03 60 00 - Grouting Specification Summary

This is a technical specification document for grouting work prepared by Herbert, Rowland & Grubic, Inc. for the Borough of Elizabethtown's sanitary sewer improvements project in Pennsylvania. The specification details two primary grouting product types: Portland cement grout and nonshrink cementitious grout, which will be utilized in the sewer infrastructure work. The Portland cement grout requires a two-to-one sand-to-cement ratio by volume and must achieve minimum compressive strengths of 2,400 psi at 48 hours and 7,000 psi at 28 days. The nonshrink cementitious grout, supplied as a pre-mixed formulation, must meet CRD-C621 Type D standards with compressive strengths of 4,000 psi at one day, 7,000 psi at seven days, and 10,000 to 10,800 psi at 28 days, with maximum expansion between 0.10 and 0.40 percent. Installation procedures require leakproof formwork, proper surface preparation including removal of laitance and foreign materials, grout mixing in proximity to work areas, continuous placement without pneumatic or dry-packing methods, and curing for a minimum of three days with moisture protection.

The specification establishes strict quality and environmental requirements governing material selection, handling, and installation. Portland cement must comply with ASTM C150 Type I or Type II standards, with Type II sulfate-resistant cement required for applications in contact with sanitary sewage. All water must be potable without impurities, suspended particles, or dissolved salts that could cause corrosion or volume changes. Ambient temperature conditions are restricted to a maximum of 90 degrees Fahrenheit and a minimum of 40 degrees Fahrenheit before, during, and after grouting until set. The contractor must submit product data, manufacturer instructions, and proposed mix designs to the Engineer of Record for review prior to commencing work. Manufacturers must demonstrate a minimum of three years' documented experience specializing in grout products, and all materials must arrive in original manufacturer packaging and be stored in clean, dry locations protected from moisture and dust.

View the file

Other files

File Type Posted
33 31 00 - Sanitary Sewerage Piping.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 26 13-1- RFI Form.pdf PDF
01 22 00 - Unit Prices.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
33 05 61 - Concrete Manholes and Inlets.pdf PDF
01 42 00 - References.pdf PDF
33 05 97 - Identification and Signage for Utilities.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
01 78 36 - Warranties.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
03 30 00 - Cast-in-Place Concrete.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 63 63 - Change Order Form.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
31 23 23 - Fill.pdf PDF
32 92 19 - Seeding.pdf PDF
Maintenance & Emergency Construction Details.pdf PDF
32 17 23 - Pavement Markings.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 62 76 - Contractor's Application for Payment.pdf PDF
00 31 43 - Permit Applications.pdf PDF
00 01 10 - Table of Contents.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
31 23 16 - Excavation.pdf PDF
00 60 00 - Project Forms.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
00 63 13 - RFI Form.pdf PDF
31 23 19 - Dewatering.pdf PDF
31 05 16 - Aggregates For Earthwork.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
33 01 30.11 - Television Inspection Of Sewers.pdf PDF
31 05 19.13 - Geotextiles For Earthwork.pdf PDF
31 10 00 - Site Clearing.pdf PDF
33 31 23 - Sanitary Sewerage Pressure Piping.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
01 10 00 - Project Summary.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
03 10 00 - Concrete Forming and Accessories.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
01 26 13 - Request for Interpretation.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
Show 40 more

Latest 50 of 77 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

03 60 00 --GROUTING

Herbert, Rowland & Grubic, Inc. 03 60 00 - 1 000598.0465

SECTION 03 60 00 - GROUTING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Portland cement grout.

2. Nonshrink cementitious grout.

B. Related Requirements:

1. Section 03 10 00 - Concrete Forming and Accessories: Form materials, waterstops, and accessories as required to form cast-in-place concrete and maintain structural integrity until stripping.

2. Section 03 30 00 - Cast-in-Place Concrete: Cast-in-place or in-situ concrete for structural building frames, slabs on fill or grade, and other concrete components.

1.2 REFERENCE STANDARDS

A. American Concrete Institute:

1. ACI 301 - Specifications for Structural Concrete for Buildings.

2. ACI 318 - Building Code Requirements for Structural Concrete.

B. ASTM International:

1. ASTM C33 - Standard Specification for Concrete Aggregates.

2. ASTM C40 - Standard Test Method for Organic Impurities in Fine Aggregates for

Concrete.

3. ASTM C150 - Standard Specification for Portland Cement.

4. ASTM C191 - Standard Test Methods for Time of Setting of Hydraulic Cement by

Vicat Needle.

C. U. S. Army Corps of Engineers Concrete Research Division (CRD):

1. CRD-C621 - Non-Shrink Grout.

1.3 SUBMITTALS

A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.

B. Product Data: Submit manufacturer information regarding grout.

C. Manufacturer's Certificate: Certify that products meet or exceed specified requirements.

D. Manufacturer Instructions: Submit instructions for mixing, handling, surface preparation, and placing epoxy-type and nonshrink grouts.

E. Field Quality-Control Submittals: Indicate results of Contractor-furnished tests and inspections.

Herbert, Rowland & Grubic, Inc. 03 60 00 - 2 000598.0465

1.4 QUALIFICATIONS

A. Manufacturer: Company specializing in manufacturing products specified in this Section with minimum three years' documented experience.

1.5 DELIVERY, STORAGE, AND HANDLING

A. Section 01 61 00 - Product Requirements: Requirements for transporting, handling, storing, and protecting products.

B. Inspection: Accept materials on Site in manufacturer's original packaging and inspect for damage.

C. Store materials according to manufacturer instructions.

D. Protection:

1. Protect materials from moisture and dust by storing in clean, dry location remote from construction operations areas.

2. Provide additional protection according to manufacturer instructions.

1.6 AMBIENT CONDITIONS

A. Section 01 50 00 - Temporary Facilities and Controls: Requirements for ambient condition control facilities for product storage and installation.

B. Maximum Conditions: Do not perform grouting if temperatures exceed 90 degrees F.

C. Minimum Conditions: Maintain minimum temperature of 40 degrees F before, during, and after grouting, until grout has set.

PART 2 - PRODUCTS

2.1 PORTLAND CEMENT GROUT

A. Portland Cement: Comply with ASTM C150, Type I and II:

1. Use Type II (Sulfate Resistant) cement for grout applications in contact with sanitary sewage. Use Type I cement for all other grout applications.

B. Water:

1. Potable.

2. No impurities, suspended particles, algae, or dissolved natural salts in quantities capable of causing:

a. Corrosion of steel.

b. Volume change increasing shrinkage cracking.

c. Efflorescence.

d. Excess air entraining.

C. Fine Aggregate:

1. Washed natural sand.

Herbert, Rowland & Grubic, Inc. 03 60 00 - 3 000598.0465

2. Gradation:

a. Comply with ASTM C33.

b. Represented by smooth granulometric curve within required limits.

3. Free from injurious amounts of organic impurities according to ASTM C40.

D. Mix:

1. Portland cement, sand, and water.

2. Do not use ferrous aggregate or staining ingredients in grout mixes.

2.2 NONSHRINK CEMENTITIOUS GROUT

A. Description:

1. Pre-mixed and ready-for-use formulation requiring only addition of water.

2. Nonshrink, non-corrosive, nonmetallic, non-gas forming, and no chlorides.

B. Performance and Design Criteria:

1. Certified to maintain initial placement volume or expand after set, and to meet following minimum properties when tested according to CRD-C621 for Type D nonshrink grout:

a. Setting Time:

1) Initial: Approximately two hours.

2) Final: Approximately three hours.

3) Comply with ASTM C191.

b. Maximum Expansion: 0.10 to 0.40 percent.

c. Compressive Strength:

1) One-Day: 4,000 psi.

2) Seven-Day: 7,000 psi.

3) 28-Day: 10,000 to 10,800 psi.

4) Comply with CRD-C621.

2.3 FORMWORK

A. As specified in Section 03 10 00 - Concrete Forming and Accessories.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Section 01 73 00 - Execution Requirements: Requirements for installation examination.

B. Verify areas to receive grout.

3.2 PREPARATION

A. Section 01 73 00 - Execution Requirements: Requirements for installation preparation.

B. Remove defective concrete, laitance, dirt, oil, grease, and other foreign material from concrete surfaces by brushing, hammering, chipping, or other similar means until sound and clean concrete surface is achieved.

Herbert, Rowland & Grubic, Inc. 03 60 00 - 4 000598.0465

C. Roughen concrete lightly, but not to interfere with placement of grout.

D. Remove foreign materials from metal surfaces in contact with grout.

E. Align, level, and maintain final positioning of components to be grouted.

F. Saturate concrete surfaces with clean water, and then remove excess water.

3.3 INSTALLATION

A. Formwork:

1. Construct leakproof forms anchored and shored to withstand grout pressures.

2. Install formwork with clearances to permit proper placement of grout.

3. As specified in Section 03 10 00 - Concrete Forming and Accessories.

B. Mixing:

1. Portland Cement Grout:

a. Use proportions of two parts sand and one part cement, measured by volume.

b. Prepare grout with water to obtain consistency to permit placing and packing.

c. Mix water and grout in two steps:

1) Premix using approximately 2/3 of water.

2) After partial mixing, add remaining water to bring mix to desired placement consistency and continue mixing two to three minutes.

d. Mix only quantities of grout capable of being placed within 30 minutes after mixing.

e. Do not add additional water after grout has been mixed.

f. Minimum Compressive Strength: 2,400 psi in 48 hours and 7,000 psi in 28 days.

2. Nonshrink Cementitious Grout:

a. Mix and prepare according to manufacturer instructions.

b. Minimum Compressive Strength: 2,400 psi in 48 hours and 7,000 psi in 28 days.

3. Mix grout components in proximity to Work area and transport mixture quickly and in manner not permitting segregation of materials.

C. Placing of Grout:

1. Place grout material quickly and continuously.

2. Do not use pneumatic-pressure or dry-packing methods.

3. Apply grout from one side only to avoid entrapping air.

4. Do not vibrate placed grout mixture or permit placement if area is being vibrated by nearby equipment.

5. Thoroughly compact final installation and eliminate air pockets.

6. Do not remove leveling shims for at least 48 hours after grout has been placed.

D. Curing:

Herbert, Rowland & Grubic, Inc. 03 60 00 - 5 000598.0465

1. Prevent rapid loss of water from grout during first 48 hours by use of approved membrane curing compound or by using wet burlap method.

2. Immediately after placement, protect grout from premature drying, excessively hot or cold temperatures, and mechanical injury.

3. After grout has attained its initial set, keep damp for minimum three days.

3.4 FIELD QUALITY CONTROL

A. Section 01 40 00 - Quality Requirements: Requirements for inspecting and testing.

B. Inspection and Testing:

1. Comply with ACI 301, ACI 318 and as specified in Section 01 40 00 - Quality

Requirements.

2. Submit proposed mix design of each class of grout to Engineer of Record for review prior to commencement of Work.

3. Tests of grout components may be performed to ensure compliance with specified requirements.

END OF SECTION