01 31 19 - Project Meetings.pdf
PDF 206 KB Posted
- Solicitation number
- Not on record
- Issued by
- Lancaster County, Pennsylvania
About this file
This is a specification document for Project Meetings procedures prepared by Herbert, Rowland & Grubic, Inc. for the Borough of Elizabethtown's sanitary sewer infrastructure projects in Pennsylvania. The document establishes protocols for managing project progress meetings, including a mandatory project starting meeting to be scheduled by the Owner or Engineer following contract award to establish work progress schedules, partial payment schedules, and work operation sequences. The specification permits the Owner or Engineer to schedule additional meetings upon request from any contract party, with written notice of date, time, place, and agenda provided to all parties. Each party to the contract must be represented at meetings by authorized personnel with decision-making authority whose commitments bind their respective organizations. The document stipulates that once procedures, work sequences, time schedules, and other matters are agreed upon by all concerned parties during these meetings, they become binding obligations that all parties must follow and comply with regarding both timing and performance standards.
The specification establishes that contractors cannot claim delays or damages if they fail to comply with agreed-upon procedures, sequences of operations, and time schedules established during project meetings. This provision protects the Owner and Engineer by ensuring that contractors cannot seek compensation for delays that result from their own non-compliance with mutually agreed meeting determinations. The document contains no pricing terms, set-asides, or funding information, as it functions solely as a procedural specification for contract administration and project management protocols rather than as a bid solicitation or contract award notice.
View the file
Other files
Show 40 more
Latest 50 of 77 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 31 19 - PROJECT MEETINGS
Herbert, Rowland & Grubic, Inc. 01 31 19 - 1 000598.0465
SECTION 01 31 19 - PROJECT MEETINGS
PART 1 - GENERAL
1.1 PROGRESS MEETINGS
A. Project Starting Meeting: For projects other than emergencies, a project starting meeting may be held for the purpose of establishing the work progress schedule, the progress payment (Partial Payments) schedule, and to arrive at an orderly sequence of work operations agreeable to the parties of the Contract:
1. The Owner or the Engineer shall set the date, time and place of the project starting meeting following the award of Contract.
B. Scheduling Additional Meetings: In addition to the project starting meeting, the Owner or the Engineer may schedule a meeting when requested by any party to the Contract. The Owner or the Engineer will give to each party written notice of the date, time and place, and agenda of each such scheduled meeting:
1. Such meetings shall serve to resolve conflicts, adjust work arrangements, etc., so that work stoppages and delays may be avoided.
C. Meeting Representation: Each party to the Contract shall be represented at such meetings by a person or persons vested with the authority to make necessary decisions on their behalf, and such decisions shall commit that party to the agreed procedures, sequence of operations and time schedules.
D. Determinations: Where procedures, sequence of operations, time schedules and other matters have been agreed upon by each party concerned, it shall become binding upon each party to follow and comply with said procedures, sequence of operations, time schedules, and other matters, both as to time and performance, and no claim of delay or damages by the Contractor if he fails to comply therewith will be entertained by the Owner.
PART 2 - PRODUCTS - Not Used.
PART 3 - EXECUTION – Not Used.
END OF SECTION