31 23 16 - Excavation.pdf
PDF 214 KB Posted
- Solicitation number
- Not on record
- Issued by
- Lancaster County, Pennsylvania
About this file
This is a Specification Section document for excavation work prepared by Herbert, Rowland & Grubic, Inc. for the Borough of Elizabethtown, Pennsylvania, related to the 2025 Sanitary Sewer Improvements Project (Contract No. 2025-01) and Contract 2026-01: Sewer Maintenance & Emergency Contract. The excavation specification details work including excavating for paving, roads, parking areas, and site structures, with requirements for unclassified excavation where no additional payment is provided for material difficulties. Key procedural requirements include notification to Pennsylvania One Call System, Inc. at least three working days before work begins to locate underground utilities, protection of existing utilities and structures, sloping of excavation banks to angle of repose, removal of loose matter and subsoil, and removal of lumped subsoil, boulders, and rock up to one-third cubic yard by volume. The contractor must prepare an excavation protection plan describing sheeting, shoring, and bracing materials under the direct supervision of a Professional Engineer licensed in Pennsylvania, and must request inspection of excavation and controlled fill operations in accordance with applicable code before subsequent work installation.
The specification requires contractors to verify utility locations and depths, maintain soil stability, protect excavation bottoms and adjacent soil from freezing, and prevent displacement of soil or utilities. Contractors are responsible for correcting over-excavated areas as directed by the Engineer, removing excess and unsuitable material from the site, and repairing or replacing items damaged during excavation. No specific pricing terms, set-asides, funding amounts, or incumbent information are provided within this technical specification document; such details would be contained in the bidding documents and contract terms available through PennBid.
View the file
Other files
Show 40 more
Latest 50 of 77 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
31 23 16 - EXCAVATION
Herbert, Rowland & Grubic, Inc. 31 23 16 - 1 000598.0465
SECTION 31 23 16 - EXCAVATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Excavating for paving, roads, and parking areas.
2. Excavating for site structures.
B. Related Sections:
1. Section 31 05 13 - Soils for Earthwork: Stockpiling excavated materials.
2. Section 31 05 16 - Aggregates for Earthwork: Stockpiling excavated materials.
3. Section 31 23 16.13 - Trenching: Excavating for utility trenches.
4. Section 31 23 16.26 - Rock Removal: Removal of rock during excavating.
5. Section 31 23 23 - Fill.
1.2 REFERENCES
A. Local utility standards when working within 24 inches of utility lines.
1.3 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Excavation Protection Plan: Describe sheeting, shoring, and bracing materials and installation required to protect excavations and adjacent structures and property; include structural calculations to support plan.
1.4 QUALIFICATIONS
A. Prepare excavation protection plan under direct supervision of Professional Engineer experienced in design of this Work and licensed in State of Pennsylvania.
1.5 JOB CONDITIONS
A. Existing Utilities and Services:
1. Contractor shall be responsible for verifying the location and/or depth of all utilities and services indicated within the areas of work.
2. Maintain existing utilities which must remain in service in the area of the excavation.
3. Record locations of underground utilities encountered.
B. Unclassified Excavation: No consideration will be given to the nature of materials encountered in excavating operations for structures. Therefore, as unclassified excavation, no additional payment will be made for difficulties occurring in excavating and handling of materials, including rock.
Herbert, Rowland & Grubic, Inc. 31 23 16 - 2 000598.0465
PART 2 - PRODUCTS – NOT USED.
PART 3 - EXECUTION
3.1 PREPARATION
A. Call Pennsylvania One Call System, Inc. not less than three working days before performing Work:
1. Request underground utilities to be located and marked within and surrounding construction areas.
B. Identify required lines, levels, contours, and datum.
C. Protect utilities indicated to remain from damage.
D. Protect plant life, lawns, and other features remaining as portion of final landscaping.
E. Protect bench marks, survey control points, existing structures, fences, sidewalks, paving, and curbs from excavating equipment and vehicular traffic.
3.2 EXCAVATION
A. Underpin adjacent structures which may be damaged by excavation work.
B. Excavate subsoil to accommodate building foundations, slabs-on-grade paving and site structures, and construction operations.
C. Slope banks with machine to angle of repose or less until shored.
D. Do not interfere with 45 degree bearing splay of foundations.
E. Grade top perimeter of excavation to prevent surface water from draining into excavation.
F. Trim excavation. Remove loose matter.
G. Remove lumped subsoil, boulders, and rock up to 1/3 cu yd measured by volume. Remove larger material as specified in Section 31 23 16.26.
H. Notify Engineer of unexpected subsurface conditions.
I. Correct areas over excavated as directed by Engineer.
J. Remove excess and unsuitable material from site.
K. Repair or replace items indicated to remain damaged by excavation.
Herbert, Rowland & Grubic, Inc. 31 23 16 - 3 000598.0465
3.3 FIELD QUALITY CONTROL
A. Section 01 40 00 - Quality Requirements: Field inspecting, testing, adjusting, and balancing.
B. Request inspection of excavation and controlled fill operations in accordance with applicable code.
C. Request visual inspection of bearing surfaces by inspection agency before installing subsequent work.
3.4 PROTECTION
A. Prevent displacement or loose soil from falling into excavation; maintain soil stability.
B. Protect bottom of excavations and soil adjacent to and beneath foundation from freezing.
C. Protect structures, utilities and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earth operations.
END OF SECTION