORK ELEMENTS
Monthly SVE System O&M Tasks
Geosyntec personnel will conduct 6 monthly O&M visits to the Site beginning in August 2022.
During each O&M visit, Geosyntec personnel will perform the following tasks:
• record vacuum, pressure, and temperature readings at the SVE blower;
Super Drycleaner – 6 Months O&M Year 2/Year 3 O&M LOE
• record air flow rates at the blower and three vapor extraction wells (VEWs);
• record vacuum readings at the three VEWs, VMP001, VMP005, VMP006, VMP007, and
MW006;
• drain fluids accumulated in the moisture separator and disposing of fluids in a 55-gallon drum as investigation derived waste (IDW) and collecting a VOC sample for waste characterization;
• collect groundwater level measurements from monitoring wells MW001 through
MW007;
• perform required air sampling;
• perform required groundwater sampling;
• inspect and clean the equipment compound; and
• perform periodic equipment maintenance activities recommended by equipment manufacturers.
The results of the monthly system O&M activities will be documented in a site-specific O&M log, which will be submitted to the FDEP with the monthly O&M summary emails.
A third bump test will be conducted between the October 2022 and November 2022 O&M events (approximately 6 months following the completion of the second bump test). This third bump test will be performed similarly to the first bump test conducted in October to November 2021 and will consist of collecting air samples from VEW-1 through VEW-3 and the influent during the October 2022 O&M event prior to shutting down the system and upon system startup during the November 2022 O&M event. The results of the third bump test will be provided in the monthly summary emails.
Groundwater sampling
Monitoring wells MW004, MW005, and MW006 will be sampled annually (October 2022). Prior to collecting groundwater samples, depth to water measurements will be collected from MW001 through MW007. The groundwater samples will be analyzed by a FDOH NELAC certified laboratory for VOHs using EPA Method 8260. Results of the groundwater sampling events will be documented in the O&M report for the same reporting period.
IDW Generation and Management
One drum of groundwater IDW is assumed to be generated during annual monitoring well sampling and moisture collected in the moisture separator. IDW from groundwater monitoring well sampling has been previously characterized as non-hazardous waste. Cost estimates for IDW transport and disposal are included as Attachment A. Based on the provided estimates, Erwin Remediation has the lowest rates ($110/drum for non-hazardous disposal) and will be used to transport and dispose of IDW from the site. A VOH sample is required to establish a new profile with the vendor ($73/drum).
Air sampling
Air samples will be collected from the three VEWs (VEW-1 through VEW-3) and the influent during the October 2022 O&M event prior to system shutdown and in November 2022 upon system startup. An influent air sample will also be collected during Year 3 Quarter 1 (January 2023). Air samples will be collected with a summa canister and analyzed at a fixed-base laboratory for volatile organic hydrocarbons (VOHs) by EPA Method TO-15.
Reporting
An Annual O&M Report (following Month 24 [October 2022]) and monthly email summaries will be prepared to document the results of O&M activities. The O&M report will include, at a minimum, the following:
• results of laboratory analyses of air samples (tabular and graphical form);
• results of laboratory analyses of groundwater samples (tabular and illustrative form)
• O&M activities performed during the reporting period;
• the calculated mass of PCE (and daughter products, if detected) removed by the SVE system during the reporting period, and cumulative total removed since startup;
• the SVE system hours of operation during the reporting period;
• information regarding the depth to groundwater;
• information regarding any repairs and/or modifications made to the SVE system;
• vacuum ROI data (tabular and illustrative form); and
• recommendations and conclusions pertaining to the continued operation and/or optimization of the SVE system.
Utilities
Monthly electrical utility bills have been estimated at $350 based on the previous year’s average monthly invoices from Florida Power & Light. The utilities also include a $20 monthly processing fee for electrical service.
LOE SUBTASKS
Subtask 1 – Project Management
Subtask 2 –Year 2 Quarter 4: August 2022 (Month 22) to October 2022 (Month 24) O&M and Reporting
Three months of O&M with monthly email summaries to FDEP, air sampling in Month 24, annual groundwater sampling in Month 24, and Annual Report
Subtask 3 – Year 3 Quarter 1: November 2022 (Month 25) to January 2023 (Month 27) O&M
Three months of O&M with monthly email summaries to FDEP, bump test related air sampling in Month 25, and air sampling in Month 27.
Subtask 4 – Utilities: August 2022 (Month 22) to January 2023 (Month 27)
Six months of O&M utility costs.
Invoice and Deliverable Schedule:
Subtask Deliverable Deliverable Due
Date Invoice Amount
2 Quarter 2: August 2022 to October 2022 O&M summary emails and Annual O&M report 11/30/2022 $14,549.64
1&3 Quarter 3: November 2022 to January 2023 O&M summary emails 2/28/2023 $10,415.85
4 Utilities 3/31/2023 $2,220.00 Total $27,185.49
As always, we appreciate the opportunity to continue working on this project for the FDEP. Please contact me at 561.922.1033 if you have any questions.
Sincerely, Geosyntec Consultants
Adrian Smith, P.E. Todd Kafka, P.G.
Engineer Senior Principal Geologist
Copies:
Attachments:
Cost estimate Form Attachment A – IDW Estimates
408 Ditmar Street
Pensacola, FL 32503
ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511
To: Mr. Todd Kafka - Geosyntec Consultants, Inc.
12802 Tampa Oaks Blvd, Ste 151
Tampa, FL 33637
June 14, 2022
Re: Non-Hazardous Drum Disposal Quote
Mr. Kafka:
The price for the transportation and disposal (T&D) of drums of non-hazardous soil, mud and water is listed below.
Non-Hazardous Chlorinated VOHs, Petroleum and Metals:
Description Rate Unit
T&D - Non-Haz Soil $ 110.00 Per Drum
T&D - Non-Haz Mud/Water $ 110.00 Per Drum
Non-Hazardous PFAS Impacted:
Description Rate Unit
Profile Fee $ 350.00 Per Site
T&D - Non-Haz PFOS/PFAS Impacted Soil $ 120.00 Per Drum
T&D - Non-Haz PFOS/PFAS Impacted Mud/Water $ 130.00 Per Drum
The prices listed are all inclusive without any additional fees or charges (fuel surcharge, low volume stop fee etc.) and are valid for all regions in the State of Florida except for the Florida Keys. Pricing for sites located in the Florida Keys will be bid on a case-by-case basis dependent on the volume of drums and the location.
This quote is valid for 90 days.
Respectfully, Jonathan Erwin
Erwin Remediation, Inc.
Email: ErwinRemediation@Gmail.com
Office: (850) 292-6511 mailto:Remediation@Gmail.com AGalvin Highlight
AGalvin Text Box Total cost is $110 for transport & disposal of 1 Non-haz drum of liquid
1/7/22, 11:18 AM Clark Environmental Inc.: Quote Builder quote.clarkenvironmental.com/Quotes/ViewQuote?quoteId=19200 1/2
Quote Number: 19200
QUOTE
QUOTED TO: Todd Kafka
QUOTE DATE: 1/7/2022
COMPANY NAME: Geosyntec - 2022 QUOTED BY: Craig Burns
PHONE NUMBER:
Ext.
FAX NUMBER:
PROJECT REFERENCE: Drum Trans & Disposal for non-haz materials - Petro, Dry Cleaner & PFAS
CUSTOMER PO:
CONTACT EMAIL:
SITE ADDRESS: TBD
CLARK ENVIRONMENTAL, INC. IS PLEASED TO PROVIDE THE FOLLOWING
COST ESTIMATE FOR
THE SITE/ PROJECT LISTED ABOVE.
DESCRIPTION PRICE QTY. UNIT TOTAL
NON HAZ DRUM DISPOSAL**Soils, Solids, Sludges** $80.00 DRUM $0.00
NON HAZ DRUM DISPOSAL**Liquids, PPE, Pads/Rags** $60.00 DRUM $0.00
TRANSPORTATION: 0-100 miles from CLARK Mulberry FL <6 drums/site - surcharge of $50/site
$30.00 DRUM $0.00
TRANSPORTATION: 101-250 miles from CLARK Mulberry FL <6 drums/site - surcharge of $50/site
$40.00 DRUM $0.00
TRANSPORTATION: 251-400 miles from CLARK Mulberry FL <11 drums/site - surcharge of $200/site
$50.00 DRUM $0.00
Totes T&D is available. CLARK can also deliver new drums to each site if needed :$40 + tax
$0.00 . $0.00
HAZ Drums to be quoted case-by-case $0.00 . $0.00
TOTAL REQUIRED ITEMS $0.00
TOTAL OPTIONAL ITEMS $0.00
GRAND TOTAL $0.00
NOTES: Rates apply for FL. Labs and profiles must be approved prior to pick ups.
**Petro Sites required: TCLP 4 metals & TCLP Benzene**Dry Cleaner Sites require 8260 VOH's** Craig Burns
863.327.6289 - cburns@clarkenv.com
This quote will remain valid for 2022 and based on payment in net 30 days. Quote based on an accepted and approved profile. Please sign and return to accept this quotation and by signing agree to all terms and conditions.
Name (print) Title
AGalvin Highlight
AGalvin Highlight
AGalvin Highlight
AGalvin
Total cost is $150 for transport & disposal of 1 Non-haz drum of liquid
1/7/22, 11:18 AM Clark Environmental Inc.: Quote Builder quote.clarkenvironmental.com/Quotes/ViewQuote?quoteId=19200 2/2
Signature Date
CLARK ENVIRONMENTAL, INC. * 755 Prairie Industrial Pkwy. * Mulberry, Florida 33860 Telephone: 863-425-4884 * Fax: 863-425-2854
WWW.ClarkEnvironmental.com
AGalvin Pencil
AGalvin
Total cost is $230 for transport & disposal of 1 Non-haz drum of liquid
| CEF.pdf |
| Cost Estimate |
| LOEs.pdf |
| Subtask 2 |
| Subtask 3 |
| Subtask 4 |
| Super DC SOW Year 2_3 OM_DC003B.pdf |
| SCOPE OF WORK ELEMENTS |
| Monthly SVE System O&M Tasks |
| Groundwater sampling |
| IDW Generation and Management |
| One drum of groundwater IDW is assumed to be generated during annual monitoring well sampling and moisture collected in the moisture separator. IDW from groundwater monitoring well sampling has been previously characterized as non-hazardous waste. Cos... |
| Air sampling |
| Reporting |
| Utilities |
| LOE subtasks |
| Subtask 1 – Project Management |
| Subtask 2 –Year 2 Quarter 4: August 2022 (Month 22) to October 2022 (Month 24) O&M and Reporting |
| Subtask 3 – Year 3 Quarter 1: November 2022 (Month 25) to January 2023 (Month 27) O&M |
| Subtask 4 – Utilities: August 2022 (Month 22) to January 2023 (Month 27) |
| Attachement A - IDW quotes.pdf |
| ER Quote - Geosyntec - Drum - 06.14.2022 |
| Clark Geosyntec Drum Rates 2022 |
| UES Geosyntec IDW Quote 2022 (2) |
| ADPC2F4.tmp |
| Cost Estimate |
| Super DC SOW Year 2_3 OM_DC003B.pdf |
| SCOPE OF WORK ELEMENTS |
| Monthly SVE System O&M Tasks |
| Groundwater sampling |
| IDW Generation and Management |
| One drum of groundwater IDW is assumed to be generated during annual monitoring well sampling and moisture collected in the moisture separator. IDW from groundwater monitoring well sampling has been previously characterized as non-hazardous waste. Cos... |
| Air sampling |
| Reporting |
| Utilities |
| LOE subtasks |
| Subtask 1 – Project Management |
| Subtask 2 –Year 2 Quarter 4: August 2022 (Month 22) to October 2022 (Month 24) O&M and Reporting |
| Subtask 3 – Year 3 Quarter 1: November 2022 (Month 25) to January 2023 (Month 27) O&M |
| Subtask 4 – Utilities: August 2022 (Month 22) to January 2023 (Month 27) |