Attachment 4 - Blank IGE.xlsx
XLSX spreadsheet 52 KB Posted
- Attached to
- Replace Chapel Windows B912
- Solicitation number
- FA480326Q0040
About this file
This is a blank Independent Government Estimate (IGE) template in spreadsheet format for the Chapel Windows B912 repair project at Shaw Air Force Base. The template is structured to capture detailed cost information for the window replacement construction work, organized by line items with columns for material costs, labor costs, direct costs, and line totals. The estimate includes nine primary work activities: demolition of standard windows, demolition of stained glass window frames, replacement of standard windows, installation of curtain wall and stained glass, installation of flashing, repointing masonry, repair and painting of walls, dumpster rental, and lift rental, along with supervision costs including project manager and project superintendent oversight. Cost data sources referenced include historical reference numbers (VLSB 24-0062, VLSB 24-0077, VLSB 25-0023), RSMeans construction cost databases, and the United Rentals website for equipment rental pricing.
The template requires contractors to populate unit pricing, quantities, and cost breakdowns, with provisions for calculating overhead and profit percentages to arrive at a total contract price. This blank IGE form is mandated for use by all offerors responding to solicitation FA480326Q0040, a 100% Small Business Concern Set Aside under NAICS code 236220 for the Air Force. Quotes utilizing this attachment must be submitted to SSgt Motaz Irshid or Ms. Sarah Nieves by 8 May 2026 at 10:00 A.M. EST. The project scope is limited to 60 calendar days after receipt of Notice to Proceed, with mandatory site visit attendance required on 15 April 2026 at Building 912, Shaw AFB, South Carolina.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 (NEW)
| CUI | ||||||||
| Project: | Repair Windows Chapel B912 | James Sawyer | ||||||
| Location: | Shaw AFB | 20 CES | ||||||
| Contractor: | ||||||||
| Address: | ||||||||
| PR No.: | VLSB 25-0023 | |||||||
| CUI | ||||||||
| Reference | Line No. | Item | Unit of Measure | Quantity | Material Costs | Labor Costs | Direct Cost | Line Total |
| VLSB 24-0062 | 1 | Demo Standard Window | SF | ||||
| VLSB 24-0077 | 2 | Demo Frame of Stained Glass Windows | SF | ||||
| VLSB 24-0062 | 3 | Replace Standard Window | SF | ||||
| VLSB 24-0077 | 4 | Install Curtain Wall and Stained Glass | SF | ||||
| VLSB 24-0062 | 5 | Install flashing | Ea | ||||
| RSMeans 040120200320 | 6 | Repoint Masonry | SF | ||||
| RSMeans 099123721240 | 7 | Repair / Paint Wall | SF | ||||
| RSMeans 024119190725 | 8 | Dumpster Rental | Wk | ||||
| United Rentals Website | 9 | Lift Rental | Mo | ||||
| SUPERVISION | |||||||
| 22-0063 plus 20% | 10 | Project Manager | days | ||||
| 22-0063 plus 20% | 11 | Project Superintendant | days | ||||
| Totals: | $0.00 | $0.00 | $0.00 | $0.00 |
| Material Cost: | $0.00 |
| Labor Cost: | $0.00 |
| Direct Cost: | $0.00 |
| Total Line Item Cost: | $0.00 |
| Overhead: | % | |
| Subtotal: | $0.00 |
| Profit: | % |
| Subtotal: |
| Bond: | % |
| Total Contract Price: |
File details come from the government source that posted it. Updated .