31 10 00 - Site Clearing.pdf

PDF 219 KB Posted

Attached to
Contract 2026-01: Sewer Maintenance & Emergency Contract
Solicitation number
Not on record
Issued by
Lancaster County, Pennsylvania

About this file

This is a Site Clearing specification document prepared by Herbert, Rowland & Grubic, Inc. for the Borough of Elizabethtown's sanitary sewer infrastructure projects in Pennsylvania. The specification details clearing and site preparation work including removal of trees, brush, vegetation, debris, stumps, roots, and other obstructions within designated right-of-way and temporary construction easement areas. Work includes stripping and stockpiling topsoil, grubbing to a minimum depth of 8 inches below existing ground, stump removal to at least one foot below subgrade, tree wound dressing using asphalt-based antiseptic materials, and installation of temporary 4-foot high picket snow fencing for protection of designated vegetation and benchmarks. The contractor must notify the Engineer and Owner at least 48 hours before beginning clearing operations and must coordinate a site inspection following the Work Order issuance to identify trees and features to be preserved, removed, or restored.

The specification requires contractors to comply with PA One Call regulations for utility relocation and to legally dispose of all debris off-site unless otherwise authorized by the Owner; debris may be burned on-site only if local ordinances permit and appropriate permits are obtained. Merchantable timber larger than six inches in diameter must be trimmed and stockpiled in eight-foot lengths at Engineer-designated locations and remains the property of the property owner. All topsoil stripped from the project area becomes Owner property and must be stockpiled for finish grading use only, not as backfill or removal from the property. The contractor bears responsibility for restoration of injuries to retained vegetation using approved arboricultural practices and must replace any designated plants that are permanently injured or die during construction and the correction period at no cost to the Owner.

View the file

Other files

File Type Posted
33 31 00 - Sanitary Sewerage Piping.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 26 13-1- RFI Form.pdf PDF
01 22 00 - Unit Prices.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
33 05 61 - Concrete Manholes and Inlets.pdf PDF
01 42 00 - References.pdf PDF
33 05 97 - Identification and Signage for Utilities.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
01 78 36 - Warranties.pdf PDF
03 60 00 - Grouting.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
03 30 00 - Cast-in-Place Concrete.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 63 63 - Change Order Form.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
31 23 23 - Fill.pdf PDF
32 92 19 - Seeding.pdf PDF
Maintenance & Emergency Construction Details.pdf PDF
32 17 23 - Pavement Markings.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 62 76 - Contractor's Application for Payment.pdf PDF
00 31 43 - Permit Applications.pdf PDF
00 01 10 - Table of Contents.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
31 23 16 - Excavation.pdf PDF
00 60 00 - Project Forms.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
00 63 13 - RFI Form.pdf PDF
31 23 19 - Dewatering.pdf PDF
31 05 16 - Aggregates For Earthwork.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
33 01 30.11 - Television Inspection Of Sewers.pdf PDF
31 05 19.13 - Geotextiles For Earthwork.pdf PDF
33 31 23 - Sanitary Sewerage Pressure Piping.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
01 10 00 - Project Summary.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
03 10 00 - Concrete Forming and Accessories.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
01 26 13 - Request for Interpretation.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
Show 40 more

Latest 50 of 77 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

31 10 00 - SITE CLEARING

Herbert, Rowland & Grubic, Inc. 31 10 00 - 1 000598.0465

SECTION 31 10 00 - SITE CLEARING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Clearing.

2. Removal.

3. Stripping and stockpiling topsoil.

4. Debris disposal.

1.2 DEFINITIONS

A. Clearing is defined as the removal of trees, brush, down timber, rotten wood, rubbish, any other vegetation, and other material at or above original ground elevation not designated to be saved. Clearing also includes removal and replacement of fences, walls, guideposts, guide rail, signs, and other obstructions interfering with the proposed work.

B. Grubbing is defined as the removal from below the surface of the natural ground of stumps, roots and stubs, brush, topsoil, organic materials and debris.

1.3 SUBMITTALS

A. Permits for Disposal of Debris:

1. Arrange for disposal of debris to locations outside the Owner's property, permanent easement, or right of way. Comply with all applicable laws.

2. Submit two copies of any agreement with each property owner releasing the

Owner from responsibility in connection with the disposal of the debris.

1.4 JOB CONDITIONS

A. The Contractor may clear all obstructions within the permanent right-of-way and temporary construction easement as required for construction of the new facilities except those specifically designated to be saved or restored on the Work Order or specifications or in the field. Following issuance of the Work Order or the Project Starting Meeting, Engineer and Contractor shall inspect all sites and alignments for the purpose of compliance with this paragraph. The coordination and scheduling of this inspection shall be the Contractor's responsibility.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Temporary Fencing:

1. Undamaged picket snow fence, 4’ high, formed of wooden slats, tightly woven with wire cable or plastic fencing specifically manufactured for this use.

2. Soil set fence posts, studded “T” type, 6’ high.

Herbert, Rowland & Grubic, Inc. 31 10 00 - 2 000598.0465

B. Tree Wound Dressing:

1. Antiseptic and waterproof, asphalt base.

PART 3 - EXECUTION

3.1 PREPARATION

A. Notify the Engineer and Owner at least 48 hours prior to beginning any clearing work.

B. Protect benchmarks, utilities, existing trees, shrubs and other landscape features designated for preservation with temporary fencing or barricades satisfactory to the Engineer. No material shall be stored or construction operation carried on within 4 feet of any tree to be saved or within the tree protection fence.

C. When a private enclosure fence encroaches on the work area, notify the property owner at least 3 days in advance of the clearing/grubbing operations to permit the owner to remove it, construct a supplemental fence, or make such other arrangements as may be necessary for security purposes. Upon failure of the property owner to reasonably proceed with the work required to secure his property, carefully remove the fence, in whole or in part, and neatly pile the materials onto the owner's property.

3.2 UTILITY RELOCATIONS

A. Inform all companies, individuals and others owning or controlling facilities or structures within the limits of the work which are called out in the Contract Documents to be relocated, adjusted or reconstructed in sufficient time to perform such work in conjunction with or in advance of the Contractor's operations.

B. Comply with the provisions of the PA One Call, as amended.

3.3 CLEARING

A. Confine clearing to within the limits of the permanent right of way or temporary construction easement.

B. Fell trees in a manner that will avoid damage to trees, shrubs, and other installations, which are to be retained.

C. Remove trees and shrubbery only when authorized by Engineer or Owner:

1. Perform authorized tree removal, including stumps and debris, by methods meeting Engineer's approval and at no expense to the Owner.

2. Perform authorized shrubbery removal; store shrubs in protected manner and replant or replace such shrubbery at no expense to the Owner

3. Trim merchantable timber of limbs and tops, saw timber into eight-foot lengths.

Stockpile timber at locations designated on the site by the Engineer.

Merchantable timber is timber larger than six inches in smallest diameter from which saw logs, pulpwood, posts, poles, ties or cordwood can be produced.

Herbert, Rowland & Grubic, Inc. 31 10 00 - 3 000598.0465

4. The disposal of the stockpiled timber will not form a part of the contract obligations and the stockpiled merchantable timber will remain the property of the property owner.

5. Dispose of tree removal debris in a lawful manner.

3.4 REMOVAL

A. Grub areas within the construction limits of the permanent right of way or temporary construction easement to remove roots and other objectionable material to a minimum depth of 8" below the existing ground.

B. Remove all stumps within the construction limits of the permanent right of way or temporary construction easement as needed for construction of the new utility to a depth of at least one (1) foot below subgrade unless otherwise authorized by the Engineer.

3.5 STRIPPING AND STOCKPILING TOPSOIL

A. Strip topsoil to whatever depth it may occur from areas to be excavated, filled, or graded and stockpile at a location approved by the Engineer for use in finish grading.

B. The topsoil is the property of the Owner and shall not be used as backfill or removed from the property.

3.6 DEBRIS DISPOSAL

A. Unless informed otherwise by the Owner, debris resulting from clearing and grubbing operations shall become the property of the Contractor and shall be legally disposed of.

B. Do not deposit or bury on the site debris resulting from the clearing and grubbing work.

C. Debris may be burned on site if local ordinances allow open air burning, if required permits are obtained, and if burning operations are conducted in compliance with all state and local ordinances and regulations.

3.7 RESTORATION

A. Repair all injuries to bark, trunk, limbs, and roots of remaining plants by properly dressing, cutting, tracing and painting, using approved arboricultural practices and materials.

B. Replace trees, shrubs and plants designated to be saved which are permanently injured or die during the life of the Contract and subsequent correction period as a result of construction operations with like species acceptable to the property owner.

C. Remove protective fences, enclosures and guards upon the completion of the project.

D. Restore guard posts, guard rail, signs and other interference’s to the condition equal to that existing before construction operations.

END OF SECTION