This is a specification document for Anti-Pollution Measures prepared by Herbert, Rowland & Grubic, Inc. for the Borough of Elizabethtown's sanitary sewer infrastructure projects in Pennsylvania. The document outlines the contractor's environmental compliance obligations for the 2025 Sanitary Sewer Improvements Project (Contract No. 2025-01) and the 2026-01 Sewer Maintenance & Emergency Contract. The specification requires contractors to comply with all Federal and State statutes, rules, and regulations concerning environmental pollution prevention and public natural resources preservation pursuant to Pennsylvania Act No. 247. For projects involving earthmoving activities, contractors must develop, implement, and maintain an erosion and sedimentation control plan in accordance with DEP Regulation Chapter 102 and submit the plan for review by the County Conservation District and approval by the local political subdivision and Engineer before commencing work.

The Anti-Pollution Measures specification serves as a supplemental requirement to the General Conditions (Section 00 72 00) and establishes baseline environmental stewardship standards applicable to all contractors bidding on these municipal sewer projects. The specification does not provide pricing terms, set-asides, or funding information, but rather establishes mandatory environmental compliance protocols that bidders must acknowledge and agree to implement. Contractors must have erosion control plans available at earthmoving sites, and if no plan is provided in the contract documents, contractors are responsible for developing their own plan subject to regulatory review and approval before work authorization.

View the file

Other files

File Type Posted
33 31 00 - Sanitary Sewerage Piping.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 26 13-1- RFI Form.pdf PDF
01 22 00 - Unit Prices.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
33 05 61 - Concrete Manholes and Inlets.pdf PDF
01 42 00 - References.pdf PDF
33 05 97 - Identification and Signage for Utilities.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
01 78 36 - Warranties.pdf PDF
03 60 00 - Grouting.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
03 30 00 - Cast-in-Place Concrete.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 63 63 - Change Order Form.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
31 23 23 - Fill.pdf PDF
32 92 19 - Seeding.pdf PDF
Maintenance & Emergency Construction Details.pdf PDF
32 17 23 - Pavement Markings.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 62 76 - Contractor's Application for Payment.pdf PDF
00 31 43 - Permit Applications.pdf PDF
00 01 10 - Table of Contents.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
31 23 16 - Excavation.pdf PDF
00 60 00 - Project Forms.pdf PDF
00 63 13 - RFI Form.pdf PDF
31 23 19 - Dewatering.pdf PDF
31 05 16 - Aggregates For Earthwork.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
33 01 30.11 - Television Inspection Of Sewers.pdf PDF
31 05 19.13 - Geotextiles For Earthwork.pdf PDF
31 10 00 - Site Clearing.pdf PDF
33 31 23 - Sanitary Sewerage Pressure Piping.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
01 10 00 - Project Summary.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
03 10 00 - Concrete Forming and Accessories.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
01 26 13 - Request for Interpretation.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
Show 40 more

Latest 50 of 77 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

00 73 53 – ANTI-POLLUTION MEASURES

Herbert, Rowland & Grubic, Inc. 00 73 53 - 1 000598.0465

SECTION 00 73 53 – ANTI-POLLUTION MEASURES

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Duties and requirements of Contractor under various laws and regulations, supplementing the requirements contained in the General Conditions.

1.2 RELATED SECTIONS

A. Section 00 72 00 – General Conditions

1.3 ENVIRONMENTAL POLLUTION

A. Contractor shall comply with all provisions of Federal and State statutes, rules and regulations dealing with the prevention of environmental pollution, and the preservation of public natural resources that affect the project pursuant to the provisions of Act No.

247 of the General Assembly of the Commonwealth of Pennsylvania, approved October 26, 1972.

1.4 STORMWATER POLLUTION PREVENTION

A. Any Contractor involved in an earthmoving activity is responsible for complying with the

DEP Regulation Chapter 102, Erosion Control. The Contractor must develop, implement and maintain an erosion and sedimentation control plan and must have the plan available at the earthmoving site. If an erosion and sedimentation control plan is contained in the Contract Documents or is issued by the Engineer, it shall be used until such a time that the Contractor develops a new plan and obtains review comments by the County Conservation District and approval by the local political subdivision and the Engineer.

END OF SECTION