33 01 30.11 - Television Inspection Of Sewers.pdf

PDF 219 KB Posted

Attached to
Contract 2026-01: Sewer Maintenance & Emergency Contract
Solicitation number
Not on record
Issued by
Lancaster County, Pennsylvania

About this file

This is a technical specification document for television inspection of sewers prepared by Herbert, Rowland & Grubic, Inc., applicable to the Borough of Elizabethtown's sanitary sewer improvements project in Pennsylvania. The specification outlines requirements for pipeline flushing, cleaning, and closed-circuit television (CCTV) inspection of sewer pipelines with simultaneous audio-video recording. The work must be scheduled after all sanitary sewer mains and laterals have been installed and tested. The contractor must submit video recordings in electronic format on external storage devices along with typed video logs containing detailed information including inspection dates, manhole numbers, lateral service locations, pipe size and type, joint conditions, infiltration/inflow defects, cracks, leaks, offset joints, and weather conditions. The contractor must provide a bypass pumping system plan, spill contingency plan, and field quality control results. A 48-hour notice must be given to the Owner and Engineer prior to videotaping, and both parties shall accompany the contractor during taping. All recorded videos and storage devices become the property of the Owner upon completion.

The specification requires that the recording be performed by a firm actively engaged and experienced in video recording of sewer conditions on utility projects, with the Engineer reserving the right to request sample work and investigate qualifications. The CCTV camera system must be specifically designed for sewer line inspection with pan-and-tilt capability to view lateral connections at multiple angles and capable of moving both upstream and downstream with a minimum 1,000 feet horizontal distance within one setup using a direct-reading cable position meter. Taping must occur following successful cleaning and after sanitary sewer main installation and service lateral reconnections during periods of no flow to ensure unobstructed views. The contractor must identify and record locations of flat grades, dips, deflected joints, open joints, broken pipe, protrusions, infiltration points, service connections, and all pipeline defects with horizontal distance measurements and directional references from manholes, with 100 percent pipe ID viewing achieved through pipe section plugging.

View the file

Other files

File Type Posted
33 31 00 - Sanitary Sewerage Piping.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 26 13-1- RFI Form.pdf PDF
01 22 00 - Unit Prices.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
33 05 61 - Concrete Manholes and Inlets.pdf PDF
01 42 00 - References.pdf PDF
33 05 97 - Identification and Signage for Utilities.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
01 78 36 - Warranties.pdf PDF
03 60 00 - Grouting.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
03 30 00 - Cast-in-Place Concrete.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 63 63 - Change Order Form.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
31 23 23 - Fill.pdf PDF
32 92 19 - Seeding.pdf PDF
Maintenance & Emergency Construction Details.pdf PDF
32 17 23 - Pavement Markings.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 62 76 - Contractor's Application for Payment.pdf PDF
00 31 43 - Permit Applications.pdf PDF
00 01 10 - Table of Contents.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
31 23 16 - Excavation.pdf PDF
00 60 00 - Project Forms.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
00 63 13 - RFI Form.pdf PDF
31 23 19 - Dewatering.pdf PDF
31 05 16 - Aggregates For Earthwork.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
31 05 19.13 - Geotextiles For Earthwork.pdf PDF
31 10 00 - Site Clearing.pdf PDF
33 31 23 - Sanitary Sewerage Pressure Piping.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
01 10 00 - Project Summary.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
03 10 00 - Concrete Forming and Accessories.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
01 26 13 - Request for Interpretation.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
Show 40 more

Latest 50 of 77 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

33 01 30.11 - TELEVISION INSPECTION OF SEWERS

Herbert, Rowland & Grubic, Inc. 33 01 30.11 - 1 000598.0465

SECTION 33 01 30.11 - TELEVISION INSPECTION OF SEWERS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Pipeline flushing and cleaning.

2. Television inspection of sewer pipelines.

3. Audio-video recording of pipeline interior.

B. Related Requirements:

1. Section 01 50 00 - Temporary Facilities and Controls: Safety requirements when bypassing sewage flow.

1.2 SCHEDULING

A. Schedule Work of this Section after all sanitary sewer mains and laterals have been installed and tested.

1.3 SUBMITTALS

A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.

B. Contractor shall provide video recordings in electronic format on an external storage device and typed video logs of all televised pipe sections.

C. Upon completion of the work, all videos recorded and all external storage devises utilized to store videos and/or video logs during the television inspection shall become the property of the Owner.

D. Inspection Logs:

1. Submit cleaning and television inspection logs for each section of sewer line to be rehabilitated.

2. Include following minimum information:

a. Date of television inspection.

b. Sewer section and manhole number.

c. Stationing and location of lateral services, wyes, or tees.

d. Date and clock time references.

e. Distance along reach (tape counter footage).

f. Label.

g. Verbal confirmation of sewer section and television direction in relation to direction of flow.

h. Verbal description of pipe size, type, and pipe joint length.

i. Pipe joints.

j. Infiltration/inflow defects.

k. Cracks.

l. Leaks.

Herbert, Rowland & Grubic, Inc. 33 01 30.11 - 2 000598.0465

m. Offset joints.

n. Type of weather during inspection.

E. Submit specific detailed description of proposed bypass pumping system, including written description of plan addressing schedule, quantity, capacity, and location of pumping equipment.

F. Submit spill plan to address any spills that might occur.

G. Field Quality-Control Submittals: Indicate results of Contractor-furnished tests and inspections.

1.4 QUALIFICATIONS

A. Required recording shall be performed by a firm actively engaged, experienced and knowledgeable in video recording of sewer conditions on utility projects. The Engineer reserves the right to request sample work and investigate the qualifications of any firm chosen to perform this work.

PART 2 - PRODUCTS

2.1 PORTABLE HARD DRIVE

A. Description: Digital video formatted portable hard drives.

B. Audio track containing simultaneously recorded narrative commentary and evaluations of videographer, describing in detail condition of pipeline interior.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Section 01 73 00 - Execution Requirements: Requirements for application examination.

B. Verify location of sewer pipelines to be inspected.

3.2 PREPARATION

A. Section 01 73 00 - Execution Requirements: Requirements for application preparation.

B. Flush and clean pipeline to remove sludge, dirt, sand, stone, grease, and other materials to ensure clear view of interior conditions.

C. Debris:

1. Intercept flushed debris at next downstream manhole using weir or screening device.

2. Remove and dispose of debris off Site.

D. Bypassing:

1. Refer to Section 01 57 28 - Temporary Flow Control for requirements.

Herbert, Rowland & Grubic, Inc. 33 01 30.11 - 3 000598.0465

2. Furnish temporary bypass pumping system around Work area for time required to complete television inspection.

3. Provide safety precautions, including barricades, lights, and flaggers as specified in Section 01 50 00 – Temporary Facilities and Controls.

3.3 APPLICATION

A. Closed-Circuit Television (CCTV) Camera System:

1. Use cameras specifically designed and constructed for closed-circuit sewer line inspection.

2. Use camera equipment with pan-and-tilt capability to view each lateral connection at multiple angles.

3. Use camera capable of moving both upstream and downstream with minimum

1,000 feet horizontal distance within one setup and using direct-reading cable position meter.

B. All taping to be done following successful cleaning prior to repair (if needed) and following successful installation of sanitary sewer mains and service lateral reconnections. Conduct taping during periods of no flow during bypass pumping operations to ensure unobstructed views of the completed work. Provide flow control measures as necessary at no additional costs.

C. Owner and Engineer shall accompany Contractor during taping. A 48-hour notice shall be given to the Owner and Engineer prior to videotaping.

D. Control direction of travel, panning rates, and zoom in-out rates in a manner that produces clarity of subject during playback.

3.4 FIELD QUALITY CONTROL

A. Section 01 40 00 - Quality Requirements: Requirements for inspecting and testing.

B. Pipeline Inspection:

1. Audio-video record sections of sewer pipeline between designated manholes.

2. Identify and record locations of flat grades, dips, deflected joints, open joints, broken pipe, protrusions into pipeline, and points of infiltration.

3. Locate and record service connections.

4. Record locations of pipeline defects, connection horizontal distance in feet, and direction from manholes.

5. Video-record with pipe section plugged to view 100 percent of pipe ID.

6. Use flow-control methods as specified for bypass pumping system to eliminate surcharging and to reduce flow.

END OF SECTION