This is a Task Assignment (TA) under Contract Number HW683 issued by the State of Florida Department of Environmental Protection (FDEP) to Geosyntec Consultants, Inc. for environmental site assessment activities at the Former Ruck's Park Brownfield Site located at 13760-13780 NE 5th Avenue, North Miami, Miami-Dade County, Florida (Site ID ERIC_17896). The task assignment was executed on November 5, 2025, with a completion date of March 31, 2026. The Department Project Manager is Megan Johnson (850.245.8994), and the Contractor's Project Manager is Shekhar Melkote, P.G. (570.575.2631). The services are being conducted using federal funds from the State & Tribal Response Program (SRP) cooperative agreement administered by FDEP on behalf of the U.S. Environmental Protection Agency (EPA).

The scope of work consists of five subtasks: (1) Project Management at a negotiated contract rate of $4,830.99; (2) Responses to Miami-Dade County Division of Environmental Resources (DERM) review comments and preparation of off-site contamination notifications for approximately six properties at $6,871.59; (3) Field work including soil sampling, installation of four new groundwater monitoring wells, sampling of existing and new monitoring wells, professional surveying, and investigation-derived waste (IDW) containerization at $33,700.73; (4) Compilation of a Site Assessment Report Addendum in accordance with Chapter 62-780 F.A.C. at $14,795.90; and (5) IDW off-site disposal paperwork and manifest coordination at $1,263.80. The Total Task Assignment Value is $61,463.01, to be paid on a fixed unit rate basis with invoicing tied to specific deliverable approvals. Key deliverables include responses to DERM comments and off-site notifications (due 01/09/2026), field notes and sampling logs (due 01/09/2026), Site Assessment Report Addendum and project management documentation (due 02/20/2026), and IDW disposal manifests (due 02/20/2026). Subcontractors engaged include Earth Tech Drilling for monitoring well installation ($9,110.00), Engenuity Group for surveying ($2,825.00), GeoTek Services for utility location ($750.00), Eurofins for laboratory analysis ($2,487.00), and Erwin Remediation for IDW drum disposal ($750.00).

View the file

Other files

File Type Posted
CN-370000-HW683-BF01A.pdf PDF
CN-370000-HW683-BF01B.pdf PDF
CN-370000-HW683-BF02A.pdf PDF
CN-370000-HW683-BF02ACO2.pdf PDF
CN-370000-HW683-BF04A.pdf PDF
CN-370000-HW683-BF04BCO1.pdf PDF
CN-370000-HW683-BF2BCO1.pdf PDF
CN-370000-HW683-BIL01A.pdf PDF
CN-370000-HW683-CSS02.pdf PDF
CN-370000-HW683-CSS02A.pdf PDF
CN-370000-HW683-DC002F.pdf PDF
CN-370000-HW683-DC004B.pdf PDF
CN-370000-HW683-DC004E.pdf PDF
CN-370000-HW683-DC005D.pdf PDF
CN-370000-HW683-DC005E.pdf PDF
CN-370000-HW683-DC007A.pdf PDF
CN-370000-HW683-DC007B.pdf PDF
CN-370000-HW683-DC008A.pdf PDF
CN-370000-HW683-DC008B.pdf PDF
CN-370000-HW683-DC008D.pdf PDF
CN-370000-HW683-DC009A.pdf PDF
CN-370000-HW683-DC009B.pdf PDF
CN-370000-HW683-DC009G.pdf PDF
CN-370000-HW683-DC010C.pdf PDF
CN-370000-HW683-DC011B.pdf PDF
CN-370000-HW683-DC011C.pdf PDF
CN-370000-HW683-DC011D.pdf PDF
CN-370000-HW683-DC012B.pdf PDF
CN-370000-HW683-DC016B.pdf PDF
CN-370000-HW683-DC017A.pdf PDF
CN-370000-HW683-DC018B.pdf PDF
CN-370000-HW683-DC019A.pdf PDF
CN-370000-HW683-DC019B.pdf PDF
CN-370000-HW683-DC019C.pdf PDF
CN-370000-HW683-DC019D.pdf PDF
CN-370000-HW683-DC01ACO1.pdf PDF
CN-370000-HW683-DC025B.pdf PDF
CN-370000-HW683-DC026B.pdf PDF
CN-370000-HW683-DC029A.pdf PDF
CN-370000-HW683-DC029E.pdf PDF
CN-370000-HW683-DC02ACO1.pdf PDF
CN-370000-HW683-DC02E.pdf PDF
CN-370000-HW683-DC031C.pdf PDF
CN-370000-HW683-DC032A.pdf PDF
CN-370000-HW683-DC032C.pdf PDF
CN-370000-HW683-DC035A.pdf PDF
CN-370000-HW683-DC036B.pdf PDF
CN-370000-HW683-DC037B.pdf PDF
CN-370000-HW683-DC038A.pdf PDF
CN-370000-HW683-DC039A.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O.

Object Code

Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department

Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature)

Date:

Additional signatures attached on separate page.

HW683

BF04C March 31, 2026

Geosyntec will conduct additional field assessment sampling and update the Site

Assessment Report Addendum at the below site in accordance with the cost proposal and Level of Effort (LOE) submitted to the Department on October 28, 2025.

Megan Johnson 850.245.8994 Geosyntec Consultants

Shekhar Melkote, P.G. 570.575.2631

ERIC_17896

13760-13780 NE 5th Avenue, North Miami, Miami-Dade County

Former Ruck's Park

$ 61,463.01

$ 61,463.01

Scope of Work

Geosyntec Consultants

Joseph Applegate, P.G.

Sr. Principal Hydrogeologist

Joseph Applegate Digitally signed by Joseph Applegate Date: 2025.11.05 16:44:47 -05'00'

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2025.11.05 15:11:34 -05'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WC TAFORM

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jay Collins Lt. Governor

Alexis A. Lambert Secretary

Memorandum

TO: Geosyntec Consultants, Inc. HW683 Contract File

FROM: Megan Johnson, Contract Manager

DATE: November 4, 2025

SUBJECT: Negotiation Summary – SRP28, Task Assignment (TA) BF04C Former Ruck’s Park - Site ID #: ERIC_17896 Site Assessment Activities

This TA is for conducting additional site assessment and updating the Site Assessment Report Addendum (SARA) for the Former Ruck’s Park Brownfield Site, located at 13760- 13780 NE 5th Avenue, North Miami, Miami-Dade County. The services under this task are being conducted using federal funds from the State & Tribal Response Program (SRP) cooperative agreement that is administered by the Department on behalf of the U.S.

Environmental Protection Agency (EPA).

Subtask 1: Project Management This subtask is a percentage of the overall project fees and has been negotiated as a contract rate. It includes project management, overhead, general and administrative, and fringe. The agreed upon cost of this subtask is $4,830.99.

Subtask 2: Provide Responses and Prepare Off-Site Contamination Notifications Under this task, Geosyntec will provide responses to the DERM review comment letter dated October 2, 2025, which will include a summary of additional assessment requirements and off-site notifications. Approximately six properties are currently expected to require notification, however, this total will be subject to final confirmation from DERM. The agreed upon cost of this subtask is $6,871.59.

Subtask 3: Field Work Under this subtask, Geosyntec will conduct additional soil sampling, install new groundwater monitoring wells, and sample new and existing groundwater monitoring wells. Key field activities include overseeing installation of the four new shallow depth monitoring wells, collecting soil samples at four locations for arsenic analysis, sample approximately10 monitoring wells for arsenic, PAHs, and a smaller subset for coliforms and OCPs, overseeing the survey of the new monitoring wells and soil boring locations by a professional surveyor, and containerizing all investigation derived wastes. The agreed upon cost of this subtask is $33,700.73.

Former Ruck’s Park Brownfield Site Task Assignment BF04C November 4, 2025

Subtask 4: Site Assessment Report Addendum (SARA) Under this subtask, Geosyntec will compile and integrate new data with previous data to prepare a comprehensive SARA in accordance with Chapter 62-780 F.A.C. The SARA will include recent and historical data collected during previous site assessment activities, a review and interpretation of the soil data and groundwater concentrations, soil and groundwater summary data tables, groundwater analytical results, groundwater concentration plume maps, summary and conclusions. The agreed upon cost of this subtask is $14,795.90.

Subtask 5: IDW Off-Site Disposal This subtask includes effort for completing the IDW paperwork/manifests and overseeing pickup. The agreed upon cost of this subtask is $1,263.80.

Summary The Department’s SRP Contract Manager and Geosyntec’s Contract Manager have both agreed to the scope of work and associated costs. The final cost associated with this TA is $61,463.01. Documentation of these costs is included in the Cost Proposal/Level of Effort (CP/LOE) Form and CP/LOE narrative provided by Geosyntec on October 28, 2025, and the TA Form for BF04C prepared by the Department. The final deliverable for this TA must be received by the Department no later than February 20, 2026.

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Former Rucks Park Brownfield Site SUBTASK 2: DERM Ltr RTC & Off-Site Notification

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Sr. Principal J. Applegate 6

Senior Consultant S.Melkote

Sr. Staff Professional E. Tesfamariam

Drafter J. Sea 4

TOTAL LABOR 46

10/28/2025

Assist with Property Notification with GIS Support/Figures (4 hr)

Meetings with DERM (2 hr). Prepare Responses to DERM comments (2 hr). Assist with offsite notifications (2 hr).

Meetings with DERM (2 hr). Prepare Responses (2 hr), Off-site notices (2 hrs).

Prepare Offsite Notifications for approximtaley 6 properties/entities (4 hrs each).

Off-site notices Editing/preparation (4 hr)

Project Professional M.Hensley

11/5/2025 Page 3 of 6 Subtask 2

SUBTASK 3: Fieldwork

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Sr. Principal J. Applegate 7

Senior Consultant S. Melkote 8

Sr. Staff Professional M. Guirard 50

Sr. Staff Professional S. Abelson 58

TOTAL LABOR 123

VEHICLE TYPE RATE UNIT USEAGE

Car $80.00 Day 0 $0.00 Truck $120.00 Day 5 $600.00 Van $120.00 Day 0 $0.00

Subtotal $600.00

TOTAL VEHICLE $600.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Drilling (Conventional) Earth Tech, Pompano Beach, FL Install 4 Shallow Monitoring Wells $9,110.00 $9,110.00

$0.00 $0.00 Subtotal $9,110.00

Surveying Engenuity Group, WPB, FL Survey soil, wells and verify property/fence corners $2,825.00 $2,825.00

Subtotal $2,825.00

Utilities Geotek Services, Melbourne, FL Utility locate for subsurface work $750.00 $750.00

$0.00 $0.00 Subtotal $750.00

TOTAL SUB $12,685.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

Metals -As Soil - 6020B $14.00 10 0 $140.00 Soil Percent Moisture Soil - D2216 $13.00 10 0 $130.00 Metals -As GW - 6020B $14.00 11 1 $168.00 PAHs GW - 8270 SIM $110.00 11 1 $1,320.00

OCP GW- 8018B $105.00 1 0 $105.00

Coliform, Total GW - SM9223B $52.00 5 1 $312.00 Coliform, Fecal GW - IDEXX $52.00 5 1 $312.00

Subtotal $2,487.00

TOTAL LAB $2,487.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Drilling Related Monitoring Well Installation Kit $325.00 Day 2 $650.00 Soil Assessment Kit $175.00 Day 1 $175.00 Soil Sampling Kit (Through Concrete $235.00 Day 0 $0.00

Subtotal $825.00 Analytical Related

Groundwater Sampling Kit $290.00 Day 2 $580.00 Peristaltic Pump $30.00 Day 0 $0.00 Tubing $0.30 Day 250 $75.00

Subtotal $655.00 IDW Related

Drum $100.00 Drum 0 $0.00 Subtotal $0.00

Expendables $40.00 Day 5 $200.00

Subtotal $200.00

Other $0.00 Day 0 $0.00

Subtotal $0.00

TOTAL EQUIPMENT $1,680.00

10/28/2025

Daily mob/demob (3 hr x4 days = 12 hr); Soil Sampling at about 4 locations (6 hrs); Oversee 4 new well installation (16 hr); Sample ~10 wells (16 hr);

Offsite Access (2 hr), and Fieldwork Oversight (5 hr)

Fieldwork data review (4 hr), field oversight and support (4 hr)

Daily mob/demob (3 hr x5 days = 15 hr); Soil Sampling at about 4 locations (6 hrs); Oversee 4 new well installation (16 hr); Sample ~10 wells (16 hr); Survey (5 hr)

11/5/2025 Page 4 of 6 Subtask 3

SUBTASK 4: Site Assessment Report Addendum

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Sr. Principal J. Applegate 14

Senior Consultant S. Melkote 40

Project Professional M. Hensley

Drafter J. Sea 6

TOTAL LABOR 74

10/28/2025

Senior Peer Review and signing and sealing final SARA

Update Tables, Text & Figures. Prepare draft and final Reports .

Prepare/update Draft and Final Report Figures

Assist with Technical Editing of Tables and Text

11/5/2025 Page 5 of 6 Subtask 4

SUBTASK: IDW Disposal

DATE: 10/28/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Consultant S. Melkote 2

TOTAL LABOR 2

SUBCONTRACTOR COSTS

NAME PURPOSE COST Use

IDW

Erwin Remediation IDW Drum Disposal $125.00 6 $750.00

$0.00 $0.00 Subtotal $750.00

TOTAL SUB $750.00

Coordinate IDW and Review Manifests

11/5/2025 Page 6 of 6 Subtask 5

2039 Centre Pointe Blvd, Suite 301 Tallahassee, Florida 32308

PH 850-765-9312

www.geosyntec.com

Fmr Rucks Park Brownfield_FDEP SARA_LOE Cover Ltr_Oct_28_2025

28 October 2025

Ms. Megan Johnson, Project Manager Mr. Scott L. Sweeney, Environmental Manager Brownfields and CERCLA Site Screening Division of Waste Management Florida Department of Environmental Protection 2600 Blair Stone Road Tallahassee, FL 32399-2400

Subject: Cost Proposal for Conducting Additional Sampling and Updating Site Assessment Report Addendum for the Former Rucks Park Brownfield Site, 13760-13780 NE 5th Avenue, North Miami, Florida 33168.

Brownfield ID #1314003001. DERM Facility ID No. IW5-8624/File-8022

Dear Ms. Johnson and Mr. Sweeney:

Geosyntec Consultants, Inc. (Geosyntec) is pleased to submit this proposal and Cost Estimate/Level of Effort (CEF/LOE) to address the requirements for the Former Rucks Park Brownfield Site located at 13760 – 13780 NE 5th Avenue, North Miami, Florida (the “Site”). This proposed scope of work – which includes conducting additional sampling and subsequent revisions to the Site Assessment Report Addendum (SARA) – is in response to review comments received from the Miami-Dade County Division of Environmental Resources (DERM). DERM’s review of the recent SARA (dated 16 September 2025;

Geosyntec 20251) specifically requested additional soil sampling, the installation and sampling of new and existing monitoring wells, and the preparation of off-site contamination notifications to potential affected off-site properties adjacent to the Site to be prepared and submitted to the FDEP. These tasks are necessary to finalize the site assessment and support the planned brownfields redevelopment.

The scope of work consists of the following tasks:

Subtask 1 – Project Management

This subtask includes effort for overall Project Management activities associated with various tasks described below.

1 Geosyntec. 2025. Site Assessment Report Addendum. The Former Rucks Park Brownfield Site (DERM) Facility ID:

IW5-8624/File-8022; Brownfield ID# 131403001, 13760-13780 NE 5th Avenue, North Miami, Miami-Dade County, Florida.

Geosyntec Consultants, Inc. September 16.

Ms. Johnson and Mr. Sweeney

Task 2 – Provide Responses and Prepare Off-Site Contamination Notifications

Under this task, Geosyntec will provide responses to the DERM review comment letter dated 2 October 2025, which will include a summary of additional assessment requirements and off-site notifications.

Following submittal of responses to DERM review comments, we will follow up with a call to DERM to review and confirm the scope of additional assessment activities and the specific properties requiring off-site notifications. Approximately six properties are currently expected to require notification, however, this total will be subject to final confirmation from DERM.

Task 3 - Field Work

Task 3 involves field execution of additional soil sampling, installation of new wells, and sampling of new and existing groundwater wells.

Key field activities include:

Oversee installation of the four new shallow depth wells;

Collect soil samples at four locations for arsenic analysis;

Sample approximately 10 monitoring wells for arsenic, polyaromatic hydrocarbons (PAHs), and a smaller subset for coliforms and organo-chlorine pesticides (OCPs);

Oversee survey of the new monitoring wells and soil boring locations by a professional surveyor;

Containerize and dispose all investigative-derived waste (IDW) by a licensed waste contractor (see Subtask ).

Task – Site Assessment Report Addendum (SARA)

Geosyntec will compile and integrate new data with previous data to prepare a comprehensive SARA in accordance with Chapter 62-780 FAC. The SARA will include recent and historic data collected during previous site assessment activities, a review and interpretation of the soil data and groundwater concentrations, soil and groundwater summary data tables, groundwater analytical results, groundwater concentration plume maps, summary and conclusions.

Task –IDW Off-Site Disposal

Task includes effort for completing IDW paperwork/manifests and coordinating the pickup.

Fmr Rucks Park Brownfield Site Additional Assessment and Notification Packages

Fmr Rucks Park Brownfield Site Additional Assessment and Notification Packages

Cost Estimate and Schedule:

Geosyntec contacted 3 contractors to obtain costs for well drilling, utility clearance and IDW disposal services. A summary of these bids is provided below:

Date Contractor Estimated Duration

Date Available

Costs

Well Installation 10/22/25 Earth Tech Drilling 2 days Nov ‘25 $ 9,110 10/22/25 PDS 2 days Nov ‘25 $ 8,700 10/22/25 Cascades Drilling 2 days Jan ‘26 $ 10,450

Date Contractor Estimated Duration

Date Available

Costs

Utility Clearance 10/27/25 Blood Hound - ½ day - $ 1,096 10/24/25 GeoTek Services, LLC - ½ day - $ 750 10/27/25 Geoview - ½ day - $ 900

--Not Applicable

Date Contractor Estimated Duration

Date Available

Costs

IDW Pick up and Disposal 12/16/24 Erwin 1 day Mar $ 750 1/1/25 WRI 1 day Mar $ 750 3/5/25 Hulls – No bid - - $ NA

--Not Applicable

Geosyntec recommends subcontracting Earth Tech Drilling for the monitoring well installation. Even though Earth Tech price is slightly higher than PDS (by $410), we are recommending retaining Earth Tech for several reasons. Earth Tech’s proposal includes a skid-steer for safely moving the IDW drums to a common location. The lack of a skid-steer or IDW handling plan in PDS proposal presents safety concerns that justify the minor cost difference. Earth Tech is also recommended because of their previous work experience at this Site, which is important for efficient field execution and minimizing unforeseen complications.

Based on pricing and availability, we recommend GeoTek Services, LLC and Environmental, Inc. for utility clearance, and Erwin Remediation for IDW pickup and disposal services, respectively. Eurofins, Altamonte Springs, FL, a fully-certified laboratory, will be subcontracted for soil and groundwater services. Eurofins conducted the previous analysis in 2024 and 2025. We have also included a quote from

Fmr Rucks Park Brownfield Site Additional Assessment and Notification Packages a licensed professional survey company, Engenuity Group Inc. for surveying new monitoring wells and soil borings.

The cost estimate and level of effort for conducting the site assessment and preparing the SARA is presented in attached CEF/LOE forms. The invoicing and deliverable schedule is presented below. The schedule assumes that the project Task Assignment would be issued by 7 November 2025.

Task Deliverable Deliverable Due Date

Invoice Amount

RTC to DERM Letter and Offsite Notifications 31 December 2025

$ 6,871.59

3 Fieldwork Completion – Fieldnotes 31 December 2025 $33,700.73

4 + 1 SARA Report + Project Management 13 February 2026 $ 19,626.89

5 IDW Disposal Manifests 31 January 2026 $ 1,263.80

Total: $ 61,463.01

We appreciate the opportunity to conduct this project for the FDEP. Please contact Joe Applegate at

850.556.8419 or Shekhar Melkote at 570.575.2631, if you have any questions.

Sincerely, Joseph L. Applegate, P.G. (FL) Shekhar Melkote, P.G. (FL) Sr. Principal Hydrogeologist Senior Consultant

Attachment(s): CEF/LOE Form Subcontractor Quotes

EARTH TECH DRILLING

2703 NW 19TH STREET, POMPANO BEACH, FL 33069

954.974.2424 FAX:954.974.2423

Date: 10/22/2025

FAC ID#:

PROPOSED SCOPE OF WORK:

Assumed 6 Drums Total

Develop Wells next day

Unit Unit Rate Number of Units

Extended Price

Equipment Type: DPT/Combo Track Rig whole day $1,700.00 1 $1,700.00

1/2 day $1,450.00 1 $1,450.00 day / Mob $1,500.00 1 $1,500.00

2" Well Installation per foot $30.00 60 $1,800.00

6" Surface Casing per foot $0.00

Pre-Packed PVC Well Screen (includes all materials) 5' Length Pack OD ___1"____ each $0.00

Well Riser (includes all materials) ID ___1"___ 5' Length each $0.00 per well $225.00 4 $900.00

Mobilization daily roundtrip $575.00 2 $1,150.00

Per Diem per crew / per night $0.00

DOT Approved 55-gal Drum each $80.00 6 $480.00

Permits 2 Installation Permit each $130.00 1 $130.00

Permits 2 Installation Permit each $0.00

Concrete Core each $95.00 0 $0.00

$0.00

TOTAL QUOTE PRICE $9,110.00

Notes:

Project No.: ___________________________

Subcontract Company Name: EARTH TECH DRILLING. Inc.

Subcontract Mailing Address: 2703 NW 19th Street, Pompano Beach, FL 33069

Signature and Title of Person Submitting Quote: Charles Bucher Date: 10/22/2025

Days to Complete Scope of Work: 2 Days

ETD Policy: If pea gravel is encountered, borehole advancement is terminated. If client would like to continue borehole advancement, it is at the risk of the consultant, FDEP or property owner.

DIRECT PUSH TECHNOLOGY

MISCELLANEOUS

Contractor Name: Geosyntec - Shekhar Melkote - 570 575-2631

Site Name: Former Rucks Park - 13760-13780 NE 5th Ave - North Miami, FL

(HAND CLEAR ALL LOCATIONS TO 5' or REFUSAL)

(4) MW 2" x 15' w/ 10' .010" Screen (20/30 Sand) & 8" BD Completion - Installed by Auger - No Soil Sampling

Well Completion (includes. 8" BD MH & locking well cap)

DPT/Combo Rig

Skidsteer for IDW Management (Last day of project to move drums)

Well Development

Monitoring Wells Sparge Wells Horizontal and Vertical Extraction Wells Geotechnical Drilling Direct Push

Preferred Drilling Solutions, Inc.

8820 66th St. North, Pinellas Park, FL 33782

Ph: 727-561-7477 Fax: 727-561-9028 www.pdsflorida.com

DIRECT PUSH TECHNOLOGY QUOTE FORM

Date: 10/23/25 FAC ID#:

Unit Unit Rate Number of Units

Extended Price whole day $2,125.00 2 4,250.00$ half day $1,475.00 -$ per foot $25.00 60 1,500.00$ each $110.00 -$ each $50.00 -$ each $35.00 -$ per well $150.00 4 600.00$ roundtrip $1,025.00 1 1,025.00$ per crew / per night $575.00 1 575.00$ each $75.00 6 450.00$ per day $150.00 -$ each $150.00 2 300.00$ lump sum $350.00 -$ per day $50.00 -$

TOTAL QUOTE PRICE $8,700.00

Notes: 1. Includes saw cuts, development, standby time, and decon.

Project No.:

Subcontract Company Name: Preferred Drilling Solutions, Inc. (727) 561-7477

Subcontract Mailing Address: 8820 66th St, Pinellas Park, FL 33782

Signature and Title of Person Submitting Quote: Rose Hood , Rose Hood Estimating & Scheduling Manager Date: 10/23/25

13760-13780 NE 5th Ave, North Miami, Miami-Dade County, FL

Well Completion (includes 8" MH w/ cover, concrete pad, and locking well cap)

Well Riser (includes all materials) ID 1" 5' Length

Slotted PVC Well Screen (includes all materials) 5' Length Pack OD 3.5"

Pre-Packed Well Screen (includes all materials) ID 1" 5' Length Pack OD 3.5"

Auger Attachment, 2" Well Install

Direct Push Half-Day Rate 1 - on-site half day

Site Name and Location: Fmr Rucks Park Site

Consultant Name: Geosyntec Consultants

PROPOSED SCOPE OF WORK:

(4) 2" x 15' MWs with 10' .010 screen, soil sampling as needed, drum cuttings, pads and 8" manholes

Drum development water, drums to be staged in a central location

Days to Complete Scope of Work: 2

Direct Push Daily Rate 1 - on-site day

Equipment Type: Geoprobe 8040DT, 3230DT, 7822DT, 6620DT, 6712DT

*Note: It is against PDS policy to drill in Pea Gravel. Borings in Pea Gravel will be terminated or can proceed solely at the risk of the consultant, DEP or Property Owner

Other (specify)

Steam Cleaner

Decon Pad

GeoProbe Consumables (includes tubing, points, liners, concrete patch, asphalt patch, and grouting)

DOT Approved 55-gal Drum

Per Diem

Mobilization

DIRECT PUSH TECHNOLOGY

MISCELLANEOUS

Permits

This quote is based on information provided by you and is valid for 45 days from the bid date. Your firm is responsible for 1) Obtaining any site specific permits, 2) Locating and clearly marking underground installations or utilities, 3) Furnishing dig Alert numbers at least three working days prior to scheduled start date and proof of private locating services, 4) Obtaining access to site with no overhead wires within 20' of the holes. On-site soil disposal, unless Cascade expressly assumes responsibility in writing. Cascade shall not be responsible for damages to underground improvements not clearly and accurately marked.

If bedrock, cobbles, flowing sands or other adverse or unsafe drilling conditions are encountered, drilling

GeoTek Services, LLC

24 October 2025

To: Joseph Applegate Geosyntec Consultants 2039 Centre Pointe Blvd., Suite 103 Tallahassee, Florida 32308

From: GeoTek Services, LLC 4060 Sparrow Hawk Road Melbourne, Florida 32934

RE: Utility Scanning Services – Former Rucks Park in North Miami, Florida

Mr. Applegate, GeoTek Services is pleased to respond to your request for Utility Locating services at the Former Rucks Park located in North Miami, Florida. We will scan a 10’ x 10’ area around the eight proposed bore locations as shown in your PDF drawing – with the goal of locating underground utilities. We can only scan the easily accessible open areas for utilities. Note that we cannot scan beneath fixed objects such as landscaping, fencing, buildings or vehicles. We will scan as close as reasonably possible to fixed objects such as brush, landscaping, fences, etc. Our deliverable will be marking paint and/or flags indicating the location of potential underground utilities. It is the client’s responsibility to protect and preserve all marks.

We will use both Electromagnetic Induction instruments as well as Ground Penetrating Radar (GPR) to detect objects below the surface. Due to the nature of sub-surface detection and the physical laws governing radio wave propagation, some buried objects may not be detectable due to depth, obscuration, or a weak radar signature. GeoTek Services will use industry standard best practices to locate sub-surface objects; however, some objects may not be detectable. Geotek Services does not guarantee that all underground objects can be found. GeoTek Services assumes no liability for any damages.

We request access to any as-built site plans of the scan areas prior to rendering services. Our utility scanning estimate for this project is $750.00. No out-of-pocket expenses are expected for this project. This quote is valid for sixty days.

Best Regards, Martin (Bud) Connor GeoTek Services, LLC

4060 Sparrow Hawk Road Melbourne, FL 32934-8525 info@GeoTekServices.com 321.473.7498

From: Craig Fusaro To: Joseph L. Applegate Cc: Shekhar Melkote Subject: RE: Request for a Utility Clearance Quote - Former Rucks Park, North Miami, FL Date: Monday, October 27, 2025 5:33:53 AM

CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe. If you have any suspicion, please confirm with the sender verbally that this email is authentic. If you suspect fraud, click "Phish Alert Report."

Good Morning Joseph

Thanks for the project request. Cost for the project will be our half day rate of $900. Our availability looks good for mid-November currently.

Have a great week ahead.

Craig A. Fusaro Geophysicist Southeast Florida Manager Boca Raton, Florida Office: 561-430-5296 Cell: 727-479-6338

GeoView, Inc.

St. Petersburg – Jacksonville – Orlando – Boca Raton – Boston

Providing geophysical services to geological/geotechnical, infrastructure/utility, environmental, archaeological & marine investigations.

From: Joseph L. Applegate <JApplegate@Geosyntec.com> Sent: Friday, October 24, 2025 4:54 PM To: Craig Fusaro <cfusaro@geoviewinc.com> Cc: Shekhar Melkote <SMelkote@Geosyntec.com> Subject: Request for a Utility Clearance Quote - Former Rucks Park, North Miami, FL

Hi Craig, Can you provide me with a quote to conduct utility clearance for installation of 4 MWs and 4 soil borings at this site in North Miami please? The proposed MWs are yellow circles and the SBs are red dots. This appears to be about a ½ days’ work. This work will likely take place mid to late November.

www.geoviewinc.com

The locations are on the attached map

Thank you and have a nice weekend, Joe

ESTIMATE

Blood Hound Corporate Headquarters 6500 Technology Center Dr., Suite 200 Indianapolis, IN 46278

Email: BHI@bhug.com bhug.com Website: Phone #: 888-858-9830 888-858-9829 Fax #:

ESTIMATE

Blood Hound Corporate Headquarters 6500 Technology Center Dr., Suite 200 Indianapolis, IN 46278

Email: BHI@bhug.com bhug.com Website: Phone #: 888-858-9830 888-858-9829 Fax #:

408 Ditmar Street

Pensacola, FL 32503

ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562

(850) 292-6511

To: Ms. Maria Lemes Geosyntec Consultants, Inc.

19321 US Highway 19 North Clearwater, FL 33764

December 16, 2024

Re: Non-Hazardous Drum Disposal of PFOS/PFAS Impacted Materials

Ms. Lemes:

The price for the transportation and disposal (T&D) of 55-gallon drums of non-hazardous soil, mud, and water is listed below:

Impacted with Non-Hazardous Petroleum or Chlorinated Solvents:

Description Rate Unit

T&D - Non-Haz Soil $ 110.00 Per Drum

T&D - Non-Haz Mud/Water $ 125.00 Per Drum

Impacted with Non-Hazardous PFAS/PFOS:

Description Rate Unit

Profile Fee (Charged once per site) $ 350.00 Per Site

T&D - Non-Haz PFOS/PFAS Impacted Soil $ 195.00 Per Drum

T&D - Non-Haz PFOS/PFAS Impacted Mud/Water $ 195.00 Per Drum

Dry cleaning sites will require 8260-VOH lab analysis and PFAS sites will require the full FDEP lab analysis for IDW waste characterization.

This quote is valid for 120 days.

Respectfully, Jonathan Erwin Erwin Remediation, Inc.

Email: ErwinRemediation@Gmail.com Office: (850) 292-6511

Proposal No. : 2025FC0101

Date : 1/1/2025

PROPOSAL & SHORT FORM AGREEMENT FOR WASTE DISPOSAL SERVICES

Additional Terms:

All Services subject to a minimum charge of $215.

Truck tank washouts, if needed, will be charged at $215/15-min increment.

Standby time on transportation services will be charged at an additional $175/hr after the first hour of loading.

Water treatment loads containing equal to or greater than 2% solids will be assessed a solids surcharge of $0.70/gal (applies to the solids portion of the load only).

All drums need to be properly labeled, have properly secured lids and be free of leaks.

Payment Terms: [NET 30 Days] In addition to the charges above, Customer shall reimburse Water Recovery for any tariff, permit or approval fees, tax surcharges or sales, or use or any other applicable fees related to the performance of the Services.

Proposal is based upon accuracy of information provided by Customer; any changes to the waste stream data or site conditions may result in additional charges.

Hazardous Waste Stream Profile and inventory (if applicable).

A 3% convenience fee will be added to all credit card payments.

This Proposal, the attached General Terms and Conditions, and any documentation referenced above shall constitute the entire agreement between Water Recovery and Customer with respect to the waste handling, transportation, and/or disposal of the waste identified above. By signing below, the undersigned represents his/her authority to bind Customer and generator (if different than Customer) to the terms and conditions herein. Water Recovery may withdraw this Proposal prior to acceptance, at any time.

Dated this 1st day of January, 2025.

WATER RECOVERY CUSTOMER

(Signature)

(Signature)

WATER RECOVERY CUSTOMER

Company : Water Recovery, LLC Company : Geosyntec Consultants Contact : Amanda Kimball Contact : Olivia Cain Street : 1819 Albert St. Street : 6770 South Washington Ave., Ste. 300 City, State, Zip : Jacksonville, FL 32202 City, State, Zip : Titusville FL 32780 Phone : 904-475-9320 Phone : 727-2628268 E-mail : akimball@wrijax.com E-mail : OCain@geosyntec.com

WASTE AND SERVICES INFORMATION

Generator : Various (as manifested) Waste Description : Non-hazardous industrial waste Waste Location : Various (as manifested) Anticipated Volume : Unknown Anticipated Frequency : As Needed Disposal Quote : Drummed Waste - $125/drum

Bulk Wastewater - $0.19/gallon Solidification - $0.70/gallon PFAS contaminated waste - $835/ton with 17-ton minium Rate varies, call for quote

Transportation : Waste Management Emelle, AL- $4,4250/load plus fuel surcharge when applicable.

Description of Services : Transportation and disposal of non-hazardous waste.

Printed Name/Title

Printed Name/Title

GENERAL TERMS AND CONDITIONS

1. Agreement. These General Terms and Conditions and attached Proposal (including any documentation referenced transportation, and/or management service identified on the Proposal and any applicable waste profile form(s) submitted by Customer and approved by Water ll be contingent upon execution of this Agreement and

2. Nonconforming Waste. Any waste, substance, and/or material tendered or delivered by Customer to Water Recovery (in any manner) that is not in strict conformance with the description or information on the applicable Waste Profile, as well as any substance or waste considered hazardous under any applicable federal, state, or local statute, regulation, or

3. Customer Warranties. Customer hereby represents and warrants the following: (i) the wasted tendered to or received by

Water Recovery pursuant to this Agreement is not considered Nonconforming Waste; (ii) Customer and its subcontractors (of any tier), shall comply with all applicable laws, ordinances, regulations, orders, permits, or other legal requirements executing this Agreement on behalf of another party (including but not limited to the generator of the waste) Customer represents and warrants that it has authority to bind the other party to the terms and conditions of this Agreement and if not, shall remain responsible to Water Recovery for the same.

4. Water Recovery Warranties. Water Recovery represents and warrants that it will perform the Services in a safe and workmanlike manner, consistent with reasonable industry standards, and in accordance with all applicable federal, state, and local laws, ordinances, orders, rules, and regulations.

5. Term of Agreement. This Agreement shall commence upon the effective date indicated on the Proposal and shall terminate upon the completion of Services unless otherwise terminated earlier by Water Recovery. Water Recovery may terminate this Agreement for convenience by providing Customer with thirty (30) days written notice or immediately in to timely pay any amounts owed to Water Recovery; (ii) any actual or alleged violation of any applicable federal, state, or local statute, regulation, ordinance, permit, or regulatory agency directive by Customer, its subcontractors (of any tier), or any entity or personnel whom Customer is responsible for; (iii) any attempt to or actual tender of Nonconforming Waste to Water Recovery (in any manner whatsoever); and (iv) any breach of Section 9 below.

6. Inspection/Rejection of Waste. Title to and liability of the waste shall remain with Customer and/or the generator at all discretion, it is deemed Nonconforming Waste, Wa cost and expense: (i) reject and return the waste to Customer; (ii) require Customer to remove and dispose of the Nonconforming Waste; (iii) elect to handle the Nonconforming Waste as described in Section 7 below; (iv) or any other course of action deemed necessary to comply with applicable federal, state, or local statutes, laws, regulations, ordinances, permits, or regulatory agency directives, guidance, or orders. Customer shall be responsible for any additional

-confirming Waste as set forth herein.

7. Special Handling; Nonconforming Waste. If Water Recovery elects to handle any Nonconforming Waste, Water Recovery shall have the right to manage the same in a manner deemed appropriate by Water Recovery and Customer shall be responsible for any and all related additional expenses as set forth in Section 6 above.

8. Indemnification. To the fullest extent allowable by law, the parties shall be responsible for the following allocations of liability:

a. Water Recovery. Water Recovery shall defend, indemnify, and hold harmless Customer from and against any and all related to the Services performed fault including but not limited to negligence, strict liability, breach of its warranty obligations in Section 4 above, or any other legal theory of liability attrib obligations will not apply to occurrences involving Nonconforming Waste.

Jeff Maylon/ Office Manager

b. Customer. Customer shall defend, indemnify, and hold harmless Water Recovery and its parent, subsidiary, and from and against any and all Claims arising from or related to this Agreement or the Services provided hereunder and this Agreement (including Section 3 above), or any other legal theory of liability attributable to Customer or its other subcontractors of any tier in the performance of this Agreement.

c. Waiver of Immunity. In furtherance of the foregoing indemnity obligations, Customer and Water Recovery agree to waive any immunity afforded to it under workers compensation or similar law.

9. Facility Access -loading waste in the manner directed by Water Recovery. Customer and its subcontractors (of any tier) shall comply with all rules of the facility and directions given by Water Recovery personnel. Water Recovery may revoke or deny Customer (or its subcontractors of any tier) access to the facility in the event Customer, or its subcontractors (of any tier), fail to follow any such directives, rules, or regulations, and Water Recovery shall not be responsible for any expenses related to such removal.

10. Charges and Payments. Payment to Water Recovery shall be deemed earned as Services are performed and Customer shall make payment to Water Recovery without offset or deduction the earlier of: (i) the payment term indicated on the Proposal or (ii) if no payment term is expressl invoice. Late payments shall earn interest at the rate of 1.5% per month, or the maximum amount permitted by law, whichever is less. Customer shall be responsible for and shall reimburse Water Recovery for any and all costs and

11. Consequential Damages. Neither party shall be responsible for any consequential, incidental, punitive, or special damages whatsoever (including but not limited to, business interruption, extra expense, loss of use of any property, or delay) arising out of or relating to the Services and/or this Agreement, howsoever caused and regardless of whether the same results from the negligence of a party, or otherwise and even if the possibility of such was or could have been foreseeable.

Force Majuere. Except for the obligation to make payments hereunder, neither party shall be in default for its failure to perform or delay in performance caused by events beyond its reasonable control, including, but not limited to, strikes, riots, imposition of laws or governmental orders, fires, acts of God, and inability to obtain equipment, and the affected party shall be excused from performance during the occurrence of such events

12. Counterparts and Facsimile Signatures. This Agreement may be executed in two or more counterparts, each of which will be deemed an original and all of which together will constitute the same agreement. Facsimile or email signatures and/or acknowledgement and acceptance shall be considered valid.

13. Severability. The partial or complete invalidity of any one or more provisions of this Agreement shall not affect the validity or continuing force and effect of any other provision. If any provision is invalid, in whole or in part, the balance of the provisions shall be considered reformed to reflect the intent of the parties to the greatest extent possible consistent with applicable law.

Governing Law, Venue and Legal Fees. The interpretation and performance of this Agreement shall be governed by the laws of the state of Florida which the Services are performed and any litigation or dispute arising in connection with this Agreement shall be settled by arbitration administered by the American Arbitration Association in accordance with its commercial arbitration rules, and judgment on the award entered by the arbitrator(s) may be entered into any court having jurisdiction thereof. The substantially prevailing party shall be entitled to its legal fees and costs with respect to any litigation or dispute arising pursuant to this Agreement.

14. Entire Agreement, Neutral Construction and Headings. This Agreement constitutes the entire agreement between the parties and expressly supersedes and negates any prior or contemporaneous agreements, whether written or oral. This Agreement may not be modified or amended except by a writing signed by both parties. The parties agree that each has had the opportunity to review the terms of this Agreement and to request any desired changes or clarifications and this Agreement shall be construed neutrally, and as the commemoration of the mutual assent of both parties, rather than for or against either party. The title of this Agreement and headings used herein are for reference only and shall not be construed to give any substantive meaning.

2025 10-27 Proposal Project No. 24059.01.02

October 27, 2025

Shekhar Melkote, P.G.

Senior Consultant Geosyntec Consultants, Inc.

(Vía email: SMelkote@Geosyntec.com)

Re: Professional Surveying Services Former Rucks Park North Miami, Florida

Engenuity Group Project No. 24059.01.02

Dear Mr. Melkote:

We are pleased to offer this proposal to render professional surveying services in connection with Former Rucks Park located at 13760-13780 NE 5th Avenue, North Miami, FL (Folio Number 06-2219-000-1620) (hereinafter called the ‘Project’).

Surveying Services Engenuity Group, Inc. will horizontally and vertically locate four (4) monitoring well locations (MW-12R, MW-17R, MW-19R & MW-56) as depicted on the attached graphic labeled in red, which was provided by your office. Additionally, we will horizontally and vertically locate four (4) sampling points which will be flagged in the field prior to of site visit. The monitoring wells and sampling points will provide X-Cartesian coordinates, Y-Cartesian coordinates, ground elevations and top-of-casing elevations. All elevations will be obtained in National American Vertical Datum of 1988 (NAVD 88). Lastly, we will horizontally locate the five (5) fence corners along the Western boundary of the property. X-Cartesian coordinates, Y- Cartesian coordinates will be provided to you in the report.

Surveying Services Fee: $2,825.00

The final deliverable will be an electronically signed and sealed copy of the Surveyors Report, which can be provided within twenty (20) business days of receiving authorization to proceed.

Permit Fees, Reproduction Charges and Reimbursable Expenses The Total Contract Price does not include the payment of any governmental agency submittal or processing fees. The cost of these fees and any costs incurred by the office for printing, reproduction and other reimbursable expenses such as postage, travel, and document copy charges will be billed to the client monthly.

Invoicing and Payment Work will be invoiced on a monthly basis for work completed to date. Invoice shall be paid in full by the Client within thirty (30) days of the invoice date, unless within such thirty (30) day period, Client notifies Engenuity Group, Inc. in writing of its objection to the amount of said invoice. Such notice shall be accompanied by payment of any undisputed portion of said invoice. If written objection is not received within thirty (30) days it shall constitute approval of invoice by Client. If the payment is not received within fifteen (15) days of billing date, a late charge will be added to the invoice in the amount of 1½ percent per month on the outstanding balance. If payment is not received within sixty (60) days of the invoice date, work may be suspended on the project until the outstanding invoice(s) are paid in full.

This proposal represents the entire understanding between you and us with respect to the Project. If this satisfactorily sets forth your understanding of our agreement, please execute the attached Authorization and return it to us. If you have any questions, please do not hesitate to contact us.

PURSUANT TO SECTION 558.0035 FLORIDA STATUTES, THE CONSULTANT IS THE

RESPONSIBLE PARTY FOR THE PROFESSIONAL SERVICES IT AGREES TO PROVIDE UNDER

THIS CONTRACT. NO INDIVIDUAL PROFESSIONAL EMPLOYEE, AGENT, DIRECTOR,

OFFICER OR PRINCIPAL MAY BE INDIVIDUALLY LIABLE FOR NEGLIGENCE ARISING

OUT OF THIS CONTRACT, AS LONG AS THE CONSULTANT MAINTAINS THE

PROFESSIONAL LIABILITY INSURANCE REQUIRED UNDER THIS CONTRACT AND AS

LONG AS ANY DAMAGES ARE SOLELY ECONOMIC IN NATURE AND THE DAMAGES

DO NOT EXTEND TO PERSONAL INJURIES OR PROPERTY NOT SUBJECT TO THIS

CONTRACT.

Sincerely, Approved by, Jennifer Malin, P.S.M. Andre Rayman, P.S.M.

Director of Surveying President

Graphic

File details come from the government source that posted it. Updated .