01 10 00 - Project Summary.pdf

PDF 245 KB Posted

Attached to
Contract 2026-01: Sewer Maintenance & Emergency Contract
Solicitation number
Not on record
Issued by
Lancaster County, Pennsylvania

About this file

Project Summary for Sewer Maintenance & Emergency Contract

This is a project summary document prepared by Herbert, Rowland & Grubic, Inc., for the Borough of Elizabethtown, Pennsylvania, detailing Contract 2026-01 for Sewer Maintenance & Emergency Services. The project encompasses repairs to the Borough's existing sanitary sewer and storm sewer collection and conveyance systems, with work performed through individual Work Orders issued by the Owner. Work includes both emergency response and maintenance assignments, such as repairs to address sewer collapses, force main breakdowns, sinkholes, and other serious utility system occurrences. The contract operates on a task-order basis, with the Owner determining the scope and extent of permanent restoration work through field investigations. The Owner's Representative is Jeff Kinsey, Public Works Director, located at 600 South Hanover Street, Elizabethtown, PA 17022. Sealed bids were due June 16, 2026, at 10:00 AM local time through PennBid. No mandatory pre-bid conference is scheduled for this contract. Bid security is required in the form of a Certified Check or Bid Bond in an amount not less than 10%.

The contractor must maintain existing wastewater and storm water service during all repair operations using bypass facilities as specified. Emergency work requires the contractor to respond to telephonic notification from the Owner, followed by written confirmation within 24 hours, and to deploy temporary measures at the contractor's discretion to control leakages and provide continued system service. All work must comply with Pennsylvania Department of Environmental Protection and Pennsylvania Department of Transportation requirements where applicable. The contractor is responsible for traffic control, dust management, public relations, protection of existing infrastructure, and notification of local emergency services and school districts. Material selections and methods for temporary emergency measures are at the contractor's discretion, though permanent restoration materials must conform to contract specifications. Standard Detail Drawings provided in the Project Manual serve as typical illustrations but are not exact representations of site conditions encountered.

View the file

Other files

File Type Posted
33 31 00 - Sanitary Sewerage Piping.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 26 13-1- RFI Form.pdf PDF
01 22 00 - Unit Prices.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
33 05 61 - Concrete Manholes and Inlets.pdf PDF
01 42 00 - References.pdf PDF
33 05 97 - Identification and Signage for Utilities.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
01 78 36 - Warranties.pdf PDF
03 60 00 - Grouting.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
03 30 00 - Cast-in-Place Concrete.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 63 63 - Change Order Form.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
31 23 23 - Fill.pdf PDF
32 92 19 - Seeding.pdf PDF
Maintenance & Emergency Construction Details.pdf PDF
32 17 23 - Pavement Markings.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 62 76 - Contractor's Application for Payment.pdf PDF
00 31 43 - Permit Applications.pdf PDF
00 01 10 - Table of Contents.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
31 23 16 - Excavation.pdf PDF
00 60 00 - Project Forms.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
00 63 13 - RFI Form.pdf PDF
31 23 19 - Dewatering.pdf PDF
31 05 16 - Aggregates For Earthwork.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
33 01 30.11 - Television Inspection Of Sewers.pdf PDF
31 05 19.13 - Geotextiles For Earthwork.pdf PDF
31 10 00 - Site Clearing.pdf PDF
33 31 23 - Sanitary Sewerage Pressure Piping.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
03 10 00 - Concrete Forming and Accessories.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
01 26 13 - Request for Interpretation.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
Show 40 more

Latest 50 of 77 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 10 00 – PROJECT SUMMARY

Herbert, Rowland & Grubic, Inc. 01 10 00-1 000598.0465

SECTION 01 10 00 – PROJECT SUMMARY

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Project information.

2. Work covered by Contract Documents.

3. Work by Owner.

4. Work under Separate Contracts.

5. Drawings.

6. Access to site.

7. Hazardous Environmental Conditions.

8. Work Restrictions.

9. Project Conditions.

10. Scheduling Operations.

11. Intent of Contract Documents.

B. Related Requirements:

1. Section 01 50 00 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1.2 PROJECT INFORMATION

A. Project Identification: Sewer Maintenance & Emergency Contract: Contract No. 2026-01.

1. Project Location: Borough of Elizabethtown, PA.

B. Owner: Borough of Elizabethtown, 600 South Hanover Street, Elizabethtown, PA 17022.

1. Owner's Representative:

a. Jeff Kinsey, Public Works Director, (717) 367-1700.

C. Engineer: Herbert, Rowland & Grubic, Inc., 369 East Park Drive, Harrisburg, PA 17111.

1.3 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and consists of the following:

1. Project generally includes, but is not limited to, repairs to the Borough’s existing sanitary sewer and storm sewer collection and conveyance systems, upon issuance of Work Order(s) by the Borough.

B. Work Orders: The Work of this Contract shall be performed in segments of work, as determined by the Owner, through the issuance of individual Work Orders. The Work Order Form is included in Section 00 63 36:

1. The types of work to be performed will be as stated above, and as specified in detail throughout the appropriate Specification Sections of this Project Manual.

2. The extent of the permanent restoration work to be performed will be as derived by the Owner from actual field investigations and determinations. All pavement restoration work shall conform to municipal and PennDOT requirements. The

Herbert, Rowland & Grubic, Inc. 01 10 00-2 000598.0465 permanent restoration work will be performed through the issuance of individual Work Orders.

3. The Owner will "mark out" the extent of the permanent restoration work in the field. The Contractor shall not proceed with the Work until he has made a timely request of the Owner to "mark out" the extent of work.

a. The Contractor will request the PA One Call "mark-out" to be made over the entire run from manhole to manhole or structure to structure to avoid re-calls in the case of multiple permanent restorations within any one run of piping.

C. Emergency Work: Without intending to limit or restrict the extent of Work required under emergency assignments required as part of the Contract, the Work to be performed to bring a serious situation or occurrence under control (such as a sewer collapse, force main breakdown, sinkhole, etc.) by temporary measures, shall be according to the following:

1. The temporary measures shall include the means and methods at the

Contractor's discretion to both stop wastewater or storm water leakages or accidental discharges, and to provide for a fail-safe (and properly sized) temporary means of continued system service.

a. The selections of equipment from those listed in the Bid Form, as required to perform the temporary measures, are the sole responsibility of the Contractor.

b. The types of materials required to perform the temporary measures shall be as dictated by the conditions of the emergency, except in those instances where the temporary measures are of materials consistent with the requirements for permanent restoration work. In such instances, the materials shall conform to the appropriate Specifications Sections of this Project Manual.

c. The work of the temporary measures shall also include the required emergency traffic control, including the involvement of the local police department as needed to control traffic.

2. Following the bringing under control of the serious situation or occurrence, the extent of the permanent restoration work to be performed will be as derived by the Owner from actual field investigations and determinations.

3. Emergency Notification/Response: Emergency Work constitutes bringing a serious situation or occurrence in existing utility systems under control, when called upon to do so by the Owner.

a. Emergency Notification: In the case of an emergency, telephonic notification to the Contractor for response will come from the Owner or designated authorized representative. The telephonic notification will be followed by written confirmation within 24 hours.

b. Response: Following notification, the Contractor shall initiate emergency response action in accordance with Section 00 52 00 – Agreement Between Owner and Contractor for Construction Contract.

D. Maintenance Work: Without intending to limit or restrict the extent of Work required under maintenance assignments required as part of the Contract, maintenance

Herbert, Rowland & Grubic, Inc. 01 10 00-3 000598.0465 assignments shall include repair or replacement of the Owner’s utilities in accordance with the Contract.

1.4 WORK BY OWNER

A. General: Cooperate fully with Owner so work may be carried out smoothly, without interfering with or delaying work under this Contract or work by Owner. Coordinate the Work of this Contract with work performed by Owner.

B. Summary of Owner Work: Owner shall inspect each lateral prior to replacement.

Contractor shall coordinate their Contract Work with the Owner.

1.5 WORK UNDER SEPARATE CONTRACTS

A. Owner may complete associated work under this contract and Work Orders under separate contracts. Contractor shall cooperate fully with separate contractors so that work on those contracts may be carried out smoothly, without interfering with or delaying work. Coordinate the Work of this Contract with Work performed under separate contracts.

1.6 DRAWINGS

A. Standard Detail Drawings: In general, the Standard Detail Drawings, as bound at the back of this Project Manual, cover the Work to be performed. These referenced detail drawings are hereby made part of this Contract:

1. The Standard Detail Drawings are illustrations of typical conditions and may not be exact representations of the conditions encountered under the Work of this Contract.

B. Informational Drawings and Specifications: The Drawings and associated Specifications for particular items of work ordered by the Owner may be issued to the Contractor by the Engineer. Such Drawings and Specifications, when issued, will become a part of the Contract Documents.

C. Exhibits and Maps: GIS mapping of the Owner’s wastewater and stormwater systems may be available.

1.7 ACCESS TO SITE

A. Use of Site: Do not disturb portions of Project site beyond areas in which the Work is indicated:

1. Limits: Confine construction operations areas where work is being completed.

2. Driveways, Walkways and Entrances: Keep driveways, loading areas, and entrances serving premises clear and available to Owner, Owner's employees, Herbert, Rowland & Grubic, Inc. 01 10 00-4 000598.0465 and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances by construction operations.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

B. Cleaning:

1. Continuously keep rights-of-way, storage areas, streets, roads, highways and adjacent properties free from accumulations of waste materials, excess excavation, rubbish and windblown debris resulting from construction operations.

2. Broom or water clean paved surfaces and remove surplus materials, tools, construction equipment and machinery as each work area is completed.

C. Protection:

1. Contractor shall make every effort to protect and avoid damage within the work area. Prior to the commencement of construction, the Contractor, Owner, and Engineer's representatives will meet to identify special needs and desires.

2. Contractor shall make every effort to protect and avoid damage to trees or shrubbery within the work area that are not designated for removal. Prior to the commencement of construction, the Contractor, Owner, and Engineer's representatives will meet to identify special needs and desires. The Contractor can anticipate that certain trees will be tagged for preservation.

3. The Contractor shall adequately close and/or protect all excavations, equipment, and materials stored within the site of the project.

4. It shall be the responsibility of the Contractor not to interfere with or create any hazards to traffic. No equipment or material will be stored or permitted to stand where traffic must be maintained. It shall be the responsibility of the Contractor to control dust on all roads, drives, walkways, and parking areas on which traffic is being maintained.

5. The Contractor shall take special care and attention and be responsible for the protection of all existing equipment located throughout the Project area. The Contractor shall immediately notify both the Owner, Engineer, and any authority having jurisdiction should a spill or other incident occur that may cause damage to adjacent structure, infrastructure, natural resource, etc.

D. Public Relations:

1. Contractor's attention is directed to the fact that, in the eyes of the general public, his conduct and attitude will be closely associated with that of the Owner.

Accordingly, where operations of the Contractor require personal contact with the public, the Contractor and all his employees shall conduct themselves in a courteous and respectful manner. Any violation of this section shall be considered sufficient cause for the Owner to order discharge of the employee involved, and he shall not be employed again on the work without written permission from the Owner.

2. Contractor shall use all means necessary to control dust on and near the work, including off-site borrow and stockpile areas if such dust is caused by the Contractor's operations. Thoroughly moisten all surfaces as required to prevent

Herbert, Rowland & Grubic, Inc. 01 10 00-5 000598.0465 dust from being a nuisance to the public, neighbors, and concurrent performance of other work on the site.

3. In carrying out the work, the Contractor shall interfere as little as possible with traffic. The Contractor shall provide and maintain ingress and egress for all residents along the construction route.

4. Contractor shall be responsible for notifying all local emergency services, school districts, and other public agencies with regard to control and maintenance of traffic in the work area.

5. The Contractor shall obey and follow all posted speed limits.

1.8 HAZARDOUS ENVIRONMENTAL CONDITION

A. The Contractor shall complete any mitigation in accordance with all local, state and federal laws and regulations.

1.9 WORK RESTRICTIONS

A. Work Restrictions, General: Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.

B. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

1. Notify Engineer and Owner not less than 2 days in advance of proposed utility interruptions.

2. Obtain Owner's written permission before proceeding with utility interruptions.

C. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.

D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor-air intakes.

E. By-pass pumps, hoses, and piping not used, must be removed from rights-of-way within

48 hours of last use.

1.10 PROJECT CONDITIONS

A. Conduct work in complete compliance with all of the rules, regulations and requirements of the Pennsylvania Department of Environmental Protection (DEP).

B. Conduct work in complete compliance with all of the rules, regulations and requirements of the Pennsylvania Department of Transportation (PennDOT), where applicable.

1.11 SCHEDULING OPERATIONS

Herbert, Rowland & Grubic, Inc. 01 10 00-6 000598.0465

A. Work Restrictions; Existing Sewers: The Contractor shall at all times during the Contract Time maintain the existing wastewater and storm water service and flow where repair work is being performed on existing facilities:

1. By-Pass Facilities: As specified in the Contract Documents.

1.12 INTENT OF CONTRACT DOCUMENTS

A. The intent and meaning of the Contract Documents is that the Contractor, under the terms of the Contract, will take such action as necessary and/or required to provide labor, supervision, plant, materials, supplies, equipment, power, transportation, facilities, etc., whether temporary or permanent, which are indicated or may be reasonably inferred from each Drawing and each section of these Specifications, all of which are collectively necessary and/or required for the execution of the Work.

B. The information shown on the Contract Drawings or referenced herein relative to the depiction of existing facilities is shown for information purposes only. No representatives or warranties are given or implied relative to the accuracy thereof. The data is presented or described only to indicate the general and approximate extent of existing facilities. The Contractor shall consider these facilities in the preparation of his bid and include any contingent costs in those items for which payment will be made. No separate payment will be made for adjustments or modifications in the work due to inaccuracies in the nature or assumption of existing facilities, except as may be determined or warranted by the Owner/Engineer. Payment for changes in the work, if found necessary or prudent, shall be reimbursed only through procedure outlined in the General Conditions.

C. The Contractor will note that the Contract Drawings are general in detail and scope with respect to the extent of demolition, cutting, patching, removal of existing facilities, etc.

and that all such Work will be provided by the Contractor, whether specifically indicated on the Contract Drawings or not, which is necessary for the completion of the Work or for the proper operation and appearance of the finished installation, in accordance with the intent of the Contract Documents for this Project.

PART 2 - PRODUCTS – Not Used.

PART 3 - EXECUTION – Not Used.

END OF SECTION