Project Record Documents Specification

This is a technical specification document (Section 01 78 39) for Project Record Documents prepared by Herbert, Rowland & Grubic, Inc. for the Borough of Elizabethtown's sanitary sewer improvements project (Project No. 000598.0465). The specification establishes requirements for maintaining comprehensive project records throughout construction, including one on-site set of work orders, drawings, specifications, addenda, change orders, shop drawings, product data, samples, and manufacturer instructions. Record information must be documented concurrently with construction progress, updated no less than weekly, and maintained separately from construction documents. Record drawings must accurately mark actual installation conditions using red-colored erasable pencil, with particular emphasis on concealed elements, dimensional changes, utility locations (including depth and triangulation measurements), equipment locations, internal utility routing, and schematic information converted to as-built conditions. Marked-up record documents and new drawings where required must be organized into manageable, durably bound sets with proper identification and cross-referencing between contract and shop drawings. All record drawings must be identified with the designation "PROJECT RECORD DRAWING," dated, and stamped with the contractor's name while the engineer's title block and seal are removed.

Contractors must submit PDF electronic files of all marked-up documents and miscellaneous records to the engineer with the final application for payment. Miscellaneous record submittals include material and equipment test and inspection reports, delivery slips, and other records required by individual specification sections. The specification requires entries to be complete and accurate to enable future owner reference, with particular attention to recording information before concealed installations are enclosed. New record drawings must be prepared when neither contract drawings nor shop drawings can adequately depict actual installation conditions, particularly when change orders result from accepted alternates, substitutions, or other modifications to the original contract documents.

View the file

Other files

File Type Posted
33 31 00 - Sanitary Sewerage Piping.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 26 13-1- RFI Form.pdf PDF
01 22 00 - Unit Prices.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
33 05 61 - Concrete Manholes and Inlets.pdf PDF
01 42 00 - References.pdf PDF
33 05 97 - Identification and Signage for Utilities.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
01 78 36 - Warranties.pdf PDF
03 60 00 - Grouting.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
03 30 00 - Cast-in-Place Concrete.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 63 63 - Change Order Form.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
31 23 23 - Fill.pdf PDF
32 92 19 - Seeding.pdf PDF
Maintenance & Emergency Construction Details.pdf PDF
32 17 23 - Pavement Markings.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 62 76 - Contractor's Application for Payment.pdf PDF
00 31 43 - Permit Applications.pdf PDF
00 01 10 - Table of Contents.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
31 23 16 - Excavation.pdf PDF
00 60 00 - Project Forms.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
00 63 13 - RFI Form.pdf PDF
31 23 19 - Dewatering.pdf PDF
31 05 16 - Aggregates For Earthwork.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
33 01 30.11 - Television Inspection Of Sewers.pdf PDF
31 05 19.13 - Geotextiles For Earthwork.pdf PDF
31 10 00 - Site Clearing.pdf PDF
33 31 23 - Sanitary Sewerage Pressure Piping.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
01 10 00 - Project Summary.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
03 10 00 - Concrete Forming and Accessories.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
01 26 13 - Request for Interpretation.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
Show 40 more

Latest 50 of 77 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 78 39 – PROJECT RECORD DOCUMENTS

Herbert, Rowland & Grubic, Inc. 01 78 39 - 1 000598.0465

SECTION 01 78 39 - PROJECT RECORD DOCUMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes

1. Project record documents.

2. Miscellaneous Record Submittals

B. Related Sections

1. Individual Sections for specific requirements for Project Record Documents of the

Work in those Sections.

1.2 PROJECT RECORD DOCUMENTS

A. Maintain on Site one set of the following record documents; record actual revisions to the Work:

1. Work Order/Drawings.

2. Specifications.

3. Addenda.

4. Change Orders and other modifications to the Contract.

5. Reviewed Shop Drawings, product data, and Samples.

6. Manufacturer's instruction for assembly, installation, and adjusting.

B. Ensure entries are complete and accurate, enabling future reference by Owner.

C. Store record documents separate from documents used for construction.

D. Record information concurrent with construction progress, not less than weekly.

E. Specifications: Legibly mark and record, at each product Section, description of actual products installed, including the following:

1. Manufacturer's name and product model and number.

2. Suppliers name and contact.

3. Product substitutions or alternates used.

4. Changes made by Addenda and modifications.

F. Record Drawings: Maintain one set of the Contract Drawings and Shop Drawings:

1. Preparation: Mark Drawings to show the actual installation. Require individual or entity who obtained record data to prepare the marked-up Record Prints:

a. Give particular attention to information on concealed elements that would be difficult to identify or measure and record later.

b. Accurately record information in an understandable drawing technique.

c. Record data as soon as possible after obtaining it. Record and check the markup before enclosing concealed installations.

2. Content: Types of items requiring marking include, but are not limited to, the following:

Herbert, Rowland & Grubic, Inc. 01 78 39 - 2 000598.0465

a. Dimensional changes to Drawings.

b. Revisions to details shown on Drawings.

c. Depths of foundations in relation to plant datum.

d. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements:

1) Depth of buried utility lines.

2) Dimension distances from permanent facility components that are parallel to utilities.

3) Dimension ends, corners, and junctions of buried utilities to permanent facility components using triangulation.

4) Identify and locate existing buried or concealed items encountered during Project.

e. Revisions to electrical circuitry.

f. Actual equipment locations.

g. Locations of concealed internal utilities.

h. Changes made by Addendum, Change Order or Work Order.

i. Details not on the original Contract Drawings.

j. Field records for variable and concealed conditions.

k. Record information on the Work that is shown only schematically.

3. Mark the Contract Drawings or Shop Drawings, whichever is most capable of showing actual physical conditions, completely and accurately. If Shop Drawings are marked, show cross-reference on the Contract Drawings.

4. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at same location.

5. Mark important additional information that was either shown schematically or omitted from original Drawings.

6. Note Addendum numbers, Work Order numbers, Change Order numbers, and similar identification, where applicable.

7. Prepare new Drawings where neither the Contract Drawings nor Shop Drawings are not suitable to show actual installation:

a. New Drawings may be required when a Change Order is issued as a result of accepting an alternate, substitution, or other modification.

8. Format: Identify and date each Record Drawing; include the designation

"PROJECT RECORD DRAWING" in a prominent location:

a. Cross out Engineer's title block and seal from all sheets and stamp all sheets with name of Contractor.

b. Record Drawings: Organize Record Drawings into manageable sets. Bind each set with durable paper cover sheets. Include identification on cover sheets.

G. Submit PDF electronic files of marked-up documents to Engineer with claim for final Application for Payment.

1.3 MISCELLANEOUS RECORD SUBMITTALS

A. Assemble miscellaneous records required by other Sections. Bind or file miscellaneous records and identify each. Miscellaneous records include the following:

1. Material and equipment test and inspection reports.

Herbert, Rowland & Grubic, Inc. 01 78 39 - 3 000598.0465

2. Equipment and material delivery slips.

PART 2 - PRODUCTS - Not Used.

PART 3 - EXECUTION - Not Used.

END OF SECTION