33 05 05.36 - Vacuum Testing.pdf

PDF 215 KB Posted

Attached to
Contract 2026-01: Sewer Maintenance & Emergency Contract
Solicitation number
Not on record
Issued by
Lancaster County, Pennsylvania

About this file

This is a technical specification document for vacuum testing of sanitary sewers prepared by Herbert, Rowland & Grubic, Inc., applicable to the Borough of Elizabethtown's sanitary sewer improvement projects in Pennsylvania. The specification establishes requirements for vacuum testing of all newly installed manholes and existing manholes where new sewer mains connect, with testing to be performed in accordance with ASTM C1244 standards. The testing procedure requires equipment including a vacuum pump, vacuum tester base with compression band seal, shutoff valve, calibrated vacuum gauge (to 0.1 in. Hg), stopwatch, and plugs. Test duration varies by manhole diameter: 60 seconds for 4-foot diameter, 75 seconds for 5-foot diameter, and 90 seconds for 6-foot diameter structures. The specification requires contractors to submit testing procedures, equipment lists, testing sequence schedules, and gauge calibration certificates prior to initiating testing, with final test and evaluation reports documenting all results.

The specification establishes an acceptance criterion whereby a manhole passes testing if the vacuum drop does not exceed 1 inch of mercury during the prescribed test period. Contractors must repair both interior and exterior joints to ensure permanent seals and repair any visible leaks regardless of leakage quantity. All joints must be repaired and sealed prior to testing with the manhole frame in place and backfilled. If vacuum drop exceeds 1 inch of mercury, the contractor is obligated to identify and correct the causes, complete repairs, and retest the manhole until successful results are achieved. No pricing, funding sources, or contract terms are specified in this technical specification document.

View the file

Other files

File Type Posted
33 31 00 - Sanitary Sewerage Piping.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 26 13-1- RFI Form.pdf PDF
01 22 00 - Unit Prices.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
33 05 61 - Concrete Manholes and Inlets.pdf PDF
01 42 00 - References.pdf PDF
33 05 97 - Identification and Signage for Utilities.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
01 78 36 - Warranties.pdf PDF
03 60 00 - Grouting.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
03 30 00 - Cast-in-Place Concrete.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 63 63 - Change Order Form.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
31 23 23 - Fill.pdf PDF
32 92 19 - Seeding.pdf PDF
Maintenance & Emergency Construction Details.pdf PDF
32 17 23 - Pavement Markings.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 62 76 - Contractor's Application for Payment.pdf PDF
00 31 43 - Permit Applications.pdf PDF
00 01 10 - Table of Contents.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
31 23 16 - Excavation.pdf PDF
00 60 00 - Project Forms.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
00 63 13 - RFI Form.pdf PDF
31 23 19 - Dewatering.pdf PDF
31 05 16 - Aggregates For Earthwork.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
33 01 30.11 - Television Inspection Of Sewers.pdf PDF
31 05 19.13 - Geotextiles For Earthwork.pdf PDF
31 10 00 - Site Clearing.pdf PDF
33 31 23 - Sanitary Sewerage Pressure Piping.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
01 10 00 - Project Summary.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
03 10 00 - Concrete Forming and Accessories.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
01 26 13 - Request for Interpretation.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
Show 40 more

Latest 50 of 77 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

33 05 05.36 - VACUUM TESTING

Herbert, Rowland & Grubic, Inc. 33 05 05.36 - 1 000598.0465

SECTION 33 05 05.36 - VACUUM TESTING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes: Vacuum testing of manholes.

B. Related Requirements:

1. Section 33 05 61 – Concrete Manholes: Requirements for sewage manholes.

2. Section 33 31 00 - Sanitary Sewerage Piping: Pipe materials, manholes, and accessories normally encountered with gravity sewerage piping.

1.2 REFERENCE STANDARDS

A. ASTM International:

1. ASTM C1244 - Standard Test Method for Concrete Sewer Manholes by the

Negative Air Pressure (Vacuum) Test Prior to Backfill.

1.3 SUBMITTALS

A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.

B. Submit following items prior to start of testing:

1. Testing procedures.

2. List of test equipment.

3. Testing sequence schedule.

4. Certification of test gauge calibration.

C. Test and Evaluation Reports: Indicate results of manhole tests.

1.4 REQUIREMENTS

A. Vacuum Testing shall be performed to all installed manhole(s).

B. Vacuum Testing shall be performed for all existing manhole(s) where new sewer mains are being connected to.

C. The Contractor shall determine and correct the causes of testing failure and retest until successful test results are achieved.

PART 2 - PRODUCTS

2.1 VACUUM TESTING

A. Equipment:

1. Vacuum pump.

2. Vacuum line.

3. Vacuum Tester Base:

33 05 05.36 - VACUUM TESTING

Herbert, Rowland & Grubic, Inc. 33 05 05.36 - 2 000598.0465

a. Compression band seal.

b. Outlet port.

4. Shutoff valve.

5. Stopwatch.

6. Plugs.

7. Vacuum Gauge: Calibrated to 0.1 in. Hg.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Section 01 73 00 - Execution Requirements: Requirements for installation examination.

B. Verify that manholes are ready for testing.

C. Verify that manholes are backfilled.

3.2 FIELD QUALITY CONTROL

A. Section 01 40 00 - Quality Requirements: Requirements for inspecting and testing.

B. Manhole Testing:

1. Repair both outside and inside of joint to ensure permanent seal.

2. Test manholes with manhole frame set in place.

3. Vacuum Testing:

a. Comply with ASTM C1244.

b. Plug pipe openings; securely brace plugs and pipe.

c. Inflate compression band to create seal between vacuum base and structure.

d. Connect vacuum pump to outlet port with valve open, then draw vacuum to 10 in. Hg.

e. Close valve.

f. Manhole Test Duration in Seconds:

1) Manhole Diameter of 4 Feet: 60.

2) Manhole Diameter of 5 Feet: 75.

3) Manhole Diameter of 6 Feet: 90.

g. Record vacuum drop during test period.

h. If vacuum drop of 1 in. Hg does not occur during testing period, manhole is acceptable; discontinue testing.

i. If vacuum drop is greater than 1 in. Hg during testing period, repair and retest manhole

j. If after repair vacuum test fails to meet 1-in. Hg drop during testing period, repair and retest manhole.

4. If unsatisfactory testing results are achieved, repair manhole and retest until result meets criteria.

5. Repair visible leaks regardless of quantity of leakage.

END OF SECTION